HSE 306 - Electrical
HSE 306 - Electrical
CLIENT:
CONTRACTOR:
STROYTRANSGAZ
PROJECT:
South Middle Area Gas Exploitation
Compressor Station Project,
Syria
CONTRACT #: 4/2016 Document type:
Procedure
Document ID code: Revision: Other denotations:
HSE-PC-306
File name: HSE 306 - Electrical
Document name:
Electrical
Page: 1/3
Purpose
The purpose of this work procedure is to define actions to be taken when carrying out electrical repairs in
the Contractor performed operations, locations, sites, facilities or camps.
Scope
This procedure applies to all activities involving electrical works as it is considered highly dangerous to
other performed activities.
Responsibilities
Individual Managers are responsible for ensuring that this procedure is communicated to and
implemented throughout the Contractor organization.
Line Supervisors are responsible for ensuring they and all their work force teams fully understand and
comply with this procedure at all times.
Actions
The requirement for varying voltage, phases, current and the type of electrical equipment needed
must all be assessed and preplanned.
A competent electrician shall be the only authorized and responsible person for the maintenance,
alterations, extensions and testing of the installation.
The Lock Out/ Tag Out Work Procedure should be applied at all times before any electrical work
is commenced.
The installation shall be inspected with special emphasis on cable and cords, which are prone to
mechanical damage.
Where joints in cables are required they shall be properly made with connectors; taped joints are
not permitted.
The correct type and rating of receptacle breaker and fuses must be used.
Work on live equipment should not be commenced without prior consultation with HSE
Department personnel and the establishment of safe procedures and these following conditions
must exist:
Exact voltage known
Check that all repairs have been carried out correctly and that the equipment is safe.
After completing the job, Connect power and check that all voltages are correct.