Control Loop Presentation
Control Loop Presentation
Sumanta Basu
Boiler Control Components
Load Signal
Local Mode
Set Point Boiler Turbine Output
GPC Controller
U(t) Plant
Sequence Logic for Boiler Auxiliary Equipment
Air Heater (RAPH)
Emergency PB Operated
Induced Draft Fan (IDF) Logic
Induced Draft Fan (IDF) [Start Permissive]
IDF Inlet Damper Close
IDF Outlet Damper Open
IDF Blade Angle Min. Position
Control Oil Pressure > 700 kPa
Any Control Oil Pump ON
Any Lube Oil Pump ON
Any Seal Air Fan ON
Any CCCWP ON
IDF Radial Bearing (DE) Temp. < 85°C
IDF Thrust Bearing (NDE) Temp. < 85°C
IDF Radial Bearing (NDE) Temp. < 85°C
Induced Draft Fan (IDF) [Start Permissive]...cntd
Lube Oil Temp. in Tank between 15°C & 50°C
Control Oil Temp. in Tank between 15°C & 50°C
IDF Lube Oil Flow Normal [>17.5 l/min]
IDF Motor Oil Flow to Bearing (DE) Normal [>6.8
l/min]
IDF Motor Oil Flow to Bearing (NDE) Normal
[>6.1 l/min]
ESP Inlet & Outlet Dampers Open
DP between IDF Diffuser Inner Tube and Flue
Gas Air Duct > 250Pa
Induced Draft Fan (IDF) [Start Permissive]...cntd
Below conditions are also required to start Air &
Gas Draft Group in Auto
MFT PB On
All BFP Stop
Feed Water Flow Low-Low (352 t/h) (30s)
[<70% of Minimum Flow. Minimum Flow is 25% TMCR]
[At 100% TMCR load, feed water flow is 2010 t/h]
Unstable Combustion
[When all coal pulverisers stopped AND at least LDO/HFO is being burned (Only Oil firing) then if:
(a) [(Atomizing air pressure low (2.5 kg/cm2(g)) OR LDO header pressure low (4.5 kg/cm2(g))
when LDO is being burned) OR All LDO burner valves closed] AND
(b) [(Atomizing steam pressure low (2.5 kg/cm2(g))OR HFO header pressure low (5.5 kg/cm2(g))
when HFO is being burned) OR All HFO burner valves closed]
Reheater Protection
[(When MSV/GV Closed & HPTB closed OR RSV/ICV & LPTB closed) with (30% BMCR OR at least one coal
feeder in service) (10s)
OR (When MSV/GV Closed & HPTB closed OR RSV/ICV & LPTB closed) with 20% BMCR] (20s)
[At 100% BMCR, main steam flow is 2151 t/h]
DCS Failure
BMS Failure [BMS1 OR BMS2]
Interlock Power Failure [24VDC OR 220VDC]
WSDT Level High-High (14.4m) (30s)
[Added as per ASME TDP-1]
BPS - MFT
Burner Abnormal:
In case of any of the following conditions, burner is
declared as abnormal.
Unit is synchronized with HFO firing, 1st coal Mill will come
in to service after 20% Load demand is given.
Coal Firing Sequence
[Load 18% & Demand 20%] -> [HFO (CD+EF) & Mill (D)]->
[Load 20% & Demand 35%] -> [HFO (CD+EF) & Mill (D+E)] ->
[HFO (CD) & Mill (D+E)] -> [Mill (D+E)] -> [Load 35% &
Demand 45%] -> [Mill (D+E+C)] -> [Load 50% & Demand 70%]
-> [Mill (D+E+C+B)] -> [Load 75% & Demand 99%] -> [Mill
(D+E+C+B+F)]
2nd Mill will come into service when 35% Load demand is
given.
• If Mill Rotary Separator is out of service due to VFD failure then Mill
Motor will continue to run .
• Mill output fineness will be reduced and the extent of fineness reduction
is unpredictable.
• This will increase circulating coal inside the mill that shall cause
vibration, overload and roller slip in addition to other disturbances in
boiler due to expected increase in output fineness of coal even though
mill motor operates at reduced load to avoid chocking. The resulting
vibration may damage the mill mechanically.
58
MRS VFD Bypass
• If we use MRS VFD bypass feature & when separator working at full
speed, the increase in speed of MRS will increase the fineness of coal
and decreases the output of mill. In case of VFD bypass arrangement
when MRS will run at rated speed result into reduction in the mill output
which will increase coal accumulation on the mill table top. As a result
mill tends to be overloaded, increases the vibration of the mill and may
cause damage to the mill equipment in addition to boiler load
reduction. Also the accumulation of coal on the mill table top may
reflect in to combustion of coal inside the mill and damage the mill.
MRS VFD Bypass
• Mill motor can be run at reduced load with reduction in coal flow to the
mill. But the extent of reduction of coal feeder speed is dependent on
the decision taken by the operator. The subject coal feeder shall have
to be taken in Manual mode of operation from the automatic fuel flow
control (Close loop). Under such circumstances the auto water fuel
control gets disturbed and subsequent disturbances occur in other
control loops of boiler and this tends to disturb all the boiler
parameters. Also the fireball location gets disturbed and the combustion
pattern inside the furnace gets destabilized.
• Hence MRS VFD bypass arrangement should not be used in case of VFD
failure, not to run mill since the coal fineness of mill output will be
unpredictable which may create instability in boiler operation & disturb
boiler parameters and as a result fireball location gets disturbed and
also may result in a boiler tube puncture in long operation. Due to
increment in fineness of coal, stoichiometric ratio may change which
will reflect in to moving of unburnt coal to second pass and may reflect
in to secondary combustion and also will worse opacity of chimney.
Plant Start Up
62
Plant Start Up
63
Plant Start Up
64
Boiler - Turbine Clean-up Flow
Control Concept of Boiler
• Boiler Operation Mode
100
Wet Operation Dry Operation
• Operating BCP • BCP is Out of Service
75 • Once-Through Operation from Eco to SH
Feed Water Flow (%)
• Same Condition
as Drum Boiler
25%
25
20% 30% 35% 50% 70%
▼ ▼ ▼ ▼ ▼
No.1 Mill No.2 No.3 No.4 No.5 Mill
0
0 25 50 75 100
Load (%)
Start up Control of Boiler
• Wet Operation (1/3)
HPTB
SH3
HPT IPT G
Evaporated
WS WS LPTB
WS Separate
D COND
T
WDC
Furnace M
CEP
BCP
Drain is flown into ECO
BR Condensate
ECO inlet or Condenser. Polisher
BFP BFBP
HP LP
DEA
HTR HTR
Start up Control of Boiler
• Wet Operation (2/3)
Steam Flow
Water Flow
through
SH3
W W
S S
25% Flow WET
W
S
D Load (%)
WDC
T
Furnace
Recir.
BCP 25% Minimum
Flow Flow for
BR
ECO Furnace
BFP Protection
HP
HTR
Start up Control of Boiler
• Wet Operation (3/3) WDC A /B
SC2 SH2
SC1 SH1
W W α γ γ’ γ”
S S
WSDT Level
W
S
D LT FX
WDC
γ”
Furnace
T W B
γ’ A
BCP START S WDC
BR
γ
BR
ECO
PI △ FX D
FT
BFP T
HP α
HTR
Start up Control of Boiler
• Dry Operation (1/2)
SH3
SC1 SH1
W W
S S
DRY
W
S
D Load (%)
WDC
T
Furnace
Furnace
BCP
ECO
BR
Evaporated Feed Water Flow
BFP
= Steam Flow
HP
HTR
Start up Control of Boiler WDC A/B
SH3
SC2 SH2
SC1 SH1
W W α γ γ γ
S S ’ ”
WSDT Level
W No Level
S
D LT
γ”
WDC
Furnace
T W B
γ’ A
BCP S WDC
γ
Stop BR
BR D
ECO
FT
Close T
BFP
HP α
HTR No Level
Start up Control of Boiler
• Wet/Dry Change Over
FT LT
FT
Calculate
√
√ Supercritical
Condition Required
0% T
Injection Water
Flow
△ FX
Load Demand △
FX 2 FX 3 △ FX PI
PI
Rate Rate PI
Injection water
BR valve control WDC-A control WDC-B control BCP Warming
demand Discharge flow control
demand demand
control demand demand
[operation in Wet [operation in [operation in Wet
[operation in Wet
mode] Wet mode] mode & Dry mode [operation in
(emergency)] Dry mode] mode]
Wet To Dry Transition Control
During low load (below 22% Load), drain is collected in the WSDT and
BCP is used to re- circulate this drain. This is the WET mode of
operation.
Wet to Dry Transition Control
During Wet mode of operation WSDT level is controlled using BR valve
and WDC valves.
During DRY mode, WSDT level is maintained using BCP warming return
flow control valve.
During start-up as the firing rate & load increases ,the pressure in the
separator also increases. The separator outlet pressure is converted to
temperature at saturation conditions via a steam table function
generator programmed into the control system.
The derived temperature becomes the set point for control, while the
actual separator outlet temperature is the process variable.
TB Valve
Steam Press Close on Back up Press mode
Control
WFR
Not used Steam Steam Press
Degree of Superheat Control
Press Control
or Steam Temp. Control
Control
Key Control Signals
BID is the basis for generating Feed water flow demand and Fuel Flow
demand
BID = MWD + ∆P + ∆MW (i.e. BID varies to compensate for any pressure
error and MW error)
Key Control Signals
Load Target can be given by the Operator when Unit is in CC mode
(Station mode) from Load setter Loop Plate or from Load dispatch
centre in case of CC – Dispatch mode
Spray
Governor Fuel flow control valve FDF
BFP Control
TB valve Coal feeder
FW control valve Valve
Fuel Flow and Air Flow Signal
Input (X) FUEL FLOW DEMAND
Output(Y) AIR FLOW DEMAND 2500
X Y 2000
UNIT t/h t/h
1 0 0
1500
2 143 877
3 203 1214
4 263 1460 1000
5 293 1630
6 323 1772 500
7 345 1920
8 350 1920
0
9 0 100 200 300 400
10
Air Flow Control INS
Instruments used
Control Drives
The operator can vary O2 set value using bias loop plate. O2
measurement signals have large ripples, therefore, a function generator
is provided to give some dead band on the deviation.
Air Flow Control
The AFR control is on standby mode for automatic operation, when the
firing rate demand (FRD) is at 30% MCR or < air flow demand is for a
minimum air flow rate (The air fuel ratio signal is 1.0.) or any FDF is
stopped
The AFD is cross-limited with total fuel flow to prevent fuel rich
condition in the furnace. FDF blade pitch is controlled by a controller
that receives an error signal from the comparison of an air flow demand
and an actual total measured air flow which can be determined by
adding the primary air flow for each coal mill and the secondary air flow
from FDF.
Air Flow Control
FDF blade pitch demands are forced to maximum (100%) open while
both FDF are stopped so that natural ventilation of the furnace could be
done
Stopped FDF blade pitch demand is forced to minimum (0%) open if the
other fan is running, to prevent reverse flow of the air through the
stopped fan
The FDF blade demand is fed through a direction block interlock which
blocks demand change. The direction block interlock prevents the FDF
demand increase when the surging block function detects an impending
FDF surging condition
Furnace Draft Control
Instruments used
Control Drives
Furnace pressure signals have large ripples, and therefore, time lag on the
measured signal and a function generator to give some dead band on the
deviation are provided.
Bias is used to compensate load imbalance between IDF (A) and IDF (B)
he PI controller is blocked during the INC and DEC operation depending
upon the occurrence of FCB.
Correlation between IDF moving blade position and FDF moving blade
position.
FDC 1
Furnace Draft Control FDC 2
The PAF and FDF blade position is used as the feed forward signal to
improve response during a load change.
Stopped IDF blade pitch demand is forced to minimum (0%) if the other
fan is running to prevent reverse flow of the stopped fan.
The IDF blade demand is fed through a direction block interlock which
blocks demand change during furnace draft extremes or when the
Surge is detected
MFT Condition:
IDF blade demands are forced to minimum position for 2-3 sec for
furnace implosion protection .The limit also depends upon the no of IDF
running.
IDF blade pitch demands are forced to maximum (100%) open while
both IDF are stopped for natural draft.
BID and Furnace Windbox DP Signal
200.0
X Y
MW mmH2O 160.0
0 147.0 120.0
40.0
0.0
0 100 200 300 400 500 600 700 800
SADC Oil & Coal Damper 1 2 3 4 CAT
Corner-2 Corner-8
BR-1
2nd I/P-Burner Damper Damper
A Corner-4 Corner-6
BR-2 Damper Damper
Coal dampers A (08) to F (08)
BMS & BID from DCS control SADC to obtain proper air/fuel ratio for
each burner and in each elevation
Coal & oil dampers for AB elevation is based on the condition of HFO
firing or LDO firing. An automatic switchover condition is available for
selection of the Fuel oil pressure signal based on the type of burner HFO
or LDO in service
The operator has provision to provide bias value from damper bias loop
plate based on the individual coal/oil/Aux damper grouping.
SADC Aux Air Damper Control
Total 8 nos at bottom most elevation , Fail safe condition: Air Fail Open
Corner-1 Corner-2
BR-1
Damper Damper
1st I/P
Corner-7 Corner-8
BR-2 Damper Damper
Corner-3 Corner-4
BR-1
Damper Damper
2nd I/P
Corner-5 Corner-6
BR-2 Damper Damper
8 7 6 5
1 2 3 4
SADC Aux Air Damper Control AAD
Operator has option to vary the damper position demand using bias
loop plate for left and right side respectively. In order to enhance the
controllability during a load change
BIR demand is provided for both left and right to enhance the
controllability
SADC AA Port Nozzle Angle Control AAN
Controls the angle of AA port nozzle (±30⁰) with air fail safe lock
Special logic for correcting temperature difference between the right &
the left is also considered for tuning correction different parameters of
RH Steam, Synchronization, and Gas damper are considered.
Dampers Conditions Damper operation
Coal dampers MFT and not Hot banking Open
During Hot banking mode (under Close
MFT)
Coal burner in service Program control in proportion to coal flow (Bias function based on the
boiler load or the number of operating pulverizer shall be considered.)
Coal burner out of service and Program control in proportion to oil header pressure to act as aux. air
adjacent oil burner in service damper for oil burner.
Both coal burner and adjacent oil Minimum opening *
burner out of service
Oil Dampers MFT and not Hot banking Open
During Hot banking mode (under Close
MFT)
Oil burner before light off Preset position *
Oil burner in service: Program control in proportion to oil header pressure.
Oil burner out of service Minimum opening*
Adjacent coal burner in service Program control in proportion to either of the following:
Average coal flow of upper and lower coal burner elevations, if
both the elevations are in service
Coal flow of the corresponding coal burner’s elevation, if only one
adjacent elevation is in service
Auxiliary MFT and not Hot banking Open
damper
During Hot banking mode (under Close
MFT)
A- coal burner in service Program control in proportion to coal flow of A- coal burner.
A- coal burner out of service Boiler load < 30% MCR: Diff. Press. control between furnace and
wind-box.
Boiler load > 30% MCR: Minimum opening*
Wind box Inlet Damper Control WBID
PID
Control Drives are Fail safe Lock on Air fail
Wind box Inlet Damper Controls the air flow into the burner assemblies
O2 balance between the left and right side is done for this damper, i.e.
if difference between the left and right side Eco. Outlet O2 is there then
one set of damper starts closing (Damper 1-2 and 7-8) and other starts
opening (Damper 3-4 and 5-6) or Vice Versa depending upon situation.
Steam & Water Flow Measurement
BCP warming water flow to 2RY SH is not considered in total spray water
calculation as it is within the feed water circuit.
X Y 500.00
UNIT MW t/h
1 0 0.00 400.00
2 198 136.98
300.00
3 264 171.87
5 528 310.19
100.00
6 660 376.55
X Y 2500
UNIT MW t/h
1 0 0 2000
2 198 668
1500
3 264 823
4 396 1180
1000
5 528 1588
6 594 1805 500
7 660 2010
8 698 2111 0
0 200 400 600 800
9 711.3 2151
Total Fuel Flow Signal(X) & Air Flow(Y)
X Y 125
UNIT t/h %
1 0.00 0 100
2 136.98 38.72
75
3 171.87 45.55
4 240.77 64.62 50
5 310.19 77.73
25
6 376.55 94.78
7 392.33 99.99 0
8 399.77 100.00 0.00 100.00 200.00 300.00 400.00
Fuel Flow Control
Unit is always started with LDO firing, after Hot clean up is completed
Fuel is changed over from LDO to HFO.
HFO Master will be control flow, after 4 HFO burners come in service.
HFO Load program will become AUTO, after 6 BNR comes in to service.
Unit is synchronized with HFO firing, 1st coal Mill will come in to service
after 20% Load demand is given.
2nd Mill will come into service when 35% Load demand is given.
After second Mill comes in service, Coal Master becomes AUTO and HFO
is taken Out of service.
FFD1
Fuel Flow Control HFO1
FFD3
Fuel Flow demand is generated based on BID
Fuel flow control will becomes AUTO, when more than 2 LDO burners
are taken in service
WFR is added to the Fuel flow demand. WFR is generated based on the
MS temp error , Superheat Temp Error, Furnace outlet temp error
Fuel flow demand is cross limited with Feed water flow and Air flow
Fuel flow demand is then converted to LDO flow demand / HFO flow
demand / Coal flow demand based on LDO/HFO or Coal Master is AUTO
LDO Flow CV and HFO flow CV will be modulated to control Pressure till
2 BNR or 4 BNR are in service respectively
Even when LDO or HFO flow CV are modulated to control flow, some
minimum pressure is always maintained
X Y
500
UNIT MW degC
1 0 355.20
450
2 198 355.20
3 264 363.33
4 396 382.59 400
5 528 416.12
6 594 429.15 350
7 660 433.02
8 698 434.53 300
9 711.3 434.81 0 200 400 600 800 1000
Load vs 2nd ry SH outlet temp
X Y
600.0
UNIT MW degC
1 0 526.1
2 198 526.1 550.0
3 264 536.2
4 396 540.6
5 528 543.0 500.0
6 594 544.1
7 660 544.8
8 698 544.8 450.0
0 200 400 600 800 1000
9 711.3 544.7
Load vs 3ry SH outlet temp set
X Y
600.0
UNIT MW degC
1 0 500.0
2 198 531.0 550.0
3 264 552.0
4 396 569.0
5 528 569.0 500.0
6 594 569.0
7 660 569.0
8 698 569.0 450.0
0 200 400 600 800 1000
9 711.3 569.0
Main Steam Temperature Control
MS Temp set point is a dynamic function of Load Index with Delay
WFR takes care of heat absorption of actual heating value of fuel &
burner elevation in service
The superheat rate signal is generated based on the error between
water separator inlet temperature and the saturated temperature at
water separator outlet pressure.
WFR controls the superheat rate of WS inlet steam at low load and MS
temperature at high load
Till Synchronization all SH/RH spray valves are forced Closed. Also in
Case of Steam block or MFT, Valves are forced closed
MST 1
MS Temperature Control
MST 2
After the Start up Mode is RESET, MS Temp SET will be Load based and
increase/decrease with a Rate which is also a function of Load
Index(delay)
MS Temp Bias permit is available only after MS Temp reaches 500 deg C
MST BIR is applicable only after LD(delay) is more than 50% TMCR
Control Outline of 1ry SH Spray Control valve
1ry SH Spray control valve
The valve will mainly control the WS inlet Superheat rate only when
following conditions are available:
If WFR is not able to maintain the SH rate then only Spray is used.
In DRY mode of operation, when the Load is less than 610MW and WS
outlet Press is not more than 200kg/cm2 and TWSI superheat upper or
lower limit is reached
Load based TWSI SH upper and Lower limit is determined dynamically
Whenever DSH outlet Temp nears Tsat, Over injection Controller will
control the spray valve opening to maintain the DSH outlet temperature
15°C above saturation temperature
The valve will control the Superheat rate only when following conditions
are available: In DRY mode of operation, when the Load is less than
610MW and WS outlet Press is not more than 200 kg/cm2 and TWSI
superheat upper or lower limit is reached.
Superheat Rate Controller
1ry Spray CV control (Over injection / min openingcontrol)
MS Temperature Control-2ry Spray Control valve
SH spray is applied in two stages cascade control and controlled separately on A-
side and B-side by each corresponding drive
Fail safe condition: Air Fail Close
• 2ry Spray control valve is used to maintain TFSO. Main steam temp is controlled
using cascade control.
• Primary Controller:
o This controller fine tunes the T3SI Set, based on the MST and DSDT Error.
DSDT deviation is controlled only in DRY mode of operation. DSDT error is
limited within +/- 6 Deg C.
o FF: FF signal is Load based T3SI and BIR signal.
o LL : Tsat + 15°C
o This controller will be normally in operation after MS Start up mode is RESET.
o HL: Normally 600 °C. In case the 2ry Spray CV demand is less than the min
opening required, the HL is held at the existing value. This helps to prevent
the T3SI set from increasing, and thus the Spray valve demand from
decreasing further.
MS Temperature Control-2ry Spray Control valve
Ts:
When the MS Temp start up mode is ON (From MFT till MST reaches
500°C or Operation mode changes to DRY) OR
2ry Spray CV demand is less than the min spray opening and actual MST
is less than MST Set by 10°C or more.
Whenever the Spray valve demand becomes less than its min opening and
the actual temp is less than MST Set by 10°C or more, than Primary
controller will be switched to tracking mode. This is reset wind up circuit.
• During MST Start up mode, both the controllers are in Tracking mode, and the
2ry Spray control valve will be opened as per the start up Program.
TILT
RH Temperature Control RHT 1
RHT 2
Coal Burner-B
Lower Burner Oil Burner-AB
Power cylinder
Coal Burner-A
Emergency Control
Burner tilt is based on Load index. It is adjusted to Tilt & rectify the RH
outlet A and B imbalance
When Gas distribution damper control have reached its lower limit
(20°)
During Load up & Burner nozzle angle control are ineffective or have
delayed response
Sliding Pressure Operation
Gen MS Pr
300.00
X Y
UNIT MW kg/cm2(g) 250.00
1 0 90.80
200.00
2 198 91.88
3 264 113.90 150.00
4 396 159.69 100.00
5 528 216.69
6 594 245.96 50.00
7 660 245.96 0.00
8 698 245.96 0 200 400 600 800 1000
9 711.3 245.96
Main Steam Pressure (MSP) of Modified Sliding pressure curve is higher than
Main Steam Pressure of Pure Sliding pressure curve.
Turbine control valve will automatically open/close as per set main steam
pressure
Sliding Pressure Operation
By the sliding pressure in proportion to the generator output, steam
quantity at turbine inlet can be changed at a constant volume flow
while keeping governing valve full open.
Based on the sliding pressure curve, the set value of the MS pressure
changes also and the large deviation causes large / small demand to
FW,FF,AF compared to static characteristics which lead to overshoot /
undershoot in MW generation, MS & RH steam temperature.
MSP set comes to auto if unit is synchronized & boiler is in wet / dry
mode with a deviation between MSP program set & manual set
< + /- 0.3 MPa
The HPBP Pressure set point is calculated by the sum of the MSP demand
and the specified bias.
MS Pressure Control by HPBP
After the load demand goes above the regulated load, the set point bias
is in effect. As a result of this, the HP TB control valves are normally
closed and operated as back up control to prevent the Main Steam
Pressure from rising excessively
When Fast cutback is in operation, the HPTB valve will be forced to fully
open.
The position demand of HPTB valve is used as a feed forward signal for
HPTB spray water Control valve to improve response.
BFM ensure grid frequency support but the large deviation in the
steam flow rate & pressure occurred due to this is used to
regulate the boiler input ( FWF,FFD,AFD) to stabilize the MS
pressure
Unit Coordinated Control
Unit coordinate control generates three main Demand signals –
BID – Boiler Input Demand
MWD – Turbine Master
BIR – Boiler Input rate
BID = MWD + ∆P + ∆MW (i.e. BID varies to compensate for any pressure
error and MW error)
Boiler input demand is the basis for generating Feed water flow demand and
Fuel Flow demand.
Boiler input rate is some bias added to the demands of various closed loop
to improve boiler response during transient conditions.
UCC in Sub Critical Plant
Initial pressure mode comes when runback action comes into picture or
it is selected from console.
If deviation is more than set value (Actual > required) the pressure
controller output remains as maximum saturation.
If deviation fall less than the set value the output of the pressure
controller jumps from saturation to minimum output
UCC in Sub Critical Plant
All the action start after the pressure drops by more than 10Kg/Cm2
A small pressure correction signal is applied +/- side to load set point
control
Boiler following or “constant pressure” mode is the most commonly
used mode in power plant coordinated control and MS Pressure is
maintained by fuel flow control
Control Mode selection of Super Critical Plant
Boiler control mode Control condition Remark
When the turbine master is set to AUTO with turbine valve transfer
completed just before synchronization, the BFM can be changed to BI
mode /TFM ( Turbine Master Auto , Boiler master Manual) by operator
PB
Operator can select BI mode or CC mode from Loop plate whenever the
permissive are available.
In BI mode the MW is set by the operator manually under the condition
of boiler input control manual and Turbine Master Auto.
When the turbine master is changed to MANUAL mode while the unit is in
CC mode, the control changes to BFM ( Boiler master in Auto).
When 50% runback operates & >=5 coal mills are in service ,Mill A
trips first if in service & after 1 sec Mill F trips in sequence with
first Mill-A then Mill-F .
Transient increase in condensate flow may trip the CEP due to overload
LPTB valve opens quickly to decrease RH pressure: -> Much steam (heat)
flow to condenser -> Low vacuum of condenser is concerned .
Load Fast Cut Back
Extraction stops: -> HP & LP heaters & deaerator stop -> ECO inlet
FW temperature down -> Exhaust temperature down -> Primary air
temperature down -> Coal dryness down -> Combustion stability
down -> Hence to keep combustion stability, ECO inlet temperature
needs around 160 deg.C -> Hence heat FW only in deaerator ->
Thermal stress in deaerator may increase -> If deaerator can't allow
thermal stress, heater#7 shall be operated (from CRH)
LPTB valve quick open logic to control the heat input to condenser
FCB
Press TB VALVE
MW
Press
TB VALVE Fuel
Transient Load
HP TB_100% FCB
110 28
100 26
90
Gen. Output, TB Valve Position [%], Temp [℃]
24
80
22
70
Pressure [MPa]
60 20
50 18
40
16
30
14
20
10 12
0 10
13:10 13:15 13:20 13:25 13:30 13:35
Time (hh:mm)
HPBP Functioning
HPTB
Max. Main
Opening at
Normal Steam
Max. Main MSPr at
Main Steam Pressure Max.
Boiler Steam Max. HPTB
Condition Pressure Control Mode Set Pt / Pos (Kg/cm2) HPTB
load Pressure Opening
(Kg/cm2) as reached at Opening
prevailing at (Kg/cm2)
per F(x) defined
defined
condition
condition
Wet Pressure Based on the MSP Set
Mode Control Point Curve (Series 1)
BACK UP
Dry MSP Set Point + 10 *
Pressure
Mode Kg/cm2 (Series 2)
Control Mode
Protection
100% 245.9 0.00% 267 17.70% 265.9
Close.
Protection
80% 190.4 10.00% 205 17.50% 204.3
Close.
MFT Protection
60% 138.8 0.00% 149.6 17.50% 148.6
Close.
Protection
40% 97.7 0.00% 109 20.00% 103.3
Close.
Protection
20% 86 0.00% 92.6 19.40% 87.8
152
Close.
HPTB
Max. Main
Opening at
Normal Steam
Max. Main MSPr at
Main Steam Pressure Max.
Boiler Steam Max. HPTB
Condition Pressure Control Mode Set Pt / Pos (Kg/cm2) HPTB
load Pressure Opening
(Kg/cm2) as reached at Opening
prevailing at (Kg/cm2)
per F(x) defined
defined
condition
condition
Protection open at 100%
Boiler Pressure for 20 Sec (Auto Stand by
load Control Mode), then Pressure
control in AUTO Mode
Boiler ERV ( Set Pr 269.19
Island 100% 245.9 Kg/Cm2) force opens for 10 66.00% 269.1 100.00% 261.9
( 21 MW ) sec
80% 190.4 67.00% 210.1 100.00% 208
60% 138.8 100.00% 156.3 100.00% 154.6
40% 97.7 100.00% 107.5 100.00% 107.4
20% 86 38.80% 89.6 50.60% 87.3
FCB
Protection open at 100%
Boiler Pressure for 20 Sec (Auto Stand by
load Control Mode), then Pressure
control in AUTO Mode
ERV ( Set Pr 269.19
Turbine
100% 245.9 Kg/Cm2) force opens for 10 36.00% 269.5 100.00% 262.8
Trip
sec
80% 190.4 72.00% 211.6 100.00% 209.2
60% 138.8 100.00% 161.6 100.00% 156.3
40% 97.7 100.00% 109.3 100.00% 107.5
20% 86 50.90% 91.3 70.70% 88.2
153
HPTB
Max. Main
Opening at
Normal Steam
Max. Main MSPr at
Main Steam Pressure Max.
Boiler Steam Max. HPTB
Condition Pressure Control Mode Set Pt / Pos (Kg/cm2) HPTB
load Pressure Opening
(Kg/cm2) as reached at Opening
prevailing at (Kg/cm2)
per F(x) defined
defined
condition
condition
On black out, All BFPS
Pressure Stop, therfore HTPB is
Control Protection close, till any
BFP comes into service.
Black ERV ( Set Pr 269.19
100% 245.9 0.00% 270.3 12.00% 265.8
Out Kg/Cm2) auto open
80% 190.4 0.00% 208.5 15.00% 204.6
60% 138.8 0.00% 151.8 16.00% 149.2
40% 97.7 0.00% 106.6 18.00% 103.9
20% 86 0.00% 89.2 16.40% 87.8
Turbine Speed
3800
Turbine S peed (rpm )
3750
3700
Actual Test Data Simulation
3650
3600
3550
-60 -30 0 30 60 90 120 150 180 210 240 270 300
Time (sec)
155
MS Temperature / Superheat during FCB
620 100
600 80
Temperature (℃)
Superheat (℃)
580 60
2ry Pa s s Inl et Superhea t
560 40
3ry SH Outl et Temperature
540 20
520 0
-1 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Time (min)
156
MS Pressure During FCB
310 120
Sa fety V a l v e Setti ng : 307.2 atg
300
HP TB Va l v e Openi ng 100
290
MS Pres s H i g h MF T Setti ng : 285.4 atg 80
Pressure (atg)
O pening (%)
280
Much margin to MFT set pressure because of 60
270
large capacity HP TBV
SH Outl et Des i g n Pres s : 269.2 a tg
40
260
Max:256.24atg
20
250
SH Outl et Pres s ure
240 0
-5 0 5 10 15 20 25 30 35 40 45 50 55 60
Time (sec)
157
HRH Steam Pressure During FCB
RH safety valve float due to much steam flow through HP TBV, and slower opening of LP
TBV . ERV Operation :Load before FCB ≧ 90% : 10 sec forced open, Load before FCB <
90% : Not open
80 120
75
Max:72.08atg
100
70 R H Outl e t Sa f ety V a l v e Setti n g : 7 0 .8 a tg
65
80
R H Ou tl et Pre s s u re
Pressure (atg)
60
Opening (%)
55 60
50
LP TB V a l v e 40
45
40
20
35
30 0
-30 0 30 60 90 120 150 180
Time (sec)
158
HRH Pressure during FCB
80
75 RH Outlet Safety Valve Setting : 70.8 atg
70
65
HRH Pressure (atg)
60
55
50
45
40 ERV forced open is not necessary for
35 less than 90%
30
25
20
70 80 90 * HP TBV : Quick Open 100
Unit Load before FCB (%) LP TBV : PI Control
ERV : Not Open
159
APS Special Features
HIGHEST
LEVEL APS
• <1> APS/UNIT MASTER LEVEL
GROUP GROUP • <2> GROUP/ SUB GROUP &
LEVEL /SUB-GROUP
CONTROL
SUB CONTROL LEVEL
• <3> DRIVE LEVEL
DRIVE CONTROL
DRIVE
LEVEL
APS Special Features: Start-up
• APS OPERATION PANEL (START UP) 1/2
APS AUTO
APS Special Features: Start-up
• APS OPERATION PANEL (START UP) 2/2
APS SEMI-AUTO
Pulverizer Inerting & Clearing
When the Coal Burner trips with residual coal inside Pulverizer, it is
important to cut out hot air and cold air, and to fill steam in the
Pulverizer for 2 minutes(initial set) to inert the Pulverizer.
CLEARING OPERATION
After the Pulverizer trips, Clearing Operation of
Pulverizer is required to be performed to
discharge the residual coal inside the Pulverizer
into the spillage hopper with manual initiation of
push button of OPS.
Clearing Operation is performed with the
combination sequence of MBC and Pulverizer
Spillage ash handling system, and all operation
and monitoring can be done through OPS in the
CCR.
Pulverizer Inerting & Clearing
Clearing Select
Pulverizer Inerting & Clearing
INERTING
INERTING 120sec
Pulverizer Inerting & Clearing
CLEARING IN PROGRESS
After 180sec
10sec
120sec
Thank You