Ms Project Basic Guide Part 1 - Scheduling
Ms Project Basic Guide Part 1 - Scheduling
2019/8/10
What is Microsoft Project?
Microsoft Project (or MSP) is a project
management software program
It is designed to assist project managers in:
•developing plans
•assigning resources to tasks
•tracking progress
•managing budgets
•analyzing workloads
2019/8/10
Simple scheduling basics
Start a new plan
Build a task list
Set up resources
Assign resources to tasks
Format and share your plan
Track progress: Basic techniques
2019/8/10
MAJOR PARTS OF MSP
2019/8/10
MAJOR PARTS OF MSP
2019/8/10
Start a new plan
Create a new plan and set its start date
Set nonworking days in the project calendar
Tip
In the calendar, you can use the left and right arrows to navigate to any month and
then click the date you want, or click Today to quickly choose the current date.
3. Click OK to accept the start date and close the Project Information dialog box.
2019/8/10
Set nonworking days in the project calendar
Calendars are the primary means by which you control when each task
and resource can be scheduled for work in Project., you will work with
other types of calendars; in this PPT, we focus on the project calendar.
PROJECT
INFORMATION
CALENDAR
OK
The Calendar list contains the three base calendars that are included with
Project: 1. 24 Hours Has no nonworking time 2. Night Shift Covers a late-
night “graveyard” shift schedule of Monday night through Saturday
morning, 11:00 P.M. to 8:00 A.M., with a one-hour break each day
3. Standard The traditional working day and week, Monday through Friday
from 8:00 A.M. to 5:00 P.M., with a one-hour break each day
2019/8/10
CHANGES IN CALENDAR
You customize calendars in the Change Working Time dialog box (which
opens when you click the Change Working Time button on the Project tab).
2019/8/10
TO MAKE CHANGES IN THE WORKING TIME
CHANGE WORKING TIME
WORK WEEKS
DETAILS
Use as per Project
2019/8/10
BUILD A TASK LIST
Create tasks
Enter task durations and dates
Enter milestone tasks
Create summary tasks to outline the plan
Link tasks to create dependencies
Switch task scheduling from manual to
automatic
Check a plan’s duration and finish date
Document task information
Tasks are the most basic building blocks of any project’s plan. Tasks represent the work to
be done to accomplish the goals of the project. Tasks describe work in terms of
dependencies, duration, and resource requirements. These include summary tasks,
subtasks, and milestones More broadly, what are called tasks in Project are sometimes more
generally called activities or work packages
creating tasks, entering task durations and dates, entering milestone tasks, creating
summary tasks, linking tasks to create dependencies, switching task scheduling from manual
to automatic, checking a plan’s duration and finish date, and documenting task information.
2019/8/10
CREATE TASKS
Every task in Project has one of two scheduling modes that controls how the task is scheduled: manual (the
default) or automatically scheduled. Think of a manually scheduled task as an initial placeholder you can create at
any time without affecting the rest of the schedule. You might not know more than a task name to start with, and
that’s OK. As you discover or decide more details about the task, such as when it should occur, you can add those
details to the plan. You’ll work with automatic scheduling in “Switch task scheduling from manual to automatic”
2019/8/10
To schedule a task to span nonworking and working times with an elapsed
duration
1. When entering the task’s duration, precede the duration abbreviation with an e. For
example, enter 1ed to indicate one full 24-hour day, or 1ew to equal seven 24-hour
days, or 1emo to equal thirty 24-hour days.
To calculate the duration of a manually scheduled task
1. In the Start and Finish fields for the task, enter or select the start date and finish
date values you want.
Project calculates the Duration value. Note that when the task gets switched to be
automatically scheduled, the start and finish values might change based on
predecessor relationships, the project start date, or other scheduling factors. The
duration value, however, will be preserved
2019/8/10
To mark a task of any duration as a milestone
1. Select a task name.
2. On the Task tab, in the Properties group, click Information.
3. In the Task Information dialog box, click Advanced.
4. Select the Mark Task As Milestone check box.
2019/8/10
Link tasks to create dependencies
When you link tasks, you create scheduling relationships between the tasks. These task
relationships are called dependencies, as in the start of this task is dependent upon the
completion of a prior task. When you create task dependencies (also called links),
Project
can automatically adjust the scheduling of linked tasks as changes occur in your plan.
Creating dependencies by linking tasks is crucial to getting the full benefit of the Project
scheduling engine.
predecessor tasks.
Although this might sound complicated, two tasks can have one of only four types of
task
relationships, as described in the following table.
To link tasks
1. Select the names of the tasks you want to link. If the tasks are not adjacent, select
the first task, hold down the Ctrl key, and then select the additional task or tasks.
2. On the Task tab, in the Schedule group, click the Link the Selected Tasks button
(which looks like two chain links).
Project links the tasks with a finish-to-start relationship.
2019/8/10
2019/8/10
BEFORE LINK
AFTER LINK
2019/8/10
1. In the Predecessors field for the successor task, enter the predecessor task’s ID.
You might have to scroll the table to the right to display the Predecessor column.
Or
1. Select the task for which you want to specify a predecessor task or multiple
predecessor tasks.
2. On the Task tab, in the Properties group, click the Information button.
3. On the Predecessors tab of the Task Information dialog box, enter the ID value or
select or enter the task name of the predecessor task you want, and then click OK.
2019/8/10
THANK YOU
2019/8/10