Precast Element's Erection & Installation at Site - A Case Study
Precast Element's Erection & Installation at Site - A Case Study
1. INTRODUCTION
The terms used here in these paper are brace, anchor, tower
crane , Leveling shim, Lifting beam and Prop for jointing its
errection and installation.
Fig. 2.2 Column base connections with projecting reinforcement Fig. 2.3.1 wall to wall connections with projecting bars in
bars in grouted sleeves, a) bars projecting from the base, b) bars grouted sleeves, a) interior connection, b) exterior connection
projecting from the column
Placing of beam- primary beam has already placed during
Water Tightness:.The grouted joints helped to achieve water placing of column to restraint the column. secondary beam is
tightness taking into consideration the local tropical climate with placed after half grout done . Their nomenclature, orientation
heavy monsoons. Backer rods placed at the exterior exposed face to and structural damages should be checked. Line of beam
prevent water entry. Waterproofing sealant applied at these joints should be maintained to avoid uneven offset formed visible
as an additional line of defence. after block masonry. Supports needed to those whose length is
larger than 3m and at primary secondary junction.
Full grout- All pre-cast main beam & secondary beam should
be checked as per GFC Drawings with curing period. All type
of beam sizes with length should be checked as per drawing
with required bearing, top portion shear link & main beam +
secondary beam with column junction portion. All beams, PC
Fig 2.5 Placing of slabs Fig 2.5.1 Electrical layout done Slabs & Siporex slab should be cleaned / washed before resting
before slab installation on column.
3. Conclusions
b. Erection
Erection preparation- Prior to commencing the handling and/or Quality Management- After all precast concrete panels have
erection of precast concrete elements. Check crane access to the been installed; the Contractor and the Engineer shall conduct a
site and erection platform to prevent cranes or trucks damaging final inspection to locate any damage or deficiencies. All visible
damage or deficiencies shall be repaired by the Contractor to the
the concrete floor during access. A compacted hard-fill ramp at a
satisfaction of the Engineer and acceptable to the Department
suitable gradient should be provided to a level slightly above the before final approval is granted.
concrete floor which can support the erection loads. Ensure the
dowels and leveling shims are correctly located. Sufficient space 5. Bibliography
available for precast propping or panel bracing. The lifting
i. IJCIET Volume 6, Issue 1, January (2015),
inserts are in their correct location.
www.iaeme.com/Ijciet.asp
ii. fib Bulletin 43: Structural connections for precast concrete
Erection crew buildings [email protected] • www.fib-international.org
The erection crew for handling and erection of precast elements iii. Indian Standard BUILDING DESIGN AND ERECTION
should consist of: A competent crane operator, , a dodger who USING PREFABRICATED CONCRETE — CODE OF PRACTICE
holds a national certificate, or one who is competent in the work iv. www.jifactor.com
that is to be performed; and an additional competent labor as v. Approved Code of Practice for- The Safe Handling,
required to assist with erection or placement of elements. Transportation and Erection of Precast Concrete- Published by the
Occupational Safety and Health Service, Department of Labor,
Wellington, New Zealand. May 2002
Note: A person with dual qualifications may function as both a vi. PRECAST CONCRETE CONSTRUCTION Svetlana Brzev,
rigger and dodger. British Columbia Institute of Technology, Canada Teresa Guevara-
Perez, Architect, Venezuela
Erection of tilt-up panels vii. International Journal of Emerging Trends & Technology in
The crane operator should be competent in the scope of the work Computer Science (IJETTCS) Web Site: www.ijettcs.org Email:
to be undertaken.. Whenever possible, panels should be lifted [email protected], Volume 6, Issue 3, May- June 2017
with the rigging equipment in view of the crane operator. At no viii. Precast Large Concrete Panel System Web Site:
time should any worker position themselves underneath a precast http://www.bmtpc.org
ix. 27th Conference on OUR WORLD IN CONCRETE &
element or on the underside of a tilt-up panel during erection. No
STRUCTURES: 29 - 30 August 2002, Singapore
attempt should be made to lift and erect panels in strong winds http://cipremier.com/100027054
where control of the panel may be lost. Braces at both ends x. Study on Prefabricated Concrete Beam and Column
should be connected before releasing the lifting equipment, Connections
unless designed otherwise. xi. International Journal of Applied Sciences, Engineering and
Management ISSN 2320 – 3439, Vol. 02, No. 02, March 2013, pp. 41 -
45
4. Recommendations