Main Problems in A Canal Network: Canals
Main Problems in A Canal Network: Canals
Chapter 4
4.1 INTRODUCTION
This chapter looks at problems which are frequently encountered in irrigation canal systems.
Some of these are described in detail. The last section of this chapter explains why regular
inspection of the system is required.
The main problems that can be found in an irrigation canal network include:
- limited amounts of water available at the water source;
- high water consumption in fields close to the water source resulting in water shortages
at the tail end of the scheme;
- illegal manipulation of canals and structures;
- siltation;
- plant growth;
- water losses;
- frequent overtopping; and
- low water levels due to canal erosion.
Some of these problems may be caused by sub-optimal management and organization within
the scheme, and Training Manual 10 in this series will cover that subject.
Bad design or bad construction may also be the cause of sub-optimal functioning of a
scheme. A canal may be too small to supply enough water to irrigate the area served by the
canal, and if the discharge needed is supplied to such a canal, it will be excessive and water will
overtop. Also the water level in a canal may have been wrongly determined, and if it is too low
water may not enter the fields by gravity. Check structures or even pumps will then be needed
to supply the fields with sufficient water.
If the minimum required free board levels are not respected, canals can easily overtop in
emergencies.
Canal slopes which are too steep may suffer erosion from high flow velocities. When
construction materials are not well chosen, canals may collapse.
Lack of maintenance of the canal network will also cause severe problems, which are
discussed later, in Chapter 5.
Seepage
Water that seeps through the bed and sides of a canal will be lost for irrigation. This so-called
‘seepage loss’ can be significant where a canal is constructed from material which has a high
permeability: water seeps quickly
through a sandy soil and slowly
through a clay soil, and so canals FIGURE 22
constructed in sandy soils will have Canal with seepage water at the toe of the canal
more seepage losses than canals in embankment
clay soils.
The results of seepage
through the sides of a canal can
sometimes be very obvious, such as
when fields adjacent to a canal
become very wet, and even have
standing water (See Figure 22).
Seepage loss through the
canal bed is difficult to detect
because water goes down and does not appear on the nearby ground surface. Seepage can be
reduced by:
• reinforcing the canal bank (See Section 5.3), or
• sealing or lining the canal bed and sides (See Chapter 6).
Leakage
Water may also be lost for irrigation by leakage. This water does not seep, but flows through
larger openings in the canal bed or sides.
Leaks can develop in several ways:
• by rat or termite holes in a canal bed or sides;
• eroded and washed canal bank;
• small tunnels started by seepage water in a badly compacted or sandy section of a canal
bank;
• seepage around structures, leading to severe leakages;
• gates which are not tightly sealed;
• cracked concrete canal linings, or joints that are not tightly sealed; or
• torn asphalt or plastic lining.
Leakage often starts on a small scale, but the moment that water has found a way through a
canal embankment a hole will develop through which water will leak. If the leakage is not
stopped in time, the tunnel becomes larger and the canal bank may be washed away at a certain
moment. In the case of a lined canal, the canal foundation may be undermined after some time
and the canal will collapse.
Canals 23
Serious leakage can be avoided when the canal system is inspected frequently and when
repairs are carried out immediately. The longer a hole or crack is left, the larger it will become.
Figures 23 and 24 show that quick action can save time and money.
FIGURE 23
A crack in a canal bank is repaired soon after it has been observed
In Figure 23, a small hole in a canal bank is repaired soon after it has been observed. In
Figure 24, no attention has been paid to the leak, and, after some weeks, part of the canal bank
has been washed away by the continuously leaking water. More time and money is needed to
repair the canal in this case.
Repair of a leak is described in Section 5.4.
4.2.2 Overtopping
Water in a canal may rise unexpectedly due to several reasons:
• the incoming flow through the canal offtake may be much greater than the canal capacity;
• obstacles such as stones, blocks or plant growth in the canal may dam up the water;
• outlets from a canal may be closed which should be open;
• rain or other water may be draining into the irrigation canal; or
• farmers may make temporary weirs to raise the water level.
If no action is taken, the water level can reach the top of the canal banks and overtop. See
Figure 25.
Overtopping causes erosion of the canal banks and may lead to serious breaches. It can
be avoided by improving the operation of the system. Discharges should be limited and gates
should only be closed and opened according to the planned schedule. To prevent overtopping,
which can happen even in the best irrigation systems, a spillway - also called an emergency
24 Main problems in a canal network
FIGURE 24
Delayed repair of a leakage
outlet - can be installed in the canal bank so that excess flow can be spilled without harming the
canal. See also Section 5.5, and Training Manual 8: Structures.
Another problem is that the eroded soil will be deposited , known as siltation , in structures
downstream of the eroded canal section. This may cause a malfunctioning of the structures.
Eroded soil could also be deposited in canal sections, thus reducing the capacity and causing
the flow to overtop the bank.
Canals that are constructed with
soil that contains a high content of sand
are very susceptible to erosion. To avoid
erosion of such a canal, the flow velocity
must be very low, and the side slopes
must be flat. In this respect limits are set
on the flow velocity and the side slope,
and these are given in Table 2.
When the velocity in a canal
exceeds the limiting flow velocity, un-
acceptable erosion of the canal is to be
expected, and, when the side slopes of a
canal are steeper than the limiting side
slopes, the canal banks may collapse.
These limiting values depend on the material which has been used for constructing the
canal. The flow velocity in a canal made with a clay soil can be higher than the flow velocity in
a canal made from sandy material. The banks of a clay canal can also be made steeper than the
banks of a sandy canal.
Erosion by water can be prevented by:
• reducing the flow velocity, and
• making the inner canal banks more stable,
and if a canal continues to suffer from erosion:
• lining may be a solution.
The top and outer slopes of canal embankments may also suffer from erosion. The
banks may be gullied by overtopping water or by heavy rainfall. Wetting and drying of the
earth embankments may also cause the banks to crack. Cracks can become small gullies through
the process of erosion. In this way the available free board of the canal may be reduced.
For repair and prevention, see Section 5.6, and lining is described in Chapter 6.
The repair of an eroded canal section downstream of a structure is described in Training
Manual 8: Structures, in this series.
FIGURE 27
Heavy plant growth makes inspection difficult
28 Main problems in a canal network
FIGURE 28
Clean canal embankments are conditional for rapid inspection