14 Commissioning Procedure
14 Commissioning Procedure
STVV017/B
GARBARINO S.p.A. ISTRUZIONE OPERATIVA
Pompe centrifughe Pag. 1/2
COMMISSIONING PROCEDURE
Centrifugal pumps
Before pump start up check that all indications given in the Instruction Manual, in the general
arrangement drawing and in the other technical documentation have been duly observed.
A. CHECKS
1. Visual check of the pump unit. Check if all the external screws are securely tight (baseplate anchor bolts, pump/motor jacking
screws, coupling guard screws, etc). Baseplate must be correctly installed, without any distortion/tension due to the anchor bolts
tightening.
2. Check connections of pump nozzles to delivery pipe.
3. Check presence of pressure gauge on the delivery and suction side of pump. Pressure gauges are important to check pump
performance during running.
4. Check electrical connections of the motor and cable glands tightening
5. Check by hand free rotation of the shaft after coupling guard removing. Coupling guard must be replaced before pump starting.
6. Check coupling alignment. Coupling guard must be replaced before pump starting.
7. Check that all protections of rotating units be properly and securely installed.
8. In case of oil lubrication:
• Check oil level through sight-glass or constant level oil. In case fill with oil to have correct level. Refer to Instruction Manual for
the oil type.
9. In case of grease lubrication:
• Insert grease through nipples. If nipples are not present, bearings are life-lubricated type. Refer to Instruction Manual for
grease type.
10. If external flushing for mechanical seal/packing is required:
• Check if flushing line is properly installed
11. If heat exchanger for mechanical seal is installed:
• Check if cooling lines in/out are properly installed
B. START UP
12. Make sure plant and operators are ready for the start up
13. If external flushing is required: open flushing line valve and make sure flow is present.
14. If heat exchanger is installed: open cooling lines.
15. Open suction and delivery valve to fill pipe and pump.
16. Vent pump by mean the proper valve on delivery pipe (if installed) or loosing the pressure gauge connection screw. For vertical
pumps, vent also the top side of the casing whit the valve installed on cover
17. Close delivery valve.
18. Switch the motor briefly on and off and check if the rotation is correct with the direction arrow (CW-clockwise from fan view).
19. Start the pump up
20. Check the pressure gauge to see when the pressure becomes stable. If pressure does not increase, stop the pump and repeat the
start-up after some minutes.
21. Open delivery valve to regulate pump head.
COMMISSIONING PROCEDURE
Centrifugal pumps