chips. Please chosse to use the temperature parameters of lead or lead free
3 It’s often the incomplete weld when there is problem of the BGA chips.
there is no need to remove the chips. to use repairing welding methods has
a high success rate about 85%. There is no need to remove the chips at first.
1. Use FLUX liquid to scour clean the balls at bottom of BGA chip.
2. welding it.
4 How to set temperature curve which you need this problem is very
simple As we know the melting point of Lead ball is 183 and that of
First Set maximum temperature at 220 and then RUN, this is a very
critical time right now! when the upper temperature arise to about 200 . at
can be sliding. the chip will be downward collapse, when the balls was
fully liquefaction at this time you need to see the temperature values and
www.easyBGA.com
ACHI ®
time showed by the temperature controller or soft extend the time of this
temperature 10 -15 seconds longer after the solder ball became liquid now,
For example: we are reworking a Lead-free BGA chip, suppose the 160
is the second last segments the temperature values first we must
measurement the calefactive time from 160 to 220 suppose the time
begin to run, the balls began to liquefaction when we saw at 220 and
1 From 160
to 220 the calefactive time is 40 sec.
2 At 220
and need to lasted 15 Sec
3 40 sec
15 sec +10 sec 65 sec
220 25 Sec
160 40 Sec