Operating Check List For Disel Generator: Date: Time

The document provides a checklist for operating a diesel generator with 25 steps. It includes checking that no work permits or personnel are in the area, ensuring doors and protections are properly configured, measuring power cable insulation, checking fuel levels and filter conditions, ensuring proper pressure and voltages, and verifying breaker states before declaring the system ready for operation. Safety, equipment status, and electrical configurations are all validated as part of the process.

Uploaded by

Ashfaq Bilwar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
160 views2 pages

Operating Check List For Disel Generator: Date: Time

The document provides a checklist for operating a diesel generator with 25 steps. It includes checking that no work permits or personnel are in the area, ensuring doors and protections are properly configured, measuring power cable insulation, checking fuel levels and filter conditions, ensuring proper pressure and voltages, and verifying breaker states before declaring the system ready for operation. Safety, equipment status, and electrical configurations are all validated as part of the process.

Uploaded by

Ashfaq Bilwar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

OPERATING CHECK LIST FOR DISEL GENERATOR

DATE: TIME :
EQUIPMENT TAG NO : SHIFT :
DG NO :

S.no Activity Description BASIS Result Remarks


OK/NOT OK

1 Ensure no PTW is pending on the equipment.


2 Ensure no person is working on the equipment.
4 Ensure all doors in closed condition.
5 Measure the power cable individual phase-earth
insulation resistance (with 500V/ insulation
tester). All the three reading shall be > 1.5
Mohms.
6 Ensure all logics and protections are in service.
7 Ensure module 560 auto/manual key selector
switch in auto.
8 Ensure generator breaker panel DSE 7520
auto/manual soft selector switch in auto.
9 Ensure all control MCB and battery power
supply is in service.
10 Ensure safety part breaker panel MD32-G
protection relay is in service.
11 Check fuel oil Level (Total capacity :999.9 Ltr) Middle
12 Check air filter condition. Clean
13 Check no alarm in panel. No alarm
14 Check DG local panel start Selection in remote. Loc/Rem
15 Check DG syn panel start selection in remote. Loc/Rem
16 Check Lube Oil pressure. >200kPa
17 Check battery voltage . 24V DC
17 Check battery condition / level Clean / up to
mark
18 Check coolant level Normal

19 Check fuel inlet and outlet valves are in open condition. Open / close

20 Check DG-1 breaker (1CB) is in open condition. Open / close

21 Check DG-1 breaker (3CB) is in open condition. Open / close


22 Check EMG MCC-1 incomer #1 breaker (3CB-1) is in Open / close
closed condition.
23 Check EMG MCC-1 incomer #2 breaker (2ZKK) is in

1
closed condition.
24 Check EMG MCC-1 bus coupler breaker (3ZKK) is in
closed condition.
25 Ensure all above points are satisfied, system is ready
for operation.

Witnessed By :

KSK Engineer KPS Engineer