Final Project
Final Project
Semester Project
In this project, hydraulic and geotechnical concepts were used to check the stability and
seepage potential of a zoned embankment dam using finite element and limit equilibrium
analysis methods for a proposed dam site.
From the hydraulic analysis, the dam height and spillway crest levels were fixed. In addition,
normal water level, fetch length and dead storages of the dam were computed.
On the other hand, from the geotechnical data of the foundation on the dam axis and
embankment materials, preliminary dimensions of the dam were selected and checked for
stability for upstream and downstream slopes under various loading conditions (during
construction, steady state seepage and sudden drawdown).
Finally, the save summarized results (factor of safety and seepage) of both the limit
equilibrium and finite element methods are tabulated and compared to each other.
i
Table of Contents
Abstract ............................................................................................................................................ i
3.2 Stability Analysis using Limit Equilibrium and Finite Element Methods ......................11
3.3 The Quantity of water lost from the seepage analysis ....................................................16
3.4 Comparison of the Results from LEM and FEM Method ...............................................17
4.2 Conclusion.......................................................................................................................18
References ......................................................................................................................................19
ii
Appendix –A ..................................................................................................................................20
A-3. The Test Results on Construction Materials of the Dam (Core, Shell and Foundation) ...21
Appendix –B ..................................................................................................................................21
iii
List of Figures
Figure 2.1: Spillway Location and Reservoir Area ................................................................... 2
Figure 3.1: Limits in the gradation curves separating liquefiable and non- liquefiable soils .... 9
Figure 3.2: Particle size gradation of soils susceptible to flow liquefaction under static and
earthquake loading ................................................................................................................... 10
Figure 3.4: Critical face of Downstream Slope at the end of construction .............................. 13
Figure 3.5: Critical face of Upstream Slope at the end of construction ................................... 13
Figure 3.7: Critical face of Upstream Slope under sudden drawdown condition .................... 14
iv
List of Tables
Table 2-1: Elevation - Area- Volume ------------------------------------------------------------------ 3
Table 2-3: Flood Routing using Reservoir Routing (Storage Indication Method) --------------- 6
Table 3-3: Velocity and Seepage intensity under steady state -------------------------------------16
v
List of Abbreviations
FEM - Finite Element Method
ft - Feet
km - kilo meter
m - Meter
m2 - Square meter
m3 - Cubic meter
vi
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
1. General Introduction
The purpose of this semester project is to analyze and design a zoned embankment dam on a
proposed site. The feasibility study results show that the site is suitable for the proposed
embankment dam. Detail studies carried on the proposed site and surrounding show that zoned
embankment dams are preferred due to the availability of sufficient construction materials in the
vicinity at reasonable cost of hauling. Moreover, the suitability of the site for the intent project
with adequate reservoir capacity, stable geological formations and other technical requirements
made it empirical for its selection. The dam site is assumed to be in seismic zone-III. And the
geotechnical investigation results comprising both field and laboratory results collected during
the feasibility studies are set in Appendix.
Further this project is classified in to two parts: the hydraulic part (Analysis) and analysis and
design of zoned embankment dam. Under the hydraulic part the following are cared out:
1. Selection of Dam Location
2. The Elevation-Area-Volume curve
3. The Components of reservoir (NPL, dead storage, fetch length)
4. Proposing spillway crest level
5. The Maximum height of the proposed dam
On the other hand, the geotechnical part comprises the following tasks:
1. Checking the liquefaction potential of the soils
2. Using static and pseudo-static analyses, the downstream and upstream slopes are
fixed under variety loading conditions (during construction, steady state seepage
and sudden drawdown). By using LEM and FEM methods
3. From the seepage analysis, the quantity of water lost through the dam body is
estimated
4. Comparison between all results from LEM and FEM Method and comment.
Semester Project 1
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
2. Hydraulic Analysis
Fetch
length
Area-elevation curve is obtained by measuring the area enclosed within each contour in the
reservoir site using a planimeter.
Usually a 1/5000 scaled topographic map
Elevation-storage curve:
is the integration of an area-elevation curve.
The storage between any two elevations can be obtained by the product of average surface area at
two elevations multiplied by the difference in elevation
Semester Project 2
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Area- Elevation curve is obtained by measuring the area enclosed within each contour in the
reservoir site. Elevation- Volume/storage curve is the integration of an area-elevation curve which
can be obtained by the product of average surface area at two elevations multiplied by the
difference in elevation between the contours.
885
880
875
870
Elvation (m)
865
860
Area
855
Volume
850
845
840
835
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0
Area (Mm2)/ Volume(Mm3)
Semester Project 3
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Components of reservoir
A spillway is a structure constructed at a dam site, for effective disposing of the surplus water
from upstream to downstream. Just after the reservoir gets filled up, up to the normal pool level,
water starts flowing over the top of the spillway crest (which is generally kept at normal pool
level). Depending up on the inflow rate, water will start rising above the normal pool level, and at
the same time, it will be let off over the spillway. The water can rise over the spillway crest, up to
the maximum reservoir level, which can be estimated from the inflow flood hydrograph and the
spillway characteristics, by the process of flood routing, explained in chapter two. Therefore, it is
only the spillway, which will dispose of the surplus water and will not let the water rise above the
maximum reservoir level.
A spillway can be located either within the body of the dam, or at one end of it, independently in
a saddle. If a deep narrow gorge with steep banks, separated from a flank by a hillock with its
level above the top of the dam (such as shown in Error! Reference source not found.), is
available, the spillway can be best built independently of the dam.
In addition to the space availability, soil conditions of the site shall be taken in account while
fixing the position of a specific spillway. Moreover, soil type together with other factors, like dam
type, head restriction, downstream topography, overall cost, etc., govern selection of spillway
type.
Semester Project 4
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
For the stated dam type and reservoir site, chute type spillway with broad crested entrance is
selected. Besides, its location relative to the dam axis is indicated in Figure 2.1.
Routing is the process of predicting temporal and spatial variation of a flood wave as it travels
through a river or channel reach or reservoir.
For our case, the routing process is to be done using reservoir routing applying continuity
(mass conservation). Equa. (1)
S S S I I O O
I O 2 1 2 1 2 1 .......... .......... .......... .... Equa. (1)
t t 2 2
S
Where, I = Inflow rate, O = Outflow rate and = Rate of change of storage
t
2S2 2S1
Q2 I1 I 2 ..........Equa. (2)
Q1 ..........
t t
6.00 327.12
Semester Project 5
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Using Equa. (2) and Table 2.3 above, the Reservoir routing is done using Goal seek as shown in Table
2.4 below. For the routing process, 0.75 hour time interval is considered. Additionally, initial out flow
and storage are assumed to be zero. Finally, the outflow and inflow hydrographs are plotted, as shown
Figure 2.3 below.
From Table 2.4 or Figure 2.3 below, we can see that the maximum outflow over the short ogee control
weir is 121.699 m3/sec. Besides, the corresponding height, H above the spillway crest is 2.34m.
Table 2-3: Flood Routing using Reservoir Routing (Storage Indication Method)
Semester Project 6
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
From the specified spillway location, the Spillway crest elevation (Normal reservoir level
elevation) and spillway length are 876.46m and 645m, respectively.
There are a number of factors that determine what the capacity of a reservoir or system of
reservoirs must be in order to meet the anticipated future demand from the system. These include:
Semester Project 7
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
By considering the settlement allowance(3% of the dam height) and the head over the
spillway crest (2.34m, see table 2.4)
Settlement allowance = 40*3% = 1.2m
Head over the spillway crest = 2.34
Normal pool level = dam height - (Settlement allowance + head over the spillway crest
= 40 - (1.2 +3.34) = 35.46m
b) Dead storage is located below minimum pool level. The top elevation is dictated by amount of
sediment accumulation at the end of the life time of reservoir.
Considering the lower level of the counter for sediment collection 845m-835m = 10m
c) Active storage is the storage between minimum and normal pool levels
For our case, the fetch length is measured from the given topographical map on the top of the
selected reservoir level Figure 2.1. And it is estimated to be 1.01mil or 1.625km.
Semester Project 8
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
To check the liquefaction of the soils, mainly the susceptibility of the soil has to be identified via
tracing the sieve analysis result from laboratory results of the different soils. These soil test results
are not included in our results and it has to be carried out and be traced or checked with the
following table.
Figure 3.1: Limits in the gradation curves separating liquefiable and non- liquefiable soils
The information indicating the dam site is found in seismic zone III is very important in that the
dam material has to be checked for susceptibility to liquefaction. Proper treatment methodologies
have to be recommended for every appropriate size and type of liquefaction of the different
materials.
Semester Project 9
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Figure 3.2: Particle size gradation of soils susceptible to flow liquefaction under static and
earthquake loading
(Source: Hunter and Fell, 2003a,b).
Hence as per to the given data, the effective diameter D10 of shell and core soils, the sizes are
given 0.27mm and 0.15mm respectively and when these are traced in the distribution curves
given for both static and earthquake loading, it indicates the soils are susceptible to liquefaction.
As the site of the dam is located in Seismic zone III, and it is with in the region ‘most liquefiable’
liquefaction is inevitable. And therefore damage will occur if earthquake happens.
Hence as per to the given data, the effective diameter D10 of shell and core soils, the sizes are
given 0.27mm and 0.15mm respectively and when these are traced in the distribution curves
given for both static and earthquake loading, it indicates the soils are susceptible to liquefaction.
As the site of the dam is located in Seismic zone III, and it is within the region ‘most liquefiable’
liquefaction is inevitable. And therefore damage will occur if earthquake happens.
i. Replacing with better material that have distribution out of the liquefiable range
ii. Using technologies like in-situ densification and cementing
iii. Using drains
iv. Adding free board.
Semester Project 10
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
3.2 Stability Analysis using Limit Equilibrium and Finite Element Methods
For this project we use GeoStudio and Plaxis software for stability and seepage Analysis of the
embankment dam the main difference between both software is, GeoStudio use limit equilibrium
Approach and Plaxis use Finite element method to determine the factor of safety.
There are two broad approaches to the determination of stability of embankment dams. One
approach is to determine the distribution of stresses and strains inside the embankment and its
foundations. These present a complete picture of the behavior of the dam and also enable
computation of the factor of safety on the most vulnerable surface by comparison with the shear
resistance that can be mobilized on that surface. This approach requires the application of theories
of elasticity or plasticity and solution of the equations based on those theories. General solutions
based on this approach have required gross simplifications due to the geometrically complex
nature of the boundaries, non-homogeneity of materials and their properties, and non-linearity
of the stress strain curves, particularly for cohesive soils. However, in the past twenty-five years
or so, developments in the finite-element method Together with availability of increasingly
powerful digital computers, has enabled geotechnical Designers to carry out detailed analyses of
stresses and strains with realistic assumptions. In fact, the accuracy of the results is only limited
by the reliability of input data for soil properties. This Approach has greatly enhanced the
confidence of designers in the design of dams of unprecedented heights or, under special
situations, e.g. steep abutment slopes.
However, the stress-distribution approach does not supplant the second ‘limit equilibrium’
approach in which a potential surface of sliding is assumed and the forces tending to cause slides,
or actuating forces, are compared with the resisting forces on that surface under incipient
failure conditions. The actuating forces consist of gravity forces due to the weight of the slip mass
and adverse seepage forces. During earthquakes transient inertial forces will come into play and in
certain soils a spurt in pore pressures may also occur. The resisting force is provided by the shear
strength of the soil. The ratio of actuating to resisting forces on an assumed slip surface is
considered the factor of safety on that surface. The least factor of safety is obtained by trial on a
number of assumed surfaces. The surface on which the factor of safety is the least is called the
'critical surface'. It may be noted that the distribution of shear stress on the surface is not uniform
and locally at some points the shear stress may even exceed the shear strength. The concept of
limit-equilibrium analysis is that unless the total resistance mobilized on the surface is exceeded
Semester Project 11
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
by the total shear stress, movement on the surface will not take place. The limit-
equilibrium approach is discussed in this chapter, while stress-distribution methods are taken up in
the next.
The limit-equilibrium approach is the one most commonly used by designers; the stress
distribution approach, now almost exclusively by F.E.M., is used on sections first checked by
limit equilibrium, to gain additional information and to refine the design.
The material properties of the shell, core and foundation part are determined from the soil
investigation results provided in the APPENDIX (A to C).
Using the following information, Material property and Geometry of the dam, the analysis will be as
follows.
Material property
Material
C (KN/m3) Φ (degrees) γsat (KN/m3) γdry (KN/m3)
Semester Project 12
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Factor of safety for down stream slope at the end of construction is 1.760
Semester Project 13
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Factor of safety for down stream slope for full reservior condition (Steady
Figure 3.7: Critical face of Upstream Slope under sudden drawdown condition
Semester Project 14
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
The construction is assumed to be constructed in four stages, for simplicity and to speed up the
work, because similar steps are to be carried out even though number of the construction stages
should be based on maximum depth of fill for effective compaction using the type of compacting
machine. And filling the reservoir with water, the stability is checked it will be carried out parallel
step by step along with the staged construction.
And hence, the 1st calculation with base typical cross sections is at which the soil failed at 3rd
filling stage.
And later the slope of the embankment was made gentler than the previous one. i.e. U/S 1V:3.5V
and D/S is 1V: 2.5 H. And this time the construction stage and the step by step filling was within
the allowed safety factors required by the standard we found from the book ADVANCED DAM
ENGINEERING FOR DESIGN CONSTRUCTION AND REHABILITATION, edited by Robert
B. Janson, Consulting Civil Engineer.
Hence, after the slope of the embankment and the core was made gentler, the factor of safety is
found are summarized in the following table.
Therefore, the dimension later selected that resulted with safety factor above the standard is fixed
to be the cross section of the earth fill dam.
Semester Project 15
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
When the reservoir is full, the discharge (seepage) through the dam material at selected section at
the center and at around the downstream are summarized under.
External velocity
Location Total Discharge (m3/s/m), q
(m/sec)
This is going to be used to calculate for how long the water reserved in the reservoir stays will,
and to compare it whether there is rain every year or in two years.
The allowable maximum seepage must be greater than this discharge too.
Q =1.594m3/sec
Semester Project 16
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Referring to the above summery table the factor of safety we get from both software analyses is different; it
is safe in both cases though. The factor of safety obtained from PLAXIS software is less than
obtained from GEOSTUDIO software because finite equilibrium method is relatively more
accurate than limit equilibrium. It gives more reasonable factor of safety.
Semester Project 17
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
4.2 Conclusion
Permeability of the core material is larger than that of the required specific for the core 1.06*10 -
4
m/s (according to the book, GEOTECHNICAL ENGINEERING OF DAMS, Robin Fell, Patrick
MacGregor, David Slapeledon & Graeme Bell), the permeability of most compacted earth fill core
materials is less than 10-8 or 10-9m/sec.
In embankment dams due to the nature of the soil materials and the statically indeterminate nature
of the problem, the factor of safety is not considered a precise measure of the margin of safety. Its
value can vary appreciably with the method of analysis adopted. The FS is to be interpreted in the
light of previous experience and used as a measure of comparison between alternative designs.
4.3 Recommendation
Because the core could be susceptible to seepage appropriate filter has to be provided to protect
the core material and hinder seepage of water. PLAXIS software gives more critical factor of
safety due to the method it uses so it is better to use PLAXIS rather than GEO STUDIO.
Semester Project 18
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
References
1. Coarse grained coal mine waste (Dawson et al., 1998; Taylor, 1984; Bishop et al., 1969;
2. DVANCED DAM ENGINEERING FOR DESIGN CONSTRUCTION AND
REHABILITATION, edited by Robert B. Janson, Consulting Civil Engineer.
3. GEOTECHNICAL ENGINEERING OF DAMS, Robin Fell, Patrick MacGregor, David
Slapeledon & Graeme Bell) Hutchinson, 1986)
4. Hydraulically placed mine tailings and fills in dam embankments (various published
sources)
5. Loose silty sand fills, Hong Kong (upper and lower quartile of pre 1977 fills (HKIE, 1998)
6. Sensitive clays (indicative limits from: Lefebvre, 1996; Bentley & Smalley, 1984; Mitchell
& Markell, 1974; Hutchinson, 1961,1965)
7. Sub-aqueous slopes, natural and fill slopes (Koppejan et al., 1948; Kramer, 1988; Sladen&
Hewitt 1989; Comforth et al., 1974)
Semester Project 19
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Appendix –A
A-1. Test Results on Foundation Part (Along dam axis)
Semester Project 20
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
A-3. The Test Results on Construction Materials of the Dam (Core, Shell and
Foundation)
Permeability tests
Compaction tests
Appendix –B
B-1. Report for SLOPE/W Analysis downstream
Semester Project 21
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Analysis Settings
SLOPE/W Analysis
Kind: SLOPE/W
Method: Morgenstern-Price
Settings
Side Function
Slip Surface
Tension Crack
FOS Distribution
Advanced
Number of Slices: 30
Semester Project 22
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Materials
Unit Weight: 16.19 kN/m³ Unit Weight: 19.12 kN/m³ Unit Weight: 17.53 kN/m³
Left-Zone Increment: 4
Right-Zone Increment: 4
Radius Increments: 4
Semester Project 23
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Coordinates Regions
X (m) Y (m)
Point 1 0 15
Point 2 140.5 15
Point 3 155 0
Point 4 0 0
Point 5 160.5 0
Point 6 175.5 15
Point 7 276 15
Point 8 276 0
Point 9 117 15
Point 10 199 15
Point 11 160 54
Point 12 156 54
Point 13 15.5 15
Point 14 155 55
Point 15 161 55
Point 16 261 15
Semester Project 24
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Slip Surface FOS Center (m) Radius (m) Entry (m) Exit (m)
Semester Project 25
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
-
32 12 259.19245 15.048655 13.47125 5.9724494 27.24
0.47718183
File Information
Revision Number: 23
Date: 7/4/2017
Time: 9:58:23 PM
Semester Project 26
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Project Settings
Length (L) Units: meters
View: 2D
Analysis Settings
SLOPE/W Analysis
Kind: SLOPE/W
Method: Morgenstern-Price
Settings
Side Function
Semester Project 27
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Tension Crack
FOS Distribution
Advanced
Number of Slices: 30
Materials
Semester Project 28
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Left-Zone Increment: 4
Right-Zone Increment: 4
Radius Increments: 4
Coordinates Regions
Point 1 0 15
Point 2 140.5 15
Point 3 155 0
Point 4 0 0
Semester Project 29
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Point 5 160.5 0
Point 6 175.5 15
Point 7 276 15
Point 8 276 0
Point 9 117 15
Point 10 199 15
Point 11 160 54
Point 12 156 54
Point 13 15.5 15
Point 14 155 55
Point 15 161 55
Point 16 261 15
Slip Surface FOS Center (m) Radius (m) Entry (m) Exit (m)
Semester Project 30
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Semester Project 31
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
File Information
Revision Number: 2
Date: 7/4/2017
Time: 10:09:14 PM
File Name: down streamreserviorfull.gsz
Directory: E:\PG DOcS\last project embankment\
Last Solved Date: 7/4/2017
Last Solved Time: 10:09:17 PM
Project Settings
Length (L) Units: meters
Time (t) Units: Seconds
Force (F) Units: kN
Pressure (p) Units: kPa
Strength Units: kPa
Unit Weight of Water: 9.807 kN/m³
View: 2D
Analysis Settings
SLOPE/W Analysis reservoir full
Kind: SLOPE/W
Method: Morgenstern-Price
Settings
Apply Phreatic Correction: No
Side Function
Interslice force function option: Half-Sine
Semester Project 32
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Materials
Unit Weight: 16.19 kN/m³ Unit Weight: 19.12 kN/m³ Unit Weight: 17.53 kN/m³
Semester Project 33
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Left-Zone Increment: 4
Right-Zone Increment: 4
Radius Increments: 4
Piezometric Lines
Coordinates Regions
Semester Project 34
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Points
X (m) Y (m)
Point 1 0 15
Point 2 140.5 15
Point 3 155 0
Point 4 0 0
Point 5 160.5 0
Point 6 175.5 15
Point 7 276 15
Point 8 276 0
Point 9 117 15
Point 10 199 15
Point 11 160 54
Point 12 156 54
Point 13 15.5 15
Point 14 155 55
Point 15 161 55
Point 16 261 15
Slip Surface FOS Center (m) Radius (m) Entry (m) Exit (m)
Semester Project 35
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Semester Project 36
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
File Information
Revision Number: 33
Date: 7/4/2017
Time: 10:22:45 PM
Semester Project 37
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Project Settings
View: 2D
Analysis Settings
Kind: SLOPE/W
Method: Morgenstern-Price
Settings
Side Function
Slip Surface
Tension Crack
Semester Project 38
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
FOS Distribution
Advanced
Number of Slices: 30
Materials
Foundation Shell Core
Model: Mohr-Coulomb Model: Mohr-Coulomb Model: Mohr-Coulomb
Unit Weight: 16.19kN/m³ Unit Weight: 19.12kN/m³ Unit Weight: 17.53kN/m³
Cohesion: 44.96 kPa Cohesion: 27.24 kPa Cohesion: 47.44 kPa
Phi: 25.63 ° Phi: 23.91 ° Phi: 23.94 °
Phi-B: 0 ° Phi-B: 0 ° Phi-B: 0 °
Pore Water Pressure Pore Water Pressure Pore Water Pressure
Piezometric Line: 1 Piezometric Line: 1 Piezometric Line: 1
Semester Project 39
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Left-Zone Increment: 4
276 15
Point
X (m) Y (m)
Point 1 0 15
Point 2 140.5 15
Point 3 155 0
Point 4 0 0
Point 5 160.5 0
Point 6 175.5 15
Point 7 276 15
Point 8 276 0
Point 9 117 15
Point 10 199 15
Semester Project 40
X (m) Y (m)
Point
Design1 and
0 Analysis
15 of Embankment Dams CENG 6210 2009 E.C
Point 11 160 54
Point 12 156 54
Point 13 15.5 15
Point 14 155 55
Point 15 161 55
Point 16 261 15
Critical Slip Surfaces
Slip Surface FOS Center (m) Radius (m) Entry (m) Exit (m)
Semester Project 41
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Semester Project 42
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Semester Project 43
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Semester Project 44
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
K Functions
Foundation
Model: Data Point Function
Function: X-Conductivity vs. Pore-Water Pressure
Curve Fit to Data: 100 %
Segment Curvature: 100 %
K-Saturation: 0.0001412
Data Points: Matric Suction (kPa), X-Conductivity (m/sec)
Data Point: (0.01, 0.0001412)
Data Point: (0.018329807, 0.00014111341)
Data Point: (0.033598183, 0.0001409345)
Data Point: (0.061584821, 0.00014064611)
Data Point: (0.11288379, 0.0001401765)
Data Point: (0.20691381, 0.00013939451) 0.37
Data Point: (926902, 0.00013808092)
Data Point: (0.6951928, 0.00013587243)
Data Point: (1.274275, 0.00013215006)
Data Point: (2.3357215, 0.00012598435)
Data Point: (4.2813324, 0.00011598917)
Data Point: (7.8475997, 0.00010048689)
Data Point: (14.384499, 7.8372335e-005)
Data Point: (26.366509, 5.101068e-005)
Data Point: (48.329302, 2.4754592e-005)
Data Point: (88.586679, 8.0092223e-006)
Data Point: (162.37767, 1.7203132e-006)
Data Point: (297.63514, 2.8338338e-007)
Data Point: (545.55948, 4.0109106e-008)
Data Point: (1000, 3.6893249e-009)
Estimation Properties
Volume Water Content Function: foundation
Hydraulic K Sat: 0.0001412 m/sec
Hyd. K-Function Estimation Method: Fredlund-Xing Function
Maximum: 1000
Semester Project 46
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Minimum: 0.01
Num. Points: 20
Residual Water Content: 0.3 m³/m³
Core
Model: Data Point Function
Function: X-Conductivity vs. Pore-Water Pressure
Curve Fit to Data: 100 %
Segment Curvature: 100 %
K-Saturation: 0.000106
Data Points: Matric Suction (kPa), X-Conductivity (m/sec)
Data Point: (0.01, 0.000106)
Data Point: (0.018329807, 0.000105935)
Data Point: (0.033598183, 0.00010580068)
Data Point: (0.061584821, 0.00010558418)
Data Point: (0.11288379, 0.00010523164)
Data Point: (0.20691381, 0.00010464459)
Data Point: (0.37926902, 0.00010365847)
Data Point: (0.6951928, 0.00010200055)
Data Point: (1.274275, 9.9206135e-005)
Data Point: (2.3357215, 9.4577487e-005)
Data Point: (4.2813324, 8.707402e-005)
Date point: (26.366509, 3.8294137e-005)
Data Point: (48.329302, 1.8583474e-005)
Data Point: (88.586679, 6.0125883e-006)
Data Point: (162.37767, 1.291453e-006)
Data Point: (297.63514, 2.1273816e-007)
Data Point: (545.55948, 3.0110227e-008)
Data Point: (7.8475997, 7.5436334e-005)
Data Point: (14.384499, 5.8834758e-005)
Data Point
Data Point: (1000, 2.769606e-009)
Estimation Properties
Volume Water Content Function: core
Semester Project 47
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Semester Project 48
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Estimation Properties
Volume Water Content Function: shell
Hydraulic K Sat: 0.000393 m/sec
Hyd. K-Function Estimation Method: Fredlund-Xing Function
Maximum: 1000
Minimum: 0.01
Num. Points: 20
Residual Water Content: 0.3 m³/m³
Vol. Water Content Functions
Foundation
Model: Data Point Function
Function: Vol. Water Content vs. Pore-Water Pressure
Curve Fit to Data: 100 %
Segment Curvature: 100 %
Mv: 0 /kPa
Porosity: 0.29999961
Data Points: Matric Suction (kPa), Vol. Water Content (m³/m³)
Data Point: (0.01, 0.29999961)
Data Point: (0.018329807, 0.29999916)
Data Point: (0.033598183, 0.29999812)
Data Point: (0.061584821, 0.29999573)
Data Point: (0.11288379, 0.29999014)
Data Point: (0.20691381, 0.2999769)
Data Point: (0.37926902, 0.29994529)
Data Point: (0.6951928, 0.29986923)
Data Point: (1.274275, 0.29968531)
Data Point: (2.3357215, 0.2992395)
Data Point: (4.2813324, 0.29816048)
Data Point: (7.8475997, 0.29557379)
Data Point: (14.384499, 0.28953871)
Data Point: (26.366509, 0.27634231)
Data Point: (48.329302, 0.25115239)
Data Point: (88.586679, 0.21310733)
Semester Project 49
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Semester Project 50
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Semester Project 51
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Semester Project 52
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Line 1 2 3
Line 2 3 4
Line 3 4 1
Line 4 5 6
Line 5 7 8
Line 6 8 5
Line 7 9 2
Line 8 6 10
Line 9 3 5
Line 10 10 11
Line 11 11 12
Line 12 12 9
Line 13 1 13
Line 14 13 9
Line 15 10 16
Line 16 16 7
Line 17 14 15
Line 18 15 16 Potential Seepage Face
Line 19 13 17 reserviour head- 53m
Line 20 17 14
Points
X (m) Y (m) Hydraulic Boundary
Point 1 0 15
Point 2 140.5 15
Point 3 155 0
Point 4 0 0
Point 5 160.5 0
Point 6 175.5 15
Point 7 276 15
Semester Project 53
Design and Analysis of Embankment Dams CENG 6210 2009 E.C
Point 8 276 0
Point 9 117 15
Point 10 199 15
Point 11 160 54
Point 12 156 54
Point 13 15.5 15
Point 14 155 55
Point 15 161 55
Point 16 261 15 Zero Pressure
Point 17 147.5 52.849462
Semester Project 54