Powerplant Structures - Weekly Progress S-Curve: Updated As of Feb. 20, 2019

This document provides a weekly progress update for the construction of powerplant structures for a 25MWe biomass-fired powerplant located in Brgy. Cubay, La Carlota City, Negros Occidental, Philippines, as of February 20, 2019. The cumulative planned progress was 8.31% while the actual cumulative progress achieved was 7.47%, resulting in a negative variance of 0.84%. Construction faced a delay in schedule.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views1 page

Powerplant Structures - Weekly Progress S-Curve: Updated As of Feb. 20, 2019

This document provides a weekly progress update for the construction of powerplant structures for a 25MWe biomass-fired powerplant located in Brgy. Cubay, La Carlota City, Negros Occidental, Philippines, as of February 20, 2019. The cumulative planned progress was 8.31% while the actual cumulative progress achieved was 7.47%, resulting in a negative variance of 0.84%. Construction faced a delay in schedule.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

INTENDED FOR POWERPLANT STRUCTURES ONLY

PROJECT: 25MWe BIOMASS - FIRED POWERPLANT


LOCATION: BRGY. CUBAY, LA CARLOTA CITY, NEGROS OCCIDENTAL

UPDATED AS OF FEB. 20, 2019 POWERPLANT STRUCTURES - WEEKLY PROGRESS S-CURVE


4.00% 120.00%

PLAN (%) ACTUAL (%)

CUMULATIVE PLAN = 8.31% CUMULATIVE PLAN (%) CUMULATIVE ACTUAL (%) PHYSICAL PROGRESS
(Based on Labor - Manhours)
CUMULATIVE ACTUAL = 7.47%
3.50%
Variance = -0.84%
100.00%

Remarks: Delayed of Schedule

3.00%

NOTE:
80.00%
AUGUST 10, 2018 - START OF

CUMULATIVE PROGRESS (%)


2.50% GRADUAL RESUMPTION OF
ACTIVITIES AFTER THE TAKE OVER
ON AUGUST 02, 2018
PERIODIC PROGRESS (%)

2.00% 60.00%

1.50%

40.00%

1.00%

20.00%

0.50%

0.00% 0.00%
6-Mar-19
6-Feb-19

15-May-19

22-May-19

29-May-19
13-Feb-19

20-Feb-19

27-Feb-19

3-Apr-19

2-Oct-19

9-Oct-19
3-Oct-18

10-Oct-18

17-Oct-18

24-Oct-18

31-Oct-18

10-Apr-19

17-Apr-19

24-Apr-19

10-Jul-19

17-Jul-19

24-Jul-19

31-Jul-19

16-Oct-19

23-Oct-19

30-Oct-19
7-Nov-18

5-Dec-18

13-Mar-19

20-Mar-19

27-Mar-19

3-Jul-19

7-Aug-19

4-Sep-19
14-Nov-18

21-Nov-18

28-Nov-18

12-Dec-18

19-Dec-18

26-Dec-18

14-Aug-19

21-Aug-19

28-Aug-19

11-Sep-19

18-Sep-19

25-Sep-19

6-Nov-19
2-Jan-19

9-Jan-19

5-Jun-19

13-Nov-19

20-Nov-19

27-Nov-19
16-Jan-19

23-Jan-19

30-Jan-19

1-May-19

8-May-19

12-Jun-19

19-Jun-19

26-Jun-19
PERIOD 3-Oct-18 10-Oct-18 17-Oct-18 24-Oct-18 31-Oct-18 7-Nov-18 14-Nov-18 21-Nov-18 28-Nov-18 5-Dec-18 12-Dec-18 19-Dec-18 26-Dec-18 2-Jan-19 9-Jan-19 16-Jan-19 23-Jan-19 30-Jan-19 6-Feb-19 13-Feb-19 20-Feb-19 27-Feb-19 6-Mar-19 13-Mar-19 20-Mar-19 27-Mar-19 3-Apr-19 10-Apr-19 17-Apr-19 24-Apr-19 1-May-19 8-May-19 15-May-19 22-May-19 29-May-19 5-Jun-19 12-Jun-19 19-Jun-19 26-Jun-19 3-Jul-19 10-Jul-19 17-Jul-19 24-Jul-19 31-Jul-19 7-Aug-19 14-Aug-19

PLAN (%) 0.00% 0.00% 0.00% 0.00% 0.01% 0.07% 0.20% 0.20% 0.16% 0.12% 0.15% 0.15% 0.10% 0.10% 0.19% 0.41% 0.55% 0.80% 1.09% 1.76% 2.27% 2.49% 3.31% 3.22% 3.00% 3.15% 3.29% 2.86% 3.62% 1.83% 3.05% 3.36% 3.18% 3.35% 3.01% 2.19% 2.09% 2.88% 3.39% 3.76% 3.51% 3.47% 3.53% 3.29% 2.94% 2.66%

ACTUAL (%) 0.00% 0.00% 0.00% 0.24% 0.06% 0.28% 0.09% 0.23% 0.35% 0.45% 0.80% 0.66% 0.29% 0.04% 0.34% 0.25% 0.34% 0.91% 0.27% 1.09% 0.78%

CUMULATIVE PLAN (%) 0.00% 0.00% 0.00% 0.00% 0.01% 0.08% 0.27% 0.47% 0.63% 0.75% 0.90% 1.04% 1.14% 1.24% 1.43% 1.85% 2.40% 3.20% 4.29% 6.05% 8.31% 10.80% 14.11% 17.33% 20.34% 23.48% 26.78% 29.64% 33.25% 35.09% 38.14% 41.50% 44.67% 48.03% 51.03% 53.22% 55.31% 58.19% 61.58% 65.34% 68.85% 72.32% 75.86% 79.14% 82.08% 84.74%

CUMULATIVE ACTUAL (%) 0.00% 0.00% 0.00% 0.24% 0.30% 0.58% 0.67% 0.90% 1.25% 1.70% 2.50% 3.16% 3.45% 3.49% 3.83% 4.08% 4.42% 5.33% 5.60% 6.69% 7.47%

VARIANCE (%) 0.00% 0.00% 0.00% 0.24% 0.29% 0.50% 0.40% 0.43% 0.62% 0.95% 1.60% 2.12% 2.31% 2.25% 2.40% 2.23% 2.02% 2.13% 1.31% 0.64% -0.84%

PERIOD 21-Aug-19 28-Aug-19 4-Sep-19 11-Sep-19 18-Sep-19 25-Sep-19 2-Oct-19 9-Oct-19 16-Oct-19 23-Oct-19 30-Oct-19 6-Nov-19 13-Nov-19 20-Nov-19 27-Nov-19 REMARKS

PLAN 2.65% 2.62% 2.99% 2.64% 1.63% 0.98% 0.77% 0.49% 0.21% 0.10% 0.07% 0.03% 0.05% 0.01% 0.01%

ACTUAL

CUMULATIVE PLAN 87.39% 90.01% 93.00% 95.64% 97.27% 98.25% 99.03% 99.51% 99.73% 99.83% 99.90% 99.93% 99.98% 99.99% 100.00%

CUMULATIVE ACTUAL

VARIANCE