This document provides a description and design specifications for a pre-engineered building expansion to accommodate additional crane beams. The expansion adds 5 new bays that are 106m wide and 30m long on either end of an existing building. The building will have 12m clear height and steel framing with galvalume sheeting on the side walls. The design considers wind, seismic, and crane loading based on applicable codes. The bill of materials lists the tonnage of steel required for the main frames, crane beams, bracing, purlins, sheeting and other components.

Uploaded by

Zankar R Parikh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
411 views2 pages

Boq Q19 021 118 F

This document provides a description and design specifications for a pre-engineered building expansion to accommodate additional crane beams. The expansion adds 5 new bays that are 106m wide and 30m long on either end of an existing building. The building will have 12m clear height and steel framing with galvalume sheeting on the side walls. The design considers wind, seismic, and crane loading based on applicable codes. The bill of materials lists the tonnage of steel required for the main frames, crane beams, bracing, purlins, sheeting and other components.

Uploaded by

Zankar R Parikh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

MB

PRE-ENGINEERED BUILDING FOR M/s. XXXX CRANE BEAM EXPANSION---R0

BUILDING DESCRIPTION
BUILDING TYPE BAY-01 TO BAY-05 CRANE EXPANSION
BUILDING LOCATION HYDERABAD
WIDTH C/C (m) 106.00
LENGTH C/C (m) 60.00 ( 30m ON EITHER END OF EXISTING BUILDING )
CLEAR HEIGHT (m) 12.00
MAIN FRAME COLUMN SPACING (m) 5 @ 20
BAY SPACING (m) C/C BAY-01: [email protected] + 5.5 + 2@6, BAY-02-05: 5.5 + 2@6 + [email protected]
END WALL COLUMN SPACING (m) C/C 5 @ 20

WALL CONDITION FULLY SHEETED FOR 12m HT ( Along Sidewalls only )


SHEETING - ROOF 0
CLADDING - WALL single skin Galvalume 26Ga pre painted
8 No(s). DOUBLE GIRDER WITH 10 TON CAPACITY, 20 m SPAN, 60 m TRAVELLING LENGTH AND 9.2 m TOP
Crane Type 1 ( 2 No.S IN EACH BAY ) - BAY-01
OF Cr. BRACKET
TO BAY-04HEIGHT
2 No(s). DOUBLE GIRDER WITH 20 TON CAPACITY, 20 m SPAN, 60 m TRAVELLING LENGTH AND 10.4 m TOP
Crane Type 2 - BAY-05 OF Cr. BRACKET HEIGHT

LOADS & DESIGN CODES


DESIGN CODE AISC
WIND LOADING MBMA ( 44m/s, Exposure-C )
SEISMIC LOADING IS1893 Part-I, RF-4,I-1,ZONE-II
MINIMUM WEB PLATE THICK 4 MM
MINIMUM FLANGE PLATE THICK 6 MM
MINIMUM PURLIN/GIRT THICKNESS 1.5 MM

BRACING CROSS BRACING ALONG SIDE WALLS & INTERMEDIATE COLUMNS


Frame Horizontal H/100

Crane Beam L/600

Purlin/Girt L/120

1
MB
PRE-ENGINEERED BUILDING FOR M/s. XXXX CRANE BEAM EXPANSION---R0

BOQ
BUILTUP
MAIN FRAMES 100.05 345MPA
STRUT 6.80 250MPA
CRANE BEAM 71.93 345MPA
BRACING 8.21 250MPA
SAG ROD - 12DIA ROD 1.36 250MPA
ANCHOR BOLT 10.65 250MPA
COLD FORM
PURLINS & GIRTS 7.02 345MPA / 120GSM
SHEETING
WALL AREA 1483 Sqm 6.08 550MPA
OTHERS
TRIMS 1.65 SAME WALL CLADDING
MISCELLANEOUS 7.50 BOLTS ,ETC
TOTAL TONNAGE 221.2 MT

ACCESSORIES:
NOTES:
1- ALL MAIN FRAME COLUMN BASES ARE CONSIDERED AS FIXED ( +300mm FROM FFL ).

2- PEB SCOPE INCLUDES CRANE BEAM + INDEPENDENT CRANE SUPPORTING COLUMNS + SIDE WALL GIRTS + SIDE WALL CLADDING
3- 10MT CRANE DATA (CLEINT TO CONFIRM): BRIDGE WT=8.46MT, CRAB WT=1.27MT, MAX WHEEL LOAD=77.4kN, WHEEL BASE=3.15m, TOTAL
WHEELS=4NO.S
4- 20MT CRANE DATA (CLEINT TO CONFIRM): BRIDGE WT=11.64MT, CRAB WT=1.75MT, MAX WHEEL LOAD=141.1kN, WHEEL BASE=3.80m, TOTAL
WHEELS=4NO.S

5- CRANE BEAM/CRANE SUPPORTING COLUMNS DESIGNED FOR TWO CRANES CAN COME IN ONE BAY.
6- AT COMMON WALL EXISTING FRAME CONSIDERED.
7- AT INDEPENDENT CRANE COLUMN TOP LVL ONE TIE BEAM CONSIDERED FOR 30+30m LENGTH OF THE NEW BUILDING AS SHOWN IN CUSTOMER
SKETCH.
8- STABILITY OF EXISTING BUILDING / STRENGTHENING OF EXISTING STRUCTURE NOT CONSIDERED IN SCOPE OF WORK.