Note On Project Time Management
Note On Project Time Management
Project time management includes the following processes required to ensure timely completion
of the project
i. Activity Definition: identifying the specific activities that must be performed to produce the
various project deliverables.
iii. Activity Duration Estimation: estimating the number of work periods, which will be needed
to complete individual activities
iv. Schedule Development: analyzing activity sequences, activity durations and resource
requirements to create the project schedule
ACTIVITY DEFINITION
Activity definition involves identifying and documenting the activities that are required to
be performed to produce the deliverables to meet the project objectives.
The major tool for activity definition is project WORK BREAKDOWN STRUCTURE
WBS is a task oriented family tree of activities that organize, define and display the work
to be accomplished.
WBS is the picture of the project subdivided into hierarchical units of work. At the
highest level of hierarchy project is shown. In the next level project major subdivisions
are shown. Each major subdivision is further subdivided into additional levels, as
required to identify in sufficient detail all the works involved in the project
WBS identifies the entirety( total Scope) of work involved in the project and establishes
a hierarchy of works to be accomplished for a project completion
Formation of WBS is done by subdividing the project into successively smaller work
elements until the lowest level to be controlled is reached
For each of the work elements of WBS, cost and budgets and schedule can be
established and responsibility assigned to specific project personnel
PROJECT WBS LEVELS
Project WBS are broadly divided into five levels arranged in a descending hierarchical order
Sub-project level
Task level
Work package level
Activity level
Operations level
Sub projects- are groups of major works which can be carried out independently without
interference from other works
Tasks- are subdivisions of sub-projects. Tasks are identifiable and deliverables of major work
Work Packages are subdivisions of tasks. Each work package contains a sizeable,
identifiable, measurable, cost and controllable package of work. The methodology of
execution of work package is called method statement
Activities are subdivisions of work packages and consume time and total resources
(workforce, material and equipments). Activities can be subdivided into sub activities
Operations are work content of the activities. One of more operations are required for the
completion of the activity. Operations are usually not considered in the network modeling
and analysis.
WBS provides a detailed illustration of Project Scope and hence defines the total project
Scope. Work not included in WBS is outside the project scope
WBS helps to track the schedule and monitor the time performance
WBS items are assigned under unique identifiers called account codes.
Outputs from WBS are
ACTIVITY SEQUENCING
The process of activity sequencing involves identifying and documenting the dependencies(logical
relationships) between the individual activities.
Mandatory dependencies
physical dependencies necessarily to be followed from technical considerations.
Discretionary dependencies
selecting a particular dependency where in alternate sequences are available.
External dependencies
Execution of the activity depends on certain preparatory processes or constraints which are
not part of the construction activity.
There are four types of logical relationships (or dependency links) that may exist between the
activities.
The logical relationships could be incorporated with lags and leads to obtain overlapping
relationships between the activities.
Lag is the certain amount of delay for successor activity with respect to predecessor activity
Lead means acceleration of successor activity with respect to predecessor activity.
A
Activity A must complete before start of B
B
Activity B must complete before start of C
It is always not possible to use FS relationships and same amount of paralleling of activities
or incorporation of constraints is required with the use of lags/leads in relationships.
A
( FS + X days )
B
( FS +X days ) X
Finish to start with X days of lag. Successor Activity B must start X days after completion of
predecessor activity A.
Example: Deshuttering of slab form work to be done after 7 days to gain strength. Here lag
is used to incorporate a constraint.
(FS-X days)
B
The start of the successor Activity B depends upon the start of predecessor Activity A.
A ( SS + X days )
B
X
Successor Activity B can start after X days of start of predecessor activity A
Example: In the construction of sewer line, after certain length of trench excavation the
placement of base concrete for the sewer pipe can be started.
The completion of the successor activity depends upon the finishing of the predecessor
activity A.
The activity A must complete before activity B can finish.
Activity A and Activity B must complete at same time.
AA
(FF + X days)
The successor activity B can be completed after X-days of completion of predecessor Activity A
Example: commissioning of equipment /plant can be completed after X days of Testing /Trial
run activity.
(SF + X days)
B
Start of activity A can be with a lag of X-days with respect to the finishing of Activity B
Activity sequencing shall be done in such a way that start of every activity has a logical
relationship to a predecessor and finish of every activity has a logical relationship to a
successor activity.( Except the first activity and the last activity which will not have
predecessor and successor respectively)
An activity shall be totally completed or partially completed to enable another activity
to start.
FS ( Finish to Start ) is most commonly used relationship. However to enable to
incorporate certain amount of parallelism or to incorporate constraints, overlapping
relationships can be done with the use of lags or leads along with the relationships.
Nodes with no arrow entering to the left indicate beginning activity of the project. They
have no preceding activity
Nodes with no arrows leaving from the right indicate finishing activity of the project. They
have no succeeding activity.
The position of node in PDM network is not related time in which the activity takes place.
Network is not drawn to any time scale.
REPRESENTATION OF NODE
Activity ID number
Activity Description
Activity Duration
Float
Concept of Early Start and finish and Late Start and Finish Times in PDM
An activity early start time is the earliest time it can begin based on the early
completions of the preceding activities
For activities that begin at the start project which have no predecessors, early start time
is assigned zero. For all other activities, the early start time is the latest early finish time
of its immediate predecessor activities because all the predecessor activities must be
completed before activity under consideration can be started
For beginning activities: ES = 0
For other activities: ES= Max of early finishes of all immediate predecessors
The process of calculation of early start and early finish of all the activities with the
indicated activity sequence and considering the estimated durations of the activities is
called FORWARD PASS calculations.
The result of this calculation is the determination of ES and EF of the individual activities
and the total project duration
The calculations called ‘ Backward Pass’ is done to determine the activity’s late start and
late finish times, without exceeding the project duration, obtained in the Forward Pass
calculations
The Backward Pass calculations are done beginning at the end activity of the project
o Late Finish time (LF)
o For finish activities: LF= Early Finish Time
o For other activities: LF = Minimum of late starts of all immediate successors
Esj =EFj- Dj
Efj = ESj + Dj
LFj = LSj + Dj
= ESj + Dj
For all the activities, establish early start (ES) and early finish (EF) through Forward Pass and
Late Start (LS) and Late Finish (LF) through Backward Pass calculations
Examination of each of the activity’s early start and Late start would indicate the following
situations
Difference Late Start Time and Early Start time (or Late Finish Time and Early finish time) is
called the Slack Time of the Activity or Float time of activity.
The amount of slack time available indicates the extent of the time criticality of the activity.
Activities with no slack time are called critical activities and any delay of such activities will
cause slippage in the planned project duration.
Activities with slack time are called non- critical activities and they can slip their early start
times equal to their slack time without causing slippage (extension) of total project
duration. However criticality depends upon the amount of slack and same activity could be
near critical.
The path along the network connecting the critical activities is called critical path and it is
the longest path of activities in the network. Slack times are not additive along the path and
is specific to the concerned activity .
PDM for Bored Cast In Situ Piling Work
ACTIVITY PREDECESSOR
ID ACTIVITY DESCRIPTION DURATION ACTIVITIES
1 Installing concrete batching plant 4 -
2 Mobilise and install piling rig 3 -
3 Make pile bores 2 2
4 Arrange reinforcement steel 2 -
5 Set reinforcement fabrication yard 1 -
6 Fabricate pile reinforcement 1 4,5
Place pile reinforcement and tremmie
7 concreting 1 1,3,6
8 Prepare pile test setup 14 7
9 Pile testing and dismantle test setup 4 8
10 Place pile cap shuttering 1 9
11 Place pile cap reinforcement 1 10
12 Cast Pile Cap 1 11
FS= 0 FS= 0
Install Concrete Place rft cage and Prepare Pile
1 Batching Plant FS= 0 7 tremmie concreting 8 test setup
4d FS= 0 1d 14d
FS= 0
FS= 0 FS= 0
mobilise and Make Pile bores Pile Testing and Place Pile Cap
2 install piling rig 3 9 dismantle test setup 10 Shuttering
3d 2d 4d 1d
FS= 0
FS= 0
Arrange Rft Steel FS= 0 Place Pile Cap Cast Pile Cap
4 11 Reinforcement 12
2d 1d 1d
Fabricate Rft
6 Cages
1d
Set Rft
5 fabrication yard
1d FS= 0
CALCULATION OF EARLY START AND EARLY FINISH BY FORWARD PASS
FS= 0 FS= 0
0 Install Concrete 4 FS= 0 5 Place rft cage and 6 6 Prepare Pile 20
1 Batching Plant 7 tremmie concreting 8 test setup
4d FS= 0 1d 14d
FS= 0
FS= 0 FS= 0
0 mobilise and 3 3 Make Pile bores 5 20 Pile Testing and 24 24 Place Pile Cap 25
2 install piling rig 3 9 dismantle test setup 10 Shuttering
3d 2d 4d 1d
FS= 0
FS= 0
0 Arrange Rft Steel 2 FS= 0 25 Place Pile Cap 26 26 Cast Pile Cap 27
4 11 Reinforcement 12
2d 1d 1d
2 Fabricate Rft 3
6 Cages
1d
0 Set Rft 1
5 fabrication yard
1d FS= 0
FS= 0 FS= 0
0 Install Concrete 4 FS= 0 5 Place rft cage and 6 6 Prepare Pile 20
1 Batching Plant 7 tremmie concreting 8 test setup
1 4d 5 FS= 0 5 1d 6 6 14d 20
FS= 0
FS= 0 FS= 0
0 mobilise and 3 3 Make Pile bores 5 20 Pile Testing and 24 24 Place Pile Cap 25
2 install piling rig 3 9 dismantle test setup 10 Shuttering
0 3d 3 3 2d 5 20 4d 24 24 1d 25
FS= 0
FS= 0
0 Arrange Rft Steel 2 FS= 0 25 Place Pile Cap 26 26 Cast Pile Cap 27
4 11 Reinforcement 12
2 2d 4 25 1d 26 26 1d 27
2 Fabricate Rft 3
6 Cages
4 1d 5
0 Set Rft 1
5 fabrication yard
3 1d 4 FS= 0
CRITICAL PATH AND CRITICAL ACTIVITIES
FS= 0 FS= 0
0 Install Concrete 4 FS= 0 5 Place rft cage and 6 6 Prepare Pile 20
1 Batching Plant 7 tremmie concreting 8 test setup
1 4d 5 FS= 0 5 1d 6 6 14d 20
FS= 0
FS= 0 FS= 0
0 mobilise and 3 3 Make Pile bores 5 20 Pile Testing and 24 24 Place Pile Cap 25
2 install piling rig 3 9 dismantle test setup 10 Shuttering
0 3d 3 3 2d 5 20 4d 24 24 1d 25
FS= 0
FS= 0
0 Arrange Rft Steel 2 FS= 0 25 Place Pile Cap 26 26 Cast Pile Cap 27
4 11 Reinforcement 12
2 2d 4 25 1d 26 26 1d 27
2 Fabricate Rft 3
6 Cages
4 1d 5
0 Set Rft 1
5 fabrication yard
3 1d 4 FS= 0
AA
B
B