GROUP A
Redrilling
Pile ID Type Drilled Lenght Casing Lenght Drill start Drill finish Grout Grout start Grout finish Bags Cm Remarks
Lenght
A1 V 10.2 01-Aug-18 01-Aug-18 Yes 01-Aug-18 01-Aug-18 10 COMPLETED
A2 V 10.5 07-Aug-18 07-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
A3 V 10.4 01-Aug-18 01-Aug-18 Yes 01-Aug-18 01-Aug-18 12.5 COMPLETED
A4 V 10.7 03-Aug-18 03-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
A5 V 10.4 01-Aug-18 01-Aug-18 Yes 01-Aug-18 01-Aug-18 12.5 COMPLETED
03-Aug-18 03-Aug-18 08-Jul-18 08-Jul-18 Grout for redrill
A6 V 4 11.2 Yes
10-Aug-18 10-Aug-18
B1 V 10.5 04-Aug-18 04-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
B2 V 10.5 02-Aug-18 02-Aug-18 Yes 03-Aug-18 03-Aug-18 20 COMPLETED
B3 V 10.8 04-Aug-18 04-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
B4 V 10.7 08-Aug-18 08-Aug-18
B5 V 10.7 04-Aug-18 04-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
B6 V
C1 V 11.1 10-Aug-18 10-Aug-18
C2 V 11.2 06-Aug-18 06-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
C3 V 11.2 10-Aug-18 10-Aug-18
C4 V 10.58 06-Aug-18 06-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
C5 V 11.4 10-Aug-18 10-Aug-18
C6 V 10.7 06-Aug-18 06-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
D1 V 10.5 06-Aug-18 06-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
D2 V 10.8 10-Aug-18 10-Aug-18
D3 V 10.5 06-Aug-18 06-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
D4 V 10.8 10-Aug-18 10-Aug-18
D5 V 10.5 06-Aug-18 06-Aug-18 Yes 07-Aug-18 07-Aug-18 15 COMPLETED
D6 V 10.8 10-Aug-18 10-Aug-18
E1 V
E2 V 10.8 07-Aug-18 07-Aug-18 Yes 08-Aug-18 08-Aug-18 25 COMPLETED
E3 V 10.5 10-Aug-18 10-Aug-18
E4 V 10.7 07-Aug-18 07-Aug-18 Yes 08-Aug-18 08-Aug-18 15 COMPLETED
E5 V
E6 V 6.3 07-Aug-18 07-Aug-18 Yes Drill bit broken left inside the hole
F1 V
F2 V
F3 V
F4 V
F5 V
F6 V