Guide For Equipotential Copper Earth Mat Installations Central Networks
Guide For Equipotential Copper Earth Mat Installations Central Networks
for
Equipotential Earth Mat Installation
on
Substation Structure Mounted Switches
REVISION LOG
CONTENTS
Page
Background ......................................................................................................................... 4
Safety .................................................................................................................................. 4
Testing Procedure for Installation of Gratings.................................................................... 5
Materials.............................................................................................................................. 6
Installation Guidance .......................................................................................................... 6
Background
An objective of the work is to enable live operation on isolators and switches
installed within outdoor substation compounds by release of Suspension of
Operating Practice SOP 294 (applicable to the East).
The gratings will be installed in the West where the existing foot-plates are
non-existent or inadequate (e.g. concrete with metal strips).
The work is to install a metallic grating under the operators standing
position which is electrically connected to the switch handle.
This is to ensure that persons operating the switch have their feet and
hands at the same potential should a fault occur when switching
It is essential that the gratings are placed where the operator stands
(vertical handle) or walks (rotary handle) during the operation.
The connection on the grating must be visible for the operator to check
before switching. (To prevent tripping hazards it may be necessary to
provide a light covering of stone which can be readily moved by the
operator).
A grating shall be installed at every isolator and earth switch position. A
grating shall also be installed at any fault thrower location.
The connection from the grating to the handle must go directly between the
two and must not form part of the existing conductor between the handle
and the rest of the earth grid. This is to ensure any earth fault current
flowing down the structure to the earth grid does not flow via the
connection to the grating or through the grating itself. Existing gratings that
are being replaced may need modifications to the connections to bring it in
line with the above requirement.
Safety
1) Identify a suitable reference earth connection in the substations (e.g. NER earth or obvious
earth bar in switch-room.)
2) Use a four terminal earth tester to test continuity between reference earth and the handles
of all switches where the grating is to be installed.
LEM Saturn Geo X shown – other suitable 4 terminal earth testers may also be used.
3) On a large site you can declare a new reference point by testing it back the first reference
and then make further test from there. (saves having very long leads)
4) If everything is in order then install the grating as detailed in the Installation Section below.
5) At end of the work provide results to the Control Engineer for SOP294 to be removed (East
only).
Materials
Installation Guidance
Layout of Gratings
Vertical operation Rotary operation
One grating placed centrally 500- Up to five gratings to give a 1.5m
550mm from the switch structure (+/- 0.1m) radius from the fulcrum
Remove chippings to provide a level base & flush fit. Fill grating with
further chippings for stability.
Apply contact grease to the edges of the gratings before bolting together
Contact grease
Bolt
Plain Washers
Nut
Spring Washer
Contact Grease
grating
Hook-bolt - epoxy
fixing into
Fixing spike bolted
concrete to grating and
Trench concreted in
Grating
Trench
If not covered by
chippings (not a tripping
hazard) then paint grey to
deter theft.