CB3-EC-50-CA-003-A4 Rev.1
CB3-EC-50-CA-003-A4 Rev.1
REV.1
E14005 CB3-EC-50-CA-003-A4
LOMANIS - TASIKMALAYA
Doc.
_________________________________________________________________________________________________
No CB3-EC-50-CA-003-A4 Rev. 1
Page 2 of 5
Jasa Konsultansi Feed Pipanisasi CB-III (Ex.CB-I) Lomanis - Tasikmalaya
Doc.
_________________________________________________________________________________________________
No CB3-EC-50-CA-003-A4 Rev. 1
Page 3 of 5
Jasa Konsultansi Feed Pipanisasi CB-III (Ex.CB-I) Lomanis - Tasikmalaya
TABLE OF CONTENT
1.0 SCOPE 4
2.0 CODES, STANDARS, AND REFERENCES 4
2.1 Codes and Standards 4
2.2 References 4
3.0 MATERIAL DATA 4
3.1 Quality of Materials 4
3.2 Unit Weight of Materials 5
4.0. DESIGN CONSIDERATION 5
4.1. Design Method 5
4.2. Loading Combination 5
ATTACHMENT
A. Pipe Bridge 28m
B. Pipe Bridge 44m
Doc.
__________________________________________________________________________________________________
No CB3-EC-50-CA-003-A4 Rev. 1
Page 3 of 5
Jasa Konsultansi Feed Pipanisasi CB-III (Ex.CB-I) Lomanis - Tasikmalaya
1.0 SCOPE
This document presents calculation of Pipe Bridge for Pipanisasi CB-III (Ex.CB-I) Lomanis -
Tasikmalaya.
2.2 References
- CB3-EC-50-SP-001-A4 Civil and Structure General Specification
- CB3-EC-50-SP-004-A4 Concrete Work Specification
- CB3-EC-50-SP-005-A4 Foundation Specification
- PC Pile
Minimun compressive strength = 415 kg/cm2
Doc.
__________________________________________________________________________________________________
No CB3-EC-50-CA-003-A4 Rev. 1
Page 4 of 5
Jasa Konsultansi Feed Pipanisasi CB-III (Ex.CB-I) Lomanis - Tasikmalaya
Foundation is designed to withstand static loads. Stability and soil pressure checked due to
unfactored loading combination service. Factored loading combination is subsequently
done for reinforced concrete design and unfactored loading for pile capacity check.
Loading Condition
11 D + P(E)
12 D + P(E) + W
13 D + P(O) + L + T
14 D + P(O) + W + L + T
15 D + P(T) +0.5L
16 D + P(T) + 0.25W +0.5L
Loading Condition
21 1.4(D + P(E))
22 0.9(D + P(E)) + W
23 1.2(D + P(O)) + 1.6(L + T)
24 1.2(D + P(O)) + L + 0.5W
25 1.2D + 1.2T + L + W + T
Doc.
__________________________________________________________________________________________________
No CB3-EC-50-CA-003-A4 Rev. 1
Page 5 of 5
Jasa Konsultansi Feed Pipanisasi CB-III (Ex.CB-I) Lomanis - Tasikmalaya
Doc.
________________________________________________________________________________________
No CB3-EC-50-CA-003-A4 Rev. 0
Page 6 of 6