Construction Estimate Masonry Works

The document contains construction estimates for various masonry works including computations for column footings, wall footings, columns, roof beams, slab on fill, and concrete block (CHB) for a building project. Concrete proportions and volumes are calculated for each structural element using Class A, B, or C concrete mixes. Reinforcing steel and CHB quantities are also estimated based on the computed areas.

Uploaded by

Czari Muñoz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
83 views29 pages

Construction Estimate Masonry Works

The document contains construction estimates for various masonry works including computations for column footings, wall footings, columns, roof beams, slab on fill, and concrete block (CHB) for a building project. Concrete proportions and volumes are calculated for each structural element using Class A, B, or C concrete mixes. Reinforcing steel and CHB quantities are also estimated based on the computed areas.

Uploaded by

Czari Muñoz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 29

PALINES , THOM JAYSON SPECIALIZATION 2

ARCH - 3205 15 - 53447

CONSTRUCTION ESTIMATE

MASONRY WORKS

 COMPUTATION OF COLUMN FOOTING

USING CLASS C CONCRETE PROPORTIONING

Class Proportion Cement Sand Gravel

C 1:3:6 5.48 0.44 0.88

Column footing C1-F1

V=LxWxH

1.20 x 1.20 x 0.30 = 0.432 x 3 = 1.296 cu.m

Cement : 1.296 x 5.48 = 7.10208 bags

Sand : 1.296 x 0.44 = 0.57024 cu.m

Gravel : 1.296 x 0.88 = 1.140483. cu.m

Column footing C1-F2

V=LxWxH

1.20 x 1.20 x 0.25 = 0.36 x 13 = 4.68 cu.m

Cement : 4.68 x 5.48 = 25.6464 bags

Sand : 4.68 x 0.44 = 2.0592 cu.m

Gravel : 4.68 x 0.88 = 4.1184 cu.m


 COMPUTATION OF WALL FOOTING

USING CLASS B CONCRETE PROPORTIONING

Class Proportion Cement Sand Gravel

B 1 : 2.5 : 5 6.48 0.44 0.88

Wall footing (exterior)

V=LxWxH

L = 3.90 + 3.40 + 1.30 + 2.20 + 0.80 + 1.10 + 2.20 + 2.50 + 3.50 + 2.90 + 1.30 +
4.00 = 29.1 m

W = 0.40 m

H = 0.20 m

29.1 x 0.40 x 0.20 = 2.328 cu.m

Cement : 2.328 x 6.48 = 15.08544 bags

Sand : 2.328 x 0.44 = 1.02432 cu.m

Gravel : 2.328 x 0.88 = 2.04864 cu.m

Wall footing 1 (interior)

V=LxWxH

L = 4.00 + 3.70 + 3.80 + 1.20 + 2.90 + 3.60 + 2.60 + 2.00 + 1.50 + 4.10 = 29.4 m

W = 0.40 m

H = 0.20 m

29.4 x 0.40 x 0.20 = 0.4044 cu.m

Cement : 0.4044x 6.48 = 2.620512 bags

Sand : 0.4044 x 0.44 = 0.177936 cu.m

Gravel : 0.4044 x 0.88 = 0.355872 cu.m


Wall footing 2 (firewall)

V=LxWxH

L = 10 + 7.18 = 17.18 m

W = 0.20 m

H = 0.30 m

17.18 x 0.20 x 0.30 = 1.0308 cu.m

Cement : 1.0308 x 6.48 = 6.679584 bags

Sand : 1.0308 x 0.44 = 0.453552 cu.m

Gravel : 1.0308 x 0.88 = 0.907104 cu.m

 COMPUTATION OF COLUMN

USING CLASS A CONCRETE PROPORTIONING

Class Proportion Cement Sand Gravel

A 1:2:4 7.84 0.44 0.88

Interior and Exterior

V=LxWxH

0.40 x 0.15 x 4.45 = 0.267 x 14 = 3.738 cu.m

Cement : 3.738 x 7.48 = 27.96024 bags

Sand : 3.738 x 0.44 = 1.64472cu.m

Gravel : 3.738 x 0.88 = 3.28944 cu.m

Carport

V=LxWxH

0.40 x 0.15 x 4.60 = 0.276 x 2 = 0.552 cu.m.


Cement : 0.552 x 7.48 = 4.12896 bags

Sand : 0.552 x 0.44 = 0.24288 cu.m

Gravel : 0.552 x 0.88 = 0.48576 cu.m

Firewall

V=LxWxH

V1 0.40 x 0.15 x 5.35 = 0.321 cu.m

V2 0.40 x 0.15 x 5.00 = 0.3 cu.m

V2 0.40 x 0.15 x 4.70 = 0.282 cu.m

0.321 + 0.3 + 0.282 = 0.903 cu.m

Cement : 0.903 x 7.48 = 6.75444 bags

Sand : 0.903 x 0.44 = 0.39732 cu.m

Gravel : 0.903 x 0.88 = 0.79464 cu.m

 COMPUTATION OF ROOF BEAM

USING CLASS A CONCRETE PROPORTIONING

Class Proportion Cement Sand Gravel

A 1:2:4 7.84 0.44 0.88

V=LxWxH

L = horizontal – 2.90 + 1.30 + 4.00 + 2.40 + 3.10 + 3.10 + 4.10 + 5.60 + 3.90 +
3.40 = 33.8

= vertical – 3.50 + 3.60 + 2.20 + 3.50 + 3.90+ 1.90 + 3.70 + 1.50 + 2.20 + 1.15
+ 2.30 + 1.30 + 3.50 + 3.50 = 37.75
33.8+ 37.75= 71.55 m

W = 0.15 m

H = 0.30 m

71.55 x 0.15 x 0.30 = 3.21975 cu.m

Cement : 3.21975 x 7.84 = 25.24284 bags

Sand : 3.21975 x 0.44 = 1.41669 cu.m

Gravel : 3.21975 x 0.88 = 2.22552 cu.m

 COMPUTATION OF SLAB ON FILL

USING CLASS B CONCRETE PROPORTIONING

Class Proportion Cement Sand Gravel

B 1 : 2.5 : 5 6.48 0.44 0.88

V=LxWxH

V1 = 2.60 x 2.30 x 0.10

= 0.598 cu.m

V2 = 1.50 x 2.30 x 0.10

= 0.345 cu.m

V3 = 3.80 x 3.50 x 0.10

= 1.33 cu.m

V4 = 4.90 x 4.50 x 0.10

= 2.205 cu.m

V5 = 3.80 x 4.00 x 0.10

= 1.52 cu.m

V6 = 1.20 x 1.40 x 0.10


= 0.168 cu.m

V7 = 3.10 x 1.00 x 0.10

= 3.1 cu.m

V8 = 3.80 x 3.10 x 0.10

= 1.178 cu.m

V9 = 2.20 x 1.30 x 0.10

= 0.286 cu.m

V10 = 2.20 x 4.00 x 0.10

= 0.88 cu.m

V11 = 1.50 x 2.80 x 0.10

= 0.42 cu.m

0.598 + 0.345 + 1.33 + 2.205 + 1.52 + 0.168 + 3.1 + 1.178 + 0.286 + 0.88 + 0.42

= 12.03 cu.m

Cement : 12.03 x 7.84 = 94.3152 bags

Sand : 12.03 x 0.44 = 5.2932 cu.m

Gravel : 12.03 x 0.88 = 10.5864 cu.m


 COMPUTATION OF CHB

Front

A1 5.05 x 3.60 = 18.18

W4 – 1.90 x 0.50 = 0.95

= 18.18 - 0.95 = 17.23 sq.m

A2 5.05 x 1.10 = 5.555

D1 – 2.10 x 0.90 = 1.89

= 5.555 - 1.89 = 3.665 sq.m

A3 5.05 x 3.20 = 16.16

W7- 2.00 x 2.38 = 4.76

= 16.16 - 4.76 = 11.4 sq.m

A4 5.05 x 1.10 = 5.555

d2- 2.00 x 0.58 = 1.16

= 5.555 - 1.16 = 2.37 sq.m

A5 2.40 x 0.87 = 2.088 sq.m

A6 2.70 x 1.92 = 5.184

d1 - 2.10 x 0.80 = 1.68 + 1.20

= 5.184 - 2.88 = 2.304 sq.m

A7 2.70 x 2.62 = 7.074

d3 - 2.10 x 1.40 = 2.94

= 7.074 - 2.94 = 4.134 sq.m


A8 2.70 x 0.96 = 2.592

= 2.592 - 1.20 = 1.392 sq.m

A9 2.70 x 1.55 = 4.185 sq.m

A10 0.50 x 1.92 = 0.96 sq.m

A11 0.50 x 2.62 = 1.31 sq.m

A12 0.50 x 0.90 = 0.45 sq.m

A13 0.50 x 1.31 = 0.655 sq.m

Right (firewall)

4.65 x 0.30 = 1.395 sq.m

3.17 x 0.92 = 2.9164 sq.m

3.43 x 3.17 = 10.8731 sq.m

2.25 x 0.92 = 2.07 sq.m

3.43 x 2.25 = 7.7175 sq.m

2.25 x 0.49 = 1.1025 sq.m

2.40 x 3.39 = 8.136 sq.m

exterior

2.70 x 0.85 = 2.295 sq.m

2.70 x 2.45 = 6.615 -1.47 = 5.145 sq.m

2.70 x 1.16 = 3.132 -0.25 = 2.882 sq.m

2.40 x 0.76 = 1.824 -1.26 = 0.564 sq.m

2.40 x 1.09 = 2.616 sq.m

2.40 x 1.10 = 2.64 - 0.60 = 2.04 sq.m


2.40 x 1.16 = 2.784 - 0.25 = 2.534 sq.m

Rear

2.40 x 3.45 = 8.28 - 1.20 = 7.08 sq.m

2.40 x 3.75 = 9 - 1.20 = 7.8 sq.m

2.70 x 3.45 = 9.315 - 2.07 = 7.245 sq.m

3.50 x 3.75 = 13.125 - 0.60 = 12.525 sq.m

0.50 x 3.45 = 1.725 sq.m

Left (firewall)

2.40 x 1.86 = 4.464 sq.m

3.34 x 0.53 = 1.7702 sq.m

0.97 x 1.41 = 1.3677 sq.m

0.79 x 0.45 / 2 = 0.17775 sq.m

0.50 x 1.78 = 0.89 sq.m

2.67 x 1.78 = 4.7526 sq.m

2.60 x 1.78 = 4.628 sq.m

0.63 x 1.78 = 1.1214 sq.m

1.78 x 1.03 / 2 = 0.9167 sq.m

0.50 x 2.46 = 1.23 sq.m

2.67 x 2.46 = 6.5682 sq.m

2.60 x 2.46 = 6.396 sq.m

0.72 x 2.46 = 1.7712 sq.m

1.27 x 0.26 = 0.3302 sq.m


1.27 x 2.20 / 2 = 1.397 sq.m

3.00 x 1.60 = 4.8 sq.m

2.25 x 0.80 = 1.8 sq.m

1.27 x 1.16 = 1.4732 sq.m

0.67 x 2.18 = 1.4606 sq.m

0.97 x 1.55 = 1.5035 sq.m

0.93 x 0.54 / 2 = 0.2511 sq.m

Interior

2.70 x 2.78 = 7.506 - 1.47 = 6.036 sq.m

0.50 x 2.78 = 1.39 sq.m

2.70 x 1.90 = 5.13 sq.m

0.50 x 1.90 = 0.95 sq.m

2.70 x 1.15 = 3.105 - 1.26 = 1.845 sq.m

0.50 x 1.15 = 0.575 sq.m

2.40 x 3.78 = 9.072 - 2.94 = 6.132 sq.m

2.40 x 2.60 = 6.24 sq.m

2.40 x 2.60 = 6.24 sq.m

2.40 x 3.45 = 8.28 - 2.73 = 5.55 sq.m

2.40 x 1.15 = 2.76 - 1.26 = 1.5 sq.m

2.40 x 0.82 = 1.968 sq.m

Front = 30.864 x 12.50 = 385.8 sq.m

Right = 18.076 x 12.50 = 225.95 sq.m

Rear =36.375 x 12.50 = 454.6875 sq.m

Left =49.06935 + 34.2105 = 83.27985 x 12.50 = 1,040.998125 sq.m


Interior = 43.556 x 12.50 = 544.45 sq.m

385.8 + 225.95 + 454.6875 + 1,040.998125 + 544.45

= 2,651.885625 pcs. of CHB

 COMPUTATION OF MORTAR (CHB)

Exterior

30.864 + 18.076 + 36.375 = Cement 85.315 x (0.759) = 64.754085 bags

= Sand 85.315 x (0.08438) = 7.1988797 cu.m

Firewall

Cement 83.27985 x (1.125) = 93.68983125 bags

Sand 83.27985 x (0.12500) = 10.40998125 cu.m

Interior

Cement 43.556 x (0.394) = 17.161064 bags

Sand 43.556 x (0.04375) = 1.905575 cu.m

 COMPUTATION OF CHB PLASTER

USING CLASS B CONCRETE PROPORTIONING

Exterior

385.8 + 225.95 + 454.6875 = 1,066.4375

1,066.43755 x 0.0020 = 2.1328751

Cement - 2.1328751 x 5.5 = 11.73081305 bags

Lime - 2.1328751 x 5.5 = 11.73081305 bags


Sand - 2.1328751 x 0.90 = 1.91958759 cu.m

Firewall

1,040.998125 x 0.0020 = 2.08199625

Cement - 2.08199625 x 5.5 = 11.45097938 bags

Lime - 2.08199625 x 5.5 = 11.45097938 bags

Sand - 2.08199625 x 0.90 = 1.873796625 cu.m

Interior

544.45 x 0.0020 = 1.0889

Cement - 1.0889 x 5.5 = 5.98895 bags

Lime - 1.0889 x 5.5 = 5.988.95 bags

Sand - 1.0889 x 0.90 = 0.98001 cu.m

 COMPUTATION OF COLUMN PLASTER

1st floor

Exterior

0.30 + 0.30 + 0.30 + 0.07 +0.07 + 0.30 + 0.05 + 0.05 + 0.30 + 0.20 + 0.15 +0.15
+ 0.20 + 0.10 + 0.20 + 0.30 + 0.20 + 0.06 + 0.06 + 0.30 + 0.20 + 0.30 + 0.05 +
0.05

= 4.26

2nd floor

Exterior

0.30 + 0.30 + 0.30 + 0.07 +0.07 + 0.30 + 0.05 + 0.05 + 0.30 + 0.05 + 0.05 + 0.30
+ 0.06 + 0.06 + 0.30 + 0.05 + 0.20+ 0.15 + 0.15 + 0.05 + 0.30 + 0.20 + 0.05 +
0.05 + 0.30
= 4.06

4.26 + 4.06 = 8.32/2 = 4.16 x 5.70 = 23.712

1st floor

Interior

0.08 + 0.30 + 0.30 + 0.20 + 0.30 + 0.09 + 0.20 + 0.30 + 0.20 + 0.20 + 0.30 +
0.30 + 0.15 + 0.30 + 0.20 + 0.30 + 0.09

= 3.81 x 2.70 = 10.287

2nd floor

Interior

0.09 + 0.14 + 0.06 + 0.08 + 0.21 + 0.20 + 0.30 + 0.10 + 0.20 + 0.30 + 0.10 +
0.12 + 0.10 + 0.09 + 0.30 + 0.10 + 0.30 + 0.30 + 0.04 + 0.09 + 0.06

= 3.28 x 2.40 = 7.872

Carport

0.30 + 0.30 + 0.30 + 0.30 + 0.30 + 0.30 + 0.30 + 0.30 + 0.20 + 0.20 + 0.30 +
0.30 + 0.20 + 0.20

= 3.8 x 3.03 = 11.514

0.30 + 0.30 + 0.30 + 0.30 + 0.30 + 0.30 + 0.30 + 0.30 + 0.20 + 0.20

= 2.8 x 0.92 = 2.576

= 11.514 + 2.576 = 14.09

Column extension

0.30 x 0.30 = 0.09 x 0.63 = 0.0567


0.30 x 0.30 = 0.09 x 1.84 = 0.1656

0.30 x 0.30 = 0.09 x 0.72 = 0.0648

23.712 + 10.287 + 7.872 + 14.09 + 0.0567 + 0.1656 + 0.0648 = 56.2481

Cement : 56.2481 x 0.300 = 16.87443 bags

Sand : 56.2481 x 0.025 = 1.4062025 cu.m

STEEL WORKS

 COMPUTATION OF COLUMN FOOTING STEEL BARS

F1 - FOOTING STEEL BARS

Length of 1 steel bar : 1.20 m - 0.15 = 1.05 m

With hook : 1.05 + 0.216 = 1.266 m

A. Total cutbars in 1 footing : 7 x 2 = 14 cutbars

B. Total cutbars for 13 footings : 14 x 13 = 182 cutbars

C. Total length of all the bars : 72 x 1.266 m = 91.152 m

D. Divide length to 6m steelbar : 91.152 / 6 = 15.192 pcs.

F2 - FOOTING STEEL BARS

A. 1.20 - 0.15 = 1.05 m

1.05 + 0.216 = 1.266 m

1.266 x 9 = 11.394
11.394 x 6 = 68.364

68.364 / 6 = 11.394 pcs.

B. 0.90 - 0.15 = 0.75

0.75 + 0.216 = 0.966 m

0.966 x 7 = 6.762

6.762 x 6 = 40.572

40.572 / 6 = 6.762 pcs.

 COMPUTATION OF WALL FOOTING STEEL BARS

Total length of footing

20.34 + 6.74 + 17.18 = 44.26 m

Divide to the given spacing (44.26 / 0.30 = 148.6666667 pcs.)

9D = 9 x 0.01

= 0.09 x 2 = 0.18

Horizontal bars

Footing width : 0.30 - (0.75 + 0.75 = 0.15) = 0.15

= 0.15 + 0.18 = 0.33

= 0.33 x 148.6666667

= 49.06000001 m total length of ties for horizontal bars

Vertical bars

44.26 + 0.18 = 44.44 m

= 44.44 x 3

= 133.32 m total length of ties for vertical bars


Total = 49.06000001 + 133.32 = 182.38000001

= 182.38000001 / 6 = 30.39666667 pcs.

 COMPUTATION OF VERTICAL AND HORIZONTAL STEEL BARS IN


WALL

Vertical bars

Total area of CHB

30.864 +18.076 + 36.375 + 83.27985 + 43.556 = 212.15085 sq.m

Vertical reinforcement of 0.80 = 1.60

212.15085 x 1.60

= 339.44136 / 6

339.44136 / 6

= 56.57356 pcs

Horizontal bars

Every horizontal bars at every after 3 layers

212.15085 x 2.15

= 456.1243275

456.1243275 / 6
= 76.02072125 pcs.

56.57356 pcs + 76.02072125 pcs.

= 132.59428125 pcs.

 COMPUTATION OF LATERAL TIES IN COLUMN

Notes :

Bend 9D

9 x 10 mm or 0.01 = 0.90 m x 2 = 18 m

= 0.20 m (0.040 + 0.040) + 0.30 (0.040 + 0.040)

= 0.12 + 0.22

= 0.034 x 2

= 0.60

SUMMARY = 0.68 + 0.18 = 0.86

Adopt the shortest side of the column for spacing

(0.20m) = 1 lateral tie

Carport

H / 0.20 = lateral tie

5.1 / 0.20 = 25.5 lateral ties

0.86 x 25.5 = 21.93 m

Multiply to the no.of columns (21.93 x 4 = 87.72 m)

Divide the tota length to 6m steel bar (87.72 / 6 = 14.62 pcs. of 6m steel bars)

Typical
H / 0.20 = lateral tie

6.40 / 0.20 = 32 lateral ties

0.86 x 32 = 27.52 m

Multiply to the no.of columns (27.52 x 9 = 247.68 m)

Divide the total length to 6m steel bar (247.68 / 6 = 41.28 pcs. of 6m steel bars)

Firewall

H / 0.20 = lateral tie

7.03 / 0.20 = 35.15 lateral ties

0.86 x 35.15 = 30.229 m

Multiply to the no.of columns (30.229 x 1 = 30.229 m)

Divide the total length to 6m steel bar (30.229 / 6 = 5.038166667 pcs. of 6m


steel bar)

H / 0.20 = lateral tie

8.24 / 0.20 = 41.2 lateral ties

0.86 x 41.2 = 35.432 m

Multiply to the no.of columns (35.432 x 1 = 35.432 m)

Divide the total length to 6m steel bar (35.432 / 6 = 5.905333333 pcs. of 6m


steel bar)

H / 0.20 = lateral tie

7.12 / 0.20 = 35.6 lateral ties

0.86 x 35.6 = 30.616 m

Multiply to the no.of columns (30.616 x 1 = 30.616 m)

Divide the total length to 6m steel bar (30.616 / 6 = 5.102666667 pcs. of 6m


steel bar)
5.038166667 + 5.905333333 + 5.102666667 = 16.046166667 pcs.

Total = 14.62 pcs. + 41.28 pcs. + 16.046166667 pcs. = 71.946166667 pcs.

 COMPUTATION OF STIRRUPS IN GRADE BEAM

Total length = 1.91 + 2.62 + 0.96+ 3.87 + 1.73+ 1.73 + 3.60 + 3.75 + 1.78 + 2.46
+ 1.80 + 1.15 + 3.35 = 30.71 m

3.80 m = length of beam

26 = stirrups

Total length / length of beam

30.71 / 3.80 = 8.081578947 m

8.081578947 x 26 = 210.1210526 pcs

9D = 9 x 10mm or 0.01m = 0.90 x 2 = 0.18 m

= 0.30 m ( 0.04 + 0.04 ) + 0.20 ( 0.04 + 0.04 )

= 0.30 - 0.08 + 0.20 m - 0.08

= 0.22 x 2 + 0.12 x 2

= 0.44 + 0.24

= 0.68 m

210.1210526 x 0.68 = 142.8823158 m

142.8823158 / 6 = 23.81371929 pcs.


 COMPUTATION OF STIRRUPS IN REINFORCED CONCRETE BEAM

Total length = 3.78 + 3.67 + 1.82 + 1.55 + 1.64 + 1.56 + 3.78 + 1.91 + 2.86 +
0.90 + 0.81 + 3.35 + 3.35 + 1.78 + 2.46 + 0.95 + 2.57 + 1.91 + 2.58 + 3.26 +
1.10 + 3.25 + 1.16 + 1.11 + 0.92 + 2.25 + 3.14 + 1.84 = 61.26 m

3.80 m = length of beam

26 = stirrups

Total length / length of beam

61.26 / 3.80 = 17.08157895 m

17.08157895 x 26 = 444.1210526 pcs.

9D = 9 x 10mm or 0.01m = 0.90 x 2 = 0.18 m

= 0.30 m ( 0.04 + 0.04 ) + 0.20 ( 0.04 + 0.04 )

= 0.30 - 0.08 + 0.20 m - 0.08

= 0.22 x 2 + 0.12 x 2

= 0.44 + 0.24

= 0.68 m

444.1210526 x 0.68 = 302.0023158 m

302.0023158 / 6 = 50.33371929 pcs.

 COMPUTATION OF STIRRUPS IN ROOF BEAM

Total length = 3.78 + 3.67 + 3.78 + 1.91 + 2.86 + 0.90 + 0.81 + 1.88 + 1.55 +
1.62 + 22.76 + 1.78 + 2.46 + 2.57 + 2.58 + 3.26 + 1.80 + 1.10 + 0.65 + 1.16 +
1.11 + 0.92 = 64.91 m

3.80 m = length of beam

26 = stirrups

Total length / length of beam

64.91 / 3.80 = 16.12105263 m


16.12105263 x 26 = 419.1473684 pcs.

9D = 9 x 10mm or 0.01m = 0.90 x 2 = 0.18 m

= 0.30 m ( 0.04 + 0.04 ) + 0.20 ( 0.04 + 0.04 )

= 0.30 - 0.08 + 0.20 m - 0.08

= 0.22 x 2 + 0.12 x 2

= 0.44 + 0.24

= 0.68 m

419.1473684 x 0.68 = 285.0202105 m

285.0202105 / 6 = 47.50336842 pcs.

 COMPUTATION OF LONGITUDINAL STEEL BARS IN COLUMN

Bend = 9D

9 (16mm or 0.016 m)

= 0.144 x 2

= 0.288 m

Carport

H + 0.288

5.45 + 0.288

= 5.738

6 bars x 4 columns = 20 steel bars

5.738 x 20 = 114.76

114.76 / 6 = 19.12666667 pcs. of 6m x 16mm temp bars


Typical

H + 0.288

7.00 + 0.288

= 7.288

6 bars x 9 columns = 54 steel bars

7.288 x 54 = 393.552

393.552 / 6 = 65.592 pcs. of 6m x 16mm temp bars

Firewall

H + 0.288

7.83 + 0.288

= 8.118

6 bars x 1 column = 6 steel bars

8.118 x 6 = 48.708

48.708 / 6 = 8.118 pcs. of 6m x 16mm temp bars

H + 0.288

9.04 + 0.288

= 9.328

6 bars x 1 column = 6 steel bars

9.328 x 6 = 55.968

55.968 / 6 = 9.328 pcs. of 6m x 16mm temp bars

H + 0.288

7.92 + 0.288

= 8.208

6 bars x 1 column = 6 steel bars


8.208 x 6 = 49.248

49.248 / 6 = 8.208 pcs. of 6m x 16mm temp bars

 COMPUTATION OF SLAB ON FILL REINFORCEMENT

1.71 x 1.50 = 2.565 sq.m

5.00 x 3.50 = 17.5 sq.m

1.45 x 1.25 = 1.8125 sq.m

3.60 x 1.20 = 4.32 sq.m

2.90 x 1.90 = 5.51 sq.m

2.00 x 1.80 = 3.60 sq.m

1.90 x 1.00 = 1.90 sq.m

5.95 x 2.80 = 16.66 sq.m

6.10 x 1.25 = 7.625 sq.m

2.565 + 17.5 + 1.8125 + 4.32 + 5.51 + 3.60 + 1.90 + 16.66 + 7.625

Total area = 69.4665 sq.m

Length of the bar : 69.4665 x (8”) 2.083 = 144.6987195 m

144.6987195 / 6 = 24.11645325 pcs.

 COMPUTATION OF ONE WAY SLAB REINFORCEMENT

Areas

1.55 x 0.75 = 1.1625 sq.m

1.91 x 0.83 = 1.5853 sq.m

2.49 x 1.87 = 4.6563 sq.m

1.70 x 2.49 = 4.233 sq.m

1.19 x 1.88 = 2.2372 sq.m

0.96 x 3.21 = 3.0816 sq.m


2.35 x 1.75 = 4.1125 sq.m

1.1625 + 1.5853 + 4.6563 + 4.233 + 2.2372 + 3.0816 + 4.1125

Total area = 21.0684 sq.m

Length of the bar : 21.0684 x (8”) 2.083 = 43.8854772 m

43.8854772 / 6 = 7.3142462 pcs.

 COMPUTATION OF TWO WAY SLAB REINFORCEMENT

Areas

1.30 x 1.50 = 1.95 sq.m

2.51 x 2.40 = 6.024 sq.m

3.23 x 3.35 = 10.8205 sq.m

1.95 + 6.024 + 10.8205

Total area = 18.8205 sq.m

18.8205 x (6”) 3.040 = 57.21432 m

57.21432 / 6 = 9.53572 pcs.

 COMPUTATION OF TIE WIRES

Column Footing

Footing 1 = 9 x 9

= 81

Multiply to the no. of footing = (81 x 4 = 324 )

Then multiply to the length of wire = (324 x 0.30 = 97.2 m. long )

Footing 2 = 9 x 7
= 63

Multiply to the no. of footing = (63 x 6 = 378 )

Then multiply to the length of wire = (378 x 0.30 = 113.4 m. long )

Footing 3 = 7 x 7

= 49

Multiply to the no. of footing = (49 x 1 = 49)

Then multiply to the length of wire = (49 x 0.30 = 14.7 m. long )

Footing 4 = 7 x 7 = 49 ,

7 x 7 = 49 ,

8 x 7 = 56

= 154

Multiply to the no. of footing = (154 x 1 = 154)

Then multiply to the length of wire = (154 x 0.30 = 46.2 m. long )

Footing 5 = 28 x 7

= 196

Multiply to the no. of footing = (196 x 1 = 49)

Then multiply to the length of wire = (196 x 0.30 = 58.8 m. long )

Wall Footing

148.6666667 pcs. x 3 = 446.000001 pcs.

= 446.000001 x 0.30

= 133.800003 m. long
Column

Carport

Lateral ties x the no. of column x no. of longtitudinal bars

14.62 x 4 = 58.48

58.48 x 6 = 350.88

350.88 x 0.30 = 105.264 m. long

Typical

Lateral ties x the no. of column x no. of longitudinal bars

41.28 x 9 = 371.52

371.52 x 6 = 2,229.12

2,229.12 x 0.30 = 668.736 m. long

Firewall

Lateral ties x the no. of column x no. of longitudinal bars

5.038166667 x 1 = 5.038166667

5.038166667 x 6 = 30.229

30.229 x 0.30 = 9.068700001 m. long

Lateral ties x the no. of column x no. of longitudinal bars

5.905333333 x 1 = 5.905333333

5.905333333 x 6 = 35.432

35.432 x 0.30 = 10.6296 m. long

Lateral ties x the no. of column x no. of longitudinal bars

5.102666667 x 1 = 5.102666667
5.102666667 x 6 = 30.616

30.616 x 0.30 = 9.184800001 m. long

9.068700001 + 10.6296 + 9.184800001

Total = 28.883100002 m. long

Grade Beam

Total no. of stirrups x no. of steel bars

23.81371929 x 6 = 142.8823157

142.8823157 x 0.38

= 54.29527998 m. long

Reinforced Concrete Beam

Total no. of stirrups x no. of steel bars

50.33371929 x 6 = 302.0023157

302.0023157 x 0.38

= 114.76088 m. long

Roof Beam

Total no. of stirrups x no. of steel bars

47.50336842 x 6 = 285.0202105

285.0202105 x 0.38

= 108.30768 m. long

Vertical and Horizontal bars

Vertical

212.15085 / 5.6 = 37.88408036 m. long


Horizontal

1.91+2.62+1.06+1.60+0.87+1.92+2.62+0.96+1.55+1.92+2.62+0.90+1.31+0.30+
0.92+3.17+0.92+2.25+0.49+3.39+0.85+2.45+1.16+0.76+1.09+1.10+1.16+3.45+
3.75+3.45+3.75+3.45+1.86+0.53+1.41+0.45+1.78+1.78+1.78+1.78+1.03+2.46+
2.46+2.46+2.46+0.26+2.20+1.60+0.80+1.16+2.18+1.55+0.54+2.78+2.78+1.90+
1.90+1.15+1.15+3.78+2.60+2.60+ 3.45+1.15+0.82 = 235.8 m

456.1243275 / 235.8

=1.934369497

37.88408036 x 1.934369497

= 73.28180949 x 0.30

= 21.98180949 m. long

Slab on Fill

61.4925 x 2.93 = 180.173025

180.173025 / 3.75m = 48.04614

48.046142 = 2308.431569

2308.431569 x 0.30

= 692.5294707 m. long

S1

= 21.7694 sq.m x 0.152 = 3.3089488 kg.

S2

= 18.6434 sq.m x 0.282 = 5.2574388 kg.

Add all length / 53 = kg + add s1 and s2 kg = kg


97.2 + 113.4 +14.7+ 46.2 + 58.8 + 133.800003 + 105.264 + 668.736 +
28.883100002 + 54.29527998 + 114.76088 + 108.30768 + 37.88408036 +
21.98180949 + 692.5294707 = 2296.742303532 m

2296.742303532 / 53 = 43.33476044 kg

43.33476044 + 3.3089488 + 5.2574388 = 51.90114804 kg