Description NO. Description NO. Description NO. Description NO
Description NO. Description NO. Description NO. Description NO
PROGRAM OF WORK
( For All Types of Projects )
Roads
B. INDIRECT COST
1. Mobilization/Demobilization
2. Overhead, Contengencies and Miscellaneous 6.51% ₱ 3,231,869.02
(7% to 12% of A1 to A4)
3. Profit (5% to 12% of A1 to A4) 5.80% ₱ 2,877,313.01
4. Value Added Tax 10.17% ₱ 5,049,071.40
SUB-TOTAL (Contract Cost) 94.91% ₱ 47,124,666.12
III - CONTENGENCIES/RESERVES
1. Physical (Up to 5% of the estimated
contract cost)
2. Price Escalation (Up to 12% of the
estimated contract cost)
3. Budgetary Reserve
SUB-TOTAL
Prepared: Submitted :
Checked: Reviewed :
Approved:
Installation of Formworks
a. Skilled Laborer 2 1 51.51 103.02
b. Laborer 4 1 39.73 158.92
Sub - Total for A 856.84
a. Plywood Marine, 1/4" thk. X 4' x 8' sq.ft. 8.00 450.00 3,600.00
b. Good Lumber bd.ft. 84.00 70.00 5,880.00
c. Enamel Paint pc 2.00 550.00 1,100.00
d. Assorted Common Wire Nail kg. 5.00 70.00 350.00
e. Lighting and Accessories sets 4.00 2,500.00 10,000.00
G.
H.
I.
J.
K. Total Unit Cost 350,622.03
Project Name: Road Upgrading (Unpaved to Paved) Based on Gravel Road Strategies
Traffic Benchmark for Upgrading to Paved Road Standards
La Paz - Javer - Bito Road
Chainage 2558 - Chainage 2848
Chainage 2900 - Chainage 3095
Chainage 3649 - Chainage 3807
Chainage 4105 - Chainage 4522
Chainage 4602 - Chainage 5625
Chainage 5923 - Chainage 6315
ROAD
1 100 Removal of Stone Masonry
2 100 (3) Removal of RCPC (24"Ø) - 610mm
3 102 (2) Removal of Existing Concrete Pavement
4 103 (1) Embankment, from Roadway Excavation
5 103 (3) Embankment, from Structure Excavation
6 103 (6) Embankment, from Borrow
7 104 (1) Subgrade Preparation (Common Excavation)
8 105 Aggregate Sub-Base Course
9 200 Aggregate Base Course
10 300 PCC Pavement, 230 mm. thk.
11 311 Reinforcing Steel Bar, Grade 40 (Minor Structures)
12 404 Structural Concrete Class A (Minor Structure)
13 405 Pipe Culverts (36" dia.) - 910 mm
14 500 (3) Stone Masonry
15 505 (5) Masonry Works (CHB Lined Canal)
16 506 Construction Safety & Health
17 603 (3)a Project Billboard
18 603 (3)a Traffic Management
622 (1)
622 (3)
SPCL I
SPCL II
SPCL III
SPCL IV
SPCL V
TOTAL
NOTE: ENTER DATA ON THIS SUMMARY ON THE CELLS WITH GREEN COLOR ONLY.
canal length
canal excavation
canal concrete
canal chb area
canal reinforcement
TOTAL LENGTH
d Strategies
35,966,412.69 22,685,572.70
#REF!
#REF!
SUMMARY UNIT DUPA UNIT
INDIRECT COST TOTAL COST COST COST REMARKS
11,158,253.43 47,124,666.12
- -
NTRACT COST 47,124,666.12 #REF!
V'T. EXPENDITURES:
EAO (2% of Contract 1,000,000.00 #REF!
RROW #REF!
PRICE ESCALATION #REF!
EIA #REF!
GAD 1,500,000.00
Advertisement 25,000.00
#REF!
49,649,666.12
APPROVED BUDGET FOR THE CONTRACT
Road Upgrading (Unpaved to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road Standards, La Paz - Javer - Bito Road
Project Name and Location
ANNEX "A"
Stations : Chainage 2558 - Chainage 2848, Chainage 2900 - Chainage 3095, Chainage 3649 - Chainage 3807 APPROPRIATION : P 50,000,000.00
Chainage 4105 - Chainage 4522, Chainage 4602 - Chainage 5625, Chainage 5923 - Chainage 6315
CESAR V. MAKABENTA, DM NORBERTO P. BOCO CARLOS G. VELOSO ANGELITA G. OPINA EDGAR B. TABACON, CESO IV ROLANDO M. ASIS, CESO III
Engineer III Chief, Planning & Design Section District Engineer Chief, Planning & Design Division Assistant Regional Director Regional Director
EQUIPMENT RENTAL MANPOWER RATE
Truck-mounted Crane ( 31T 14,120.00 Carpenter 309.40
Crawler Crane ( 61T-70T ) 29,520.00 Foreman 428.40
Plate Compactor 1,860.00 Laborer 238.00
Air Compressor, 51Hp 3,032.00 Mason 309.40
Backhoe, Cap 0.80 M^3 12,296.00 Steelman 309.40
Bar Bender 334.50 Welder 309.40
Bar Cutter 334.50 Operators 309.40
Batching Plant, Cap 30 M^ 9,035.92 Painter 309.40
Bulldozer 28,950.00 Riggerman 309.40
Chainsaw 650.00 Engineer 650.00
Bulldozer 28,950.00 SELDOM USED
Concrete Cart 250.00 MANPOWER: RATE:
Concrete Mixer 1,376.00
Concrete Saw 2,327.30
Concrete Vibrator 972.00
Concrete Screeder 1,035.12
Diesel Hammer 4,997.00
Drop Hammer w/ guide 650.00
Dumptruck, Cap. 11 M^3 10,816.00
Generator, 125 KVA 1,214.00
Jackhammer 575.00
Hydraulic Jack, 50T 6,000.00
Payloader, Cap 1.5 M^3 13,864.00
Vibratory Roller, 1 tonner 8,680.00
Road Grader, 140Hp / 67 I 17,384.00
Road Roller, Cap. 9-11 MT 4,536.00
Transit Mixer,Cap 5 M^3 10,232.00
Stake truck w/ boom 8,325.00
Water Truck, Cap 1000 Lite 8,520.00
Pneumatic Road Roller 4,424.00
SELDOM USED EQPT. RATE
Asphalt Distributor, 5Hp/5 7,488.00
Tower Lights, 2.70 kW w/ g 2,625.00
Concrete Pump ( 95HP ) 8,220.00
Asphalt Paver, 90 Hp/10 FT 11,312.00
Cable tensioner 3,650.00
Power Tools 1,500.00
Drilling Machine 500.00
Electric Sheer Cutter 550.00
Grinding Machine 250.00
Oxygen Outfit 220.00
Paint Outfit 220.00
Sand Blasting Machine 120.00
Water Pump 295.00
Welding Outfit 550.00
Grouting Machine 350.00
Concrete Bucket 832.50
Chaulking Gun 1,000.00
Spray Gun 500.00
MATERIAL UNIT PRICE
Aggregate Base Course Materials Cu. M. 910.00
Aggregate Subbase Course Materials Cu. M. 460.00
Boulders Cu. M. 800.00
Coco Lumber Bd. Ft. 25.00
Coco Trunks Pcs. 500.00
CWN, Assorted Kg. 50.00
CWN, Assorted Kegs 2,500.00
Tie Wire Roll 2,024.00
Crushed Gravel Cu. M. 1,150.00
Plywood, 1/4" x 4' x 8' Pcs. 950.00
Anchor bars kgs. 80.00
Portland Cement Bags 225.00
Yakal Lumber Bd. Ft. 45.00
Reinforcing Steel Bars, Grade 40 Kg. 60.00
Fine Sand Cu. M. 1,100.00
CHB, 4" thick Pcs. 15.00
Tie Wire Kg. 50.00
Bearing Pad, 36 x 400 x 700 Hardness 6 Pcs. 4,500.00
GI Pipe, 70mm dia. X 500 Pcs. 300.00
GI Sheet, gauge 16 sht 1,200.00
Plywood, 3/8" X 4' X 8' Pcs. 500.00
PVC Pipe Pcs. 85.00
Calcified Materials Cu. M. 800.00
7/8" f x 3" HTB Pcs. 55.00
Welding Rod box 1,500.00
Mastic Compound kgs. 30.00
Rust Converter Gal 285.00
GI Pipe, 70mm f x 500 Pcs. 300.00
Reinforcing Steel Bars, Grade 40 Kg. 60.00
Embankment Materials Cu. M. 260.00
SELDOM USED MATERIALS UNIT PRICE
Structural Epoxy Gal 4,200.00
Oxygen Tanks 1,350.00
Acetelyne Tanks 2,100.00
Electrodes boxes 1,500.00
12" x 65.00 #/ft Wide Flange Pcs. 34,500.00
Ordinary Plywood, 1/4" tihick Pcs. 550.00
Epoxy Red Lead Primer Gal 1,650.00
Epoxy Aluminum Paint Gal 1,800.00
3"x 7.10 lbs/ft"x 7' Channel Pcs. 710.00
1/2" f x 1" HTB Pcs. 35.00
Paint Brush Pcs. 120.00
Paint Thinner Gal 300.00
45 deg Elbow x 100 mm GI (S-40) Pcs. 400.00
100mm f x 6.00m GI Pipe (S-40) Pcs. 2,500.00
Steel Plate 1200 x 2400 x 10 Pcs. 8,100.00
Steel Plate 1200 x 2400 x 6 Pcs. 5,600.00
Steel Bearing set 95,000.00
8" x 15.50 #/ft Structural Tee Pcs. 9,500.00
Project Name: Road Upgrading (Unpaved to Paved) Based on Gravel Road Strategies
Location: -
La Paz, Leyte
REF. NO. Name & Capacity HOURLY RATE DAILY RATE REMARKS
REF. NO. Name & Capacity HOURLY RATE DAILY RATE REMARKS
UNIT PRICE
(Based on
HAULING
REF. NO. DESCRIPTION UNIT Canvass or TOTAL PRICE REMARKS
COST
Regional Price
Monitoring)
M01 Portland Cement Bag 250.00 #REF! #REF! See attached hauling cost analysis
M02 Sand Cu.m. 1,200.00 183.00 1,383.00 See attached hauling cost analysis
M03 Gravel Cu.m. 1,800.00 183.00 1,983.00 See attached hauling cost analysis
M04 Aggregate Subbase Course Cu.m. 800.00 602.00 1,402.00
Natural Gravel Cu.m. 1,300.00 602.00 1,902.00
M05 Granular Materials Cu.m. 520.00 520.00
M06 Reinforcing Steel Bar, Grade 40 Kg 50.00 1.00 51.00 See attached hauling cost analysis
M06 Reinforcing Steel Bar, Grade 60 Kg 55.00 1.00 56.00
M07 Tie Wire # 16 Kg 54.00 - 54.00
M08 Boulders (Rock Class "A") Cu.m. 1,300.00 189.00 1,489.00 See attached hauling cost analysis
M09 PVC Pipe, 2"Ø lin m 100.00 - 100.00
M10 0.910mm Ø RCPC Pc - - -
M11 Steel Forms L.M - - -
M12 Curing Compound Liter 150.00 - 150.00
M13 Asphalt Sealant Liter 120.00 - 120.00
M14 Form Lumber, Coco bd.Ft. 20.00 - 20.00
M14 Good Lumber, Falsework bd.Ft. 40.00 - 40.00
M15 Yakal Lumber bd.Ft. 50.00 - 50.00
M16 Marine Plywood, 4' X 8' X 1/2" Pc 650.00 - 650.00
M17 Ordinary Plywood, 4' X 8' X 1/2" Pc 580.00 - 580.00
M18 CW nails, Assorted Kg 70.00 - 70.00
M19 4' x 8' - Tarpauline (Printed) Pc 950.00 - 950.00
M20 Embankment Materials, Selcted Borrow cu m 350.00 - 350.00
M21 Coco Trunk / Log L.M 83.00 - 83.00
M21 Pile Shoe pc 2,200.00 - 2,200.00
M21 Filter Cloth Sq. M. 450.00 - 450.00
M23 Precast RC Piles(450mX 450mm) L.M. 4,500.00 250.00 4,750.00
M24 Steel Sheet Piles kg 120.00 - 120.00
M25 Premolded Expansion Joint Filler Sq. M. 900.00 - 900.00
M26 Welding Rod kg 80.00 - 80.00
M26 Sructural Steel kg 65.00 - 65.00
Road Upgrading (Unpaved to Paved) Based on Gravel Road Strategies
La Paz - Javer - Bito Road
-
La Paz, Leyte
PORTLAND CEMENT
Source: Tacloban
LOADING: Free
UNLOADING
Manual unloading:
Rate of Manual unloading = 0.5 min. per bag
No. of bags/truck = 10000 kg. / 40 kg. per bag
= 250 bags
Time = 250 bags x 0.5 min. per bag
= 125 min.
= 2.08 hrs.
RETURN TRIP
Distance = 41 km.
12 km.
Speed = 40 kph
30 kph
Hauling Time = 1.425 hrs.
La Paz, Leyte
LOADING: Free
UNLOADING
Time: 2 min.
= 0.0333333333 hr.
RETURN TRIP
Distance = 12 km.
Speed = 30 kph
Hauling Time = 0.4 hrs.
600.00 + 183.00
MAT'L. COST = 783.00
La Paz, Leyte
LOADING: Free
UNLOADING
Time: 2 min.
= 0.0333333333 hr.
RETURN TRIP
Distance = 12 km.
Speed = 30 kph
Hauling Time = 0.4 hrs.
700.00 + 183.00
MAT'L. COST = 883.00
SAND
LOADING: Free
UNLOADING
Time: 2 min.
= 0.0333333333 hr.
RETURN TRIP
Distance = 12 km.
Speed = 30 kph
Hauling Time = 0.4 hrs.
800.00 + 183.00
MAT'L. COST = 983.00
GRAVEL
LOADING: Free
UNLOADING
Time: 2 min.
= 0.0333333333 hr.
RETURN TRIP
Distance = 12 km.
Speed = 30 kph
Hauling Time = 0.4 hrs.
1,200.00 + 183.00
MAT'L. COST = 1,383.00
LOADING: Free
UNLOADING
Time: 2 min.
= 0.0333333333 hr.
RETURN TRIP
Distance = 12 km.
Speed = 30 kph
Hauling Time = 0.4 hrs.
300.00 + 183.00
MAT'L. COST = 483.00
BOULDERS
LOADING: Free
UNLOADING
Time: 4 min.
= 0.0666666667 hr.
RETURN TRIP
Distance = 12 km.
Speed = 30 kph
Hauling Time = 0.4 hrs.
800.00 + 189.00
MAT'L. COST = 989.00
LOADING: Free
UNLOADING
Time = 3 hr.
RETURN TRIP
Distance = 23 km. (Rolling)
12 km. (Mountainous)
Speed = 40 kph (Rolling)
30 kph (Mountainous)
Hauling Time = 0.975 hrs.
Source: Tacloban
LOADING: Free
UNLOADING
Manual Unloading: Free
Time = 4 hrs.
RETURN TRIP
Distance = 41 km. (Rolling)
12 km. (Mountainous)
Speed = 40 kph (Rolling)
30 kph (Mountainous)
Hauling Time = 1.425 hrs.
50.00 + 1.00
MAT'L. COST = 51.00
RETURN TRIP
Basic Equipment SPEED Rate Hauling Rate of Manual Time SPEED Hauling SUBTOTAL 10% allow. TOTAL Hauling Material
Materials Unit Capacity Amount
Price USE (km/hr) per hr Time Unloading (hr) (km/hr) Time TIME (hr) per delay TIME Cost COST
Aggregate Subbase Cour cu.m. 600 Dump truck 20 11 cu.m. 1,352.00 0.7 2 min/cu.m. 0.37 30 0.47 1.54 0.154 1.694 2,290 208 808.00 say 810.00
Aggregate Base Course cu.m. 650 Dump truck 20 11 cu.m. 1,352.00 0.7 2 min/cu.m. 0.37 30 0.47 1.54 0.154 1.694 2,290 208 858.00 say 860.00
Gravel cu.m. 850 Dump truck 20 11 cu.m. 1,352.00 0.7 2 min/cu.m. 0.37 30 0.47 1.54 0.154 1.694 2,290 208 1,058.00 say 1,060.00
Boulder cu.m. 730 Dump truck 20 11 cu.m. 1,352.00 0.7 2 min/cu.m. 0.37 30 0.47 1.54 0.154 1.694 2,290 208 938.00 say 940.00
Sand cu.m. 800 Dump truck 20 11 cu.m. 1,352.00 0.7 2 min/cu.m. 0.37 30 0.47 1.54 0.154 1.694 2,290 208 1,008.00 say 1,010.00