Conbit FTR White Paper
Conbit FTR White Paper
EFFECTIVE
FLARE TIP
REPLACEMENT
SAFETY
Safety is paramount with multiple aspects regarding personnel, equipment, infrastructure and the environment
to consider in delivering a safe project.
The flare tip is sited above the plant or above water and so the possibility of the unit itself or parts of the
handling equipment dropping presents a significant risk, as does the need for rope access work.
Time pressure, which is always present during shutdowns, increases the risk a hazardous situation occurring, and
that is why offshore operators frequently look to a specialist contractor to ensure the work is carried out safely.
The key criteria to consider when selecting a specialist contractor are:
• The power of preparation. Detailed method statements and 3D renderings of procedures allow all those
involved to have the best view of the planned work and can prove invaluable in identifying required
precautions during the Hazard Identification (HAZID) stage.
• The quality and condition of equipment. A supplier with their own inventory and strong equipment
management processes can be critical to project safety.
• The safety record of the supplier. Strong safety records provide assurance that you are working with a
conscious supplier who prioritises safety.
TIME CHALLENGE
Flare tip replacement can be on the critical path during maintenance shutdowns, which means delays or time
savings in the replacement work can have a direct impact on plant performance.
Operators of offshore assets require confidence that schedules will run to time, so selecting not just the right
supplier but also the best working methods is essential.
• Repetition and routine in flare tip replacement can make a major difference in the time required to safely
and accurately finish the work. Selecting a supplier with a strong track record in similar work is the best
way to achieve this.
• Communication lines should be kept as short as possible. The offshore team can make decisions
independently, which can save valuable time. The offshore team is able to determine the impact of their
decisions and can consider whether further consultation with the engineering team is required.
ENGINEERING CHALLENGE
There are three ways in which offshore flare tip replacements are more challenging than onshore lifting projects.
These challenges demand both strong engineering skills and well trained offshore teams to ensure a smooth
transfer from planning to implementation.
The combination of these facets is highly valued by many offshore operators, and Conbit has found the following
factors are often crucial when assessing engineering capabilities.
• Strong structural engineering and analysis experience. The dynamic factors of the lifting operation require
detailed structural analysis. Flare tip lifting to and from supply vessels are engineered without the use of
motion compensated systems. The use of high speed winches in combination with light weight lifting material
demands detailed feasibility analysis by qualified structural engineers.
• Offshore operators demand engineering that can be verified. The reporting style of Conbit allows for third party
checks, which is like a breath of fresh air for the project team of the client.
• In our operation, we have more and more interactions with third party Marine Warranty Surveyors. Offshore
operators feel confident that they are able to convince these parties of the feasibility of the engineered solution
with the engineering documents provided by Conbt. Often, our clients let Conbit take control of the MWS
process and be in direct contact, which increases the project’s efficiency.
Shutdowns for flare tip maintenance and replacement are typically planned well in advance as they require
cessation of production at the facility. They are therefore kept to a minimum, limited to unavoidable repairs
and replacement. The flare is the last part of the plant that is shut off and the first to be turned on, which puts
pressure on the team completing the flare scope.
Safety at flare tip The flare tip access platform Standard riggers at the flare Crew is used to working at
access platform is small and there are no tip access platform. this altitude.
rapid escape possibilities if
the load starts to swing.
Exposure Limited in time. The Minimum exposure. Operation will take 3-5 days
operation will draw at the top of the flare.
attention.
Visibility on the load From the cockpit, the pilot Line of sight depends on Clear line of sight from
usually cannot see where the positioning of the jack winch to load.
the hook is – even with up vessel, which depends
plexiglass side-bubbles or on soil conditions and other
removable doors. The pilot jack-up barge activities.
must rely on the signaller’s
communication to
manoeuvre into position.
Load positioning Hovering with a load is a The long line of the crane The load can be controlled
difficult, fatiguing and might cause some swinging from within arm’s reach.
potentially dangerous of the load.
activity that requires a high
level of pilot concentration
and should therefore be
limited in time.
Standby Full spread rate applies. Full spread rates apply. Limited cost impact.
Associated services Different crew required to Additional lifting equipment Equipment can be used for
perform rigging below the required for lifting below the lifting below the flare tip
flare tip access platform, flare tip access platform. access platform. The same
and for mechanical works Additional crew required for crew can perform mechan-
mechanical works. ical works and repair and
modification services.
In some flare structures, a davit or other permanent lifting structure is incorporated. Many offshore operators
integrate this permanent lifting solution into the design during the construction of the offshore facility, because
they feel that they need to take precautions for the future. The main disadvantage of permanently installed lifting
systems is that you need to inspect and test them before use. These activities need to take place within the
shutdown period. If the system does not pass the tests, you cannot complete the flare tip replacement as
planned. It will either jeopardise the shutdown duration and/or the budget, or the flare tip cannot be replaced.
MECHANICAL HANDLING –
THE MOST EFFECTIVE SOLUTION
Conbit advocates the use of handling flare tips with temporary lifting equipment. The lifting equipment is installed
at the flare tip access platform and is operated by winches, which remain at deck level.
Shell Philippines contracted Conbit to replace the flare tip on their PROJECT
Malamaya offshore facility, in the West Philippine Sea.
ENGINEERING
The flare tip (weighing 4160 kg) was replaced during the 2017 shutdown. PROCUREMENT
Shell approached Conbit because of our specialized flare tip replacement INSTALLATION
service. Our highly experienced rope-access technicians and riggers have
proved themselves to be readily adaptable to changing situations and Client
weather conditions offshore. Shell Philippines Exploration BV
Project Name
Malampaya flare tip replacement
PERFORMANCE
The client’s management was
delighted with Conbit’s execution
of this project, because this highly
critical activity was completed on
time, within budget and safely.
PROJECT
ENGINEERING
INSTALLATION
Client
Project Name
The flare tip at the flare tip access platform (FTAP) required replacement THE POWER OF PREPERATION
during the shutdown. A base frame and lift boom were utilised to Conbit prepared for the manoeuvre
perform the mechanical handling in the removal of a pre-existing flare tip with a thorough engineering plan
and replacement with a new one weighing 442kg and measuring and ensured all operators were
3.747mm x 819mm. A supply vessel was used to move the existing and well-trained and were expertise in
new flare tip to and from the platform. flare-tip operations. Conbit
monitored the sea state and the
It was completed within four days. wind speed. The flare tip access
platform had a sufficient amount of
The Kingfish A (KFA), Kingfish B (KFB) and West Kingfish (WKF) strong points to carry the loads of
platforms are located within Production Area VIC/L07 approximately 72 the lifting system and the flare tip.
to 77 km off the Gippsland coast in approximately 77 to 78 m of water To assure all stakeholders involved,
depth. The KFA platform is connected to the KFB platform by the KFA- factory acceptance test (FAT) took
KFB400 pipeline; the KFB platform is connected to the Halibut (HLA) place during the engineering phase
platform by the KFB-HLA500 pipeline; and the WKF platform is connected at the Conbit warehouse, with the
to the KFA platform by the WKF-KFA300 pipeline. client witnessing it.
CHALLENGES
Conbit was required to mobilise
the equipment in a very short
timeframe, which tested the
logistics team’s ability. With expert
planning and shipping of
equipment, Conbit could negotiate
this challenge.
BAD WEATHER
Conbit monitored the weather prior
and during operations as bad
weather was anticipated which had
the potential to limit access to the
platform and disrupt the overall
operation. The staffing schedule
had to be adjusted to ensure that
the work would be completed
before the weather impacted on
the operation and had to dismantle
Photo: Dismantling lift boom Photo: Preparation for rotating the equipment after the weather
new flare tip. had passed, three days later.
ENGINEERING
INSTALLATION
Client
Project Name
CHALLENGES
Conbit faced the unexpected
challenge of performing the
offshore lift to a supply vessel with
no dynamic positioning. This
impacted the timing and created
further challenges of keeping the
vessel level and finding the critical
moment for the touch-down. As a
Photo: Disconnecting the rigging line result, Conbit devised an action
from the load plan to minimise this impact.
ADDITIONAL SCOPE
Conbit were also tasked with
removing existing piping using
their lightweight rigging equipment
and changing out the elbow from
underneath the flare-tip, weighing
350kg. By remaining flexible and
adaptable, Conbit could easily take
on this additional scope for the
client.
We believe that in our business preparation is key. We prepare our projects so thoroughly that they
always run smoothly and efficiently. This is how we make a difference for our clients.
Our people are what make Conbit the leader in our field. For us, project preparation is all about
teamwork in an open and transparent atmosphere. We challenge ourselves to go beyond limiting
boundaries to find better and more creative solutions and to design, supply, install and maintain
projects perfectly, safely and on time. Our clients rely on us not only because of our strong team
that works with them in close consultation but also because we invest in the latest technologies and
equipment to meet their needs, so that they can excel in their industry.
With over 20 years of experience, we have a proven track record in special lifting and structural
engineering. Clients come to us for our full-service approach and our innovative customized
solutions. In preparing our projects so thoroughly we create a reliable, safe and sustainable base,
from which we have a powerful impact in our clients’ benefit.
Conbit
Steenoven 5, 5626 DK Eindhoven, The Netherlands, T: +31 40 711 45 05 E: [email protected]