Cable Stayed Bridge (Content)
Cable Stayed Bridge (Content)
Midas
Training
Series
midas
Practical Modeling for Civil
3. Nonlinear Effect
a. Sag effects of long cables
b. P-Delta effects
c. Large deformations
d. Material nonlinearity 2018
Extra-dosed Bridge
Cable-stayed Bridge
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
1. Introduction
4
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
1. Introduction
5
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
1. Introduction
1 2 3 4
Determine Back
Determine Cable Determine Deck Determine Pylon
span to main span
Spacing Stiffness Height
ratio
5 6 7 8
Deck Erection
Determine Deck Form
Preliminary Cable Deck Design (Backward /
(Concrete /
Force Forward Stage
Composite / Hybrid)
Analysis)
Unknown Load Factor
9 X
Lack of Fit Force
Unknown Load Factor
Cable Force Tuning
Static Analysis Dynamic Analysis
6
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
1. Introduction
The ratio between back span and the main span should be less than 0.5. It influences the
uplift forces at the anchor pier and the range of load within the back stay cables supporting
the top of the pylon.
The spacing of the stay anchors along the deck should be compatible with the capacity of the
longitudinal girders and limit the stay size.
The spacing should also be small enough so that the deck may be erected by the free
cantilevering method.
7
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
1. Introduction
The deflection of the longitudinal girders is primarily determined by the stay layout.
Depth of girders should be kept to minimum, subject to sufficient area and stiffness being
provided to carry the large compressive forces without buckling.
The height of the pylon will determine the overall stiffness of the structure. As the stay angle
increases, the required stay size will decrease as will the height of the pylon. However, the
deflection of the deck will increase as each stay becomes longer.
The most efficient stay is that with a stay inclination of 45°. In practice the efficiency of the
stay is not significantly impaired when the stay inclination is varied within 25 ~ 65°.
This implies an optimum ratio of pylon height above the deck (h) to main span (l) is between
0.2 and 0.25.
a
b 8
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
1. Introduction
The main span stay forces resist the dead loads such that there is no deflection of the deck or
pylon and the vertical components due to these loads are therefore known.
An initial approximation of the main span stay forces can be determined by considering the
structure as a simple truss ignoring bending stiffness of both the pylon and the deck. Ignoring
bending stiffness of the pylon will be a valid assumption as the bending stiffness of the pylon
is usually small when compared to the axial stiffness of the stays.
The back stay anchoring forces can be calculated assuming the horizontal component of the
main span and back span stay forces are balanced at the pylon.
The primary factors influencing the choice of deck will be the length of the main span and
deck width.
Concrete deck section is the most economic for the span range 200-400m and the composite
deck above 400m.
Above 600m a hybrid combination is economic with the back span as concrete and the main
span in an all steel construction. 9
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
1. Introduction
1. Introduction
For the final analysis, the most common approach is to model either a half or the entire
structure as a space frame. The pylon, deck and the stays will usually be represented within
the space frame model by “bar/truss” elements.
The stays can be represented with a small inertia and a modified modulus of elasticity that will
mimic the sag behavior of the stay.
11
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
Modeling Techniques:
12
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
Example Problem 1:
General Layout
13
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
Example Problem 1:
Tower Layout
14
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
15
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
16
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
Modeling symmetric
or Asymmetric bridge
Truss & Cable
element
Box sloped girders
Vertical station of
Girder
Below model is used for Final Stage Analysis with the relevant boundary conditions.
18
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
Truss Element
•Uniaxial tension-compression line element
•Used to model space trusses or diagonal braces
•Undergoes axial deformation only
element length
Lh: horizontal projection length of the cable element 20
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
21
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
The sag has a softening effect on the cable stiffness so that this results in a non-linear force-displacement relationship. For large values
of sag, the cable has a relatively low stiffness. As the sag decreases, the cable stiffness increases and the behavior of the cable comes
close to a truss bar tension element.
22
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
1. Starting Point of a cable stayed bridge is an 1. To determine the forces in the cable stays at each
idealized stressed state at a given time : this is construction stage.
called final stage.
2. Check stresses in the girder, pylon and cables at each
2. Static and dynamic analyses and section design construction stage.
are undertaken using the final stage.
3. Check deformation of the structure at each
3. Construction Sequence and Cable installation construction stage. Provide Camber accordingly.
forces are developed such that the final stage is
achieved at the given time.
24
Cable Stayed Bridge Design in midas Civil
Midas
Training
25
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
3. Nonlinear Effect
element length
Lh: horizontal projection length of the cable element
26
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
3. Nonlinear Effect
27
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
3. Nonlinear Effect
28
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
Copy &
Paste
29
Unknown Load Factor Method in Midas civil
Unknown Load Factor: It is a feature with which you can calculate the cable pretension force that would satisfy certain c
onstraints in terms of displacements, bending moments etc.
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
Square: The linear sum of the squares of Load factor x scale factor
Max Abs: The maximum of the absolute values of Load factor x scale factor
Sign of Unknowns: Assign the sign of the unknown load factors to be calculated.
Negative: Limit the range of the calculated values to the negative (-) field.
Both: Do not limit the range of the calculated values.
Positive: Limit the range of the calculated values to the positive (+) field.
Linear
T2
Numerous solutions
satisfying the inequality
conditions Square
Square
T1 Max. Abs
Linear Max. Abs
33
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
Moment/Displacement
at the corresponding
element/Node ID due
to a unit load applied
for each load case.
Ti δi
Example Problem 1:
35
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
36
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
The unknown load factors obtained by using the Unknown Load Factor feature for the final stage
model do not include the change in stiffness of the cable due to the change in pretension.
Therefore the user must use truss element in Unknown Load Factor. In order to determine the
pretension in the truss element to satisfy constraints, iteration will be required. The following
procedure can be adopted:
1. Define the constraints and obtain the Unknown Load Factors for the Pretension Forces.
2. Determine the Pretension Force by multiplying those factors with the assigned Pretension Loads
3. Change the Pretension Forces with the new ones ( obtained in step 2)
4. Perform the Analysis.
5. Check whether the constraints are satisfied with modified pretensions
6. If not then determine the Unknown load factors again and keep repeating steps 2 to 5 till you get
the constraints satisfied after static analysis ( step 5)
37
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
Reduce the repetitive computation process to obtain the optimum cable pretension.
Calculates the effects of the cable pretension (or load factor) on the displacements/
member forces/ stresses through influence matrix and updates the results graph in real
time.
38
- Part -2
5. Construction Stage Analysis Midas
a. Backward and forward analysis Training
b. Initial cable forces at the time of installation Series
c. Unknown Load Factor function midas
d. Example Problem 2
e. Camber Control
Civil
f. Consideration in Construction Stage
6. Dynamic Analysis
a. Initial Stiffness in Cable Elements
b. Modal analysis
c. Seismic analysis 2018
7. Post-Processing
a. Max / Min stress check during erection
b. Cable configuration
c. Cable efficiency
41
One of the difficulties associated with forward stage analysis is to find tension forces at
construction stages. With the facility of the lack of fit force functionality, additional pretension
loads, which are introduced during the installation of cables, are calculated, and member forces
are preloaded at Key Segment such that member forces at key segment closure are the same as
those at the completed state. Using these pretension and member forces, forward stage analyses
are performed.
*Limitation
Not applicable with Creep/Shrinkage option.
43
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
44
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
45
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
46
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
47
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
Modeling Method
Method 1) Create a stage in which only cables are activated and the stage duration is zero. Specify the stage as
‘Unknown’.
Method 2) Save results for ‘Additional Steps’ as well as ‘Stage’ in the Construction Stage dialog. Activate cables at
the first step of a stage. Specify the step as ‘Unknown’ in the Unknown Load Factor function.
48
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
49
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
50
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
51
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
52
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
53
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
54
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
55
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
56
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
[Manufactured Camber]
=Stage/Step Real Displacement
Real disp. at the point 1: δ11+ δ12+ δ13
Real disp. at the point 2: δ21+ δ22+ δ23
Real disp. at the point 3: δ31+ δ32+ δ33
Active
[Construction Camber]
=Net Deformation
Net disp. at the point 1: δ11+ δ12+ δ13
Net disp. at the point 2: δ22+ δ23
Net disp. at the point 3: δ33
57
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
58
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
59
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
Displacement with
considering Camber Displ. Option
60
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
Large Displacement
(Lateral Stiffness + Sag Effect N/A V V
+ Large Deformation)
Temperature Gradient V V
V
V
Camber Control (Construction Camber &
(Construction Camber)
Manufacture Camber)
Temporary Support
V V
& Temporary Cable
Cable Tensioning
No Need V
in Multiple Steps
62
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
6. Dynamic Analysis
63
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
6. Dynamic Analysis
Type of Analysis
Eigen Vectors
Subspace Iteration
Lanczos
Ritz Vectors
64
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
6. Dynamic Analysis
7. Post-processing
Min/Max
Final Stage
66
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
In the cable stayed bridge or suspension bridge, engineers will determine the initial cable force
in the complete state(final shape) without construction stage. After that, construction stage
analysis will be performed.
If this initial cable force is correctly found, the cable force will be above 70% of its yielding force
and it will behave very similar to the truss element. Therefore in the most of the general cable-
stayed bridge, the engineers can assume the cable to act like truss element and there is no need
to consider large deformation analysis (=nonlinear geometric analysis).
However, if the bridge span is very large (ex. Larger than 600m) and shape is complex (like
stonecutter bridge or sutong bridge), engineers will perform large deformation analysis.
There is no clear criteria when exactly the engineer need to perform nonlinear analysis.
However, in the general case for cable bridge, it is not very common to perform nonlinear
geometric analysis if they have correct value of initial cable force.
One way to determine it clear will be performing both analysis, linear and nonlinear. By
comparing the results, if the difference in these two analysis are very large, nonlinear analysis
will be needed.
67
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
(2) Why I cannot obtain cable force using Unknown Load Factor with Cable elements?
As Unknown Load Factor is based on the linear stiffness algorithm, cable element for which
element stiffness keep changing cannot be considered. In the optimal algorithm, different
stiffness term in summation will results in negative pretension value.
Therefore, in Unknown Load Factor, cables must be modeled using Truss elements. After
obtaining initial cable force, we can manually change the element into Equivalent Truss or
Catenary elements by entering the initial cable force as Pretension Load (Load > Prestress >
Pretension Load). In this case, the value in cable element force (Lu / Pretension /
Horizontal) can be entered as arbitrary value.
68
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
(3) How to perform Post CS analysis using the cable force obtained in CS analysis?
If construction stage analysis has been performed with Dead Load, and “Convert Final Stage
Member Forces to Initial Forces for Post C.S.” option is checked on in Construction Stage
Analysis Control, the member forces at the last CS will be shown in Initial Element Forces(CS)
table (Load > Static Load > Initial Forces > Small > Initial Element Forces(CS)).
If we would like to modify some cable forces, we can enter it in “Initial Element Force Table”. It
can be applied into geometric stiffness of the structure at the Post CS and this has priority than
Initial Element Forces(CS) table.
Initial force will not be reflected into Member Forces of an element. In order to do so, check on
“Add Initial Force to Element Force” option in Initial Force Control Data.
When both Initial Element Force and Cable Pretension (Lu / Pretension / Horizontal) are
entered, Initial Element Force Table has a priority.
69
Cable Stayed Bridge Design in midas Civil
Midas
Training
Series
70
Thank you