Micropiles Monitoring Table

The document summarizes the drilling and installation of micropiles for a tower crane foundation. It includes details on 26 piles across groups A through F, listing information such as pile type, drilled length, casing length, drilling dates, grouting dates and amounts. Some piles are noted as completed while others are still in progress, and one pile had a broken drill bit left in the hole.

Uploaded by

edla3710
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
44 views

Micropiles Monitoring Table

The document summarizes the drilling and installation of micropiles for a tower crane foundation. It includes details on 26 piles across groups A through F, listing information such as pile type, drilled length, casing length, drilling dates, grouting dates and amounts. Some piles are noted as completed while others are still in progress, and one pile had a broken drill bit left in the hole.

Uploaded by

edla3710
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

TOWER CRANE MICROPILES Data Date 10-Aug-18

GROUP A
Redrilling
Pile ID Type Drilled Lenght Casing Lenght Drill start Drill finish Grout Grout start Grout finish Bags Cm Remarks
Lenght
A1 V 10.2 01-Aug-18 01-Aug-18 Yes 01-Aug-18 01-Aug-18 10 COMPLETED
A2 V 10.5 07-Aug-18 07-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
A3 V 10.4 01-Aug-18 01-Aug-18 Yes 01-Aug-18 01-Aug-18 12.5 COMPLETED
A4 V 10.7 03-Aug-18 03-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
A5 V 10.4 01-Aug-18 01-Aug-18 Yes 01-Aug-18 01-Aug-18 12.5 COMPLETED
03-Aug-18 03-Aug-18 08-Jul-18 08-Jul-18 Grout for redrill
A6 V 4 11.2 Yes
10-Aug-18 10-Aug-18
B1 V 10.5 04-Aug-18 04-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
B2 V 10.5 02-Aug-18 02-Aug-18 Yes 03-Aug-18 03-Aug-18 20 COMPLETED
B3 V 10.8 04-Aug-18 04-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
B4 V 10.7 08-Aug-18 08-Aug-18
B5 V 10.7 04-Aug-18 04-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
B6 V
C1 V 11.1 10-Aug-18 10-Aug-18
C2 V 11.2 06-Aug-18 06-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
C3 V 11.2 10-Aug-18 10-Aug-18
C4 V 10.58 06-Aug-18 06-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
C5 V 11.4 10-Aug-18 10-Aug-18
C6 V 10.7 06-Aug-18 06-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
D1 V 10.5 06-Aug-18 06-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
D2 V 10.8 10-Aug-18 10-Aug-18
D3 V 10.5 06-Aug-18 06-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
D4 V 10.8 10-Aug-18 10-Aug-18
D5 V 10.5 06-Aug-18 06-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
D6 V 10.8 10-Aug-18 10-Aug-18
E1 V
E2 V 10.8 07-Aug-18 07-Aug-18 Yes 08-Aug-18 08-Aug-18 25 COMPLETED
E3 V 10.5 10-Aug-18 10-Aug-18
E4 V 10.7 07-Aug-18 07-Aug-18 Yes 08-Aug-18 08-Aug-18 15 COMPLETED
E5 V
E6 V 6.3 07-Aug-18 07-Aug-18 Yes Drill bit broken left inside the hole
F1 V
F2 V
F3 V
F4 V
F5 V
F6 V