Commissioning Training v1
Commissioning Training v1
COMMISSIONING
Part 2: Planning
1. Risk Assessment
Hazard and Operability Analysis (HAZOP)
2. System Definition
-The pre-commissioning and commissioning of the plant will be carried out on a system by system
and unit by unit basis. Therefore, each unit is divided into logical process and/or piping and
equipment systems or subsystems.
P&ID Master Set
-Mark the different systems with different colors. Be sure that you are using the latest revision.
3. Completion Prioritization
-This means you have to think about the right order for commissioning of the systems.
According Start-Up Sequence
4. Software
-You have to consider which software tools you will use to recall your commissioning progress and
to capture your test results.
Integrated Commissioning & Progress Systems (ICAPS)
-Specialized software tool for commissioning. It has been developed by TOTAL. It manages
preparation, execution and monitoring of all pre-commissioning and commissioning activities
as per OPERCOM specifications.
5. Documents
-Should be prepared before the commissioning team will be on site.
Time Schedule
Organizational Chart
Checklist
Operating Manual
Pre-commissioning Procedures
Commissioning Procedures
Safety Procedures
Quality Control Procedures
Security Procedures
Emergency Response Procedures
Status Progress Reporting
Test Records
Punch List Template
6. Manpower
-Includes:
Pre-commissioning Team
Commissioning Team
Operating Team
Maintenance Team
Client’s Team
Contractors
Vendors
Licensors
Support from Office
7. Material
-It is important to plan the materials needed during pre-commissioning and commissioning in
advance. Includes, for example:
Blinds
Spool Pieces
Hoses
Additional Gaskets
Sample Bottles
8. Equipment
-It depends on the type of the plant you want to commission which additional equipment will be
needed. For example:
Steam Blowing Equipment
9. Tools
Tool Kits
10.OPERCOMTM
-This is a methodology developed by TOTAL and tailored to the oil and gas industry. The main
objectives of OPERCOM include safety, planning, confidence, efficiency, consistency and economy.
Part 5: Pre-Commissioning
1. What is Pre-Commissioning?
The term pre-commissioning is used for activities after construction completion, such as
cleaning, catalyst loading, dry-runs and checks within the systems in order to prepare these
items/systems for the next step – commissioning.
Pre-commissioning activities can be done after or as well before mechanical completion (MC).
API Recommended Practice 1FSC
“Group of energized and static test that constitute verification that the equipment or
component is fabricated, installed, cleaned, and tested in accordance with the design
and ready for commissioning”
Also: “static commissioning”
2. Pre-Commissioning Activities
-Examples are:
Flushing, Blowing and Drying Activities
Chemical Cleaning
Final Inspection and Closing of Vessels and Tanks
Final reinstatement of System of Sub-systems
Air Tightness “Leak” Testing of Systems
Lubricants Application
Pre-commissioning “Run-In” of Major Rotating Equipment and Electrical Motors
Installation of Filters
Packing of Distillation Columns
Loading of catalyst and molecular sieve beds
Refractory dry-out
Vendor and Factory Acceptance Testing
Instrument, Electrical and Motor Loop Testing
Punch Listing
3. Pre-Commissioning Sequence
-Example:
1. Power and control system (electrical sub-stations)
2. Building power, HVAC, fire & gas protection
3. DCS and PLC systems and instrumentation
4. Raw water and firefighting systems
5. Waste water treatment system
6. Oily sewer / clean sewer systems and chemical sewer & neutralization pits
7. Service water / potable water / cooling water systems
8. Instrument air / plant air and regeneration air systems
9. Water treatment systems, demineralization units and boiler water system
10. Nitrogen System
11. Flare System
12. Plant safety equipment and fire & gas detection
13. Fuel gas and fuel oil system
14. Slop System
15. Flushing oil system
16. Boiler System with steam & condensate networks
17. Amine, aromatics and caustic drain system
18. Feed & product storage systems
19. Product feed system
20. Sour water treatment section and chemical handling treatment section
21. Amine treatment section
22. All process system in order of “priority”
4. Pre-Commissioning Procedures
-Example:
1. Spectacle blind installation checks (Note: All slip blinds or spectacle plates utilized must be given
a suitable tail or handle so immediate identification can be made in the field)
2. Non-return valve internals installation checks
3. Thermal refractory lining installation checks
4. Mechanical interlock checks
5. Fitting of all locks on the valves
6. Packing of a distillation or scrubbing column
7. Packing a reactor with catalyst
8. Installation of filter medium and cartridges
9. Air blowing
10. Steam blowing
11. Water flushing
12. Chemical cleaning
13. Tightness test
14. Cooling water passivation
15. Mechanical test run of pumps
5. Pre-Commissioning Checklists
Many different checklists for different types of equipment
To record the inspection and status of equipment items within the plant
To conform readiness for commissioning
Often to be witnessed by client, PMC & licensor
6. Pre-Commissioning Test Records
-Pre-commissioning activity test records are prepared to record the satisfactory completion of
various systems preparation task & activities. Like:
Cleaning
Chemical cleaning
Drying
Air tightness test
Loading of catalysts
Blinds list
Performance indicators
-Includes:
Construction QA/QC documentation
System punch list (commissioning punch)
Piping pre-commissioning activities
Stationary equipment pre-commissioning activities
Rotating equipment pre-commissioning activities
Instrumentation pre-commissioning activities
Tightness test
Reporting (we can count the total, completed and remaining task which should have be
done)
7. Pre-Commissioning Additional Records
-Example:
Request for mechanical completion acceptance
Mechanical completion certificate
Release for pre-commissioning notice
Punch list report of outstanding punch points
8. Vendor Specialist
-Used in:
For major items of rotating machinery, major utility systems and special electrical and
instrument control equipment
Package units
9. Licensor
-Will do the:
Final inspection of “critical” equipment installation
Supervision of catalyst and chemical loading
10. Ready for Commissioning (RFC)
-This means:
Pre-commissioning activities are completed, and the systems are ready to commence
commissioning
According to API Recommended Practice 1FSC, “Minor milestone in project when pre-
commissioning activities for a discipline (electrical, instrumentation, mechanical, piping, etc.) are
essentially complete and ready to commence commissioning.”
Protocol
Part 6: Commissioning
1. What is Commissioning?
It is usually the phase in a project after pre-commissioning when design process fluids are
introduced to the systems and sub-systems. Sometimes commissioning means running the
systems with a safe fluid only.
Commissioning moves the project from the “end of the construction” closed to the “commercial
operation” status.
API Recommended Practice 1FSC
“Group of energized and dynamic tests that constitute verification that each system or
sub-system is fabricated, installed, cleaned, and tested in accordance with design and
the systems are ready for start-up.”
A complete, well-planned and accurately documented commissioning effort is one of
the key factors that contribute to a trouble-free start-up (the next step).
2. Grey Area
Cold Commissioning
Dry Commissioning
Tests and procedures that are conducted without solvents or process fluids yet
introduced to the plant.
Sometimes already done during pre-commissioning
Example activities
Interlock and emergency shut-down tests
Control system sequence checks
Wet Commissioning
Water or a solvent has been introduced into the systems or sub-systems.
Tests and procedures conducted with water or solvent.
“Operating scenarios”
Example activities
Running pumps with closed loops
Interlock and emergency shut-down tests
Hot Commissioning
Synonym “Live Commissioning
Design process fluids are introduced to the systems and sub-systems
Activities similar to “Wet Commissioning”
3. RFC
Milestone “Ready For Commissioning”
Pre-commissioning activities are completed and the systems are ready to commence
commissioning
Protocol
API Recommended Practice 1FSC
“Minor milestone in project when pre-commissioning activities for a discipline
(electrical, instrumentation, mechanical, piping, etc.) are essentially complete and ready
to commence commissioning”
4. Safety
PTW
Permit to work system adequate?
Security
“Fencing” of facilities, access control, protection from on-going construction areas, etc.
Emergency response
These procedures must be in place, commissioning staff trained in their role in such
procedures and “practice drills” held to confirm effectiveness.
5. Common Activities
Functional checks
Operating adjustment
Final leak testing
Final drying
Purging / inerting
First fills
Operation of systems and sub-systems
Completion of system turnover and completion package
6. Sequence
Commissioning of the facilities will be carried out on a “system-by-system” and “unit-by-unit”
basis.
Utilize a “backwards” approach
Control system, DCS, PLC
Utilities (air, nitrogen, water, steam)
Product storage, tank systems and loading
Core process units (reaction, distillation)
Raw materials feeds
Raw materials storage
7. Commissioning Procedures
Utilities and services
Water or solvent commissioning – For each system
Process fluid commissioning – For each system
8. Interfaces (“real” example)
Operations and maintenance
By company
“Hands-on” activities for commissioning (and start-up, operation and
performance test) of the plant under the direction, advise and supervision of
the contractor’s commissioning staff, but directly coordinated/supervised by
company’s commissioning staff.
Product Quality Control
By Company
Performing product quality control laboratory analysis for the new facilities
under the supervision of the contractor during the commissioning and
performance test phase
Production Planning
By company and contractor
Company’s production planning for the existing facilities and contractor’s
production plan for the commissioning and operation of the new facilities must
be integrated during the commissioning, start-up and initial operation phase.
This commences with first requirements for fuel gas, etc. from the existing plant
for boilers start-up and heaters dry-out through initial feedstock transfer and
final product storage, blending and shipping.
Emergency Response, Security, Safety
By company and contractor
Contractor’s emergency response plan for commissioning will require the
support of company and company’s local facilities/services
The new plant will be integrated with the existing facilities at commissioning
and start-up. Security of the new facilities requires coordination with the
existing.
Operations safety procedures and permit system for the new facilities must be
coordinated with the existing facilities from initial commissioning and start-up.
Maintenance Support
By company
Company will perform “hands-on” duties and give technical support during
commissioning and start-up for routine maintenance activities and checks. Such
work will be coordinated with company’s maintenance team.
Vendors
By contractor
All commissioning activities by contractor’s vendor specialist will be carried out
under the supervision of contractor’s commissioning team.
Licensor
Where necessary, the process licensor may supervise the commissioning of relevant
systems and provide technical assistance.
Process operating parameters and conditions will be advised by process licensor’s
process engineers.
9. PSSR
Pre-Start-Up Safety Review
Usually by systems
Usually managed by commissioning manager
Client commissioning team
Contractor commissioning team
Licensor
10. RFSU
Milestone “Ready For Start-Up”
API Recommended practice 1FSC
Signifies that system construction, pre-commissioning, and commissioning work are
complete and the required safety verification is ready to commerce start-up.
Protocol
Part 7: Start-Up
1. What is Start – Up?
The phase in a project where the entire plant (all systems and sub-systems) are taken into
operation. Process fluids are introduced and process conditions are established with the intent
of making products.
2. RFSU
3. Shift Works
Client
Contactor
Vendors
Licensor
Who?
How?
What?
Paper or electronically?
Client and / or contractor?
5. PSSR
6. Pre-Start-Up Checks
7. Start-Up Procedures
The entire plant is running in continuous operation, fine-tuned and prepared for the
performance test.
2. Shift Works
Client
Contractor
Vendors
Licensor
3. Shift Log Book
Hopefully already set-up during start-up phase
Who?
How?
What?
Paper or electronically?
Client and / or contractor?
4. Activities
Fine tuning of control loops
Tuning of process
Testing of operating limits
Emergency shut down?
Preparation of performance test
Data collection
Equipment data
Process data
Performance data
5. Interface (“real” example)
Operations and Maintenance
By company
“hands-on” activities
Product Quality Control
By company
product quality control laboratory analysis
Production Planning
By company and contractor
Emergency Response, Security, Safety
By company and contractor
Maintenance Support
By company
“hands-on” duties and technical support
Vendors
By contractor
Licensor
Where necessary, the process licensor may supervise the start-up of relevant system
and provide technical assistance.
Process operating parameters and condition will be advised by process licensor’s
process engineers.
6. Performance Testing
Mutual agreement between client, contractor and licensor
The phase starting after handling over the plant to the client (FAC) – until operations assistance
is not needed anymore and the outstanding punch points are solved.
2. Activities
Adjustments, modifications and fault correction
Completion of outstanding punch list items
The first routine maintenance checks are performed, findings evaluated and reported
Process equipment and items covered by warranty are observed for possible problems
Operating data is collected and evaluated to ensure consistent plant operations are maintained
3. Interfaces
Contractor
Solving of outstanding punch points
Usually, at the beginning a few experienced commissioning engineers from the “old”
crew
Later usually just one
He or she is the first contact person for thee client in the daily routine
Usually, just in a day shift
Company
Production Planning
Operations
Maintenance
Product Quality Control
Emergency response, Security, Safety
Vendors
By Company
For repair works
Licensor
Where necessary, the process licensor may supervise the operation of relevant systems
and provide technical assistance
4. Duration
Varies from plant to plant and industry to industry
From a couple of months till years (yes, really)