Table 1. Project Activities and Duration Duration (Days)

The document provides a table outlining the activities, duration, and critical path for a construction project. It lists 14 activities with durations ranging from 0 to 18 days. It then shows 5 potential paths through the activities with total durations ranging from 67 to 92 days. The critical path with the longest duration of 92 days is highlighted.

Uploaded by

Arnold Apostol
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
71 views

Table 1. Project Activities and Duration Duration (Days)

The document provides a table outlining the activities, duration, and critical path for a construction project. It lists 14 activities with durations ranging from 0 to 18 days. It then shows 5 potential paths through the activities with total durations ranging from 67 to 92 days. The critical path with the longest duration of 92 days is highlighted.

Uploaded by

Arnold Apostol
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

Table 1.

Project Activities and Duration

Duration
Activity Description
(Days)
1-2 Preparatory Works 4
2-3 Excavation Works 5
3-4 Foundation Works 10
4-5 Column Structure Works 10
4-6 Sloof Works 4
6-7 Wall Layering and Frame Works 13
7-9 Dummy 0
5-8 Roof Truss (steel) Works 9
8-9 Roof (Ceiling And Tiles) Works 13
9-10 Sanitary Works and Electrical Installation 16
9-11 Plastering/ Moulding 18
10-11 Floor Works 12
Installation Works ( Lamps, Glass, Doors,
7-12 Windows, Switches, Outlets, Locks, Sanitation 18
and other Accessories)
11-13 Painting Works 7
12-13 Fencing Works 10
13-14 Finishing/ Complementary Works 6

Path Total Duration (days)


I 1-2-3-4-5-8-9-10-11-13-14 4+5+10+10+9+13+16+12+7+6 92days
II 1-2-3-4-5-8-9-11-13-14 4+5+10+10+9+13+18+7+6 82days
III 1-2-3-4-6-7-9-10-11-13-14 4+5+10+4+13+0+16+12+7+6 77days
IV 1-2-3-4-6-7-9-11-13-14 4+5+10+4+13+0+18+7+6 67days
V 1-2-3-4-6-7-12-13-14 4+5+10+4+13+18+10+6 70days

Note:
The path that was highlighted with dark blue show the critical path of
the network diagram.
Scheduling of Project with PERT/CPM

Duration Total Free


Activity Description ES EF LS LF
(Days) Float Float
1-2 Preparatory Works 4 0 4 0 4 0 0
2-3 Excavation Works 5 4 9 4 9 0 0
3-4 Foundation Works 10 9 19 9 19 0 0
Column Structure 19 29 19 29 0 0
4-5 10
Works
4-6 Sloof Works 4 19 23 41 45 22 0
Wall Layering and 23 36 45 58 22 0
6-7 13
Frame Works
7-9 Dummy 0 36 36 51 51 15 0
Roof Truss (steel) 29 38 29 38 0 0
5-8 9
Works
Roof (Ceiling And 38 51 38 51 0 0
8-9 13
Tiles) Works
Sanitary Works and 51 67 51 67 0 0
9-10 Electrical 16
Installation
Plastering/ 51 69 61 79 10 10
9-11 18
Moulding
10-11 Floor Works 12 67 79 67 79 0 0
Installation Works 36 54 58 76 22 0
(Lamps, Glass,
Doors, Windows,
7-12 Switches, Outlets, 18
Locks, Sanitation
and other
Accessories)
11-13 Painting Works 7 79 86 79 86 0 0
12-13 Fencing Works 10 54 64 76 86 22 22
Finishing/ 86 92 86 92 0 0
13-14 Complementary 6
Works
The Network Diagram
10

16
9 13
5 8 9 12

18
10
4 5 10 7 6
11 13 14
1 2 3 4

4
10

6 7 12
13 18
LEGEND

Dummy
Critical Path
Activity
Event
Probable Time Estimates
Probability
Z at 90
Expected Path V2 that it will
Path Activity a m b V2 days or
Time Total Path finish in
less
96 days
1-2-3-4-5-8-9-10-11-13-14 1-2 3 4 5 4 0.11
2-3 3 5 6 4 5/6 0.25
3-4 8 10 10 9 2/3 0.11
4-5 7 10 11 9 2/3 0.44
5-8 8 9 11 9 1/6 0.25
91.33 2.28 0.29 61%
8-9 11 13 14 12 5/6 0.25
9-10 15 16 18 16 1/6 0.25
10-11 11 12 13 12 0.11
11-13 6 7 9 7 1/6 0.25
13-14 4 6 7 5 5/6 0.25
1-2-3-4-5-8-9-11-13-14 1-2 3 4 5 4 0.11
2-3 3 5 6 4 5/6 0.25
3-4 8 10 10 9 2/3 0.11
4-5 7 10 11 9 2/3 0.44
5-8 8 9 11 9 1/6 81.17 0.25 2.36 4.59 100%
8-9 11 13 14 12 5/6 0.25
9-11 16 18 20 18 0.44
11-13 6 7 9 7 1/6 0.25
13-14 4 6 7 5 5/6 0.25
Probability
Z at 90
Expected Path V2 that it will
Path Activity a m b V2 days or
Time Total Path finish in
less
96 days
1-2-3-4-6-7-9-10-11-13-14 1_2 3 4 5 4 0.11
2_3 3 5 6 4 5/6 0.25
3_4 8 10 10 9 2/3 0.11
4_6 3 4 6 4 1/6 0.25
6_7 11 13 14 12 5/6 0.25
76.67 1.83 8.36 100%
7_9 0 0 0 0 0.00
9_10 15 16 18 16 1/6 0.25
10_11 11 12 13 12 0.11
11_13 6 7 9 7 1/6 0.25
13_14 4 6 7 5 5/6 0.25
1-2-3-4-6-7-9-11-13-14 1_2 3 4 5 4 0.11
2_3 3 5 6 4 5/6 0.25
3_4 8 10 10 9 2/3 0.11
4_6 3 4 6 4 1/6 0.25
6_7 11 13 14 12 5/6 66.50 0.25 1.92 13.30 100%
7_9 0 0 0 0 0.00
9_11 16 18 20 18 0.44
11_13 6 7 9 7 1/6 0.25
13_14 4 6 7 5 5/6 0.25
1-2-3-4-6-7-12-13-14 1_2 3 4 5 4 0.11
2_3 3 5 6 4 5/6 0.25
3_4 8 10 10 9 2/3 0.11
4_6 3 4 6 4 1/6 0.25
69.33 1.72 13.16 100%
6_7 11 13 14 12 5/6 0.25
7_12 16 18 19 17 5/6 0.25
12_13 9 10 12 10 1/6 0.25
13_14 4 6 7 5 5/6 0.25
Man Power Leveling

Duration
Activity Description No. of Men
(Days)
1-2 Preparatory Works 4 5
2-3 Excavation Works 5 7
3-4 Foundation Works 10 5
4-5 Column Structure Works 10 9
4-6 Sloof Works 4 5
Wall Layering and Frame
6-7 13 9
Works
7-9 Dummy 0 0
5-8 Roof Truss (steel) Works 9 6
Roof (Ceiling And Tiles)
8-9 13 5
Works
Sanitary Works and Electrical
9-10 16 6
Installation
9-11 Plastering/ Moulding 18 4
10-11 Floor Works 12 5
Installation Works (Lamps,
Glass, Doors, Windows,
7-12 Switches, Outlets, Locks, 18 9
Sanitation and other
Accessories)
11-13 Painting Works 7 7
12-13 Fencing Works 10 7
Finishing/ Complementary
13-14 6 4
Works
Calculating Man Power Labor Cost
Note:
The assumed daily rate is is Php. 300.00/ day/ men
From:

1-4 days 5 men x 4 days 20 men - days


4-9 days 7 men x 5 days 35 men - days
9-19 days 5 men x 10 days 50 men - days
19-23 days 4 men x 13 days 52 men - days
23-29 days 18 men x 6 days 108 men - days
29-36 days 15 men x 7 days 105 men - days
36-51 days 14 men x 15 days 210 men - days
51-54 days 19 men x 3 days 57 men - days
54-64 days 15 men x 10 days 150 men - days
64-67 days 10 men x 3 days 30 men - days
67-69 days 9 men x 2 days 18 men - days
69-79 days 5 men x 10 days 50 men - days
79-86 days 7 men x 7 days 49 men - days
86-92 days 4 men x 6 days 24 men - days
TOTAL 958 men - days

The Average Mean Daily in a Project:


958/92 = 10.41 say 11 men/day
Total Man Power Labor Cost:
958 men – days x Php. 300.00/ day/ men
= Php. 287, 400.00