Adr Case Digests Genprinciples
Adr Case Digests Genprinciples
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
1
ATTY.
BUSTAMANTE
ABSR
On
August
6,
2014,
respondent
filed
a
Motion
to
Withdraw
Amended
Statement
of
Claims9
in
the
light
of
petitioner's
opposition
to
the
admission
of
the
Amended
Statement
of
Claims
and
to
avoid
further
delay
in
the
arbitration
of
its
claims,
without
prejudice
to
the
filing
of
such
claims
for
liquidated
and
other
damages
at
the
appropriate
time
and
proceeding.
Thereafter,
respondent
filed
a
motion
to
resume
proceedings.
However,
on
May
4,
2015,
respondent
filed
anew
a
Motion
to
Admit
Attached
Amended
Statement
of
Claims
dated
April
30,
2015,
increasing
the
actual
damages
sought
to
₱390,000,000.00,
plus
an
additional
₱l0,000,000.00
for
exemplary,
temperate
or
nominal
damages.10
On
November
6,
2015,
petitioner
filed
an
Opposition
to
the
Motion
to
Admit
Attached
Amended
Statement
of
Claims.
PROCEDURAL
ORDER
NO.
11
Grants
the
Motion
to
Admit
on
the
premise
that
BCA
will
no
longer
present
any
additional
evidence-‐in-‐chief
to
prove
the
bigger
claim
in
the
Amended
Statement.
For
the
additional
claim
of
300
million
pesos,
BCA
should
pay
the
additional
fee
of
5%
or
15
million
pesos.
Having
paid
12
million
pesos,
the
balance
of
3
million
pesos
shall
be
payable
upon
submission
of
this
case
for
resolution.
No
award
shall
be
issued
and
promulgated
by
the
Tribunal
unless
the
balance
of
40%
in
the
Arbitrators'
fees
for
the
original
Claim
and
Counterclaim,
respectively,
and
the
balance
of
3
million
for
the
Amended
Claim,
are
all
fully
paid
by
the
parties.
BOTH
PARTIES
FILED
AN
MR
PROCEDURAL
ORDER
NO.
12
Denied
petitioner's
motion
for
reconsideration
of
Procedural
Order
No.
11,
petitioner
filed
this
petition
for
certiorari
under
Rule
65
of
the
Rules
of
Court
with
application
for
issuance
of
a
temporary
restraining
order
and/or
writ
of
preliminary
injunction,
seeking
to
annul
and
set
aside
Procedural
Order
No.
11
dated
February
15,
2016
and
Procedural
Order
No.
12
dated
June
8,
2016.
Petitioner
stated
that
it
opted
to
file
the
petition
directly
with
this
court
in
view
of
the
immensity
of
the
claim
concerned,
significance
of
the
public
interest
involved
in
this
case,
and
the
circumvention
of
the
temporary
restraining
order
issued
by
this
Court
in
Department
of
Foreign
Affairs
v.
BCA
International
Corporation,
docketed
as
G.R.
No.
210858.
It
cited
Department
of
Foreign
Affairs,
et
al.
v.
Hon.
Judge
Falcon,15
wherein
the
Court
overlooked
the
rule
on
hierarchy
of
courts
and
took
cognizance
of
the
petition
for
certiorari.
ISSUE:
WHETHER
OR
NOT
THE
ALTERNATIVE
RELIEF
IN
THE
AMENDED
STATEMENT
OF
CLAIMS
FALLS
OUTSIDE
THE
SCOPE
OF
THE
ARBITRATION
CLAUSE;
HENCE,
OUTSIDE
THE
JURISDICTION
OF
THE
AD
HOC
ARBITRAL
TRIBUNAL
HELD:
NO.
The
Agreement
provides
for
the
resolution
of
dispute
between
the
parties
in
Section
19.02
thereof,
thus:
2
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
A ATTY.
BUSTAMANTE
ABSR
If
the
Dispute
cannot
be
settled
amicably
within
ninety
(90)
days
by
mutual
discussion
as
contemplated
under
Section
19.01
herein,
the
Dispute
shall
be
settled
with
finality
by
an
arbitrage
tribunal
operating
under
International
Law,
hereinafter
referred
to
as
the
"Tribunal,"
under
the
UNCITRAL
Arbitration
Rules
contained
in
Resolution
31/98
adopted
by
the
United
Nations
General
Assembly
on
December
15,
1976,
and
entitled
"Arbitration
Rules
on
the
United
Nations
Commission
on
the
International
Trade
Law."
The
DFA
and
BCA
undertake
to
abide
by
and
implement
the
arbitration
award.
The
place
of
arbitration
shall
be
Pasay
City,
Philippines,
or
such
other
place
as
may
mutually
be
agreed
upon
by
both
parties.
The
Arbitration
proceeding
shall
be
conducted
in
the
English
language.
Under
Article
33
of
the
UNCITRAL
Arbitration
Rules
governing
the
parties,
"the
arbitral
tribunal
shall
apply
the
law
designated
by
the
parties
as
applicable
to
the
substance
of
the
dispute."
"Failing
such
designation
by
the
parties,
the
arbitral
tribunal
shall
apply
the
law
determined
by
the
conflict
of
laws
rules
which
it
considers
applicable."
Established
in
this
jurisdiction
is
the
rule
that
the
law
of
the
place
where
the
contract
is
made
governs,
or
lex
loci
contractus.17
As
the
parties
did
not
designate
the
applicable
law
and
the
Agreement
was
perfected
in
the
Philippines,
our
Arbitration
laws,
particularly,
RA
No.
876,18
RA
No.
928519
and
its
IRR,
and
the
Special
ADR
Rules
apply.20
The
IRR
of
RA
No.
9285
provides
that
"[t]he
arbitral
tribunal
shall
decide
the
dispute
in
accordance
with
such
law
as
is
chosen
by
the
parties.
In
the
absence
of
such
agreement,
Philippine
law
shall
apply.”
x
x
x
x
The
IRR
of
RA
9285
reiterate
that
RA
9285
is
procedural
in
character
and
applicable
to
all
pending
arbitration
proceedings.
Consistent
with
Article
2046
of
the
Civil
Code,
the
Special
ADR
Rules
were
formulated
and
were
also
applied
to
all
pending
arbitration
proceedings
covered
by
RA
9285,
provided
no
vested
rights
are
impaired.
Thus,
contrary
to
DFA's
contention,
RA
9285,
its
IRR,
and
the
Special
ADR
Rules
are
applicable
to
the
present
arbitration
proceedings.
The
arbitration
between
the
DF
A
and
BCA
is
still
pending,
since
no
arbitral
award
has
yet
been
rendered.
Moreover,
DF
A
did
not
allege
any
vested
rights
impaired
by
the
application
of
those
procedural
rules.
2. G.R.
No.
210858
June
29,
2016
DEPARTMENT
OF
FOREIGN
AFFAIRS,
Petitioner,
vs.
BCA
INTERNATIONAL
CORPORATION,
Respondent.
CARPIO,
J.:
ISSUE
AT
POINT: :
WHETHER
OR
NOT
THE
1976
UNCITRAL
ARBITRATION
RULES
AND
THE
RULES
OF
COURT
APPLY
TO
THE
PRESENT
ARBITRATION
PROCEEDINGS,
NOT
RA
9285
AND
THE
SPECIAL
ADR
RULES
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
3
ATTY.
BUSTAMANTE
ABSR
HELD:
Arbitration
is
deemed
a
special
proceeding13
and
governed
by
the
special
provisions
of
RA
9285,
its
IRR,
and
the
Special
ADR
Rules.
14
RA
9285
is
the
general
law
applicable
to
all
matters
and
controversies
to
be
resolved
through
alternative
dispute
resolution
methods.
15
While
enacted
only
in
2004,
we
held
that
RA
9285
applies
to
pending
arbitration
proceedings
since
it
is
a
procedural
law,
which
has
retroactive
effect:
While
RA
9285
was
passed
only
in
2004,
it
nonetheless
applies
in
the
instant
case
since
it
is
a
procedural
law
which
has
a
retroactive
effect.
Likewise,
KOGIES
filed
its
application
for
arbitration
before
the
KCAB
on
July
1,
1998
and
it
is
still
pending
because
no
arbitral
award
has
yet
been
rendered.
Thus,
RA
9285
is
applicable
to
the
instant
case.
Well-‐settled
is
the
rule
that
procedural
laws
are
construed
to
be
applicable
to
actions
pending
and
undetermined
at
the
time
of
their
passage,
and
are
deemed
retroactive
in
that
sense
and
to
that
extent.
As
a
general
rule,
the
retroactive
application
of
procedural
laws
does
not
violate
any
personal
rights
because
no
vested
right
has
yet
attached
nor
arisen
from
them.
16
(Emphasis
supplied)
The
IRR
of
RA
9285
reiterate
that
RA
9285
is
procedural
in
character
and
applicable
to
all
pending
arbitration
proceedings.17
Consistent
with
Article
2046
of
the
Civil
Code,
18
the
Special
ADR
Rules
were
formulated
and
were
also
applied
to
all
pending
arbitration
proceedings
covered
by
RA
9285,
provided
no
vested
rights
are
impaired.
19Thus,
contrary
to
DFA's
contention,
RA
9285,
its
IRR,
and
the
Special
ADR
Rules
are
applicable
to
the
present
arbitration
proceeding.
The
arbitration
between
the
DFA
and
BCA
is
still
pending,
since
no
arbitral
award
has
yet
been
rendered.
Moreover,
DFA
did
not
allege
any
vested
rights
impaired
by
the
application
of
those
procedural
rules.
RA
9285,
its
IRR,
and
the
Special
ADR
Rules
provide
that
any
party
to
an
arbitration,
whether
domestic
or
foreign,
may
request
the
court
to
provide
assistance
in
taking
evidence
such
as
the
issuance
of
subpoena
ad
testificandum
and
subpoena
duces
tecum.20
The
Special
ADR
Rules
specifically
provide
that
they
shall
apply
to
assistance
in
taking
evidence,21
and
the
RTC
order
granting
assistance
in
taking
evidence
shall
be
immediately
executory
and
not
subject
to
reconsideration
or
appeal.22
An
appeal
with
the
Court
of
Appeals
(CA)
is
only
possible
where
the
RTC
denied
a
petition
for
assistance
in
taking
evidence.
23
An
appeal
to
the
Supreme
Court
from
the
CA
is
allowed
only
under
any
of
the
grounds
specified
in
the
Special
ADR
Rules.24
We
rule
that
the
DFA
failed
to
follow
the
procedure
and
the
hierarchy
of
courts
provided
in
RA
9285,
its
IRR,
and
the
Special
ADR
Rules,
when
DFA
directly
appealed
before
this
Court
the
RTC
Resolution
and
Orders
granting
assistance
in
taking
evidence.
4
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
A ATTY.
BUSTAMANTE
ABSR
DFA
contends
that
the
RTC
issued
the
subpoenas
on
the
premise
that
RA
9285
and
the
Special
ADR
Rules
apply
to
this
case.
However,
we
find
that
even
without
applying
RA
9285
and
the
Special
ADR
Rules,
the
RTC
still
has
the
authority
to
issue
the
subpoenas
to
assist
the
parties
in
taking
evidence.
The
1976
UNCITRAL
Arbitration
Rules,
agreed
upon
by
the
parties
to
govern
them,
state
that
the
"arbitral
tribunal
shall
apply
the
law
designated
by
the
parties
as
applicable
to
the
substance
of
the
dispute.
Failing
such
designation
by
the
parties,
the
arbitral
tribunal
shall
apply
the
law
determined
by
the
conflict
of
laws
rules
which
it
considers
applicable.
"25
Established
in
this
jurisdiction
is
the
rule
that
the
law
of
the
place
where
the
contract
is
made
governs,
or
lex
loci
contractus.26
Since
there
is
no
law
designated
by
the
parties
as
applicable
and
the
Agreement
was
perfected
in
the
Philippines,
"The
Arbitration
Law,"
or
Republic
Act
No.
876
(RA
876),
applies
Considering
that
this
petition
was
not
filed
in
accordance
with
RA
9285,
the
Special
ADR
Rules
and
1976
UNCITRAL
Arbitration
Rules,
this
petition
should
normally
be
denied.
However,
we
have
held
time
and
again
that
the
ends
of
justice
are
better
served
when
cases
are
determined
on
the
merits
after
all
parties
are
given
full
opportunity
to
ventilate
their
causes
and
defenses
rather
than
on
technicality
or
some
procedural
imperfections.
29More
importantly,
this
case
is
one
of
first
impression
involving
the
production
of
evidence
in
an
arbitration
case
where
the
deliberative
process
privilege
is
invoked.
3. G.R.
No.
135362
December
13,
1999
HEIRS
OF
AUGUSTO
L.
SALAS,
JR
vs.
LAPERAL
REALTY
CORPORATION,
ROCKWAY
REAL
ESTATE
CORPORATION,
SOUTH
RIDGE
VILLAGE,
INC.,
MAHARAMI
DEVELOPMENT
CORPORATION
DE
LEON,
JR.,
J.:
FACTS:
Augusto
Salas,
Jr.
was
the
registered
owner
of
a
vast
tract
of
land
in
Lipa
City,
Batangas.
He
entered
into
an
Owner-‐Contractor
Agreement
with
Respondent
Laperal
Realty
Corporation
to
render
and
provide
complete
(horizontal)
construction
services
on
his
land.
Said
agreement
contains
an
arbitration
clause,
to
wit:
“ARTICLE
VI.
ARBITRATION.
All
cases
of
dispute
between
CONTRACTOR
and
OWNER’S
representative
shall
be
referred
to
the
committee
represented
by:
1.One
representative
of
the
OWNER;
2.One
representative
of
the
CONTRACTOR;
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
5
ATTY.
BUSTAMANTE
ABSR
3.
One
representative
acceptable
to
both
OWNER
and
CONTRACTOR.”
Salas,
Jr.
then
executed
a
Special
Power
of
Attorney
in
favor
of
Respondent
Laperal
Realty
to
exercise
general
control,
supervision
and
management
of
the
sale
of
his
land,
for
cash
or
on
installment
basis.
By
virtue
thereof,
Respondent
Laperal
Realty
subdivided
said
land
and
sold
portions
thereof
to
Respondents
Rockway
Real
Estate
Corporation
and
South
Ridge
Village,
Inc.
in
1990;
to
Respondent
spouses
Abrajano
and
Lava
and
Oscar
Dacillo
in
1991;
and
to
Respondents
Eduardo
Vacuna,
Florante
de
la
Cruz
and
Jesus
Vicente
Capalan
in
1996
(Respondent
Lot
Buyers
hereinafter).
Back
in
1989,
Salas,
Jr.
left
his
home
in
the
morning
for
a
business
trip
to
Nueva
Ecija.
He,
however,
never
returned
on
that
unfaithful
morning.
Seven
years
later
or
in
1996,
his
wife,
Teresita
Diaz-‐Salas
filed
with
the
RTC
of
Makati
City
a
verified
Petition
for
the
Declaration
of
Presumptive
Death,
which
Petition
was
granted.
In
1998,
Petitioners,
as
heirs
of
Salas,
Jr.
filed
in
the
RTC
of
Lipa
City
a
Complaint
for
Declaration
of
Nullity
of
Sale,
Reconveyance,
Cancellation
of
Contract,
Accounting
and
Damages
against
Respondents.
Respondent
Laperal
Realty
filed
a
Motion
to
Dismiss
on
the
ground
that
Petitioners
failed
to
submit
their
grievance
to
arbitration
as
required
under
Article
VI
of
the
Owner-‐Contractor
Agreement.
Respondent
spouses
Abrajano
and
Lava
and
Respondent
Dacillo
filed
a
Joint
Answer
with
Counterclaim
and
Crossclaim
praying
for
dismissal
of
Petitioners’
Complaint
for
the
same
reason.
The
RTC
then
issued
the
herein
assailed
Order
dismissing
Petitioners’
Complaint
for
non-‐compliance
with
the
foregoing
arbitration
clause.
Hence
the
present
Petition
for
Review
on
Certiorari
under
Rule
45.
ISSUE:
WHETHER
OR
NOT
THE
ARBITRATION
CLAUSE
UNDER
ARTICLE
VI
OF
THE
OWNERCONTRACTOR
AGREEMENT
IS
BINDING
UPON
THE
RESPONDENT
LOT
BUYERS
ARGUMENTS:
Petitioners
argue
that
(1)
their
causes
of
action
did
not
emanate
from
the
Owner-‐Contractor
Agreement,
(2)
that
their
causes
of
action
for
cancellation
of
contract
and
accounting
are
covered
by
the
exception
under
the
Arbitration
Law,
and
(3)
that
failure
to
arbitrate
is
not
a
ground
for
dismissal.
Petitioners
claim
that
they
suffered
lesion
of
more
than
one-‐fourth
(1/4)
of
the
value
of
Salas,
Jr.’s
land
when
Respondent
Laperal
Realty
subdivided
it
and
sold
portions
thereof
to
Respondent
Lot
Buyers.
Thus,
they
instituted
action
against
6
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
A ATTY.
BUSTAMANTE
ABSR
both
Respondent
Laperal
Realty
and
Respondent
Lot
Buyers
for
rescission
of
the
sale
transactions
and
reconveyance
to
them
of
the
subdivided
lots.
They
argue
that
rescission,
being
their
cause
of
action,
falls
under
the
exception
clause
in
Sec.
2
ofRepublic
Act
No.
876
which
provides
that
“such
submission
[to]
or
contract
[of
arbitration]
shall
be
valid,
enforceable
and
irrevocable,
save
upon
such
grounds
as
exist
at
law
for
the
revocation
of
any
contract”.
HELD:NO.
Respondent
Lot
Buyers
are
neither
parties
to
the
Agreement
nor
the
latter’s
assigns
or
heirs.
Consequently,
the
right
to
arbitrate
as
provided
in
Article
VI
of
the
Agreement
was
never
vested
in
Respondent
Lot
Buyers.
Respondent
Laperal
Realty,
on
the
other
hand,
as
a
contracting
party
to
the
Agreement,
has
the
right
to
compel
Petitioners
to
first
arbitrate
before
seeking
judicial
relief.
However,
to
split
the
proceedings
into
arbitration
for
Respondent
Laperal
Realty
and
trial
for
the
Respondent
Lot
Buyers,
or
to
hold
trial
in
abeyance
pending
arbitration
betweenPetitioners
and
Respondent
Laperal
Realty,
would
in
effect
result
in
multiplicity
of
suits,
duplicitous
procedure
and
unnecessary
delay.
On
the
other
hand,
it
would
be
in
the
interest
of
justice
if
the
trial
court
hears
the
complaint
against
all
herein
Respondents
and
adjudicates
Petitioners’
rights
as
against
theirs
in
a
single
and
complete
proceeding.
Petition
is
GRANTED.
The
assailed
Order
of
RTC
of
Lipa
City
is
NULLIFIED
and
SET
ASIDE.
4.HOME
BANKERS
SAVINGS
AND
TRUST
COMPANY,
petitioner,
vs.
COURT
OF
APPEALS
and
FAR
EAST
BANK
&
TRUST
CO.,
INC.
respondents.
G.R.
No.
115412,
November
19,
1999
BUENA,
J.:
FACTS:
Victor
Tancuan
issued
Petitioner
Home
Bankers
Savings
and
Trust
Company
a
check
while
Eugene
Arriesgado
issued
Private
Respondent
Far
East
Bank
and
Trust
Company
three
checks;
both
checks
totaling
the
amount
of
P25,250,000.00.
Tancuan
and
Arriesgado
exchanged
each
other’s
checks
and
deposited
them
with
their
respective
banks
for
collection.
When
FEBTC
presented
Tancuan’s
HBSTC
check
for
clearing,
it
was
dishonored
for
being
DAIF.
Meanwhile,
HBSTC
sent
Arriesgado’s
3
FEBTC
checks
through
the
Philippine
Clearing
House
Corporation
(PCHC)
to
FEBTC
but
was
returned
for
being
DAIF.
HBSTC
receive
the
notice
of
dishonor
but
refused
to
accept
the
checks
and
returned
them
to
FEBTC
through
the
PCHC
for
the
reason
“Beyond
Reglementary
Period,”
implying
that
HBSTC
already
treated
the
3
checks
as
cleared
and
allowed
the
proceeds
thereof
to
be
withdrawn.
FEBTC
demanded
reimbursement
for
the
returned
checks
and
inquired
from
HBSTC
whether
it
had
permitted
any
withdrawal
of
funds
against
the
unfunded
checks.
HBSTC,
however
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
7
ATTY.
BUSTAMANTE
ABSR
refused
to
make
any
reimbursement
and
to
provide
FEBTC
with
the
needed
information.
Thus,
FEBTC
submitted
the
dispute
for
arbitration
before
the
PCHC
Arbitration
Committee,
under
its
Supplementary
Rules
on
Regional
Clearing
to
which
FEBTC
and
HBSTC
are
bound
as
participants
in
the
regional
clearing
operations
administered
by
the
PCHC.
While
the
arbitration
proceeding
was
still
pending,
FEBTC
filed
an
action
for
sum
of
money
and
damages
with
preliminary
attachment
against
HBSTC.
HBSTC
moved
to
dismiss
on
the
ground
that
there
is
no
cause
of
action
and
because
it
seeks
to
enforce
an
arbitral
award
which
as
yet
does
not
exist.
The
trial
court
denied
the
motion
to
dismiss
and
the
motion
for
reconsideration.
Petitioner
then
filed
a
petition
for
certiorari
with
respondent
CA
to
which
it
had
dismissed.
ISSUE:
Whether
or
not
private
respondent
which
commenced
an
arbitration
proceeding
under
the
auspices
of
the
PCHC
may
subsequently
file
a
separate
case
in
court
over
the
same
subject
matter
despite
the
pendency
of
that
arbitration,
simply
to
obtain
the
provisional
remedy
of
attachment
against
the
adverse
party
in
the
arbitration
proceeding.
HELD:
We
find
no
merit
in
the
petition.
Section
14
of
Republic
Act
876,
otherwise
known
as
the
Arbitration
Law,
allows
any
party
to
the
arbitration
proceeding
to
petition
the
court
to
take
measures
to
safeguard
and/or
conserve
any
matter
which
is
the
subject
of
the
dispute
in
arbitration.
Petitioner’s
exposition
of
the
foregoing
provision
deserves
scant
consideration.
Section
14
simply
grants
an
arbitrator
the
power
to
issue
subpoena
and
subpoena
duces
tecum
at
any
time
before
rendering
the
award.
The
exercise
of
such
power
is
without
prejudice
to
the
right
of
a
party
to
file
a
petition
in
court
to
safeguard
any
matter
which
is
the
subject
of
the
dispute
in
arbitration.
In
the
case
at
bar,
private
respondent
filed
an
action
for
a
sum
of
money
with
prayer
for
a
writ
of
preliminary
attachment.
Undoubtedly,
such
action
involved
the
same
subject
matter
as
that
in
arbitration,
i.e.,
the
sum
of
P25,200,000.00
which
was
allegedly
deprived
from
private
respondent
in
what
is
known
in
banking
as
a
“kiting
scheme.”
However,
the
civil
action
was
not
a
simple
case
of
a
money
claim
since
private
respondent
has
included
a
prayer
for
a
writ
of
preliminary
attachment,
which
is
sanctioned
by
section
14
of
the
Arbitration
Law.
Simply
put,
participants
in
the
regional
clearing
operations
of
the
Philippine
Clearing
House
Corporation
cannot
bypass
the
arbitration
process
laid
out
by
the
body
and
seek
relief
directly
from
the
courts.
In
the
case
at
bar,
undeniably,
private
respondent
has
initiated
arbitration
proceedings
as
required
by
the
PCHC
rules
and
regulations,
and
pending
arbitration
has
sought
relief
from
the
trial
court
for
measures
to
safeguard
and/or
conserve
the
subject
of
the
dispute
under
arbitration,
8
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
A ATTY.
BUSTAMANTE
ABSR
as
sanctioned
by
section
14
of
the
Arbitration
Law,
and
otherwise
not
shown
to
be
contrary
to
the
PCHC
rules
and
regulations.
At
this
point,
we
emphasize
that
arbitration,
as
an
alternative
method
of
dispute
resolution,
is
encouraged
by
this
Court.
Aside
from
unclogging
judicial
dockets,
it
also
hastens
solutions
especially
of
commercial
disputes.
The
Court
looks
with
favor
upon
such
amicable
arrangement
and
will
only
interfere
with
great
reluctance
to
anticipate
or
nullify
the
action
of
the
arbitrator.
Wherefore,
premises
considered,
the
petition
is
hereby
dismissed
and
the
decision
of
the
court
a
quo
is
affirmed.
5.
G.R.
No.
141833
March
26,
2003
LM
POWER
ENGINEERING
CORPORATION,
petitioner,
vs.
CAPITOL
INDUSTRIAL
CONSTRUCTION
GROUPS,
INC.,
respondent.
PANGANIBAN,
J.:
FACTS:
LM
Power
Engineering
Corporation
and
Capitol
Industrial
Construction
Groups
Inc.
entered
into
a
Subcontract
Agreement
involving
electrical
work
at
the
Third
Port
of
Zamboanga.
Due
to
the
inability
of
the
petitioner
to
procure
materials,
Capitol
Industrial
took
over
some
of
the
work
contracted
to
the
former.
After
the
completion
of
the
contract,
petitioner
billed
respondent
in
the
amount
of
P6,
711,813.90
but
the
respondent
refused
to
pay.
Petitioner
filed
with
the
RTC
of
Makati
a
Complaint
for
the
collection
of
the
amount
representing
the
alleged
balance
due
it
under
the
subcontract.
Respondent
filed
a
Motion
to
Dismiss,
alleging
that
the
Complaint
was
premature,
due
to
the
absence
of
prior
recourse
to
arbitration.
RTC
denied
the
Motion
on
the
ground
that
the
dispute
did
not
involve
the
interpretation
or
the
implementation
of
the
Agreement
and
was
not
covered
by
the
arbitral
clause
and
ruled
in
favor
of
the
petitioner.
Respondent
appealed
to
the
CA,
the
latter
reversed
the
decision
of
the
RTC
and
ordered
the
referral
of
the
case
to
arbitration.
ISSUE:
WHETHER
OR
NOT
THERE
IS
A
NEED
FOR
THE
PRIOR
ARBITRATION
BEFORE
FILING
OF
THE
COMPLAINT
WITH
THE
COURT.
HELD:
YES.
The
case
at
hand
involves
technical
discrepancies
that
are
better
left
to
an
arbitral
body
that
has
expertise
in
the
subject
matter.
Moreover,
the
agreement
between
the
parties
contains
arbitral
clause
that
“any
dispute
or
conflict
as
regards
to
interpretation
and
implementation
of
this
agreement
which
cannot
be
settled
between
respondent
and
petitioner
amicably
shall
be
settled
by
means
of
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
9
ATTY.
BUSTAMANTE
ABSR
arbitration”.
The
resolution
of
the
dispute
between
the
parties
herein
requires
a
referral
to
the
provisions
of
their
agreement.
Within
the
scope
of
the
arbitration
clause
are
discrepancies
as
to
the
amount
of
advances
and
billable
accomplishments,
the
application
of
the
provision
on
termination,
and
the
consequent
set-‐off
of
expenses.
There
is
no
need
for
prior
request
for
arbitration
by
the
parties
with
the
CIAC
in
order
for
it
to
acquire
jurisdiction
because
when
a
contract
contains
a
clause
for
the
submission
of
a
future
controversy
to
arbitration,
it
is
not
necessary
for
the
parties
to
enter
into
a
submission
agreement
before
the
claimant
may
invoke
the
jurisdiction
of
CIAC.
The
arbitral
clause
in
the
agreement
is
a
commitment
on
the
part
of
the
parties
to
submit
to
arbitration
the
disputes
covered
therein.
6.
LUZON
IRON
DEVELOPMENT
GROUP
CORPORATION
AND
CONSOLIDATED
IRON
SANDS,
LTD.,Petitioners,
v.
BRIDESTONE
MINING
AND
DEVELOPMENT
CORPORATION
AND
ANACONDA
MINING
AND
DEVELOPMENT
CORPORATION,
Respondents.
G.R.
No.
220546,
December
07,
2016
MENDOZA,
J.:
FACTS:
On
October
25,
2012,
respondents
Bridestone
Mining
and
Development
Corporation
(Bridestone)
and
Anaconda
Mining
and
Development
Corporation
(Anaconda)
filed
separate
complaints
before
the
RTC
for
rescission
of
contract
and
damages
against
petitioners
Luzon
Iron
Development
Group
Corporation
(Luzon
Iron)
and
Consolidated
Iron
Sands,
Ltd.
(Consolidated
Iron),
docketed
as
Civil
Case
No.
12-‐
1053
and
Civil
Case
No.
12-‐1054,
respectively.
Both
complaints
sought
the
rescission
of
the
Tenement
Partnership
and
Acquisition
Agreement
(TPAA)4
entered
into
by
Luzon
Iron
and
Consolidated
Iron,
on
one
hand,
and
Bridestone
and
Anaconda,
on
the
other,
for
the
assignment
of
the
Exploration
Permit
Application
of
the
former
in
favor
of
the
latter.
The
complaints
also
sought
the
return
of
the
Exploration
Permits
to
Bridestone
and
Anaconda.5
Thereafter,
Luzon
Iron
and
Consolidated
Iron
filed
their
Special
Appearance
with
Motion
to
Dismiss6separately
against
Bridestone's
complaint
and
Anaconda's
complaint.
Both
motions
to
dismiss
presented
similar
grounds
for
dismissal.
They
contended
that
the
RTC
could
not
acquire
jurisdiction
over
Consolidated
Iron
because
it
was
a
foreign
corporation
that
had
never
transacted
business
in
the
Philippines.
Likewise,
they
argued
that
the
RTC
had
no
jurisdiction
over
the
subject
matter
because
of
an
arbitration
clause
in
the
TPAA.
On
December
19,
2012,
the
RTC
ordered
the
consolidation
of
the
two
cases.7
Subsequently,
Luzon
Iron
and
Consolidated
Iron
filed
their
Special
Appearance
and
Supplement
to
Motions
to
Dismiss,8
dated
January
31,
2013,
10
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
ATTY.
BUSTAMANTE
ABSR
seeking
the
dismissal
of
the
consolidated
cases.
The
petitioners
alleged
that
Bridestone
and
Anaconda
were
guilty
of
forum
shopping
because
they
filed
similar
complaints
before
the
Department
of
Environment
and
Natural
Resources
(DENR),
Mines
and
Geosciences
Bureau,
Regional
Panel
of
Arbitrators
against
Luzon
Iron.
RTC:
Denied
the
motions
to
dismiss,
as
well
as
the
supplemental
motion
to
dismiss,
finding
that
Consolidated
Iron
was
doing
business
in
the
Philippines,
with
Luzon
Iron
as
its
resident
agent.
CA:
It
agreed
that
the
court
acquired
jurisdiction
over
the
person
of
Consolidated
Iron
because
the
summons
may
be
validly
served
through
its
agent
Luzon
Iron,
considering
that
the
latter
was
merely
the
business
conduit
of
the
former.
The
CA
also
sustained
the
jurisdiction
of
the
RTC
over
the
subject
matter
opining
that
the
arbitration
clause
in
the
TPAA
provided
for
an
exception
where
parties
could
directly
go
to
court
ISSUE:
WHETHER
THE
COURT
OF
APPEALS
ERRED
IN
RULING
THAT
THE
TRIAL
COURT
HAS
JURISDICTION
OVER
THE
SUBJECT
MATTER
OF
THE
CONSOLIDATED
CASES
HELD:
YES.
If,
for
any
reasonable
reason,
the
Parties
cannot
resolve
a
material
fact,
material
event
or
any
dispute
arising
out
of
or
in
connection
with
this
TPAA,
including
any
question
regarding
its
existence,
validity
or
termination,
within
90
days
from
its
notice,
shall
be
referred
to
and
finally
resolved
by
arbitration
in
Singapore
in
accordance
with
the
Arbitration
Rules
of
the
Singapore
International
Arbitration
Centre
("SIAC
Rules")
for
the
time
being
in
force,
which
rules
are
deemed
to
be
incorporated
by
reference
in
this
clause
15.1.30
The
RTC,
as
the
CA
agreed,
countered
that
Paragraph
14.8
of
the
TPAA
allowed
the
parties
to
directly
resort
to
courts
in
case
of
a
direct
and/or
blatant
violation
of
the
provisions
of
the
TPAA.
Paragraph
14.8
stated:
Each
Party
agrees
not
to
commence
or
procure
the
commencement
of
any
challenge
or
claim,
action,
judicial
or
legislative
enquiry,
review
or
other
investigation
into
the
sufficiency,
validity,
legality
or
constitutionality
of
(i)
the
assignments
of
the
Exploration
Permit
Applications(s)
(sic)
to
LIDGC,
(ii)
any
other
assignments
contemplated
by
this
TPAA,
and/or
(iii)
or
(sic)
any
agreement
to
which
the
Exploration
Permit
Application(s)
may
be
converted,
unless
a
direct
and/or
blatant
violation
of
the
provisions
of
the
TPAA
has
been
committed.31
Thus,
consistent
with
the
state
policy
of
favoring
arbitration,
the
present
TPAA
must
be
construed
in
such
a
manner
that
would
give
life
to
the
arbitration
clause
rather
than
defeat
it,
if
such
interpretation
is
permissible.
With
this
in
mind,
the
Court
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
1
ATTY.
BUSTAMANTE
1
ABSR
views
the
interpretation
forwarded
by
the
petitioners
as
more
in
line
with
the
state
policy
favoring
arbitration.
Paragraphs
14.8
and
15.1
of
the
TPAA
should
be
harmonized
in
such
a
way
that
the
arbitration
clause
is
given
life,
especially
since
such
construction
is
possible
in
the
case
at
bench.
A
synchronized
reading
of
the
abovementioned
TPAA
provisions
will
show
that
a
claim
or
action
raising
the
sufficiency,
validity,
legality
or
constitutionality
of:
(a)
the
assignments
of
the
EP
to
Luzon
Iron;
(b)
any
other
assignments
contemplated
by
the
TPAA;
or
(c)
any
agreement
to
which
the
EPs
may
be
converted,
may
be
instituted
only
when
there
is
a
direct
and/or
blatant
violation
of
the
TPAA.
In
turn,
the
said
action
or
claim
is
commenced
by
proceeding
with
arbitration,
as
espoused
in
the
TPAA.
The
Court
disagrees
with
the
respondents
that
Paragraph
14.8
of
the
TPAA
should
be
construed
as
an
exception
to
the
arbitration
clause
where
direct
court
action
may
be
resorted
to
in
case
of
direct
and/or
blatant
violation
of
the
TPAA
occurs.
If
such
interpretation
is
to
be
espoused,
the
arbitration
clause
would
be
rendered
inutile
as
practically
all
matters
may
be
directly
brought
before
the
courts.
Such
construction
is
anathema
to
the
policy
favoring
arbitration.
A
closer
perusal
of
the
TPAA
will
also
reveal
that
paragraph
14
and
all
its
sub-‐
paragraphs
are
general
provisions,
whereas
paragraphs
15
and
all
its
sub-‐clauses
specifically
refer
to
arbitration.
When
general
and
specific
provisions
are
inconsistent,
the
specific
provision
shall
be
paramount
and
govern
the
general
provision.34
7. GR.
No.
196072,
September
20,
2017
STEAMSHIP
MUTUAL
UNDERWRITING
ASSOCIATION
(BERMUDA)
LIMITED,
Petitioner,
v.
SULPICIO
LINES,
INC.,
Respondent.
LEONEN,
J.:
FACTS:
An
insured
member
may
be
compelled
to
arbitration
pursuant
to
the
Rules
of
the
Protection
and
Indemnity
Club,
which
were
incorporated
in
the
insurance
policy
by
reference.
Where
there
are
multiple
parties,
the
court
must
refer
to
arbitration
the
parties
covered
by
the
agreement
while
proceeding
with
the
civil
action
against
those
who
were
not
bound
by
the
arbitration
agreement.
Steamship
was
a
Bermuda-‐based
Protection
and
Indemnity
Club,
managed
outside
London,
England.6
It
insures
its
members-‐shipowners
against
"third
party
risks
and
liabilities"
for
claims
arising
from
(a)
death
or
injury
to
passengers;
(b)
loss
or
damage
to
cargoes;
and
(c)
loss
or
damage
from
collisions.7
Sulpicio
insured
its
fleet
of
inter-‐island
vessels
with
Steamship
for
Protection
&
Indemnity
risks
through
local
insurance
agents,
Pioneer
Insurance
and
Surety
12
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
ATTY.
BUSTAMANTE
ABSR
Corporation
(Pioneer
Insurance)
or
Seaboard-‐Eastern
Insurance
Co.,
Inc.
(Seaboard-‐
Eastern).8
One
(1)
of
these
vessels
was
the
M/V
Princess
of
the
World,
evidenced
by
a
Certificate
of
Entry
and
Acceptance
issued
by
Steamship.
On
July
7,
2005,
M/V
Princess
of
the
World
was
gutted
by
fire
while
on
voyage
from
Iloilo
to
Zamboanga
City,
resulting
in
total
loss
of
its
cargoes.
The
fire
incident
was
found
by
the
Department
of
Interior
and
Local
Government
to
be
"accidental"
in
nature.10
Sulpicio
claimed
indemnity
from
Steamship
under
the
Protection
&
Indemnity
insurance
policy.
Steamship
denied
the
claim
and
subsequently
rescinded
the
insurance
coverage
of
Sulpicio's
other
vessels
on
the
ground
that
"Sulpicio
was
grossly
negligent
in
conducting
its
business
regarding
safety,
maintaining
the
seaworthiness
of
its
vessels
as
well
as
proper
training
of
its
crew."11
On
June
28,
2007,
Sulpicio
filed
a
Complaint12
with
the
Regional
Trial
Court
of
Makati
City
against
Steamship;
one
(1)
of
its
directors,
Gary
Rynsard;
and
its
local
insurance
agents
Pioneer
Insurance
and
Seaboard-‐Eastern
for
specific
performance
and
damages.
This
Complaint
was
docketed
as
Civil
Case
No.
07-‐577,
was
amended
on
August
10,
2007,13
and
further
amended
on
September
11,
2007.14
Steamship
filed
its
Motion
to
Dismiss
and/or
to
Refer
Case
to
Arbitration15
pursuant
to
Republic
Act
No.
9285,
or
the
Alternative
Dispute
Resolution
Act
of
2004
(ADR
Law),
and
to
Rule
4716
of
the
2005/2006
Club
Rules,
which
supposedly
provided
for
arbitration
in
London
of
disputes
between
Steamship
and
its
members.17
The
other
defendants
filed
separate
motions
to
dismiss.18
Branch
149,
Regional
Trial
Court,
Makati
City
denied
the
motions
to
dismiss.
In
its
July
11,
2008
Order,19
denying
Steamship's
motion
and
supplemental
motion
to
dismiss
and
citing20European
Resources
and
Technologies,
Inc.
v.
Ingenieuburo
Birkhann
+
Nolte,
Ingeniurgesellschaft
Gmbh21
the
Regional
Trial
Court
held
that
"arbitration
[did]
not
appear
to
be
the
most
prudent
action,
.
.
.
considering
that
the
other
defendants
.
.
.
ha[d]
already
filed
their
[respective]
[a]nswers."22
Steamship
filed
its
Motion
for
Reconsideration,23
but
it
was
likewise
denied
in
the
Order24
dated
September
24,
2008.
Steamship
assailed
trial
court
orders
before
the
Court
of
Appeals
through
a
Rule
65
Petition,
docketed
as
CA-‐G.R.
SP
No.
106103.25
The
Court
of
Appeals
dismissed
the
petition
in
its
November
26,
2010
Decision.26
It
found
no
grave
abuse
of
discretion
on
the
part
of
the
trial
court
in
denying
Steamship's
Motion
to
Dismiss
and/or
to
Refer
Case
to
Arbitration27
or
any
convincing
evidence
to
show
that
a
valid
arbitration
agreement
existed
between
the
parties.28
Steamship's
Motion
for
Reconsideration
of
this
Decision
was
likewise
denied
in
the
Resolution29
dated
March
10,
2011.
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
1
ATTY.
BUSTAMANTE
3
ABSR
ISSUE:
WHETHER
OR
NOT
THERE
IS
A
VALID
AND
BINDING
ARBITRATION
AGREEMENT
BETWEEN
STEAMSHIP
MUTUAL
UNDERWRITING
(BERMUDA)
LIMITED
AND
SULPICIO
LINES,
INC
HELD:YES.
It
is
the
State's
policy
to
promote
party
autonomy
in
the
mode
of
resolving
disputes.126
Under
the
freedom
of
contract
principle,
parties
to
a
contract
may
stipulate
on
a
particular
method
of
settling
any
conflict
between
them.127
Arbitration
and
other
alternative
dispute
resolution
methods
like
mediation,
negotiation,
and
conciliation
are
favored
over
court
action.
Republic
Act
No.
9285128
expresses
this
policy:
Section
2.
Declaration
of
Policy.
—
It
is
hereby
declared
the
policy
of
the
State
to
actively
promote
party
autonomy
in
the
resolution
of
disputes
or
the
freedom
of
the
parties
to
make
their
own
arrangements
to
resolve
their
disputes.
Towards
this
end,
the
State
shall
encourage
and
actively
promote
the
use
of
Alternative
Dispute
Resolution
(ADR)
as
an
important
means
to
achieve
speedy
and
impartial
justice
and
declog
court
dockets.
As
such,
the
State
shall
provide
means
for
the
use
of
ADR
as
an
efficient
tool
and
an
alternative
procedure
for
the
resolution
of
appropriate
cases.
Likewise,
the
State
shall
enlist
active
private
sector
participation
in
the
settlement
of
disputes
through
ADR.
This
Act
shall
be
without
prejudice
to
the
adoption
by
the
Supreme
Court
of
any
ADR
system,
such
as
mediation,
conciliation,
arbitration,
or
any
combination
thereof
as
a
means
of
achieving
speedy
and
efficient
means
of
resolving
cases
pending
before
all
courts
in
the
Philippines
which
shall
be
governed
by
such
rules
as
the
Supreme
Court
may
approve
from
time
to
time.
(Emphasis
supplied)
Arbitration,
as
a
mode
of
settling
disputes,
was
already
recognized
in
the
Civil
Code.129
In
1953,
Republic
Act
No.
876
was
passed,
which
reinforced
domestic
arbitration
as
a
process
of
dispute
resolution.
Foreign
arbitration
was
likewise
recognized
through
the
Philippines'
adherence
to
the
United
Nations
Convention
on
the
Recognition
and
Enforcement
of
Foreign
Arbitral
Awards
of
1958,
otherwise
known
as
the
New
York
Convention.130
Republic
Act
No.
9285
sets
the
basic
principles
in
the
enforcement
of
foreign
arbitral
awards
in
the
Philippines.131
Consistent
with
State
policy,
"arbitration
agreements
are
liberally
construed
in
favor
of
proceeding
to
arbitration."132
Every
reasonable
interpretation
is
indulged
to
give
effect
to
arbitration
agreements.
Thus,
courts
must
give
effect
to
the
arbitration
clause
as
much
as
the
terms
of
the
agreement
would
allow.133
"Any
doubt
should
be
resolved
in
favor
of
arbitration."134
Thus,
an
arbitration
agreement
that
was
not
embodied
in
the
main
agreement
but
set
forth
in
another
document
is
binding
upon
the
parties,
where
the
document
was
incorporated
by
reference
to
the
main
agreement.
The
arbitration
agreement
contained
in
the
Club
Rules,
which
in
turn
was
referred
to
in
the
Certificate
of
Entry
and
Acceptance,
is
binding
upon
Sulpicio
even
though
there
was
no
specific
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
1
ATTY.
BUSTAMANTE
5
ABSR
stipulation
on
dispute
resolution
in
this
Certificate.
Furthermore,
as
stated
earlier,
Sulpicio
became
a
member
of
Steamship
by
the
very
act
of
making
a
contract
of
insurance
with
it.
The
Certificate
of
Entry
and
Acceptance
issued
by
Steamship
states
that
"[its]
name
has
been
entered
in
the
Register
of
Members
of
the
Club
as
a
Member."157
Sulpicio
admits
its
membership
and
the
entry
of
its
vessels
to
Steamship.
8.DEPARTMENT
OF
PUBLIC
WORKS
AND
HIGHWAYS,
Petitioner,
v.
CMC/MONARK/PACIFIC/HI-‐TRI
JOINT
VENTURE,
Respondent.
G.R.
No.
179732,
September
13,
2017
LEONEN,J.
FACTS:
As
the
administrative
agency
tasked
with
resolving
issues
pertaining
to
the
construction
industry,
the
Construction
Industry
Arbitration
Commission
enjoys
a
wide
latitude
in
recognition
of
its
technical
expertise
and
experience.
Its
factual
findings
are,
thus,
accorded
respect
and
even
finality,
particularly
when
they
are
affirmed
by
an
appellate
court.
This
is
a
Petition
for
Review
on
Certiorari1
assailing
the
Court
of
Appeals
Decision2
dated
September
20,
2007
in
CA-‐G.R.
SP
Nos.
88953
and
88911,
which
affirmed
the
March
1,
2005
Award
of
the
Construction
Industry
Arbitration
Commission
(CIAC).
On
April
29,
1999,
Republic
of
the
Philippines,
through
the
Department
of
Public
Works
and
Highways
(DPWH),
and
CMC/Monark/Pacific/Hi-‐Tri
J.V.
(the
Joint
Venture)
executed
"Contract
Agreement
for
the
Construction
of
Contract
Package
6MI-‐9,
Pagadian-‐Buug
Section,
Zamboanga
del
Sur,
Sixth
Road
Project,
Road
Improvement
Component
Loan
No.
1473-‐PHI"3
(Contract)
for
a
total
contract
amount
of
P713,330,885.28.4
Parts
I
(General
Conditions
with
forms
of
tender
+
agreement)
and
II
(Conditions
of
Particular
Application
+
Guidelines
for
Preparation
of
Part
II
Clauses)
of
the
"Conditions
of
Contract
for
Works
of
Civil
Engineering
Construction
of
the
Federation
International
Des
Ingenieurs
-‐
Conseils"
(Conditions
of
Contract)
formed.
part
of
the
Contract.5
DPWH
hired
BCEOM
French
Engineering
Consultants
to
16
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
ATTY.
BUSTAMANTE
ABSR
oversee
the
project.6
On
October
23,
2002,
or
while
the
project
was
ongoing,
the
Joint
Venture's
truck
and
equipment
were
set
on
fire.
On
March
11,
2003,
a
bomb
exploded
at
Joint
Venture's
hatching
plant
located
at
Brgy.
West
Boyogan,
Kumalarang,
Zamboanga
del
Sur.
According
to
reports,
the
bombing
incident
was
caused
by
members
of
the
Moro
Islamic
Liberation
Front.7
The
Joint
Venture
made
several
written
demands
for
extension
and
payment
of
the
foreign
component
of
the
Contract.
There
were
efforts
between
the
parties
to
settle
the
unpaid
Payment
Certificates
amounting
to
P26,737,029.49.
Thus,
only
the
foreign
component
of
US$358,227.95
was
up
for
negotiations
subject
to
further
reduction
of
the
amount
on
account
of
payments
subsequently
received
by
the
Joint
Venture
from
DPWH.8
In
a
letter
dated
September
18,
2003,
BCEOM
French
Engineering
Consultants
recommended
that
DPWH
promptly
pay
the
outstanding
monies
due
the
Joint
Venture.9
The
letter
also
stated
that
the
actual
volume
of
the
Joint
Venture's
accomplishment
was
"2,732m2
of
hardrock
and
4,444m3
of
rippable
rock,"
making
the
project
80%
complete
when
it
was
halted.10
On
March
3,
2004,
the
Joint
Venture
filed
a
Complaint11
against
DPWH
before
CIAC.
Meanwhile,
on
July
8,
2004,
the
Joint
Venture
sent
a
"Notice
of
Mutual
Termination
of
Contract",13
to
DPWH
requesting
for
a
mutual
termination
of
the
contract
subject
of
the
arbitration
case.
This
is
due
to
its
diminished
financial
capability
due
to
DPWH's
late
payments,
changes
in
the
project
involving
payment
terms,
peace
and
order
problems,
and
previous
agreement
by
the
parties.
On
July
16,
2004,
then
DPWH
Acting
Secretary
Florante
Soriquez
accepted
the
Joint
Venture's
request
for
mutual
termination
of
the
contract.14
After
hearing
and
submission
of
the
parties'
respective
memoranda,15
CIAC
promulgated
an
Award16
on
March
1,
2005,
directing
DPWH
to
pay
the
Joint
Venture
its
money
claims
plus
legal
interest.
CIAC,
however,
denied
the
Joint
Venture's
claim
for
price
adjustment
due
to
the
delay
in
the
issuance
of
a
Notice
to
Proceed
under
Presidential
Decree
CA:
Sustained
CIAC's
Award
with
certain
modifications
and
remanded
the
case
to
CIAC
for
the
determination
of
the
number
of
days'
extension
that
the
Joint
Venture
is
entitled
to
and
"the
conversion
rate
in
peso.
ISSUE:
WHETHER
OR
NOT
THE
COURT
OF
APPEALS
GRAVELY
ERRED
IN
RENDERING
THE
ASSAILED
DECISION
BECAUSE
IT
COMPLETELY
IGNORED,
OVERLOOKED,
OR
MISAPPRECIATED
FACTS
OF
SUBSTANCE,
WHICH,
IF
DULY
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
1
ATTY.
BUSTAMANTE
7
ABSR
CONSIDERED,
WOULD
MATERIALLY
AFFECT
THE
OUTCOME
OF
THE
CASE
HELD:NO.
CIAC
was
created
under
Executive
Order
No.
1008,
or
the
"Construction
Industry
Arbitration
Law."
It
was
originally
under
the
administrative
supervision
of
the
Philippine
Domestic
Construction
Board59
which,
in
turn,
was
an
implementing
agency
of
the
Construction
Industry
Authority
of
the
Philippines.60
The
Construction
Industry
Authority
of
the
Philippines
is
presently
a
part
of
the
Department
of
Trade
and
Industry
as
an
attached
agency.61
CIAC's
specific
purpose
is
the
"early
and
expeditious
settlement
of
disputes"62
in
the
construction
industry
as
a
recognition
of
the
industry's
role
in
"the
furtherance
of
national
development
goals."63
Section
4
of
the
Construction
Industry
Arbitration
Law
lays
out
CIAC's
jurisdiction:
Section
4.
Jurisdiction.
-‐
The
CIAC
shall
have
original
and
exclusive
jurisdiction
over
disputes
arising
from,
or
connected
with,
contracts
entered
into
by
parties
involved
in
construction
in
the
Philippines,
whether
the
dispute
arises
before
or
after
the
completion
of
the
contract,
or
after
the
abandonment
or
breach
thereof.
These
disputes
may
involve
government
or
private
contracts.
For
the
Board
to
acquire
jurisdiction,
the
parties
to
a
dispute
must
agree
to
submit
the
same
to
voluntary
arbitration.
The
jurisdiction
of
the
CIAC
may
include
but
is
not
limited
to
violation
of
specifications
for
materials
and
workmanship;
violation
of
the
terms
of
agreement;
interpretation
and/or
application
of
contractual
time
and
delays;
maintenance
and
defects;
payment,
default
of
employer
or
contractor
and
changes
in
contract
cost.
CIAC's
authority
to
arbitrate
construction
disputes
was
then
incorporated
into
the
general
statutory
framework
on
alternative
dispute
resolution
through
Republic
Act
No.
9285,
the
"Alternative
Dispute
Resolution
Act
of
2004".
Section
34
of
Republic
Act
No.
9285
specifically
referred
to
the
Construction
Industry
Arbitration
Law,
while
Section
35
confirmed
CIAC's
jurisdiction:
CHAPTER
6
-‐
ARBITRATION
OF
CONSTRUCTION
DISPUTES
Section
34.
Arbitration
of
Construction
Disputes:
Governing
Law.
-‐
The
arbitration
of
construction
disputes
shall
be
governed
by
Executive
Order
No.
1008,
otherwise
known
as
the
Constitution
Industry
Arbitration
Law.
Section
35.
Coverage
of
the
Law.
-‐
Construction
disputes
which
fall
within
the
original
and
exclusive
jurisdiction
of
the
Construction
Industry
Arbitration
Commission
(the
"Commission")
shall
include
those
between
or
among
parties
to,
or
who
are
otherwise
bound
by,
an
arbitration
agreement,
directly
or
by
reference
whether
such
parties
are
project
owner,
contractor,
subcontractor,
quantity
18
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
ATTY.
BUSTAMANTE
ABSR
surveyor,
bondsman
or
issuer
of
an
insurance
policy
in
a
construction
project.
The
Commission
shall
continue
to
exercise
original
and
exclusive
jurisdiction
over
construction
disputes
although
the
arbitration
is
"commercial"
pursuant
to
Section
21
of
this
Act.
As
a
general
rule,
findings
of
fact
of
CIAC,
a
quasi-‐judicial
tribunal
which
has
expertise
on
matters
regarding
the
construction
industry,
should
be
respected
and
upheld.
In
National
Housing
Authority
v.
First
United
Constructors
Corp.,64
this
Court
held
that
CIAC's
factual
findings,
as
affirmed
by
the
Court
of
Appeals,
will
not
be
overturned
except
as
to
the
most
compelling
of
reasons:
As
this
finding
of
fact
by
the
CIAC
was
affirmed
by
the
Court
of
Appeals,
and
it
being
apparent
that
the
CIAC
arrived
at
said
finding
after
a
thorough
consideration
of
the
evidence
presented
by
both
parties,
the
same
may
no
longer
be
reviewed
by
this
Court.
The
all
too-‐familiar
rule
is
that
the
Court
will
not,
in
a
petition
for
review
on
certiorari,
entertain
matters
factual
in
nature,
save
for
the
most
compelling
and
cogent
reasons,
like
when
such
factual
findings
were
drawn
from
a
vacuum
or
arbitrarily
reached,
or
are
grounded
entirely
on
speculation
or
conjectures,
are
conflicting
or
are
premised
on
the
supposed
evidence
and
contradicted
by
the
evidence
on
record
or
when
the
inference
made
is
manifestly
mistaken
or
absurd.
This
conclusion
is
made
more
compelling
by
the
fact
that
the
CIAC
is
a
quasi-‐judicial
body
whose
jurisdiction
is
confined
to
construction
disputes.
Indeed,
settled
is
the
rule
that
findings
of
fact
of
administrative
agencies
and
quasi-‐judicial
bodies,
which
have
acquired
expertise
because
their
jurisdiction
is
confined
to
specific
matters,
are
generally
accorded
not
only
respect,
but
finality
when
affirmed
by
the
Court
of
Appeals.65
(Emphasis
supplied)
Excluded
from
the
coverage
of
this
law
are
disputes
arising
from
employer-‐
employee
relationships
which
shall
continue
to
be
covered
by
the
Labor
Code
of
the
Philippines.
Republic
Act
No.
9184
or
the
"Government
Procurement
Reform
Act,"
recognized
CIAC's
competence
in
arbitrating
over
contractual
disputes
within
the
construction
industry:
Section
59.
Arbitration,
Any
and
all
disputes
arising
from
the
implementation
of
a
contract
covered
by
this
Act
shall
be
submitted
to
arbitration
in
the
Philippines
according
to
the
provisions
of
Republic
Act
No.
876,
otherwise
known
as
the
"Arbitration
Law":
Provided,
however,
That,
disputes
that
are
within
the
competence
of
the
Construction
Industry
Arbitration
Commission
to
resolve
shall
be
referred
thereto.
The
process
of
arbitration
shall
be
incorporated
as
a
provision
in
the
contract
that
will
be
executed
pursuant
to
the
provisions
of
this
Act:
Provided,
That
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
1
ATTY.
BUSTAMANTE
9
ABSR
by
mutual
agreement,
the
parties
may
agree
in
writing
to
resort
to
alternative
modes
of
dispute
resolution.
(Emphasis
supplied)
CIAC's
authority
to
arbitrate
construction
disputes
was
then
incorporated
into
the
general
statutory
framework
on
alternative
dispute
resolution
through
Republic
Act
No.
9285,
the
"Alternative
Dispute
Resolution
Act
of
2004".
Section
34
of
Republic
Act
No.
9285
specifically
referred
to
the
Construction
Industry
Arbitration
Law,
while
Section
35
confirmed
CIAC's
jurisdiction.
In
distinguishing
between
commercial
arbitration,
voluntary
arbitration
under
Article
219(14)
of
the
Labor
Code,66
and
construction
arbitration,
Freuhauf
Electronics
Philippines
Corporation
v.
Technology
Electronics
Assembly
and
Management
Pacific67
ruled
that
commercial
arbitral
tribunals
are
purely
ad
hoc
bodies
operating
through
contractual
consent,
hence,
they
are
not
quasi-‐judicial
agencies.
In
contrast,
voluntary
arbitration
under
the
Labor
Code
and
construction
arbitration
derive
their
authority
from
statute
in
recognition
of
the
public
interest
inherent
in
their
respective
spheres.
Furthermore,
voluntary
arbitration
under
the
Labor
Code
and
construction
arbitration
exist
independently
of
the
will
of
the
contracting
parties:
Voluntary
Arbitrators
resolve
labor
disputes
and
grievances
arising
from
the
interpretation
of
Collective
Bargaining
Agreements.
These
disputes
were
specifically
excluded
from
the
coverage
of
both
the
Arbitration
Law
and
the
ADR
Law.
Unlike
purely
commercial
relationships,
the
relationship
between
capital
and
labor
are
heavily
impressed
with
public
interest.
Because
of
this,
Voluntary
Arbitrators
authorized
to
resolve
labor
disputes
have
been
clothed
with
quasi-‐judicial
authority.
On
the
other
hand,
commercial
relationships
covered
by
our
commercial
arbitration
laws
are
purely
private
and
contractual
in
nature.
Unlike
labor
relationships,
they
do
not
possess
the
same
compelling
state
interest
that
would
justify
state
interference
into
the
autonomy
of
contracts.
Hence,
commercial
arbitration
is
a
purely
private
system
of
adjudication
facilitated
by
private
citizens
instead
of
government
instrumentalities
wielding
quasi-‐judicial
powers.
Moreover,
judicial
or
quasi-‐judicial
jurisdiction
cannot
be
conferred
upon
a
tribunal
by
the
parties
alone.
The
Labor
Code
itself
confers
subject-‐matter
jurisdiction
to
Voluntary
Arbitrators.
Notably,
the
other
arbitration
body
listed
in
Rule
43
-‐
the
Construction
Industry
Arbitration
Commission
(CIAC)
-‐
is
also
a
government
agency
attached
to
the
Department
of
Trade
and
Industry.
Its
jurisdiction
is
likewise
conferred
by
statute.
By
contrast,
the
subject
matter
jurisdiction
of
commercial
arbitrators
is
stipulated
by
the.parties.68
(Emphasis
supplied)
20
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
ATTY.
BUSTAMANTE
ABSR
8.BASES
CONVERSION
DEVELOPMENT
AUTHORITY
v.
DMCI
PROJECT
DEVELOPERS
GR
No.
173137,
Jan
11,
2016
LEONEN,
J.:
An
arbitration
clause
in
a
document
of
contract
may
extend
to
subsequent
documents
of
contract
executed
for
the
same
purpose.
Nominees
of
a
party
to
and
beneficiaries
of
a
contract
containing
an
arbitration
clause
may
become
parties
to
a
proceeding
initiated
based
on
that
arbitration
clause.
FACTS:
On
June
10,
1995,
Bases
Conversion
Development
Authority
(BCDA)
entered
into
a
Joint
Venture
Agreement[1]
with
Philippine
National
Railways
(PNR)
and
other
foreign
corporations.[2]
Under
the
Joint
Venture
Agreement,
the
parties
agreed
to
construct
a
railroad
system
from
Manila
to
Clark
with
possible
extensions
to
Subic
Bay
and
La
Union
and
later,
possibly
to
Ilocos
Norte
and
Nueva
Ecija.[3]
BCDA
shall
establish
North
Luzon
Railways
Corporation
(Northrail)
for
purposes
of
constructing,
operating,
and
managing
the
railroad
system.
BCDA
organized
and
incorporated
Northrail.[6]
Northrail
was
registered
with
the
Securities
and
Exchange
Commission
on
August
22,
1995.[7]
BCDA
invited
investors
to
participate
in
the
railroad
project's
financing
and
implementation.
Among
those
invited
were
D.M.
Consunji,
Inc.
and
Metro
Pacific
Corporation.[8]
On
February
8,
1996,
the
Joint
Venture
Agreement
was
amended
to
include
D.M.
Consunji,
Inc.
and/or
its
nominee
as
party.[9]
Under
the
amended
Joint
Venture
Agreement,
D.M.
Consunji,
Inc.
shall
be
an
additional
investor
of
Northrail.[10]
It
shall
subscribe
to
20%
of
the
increase
in
Northrail's
authorized
capital
stock.[11]
On
February
8,
1996,
BCDA
and
the
other
parties
to
the
Joint
Venture
Agreement,
including
D.M.
Consunji,
Inc.
and/or
its
nominee,
entered
into
a
Memorandum
of
Agreement.[12]
Under
this
agreement,
the
parties
agreed
that
the
initial
seed
capital
of
P600
million
shall
be
infused
to
Northrail.[13]
Of
that
amount,
P200
million
shall
be
D.M.
Consunji,
Inc.'s
share,
which
shall
be
converted
to
equity
upon
NorthraiPs
privatization.[14]
Later,
D.M.
Consunji,
Inc.'s
share
was
increased
to
P300
million.[15]
Upon
BCDA
and
Northrail's
request,[16]
DMCI
Project
Developers,
Inc.
(DMCI-‐PDI)
deposited
P300
million
into
NorthraiPs
account
with
Land
Bank
of
the
Philippines.[17]
The
deposit
was
made
on
August
7,
1996[18]
for
its
"future
subscription
of
the
Northrail
shares
of
stocks."[19]
In
NorthraiPs
1998
financial
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
2
ATTY.
BUSTAMANTE
1
ABSR
statements
submitted
to
the
Securities
and
Exchange
Commission,
this
amount
was
reflected
as
"Deposits
For
Future
Subscription."[20]
At
that
time,
NorthraiPs
application
to
increase
its
authorized
capital
stock
was
still
pending
with
the
Securities
and
Exchange
Commission.[21]
In
letters[22]
dated
April
4,
1997,
D.M.
Consunji,
Inc.
informed
PNR
and
the
other
parties
that
DMCI-‐PDI
shall
be
its
designated
nominee
for
all
the
agreements
it
entered
and
would
enter
with
them
in
connection
with
the
railroad
project.
Later,
Northrail
withdrew
from
the
Securities
and
Exchange
Commission
its
application
for
increased
authorized
capital
stock.[24]Moreover,
according
to
DMCI-‐
PDI,
BCDA
applied
for
Official
Development
Assistance
from
Obuchi
Fund
of
Japan.[25]
This
required
Northrail
to
be
a
100%
government-‐owned
and
controlled
corporation.[26]
On
September
27,
2000,
DMCI-‐PDI
started
demanding
from
BCDA
and
Northrail
the
return
of
its
P300
million
deposit.[27]
DMCI-‐PDI
cited
Northrail's
failure
to
increase
its
authorized
capital
stock
as
reason
for
the
demand.[28]
BCDA
and
Northrail
refused
to
return
the
deposit.
Upon
BCDA's
request,
the
Office
of
the
Government
Corporate
Counsel
(OGCC)
issued
Opinion
No.
116,
Series
of
2001[31]
on
June
27,
2001.
The
OGCC
stated
that
"since
no
increase
in
capital
stock
was
implemented,
it
is
but
proper
to
return
the
investments
of
both
FBDC
and
DMCI[.]"[32]
In
a
January
19,
2005
letter,[33]
DMCI-‐PDI
reiterated
the
request
for
the
refund
of
its
P300
million
deposit
for
future
Northrail
subscription.
On
August
17,
2005,[36]
DMCI-‐PDI
served
a
demand
for
arbitration
to
BCDA
and
Northrail,
citing
the
arbitration
clause
in
the
June
10,
1995
Joint
Venture
Agreement.[37]
BCDA
and
Northrail
failed
to
respond.[38]
DMCI-‐PDI
filed
before
the
Regional
Trial
Court
of
Makati[39]
a
Petition
to
Compel
Arbitration[40]
against
BCDA
and
Northrail,
pursuant
to
the
alleged
arbitration
clause
in
the
Joint
Venture
Agreement.[41]
DMCI-‐PDI
prayed
for
"an
order
directing
the
parties
to
proceed
to
arbitration
in
accordance
with
the
terms
and
conditions
of
the
agreement."[42]
BCDA
filed
a
Motion
to
Dismiss[43]
on
the
ground
that
there
was
no
arbitration
clause
that
DMCI-‐PDI
could
enforce
since
DMCI-‐PDI
was
not
a
party
to
the
Joint
Venture
Agreement
containing
the
arbitration
clause.[44]
Northrail
filed
a
separate
Motion
to
Dismiss[45]
on
the
ground
that
the
court
did
not
have
jurisdiction
over
it
and
that
DMCI-‐PDI
had
no
cause
for
arbitration
against
it.
22
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
ATTY.
BUSTAMANTE
ABSR
RTC:
The
trial
court
ruled
that
the
arbitration
clause
in
the
Joint
Venture
Agreement
should
cover
all
subsequent
documents
including
the
amended
Joint
Venture
Agreement
and
the
Memorandum
of
Agreement.
The
three
(3)
documents
constituted
one
contract
for
the
formation
and
funding
of
Northrail.[49]
The
trial
court
also
ruled
that
even
though
DMCI-‐PDI
was
not
a
signatory
to
the
Joint
Venture
Agreement
and
the
Memorandum
of
Agreement,
it
was
an
assignee
of
D.M.
Consunji,
Inc.'s
rights.
Therefore,
it
could
invoke
the
arbitration
clause
in
the
Joint
Venture
Agreement.
ISSUE:
WHETHER
DMCI-‐PDI
MAY
COMPEL
BCDA
AND
NORTHRAIL
TO
SUBMIT
TO
ARBITRATION.
HELD:
YES.
Arbitration
is
a
mode
of
settling
disputes
between
parties.[75]
Like
many
alternative
dispute
resolution
processes,
it
is
a
product
of
the
meeting
of
minds
of
parties
submitting
a
pre-‐defined
set
of
disputes.
They
agree
among
themselves
to
a
process
of
dispute
resolution
that
avoids
extended
litigation.
The
state
adopts
a
policy
in
favor
of
arbitration.
Republic
Act
No.
9285[76]
expresses
this
policy:
SEC.
2.
Declaration
of
Policy.
-‐
It
is
hereby
declared
the
policy
of
the
State
to
actively
promote
party
autonomy
in
the
resolution
of
disputes
or
the
freedom
of
the
parties
to
make
their
own
arrangements
to
resolve
their
disputes.
Towards
this
end,
the
State
shall
encourage
and
actively
promote
the
use
of
Alternative
Dispute
Resolution
(ADR)
as
an
important
means
to
achieve
speedy
and
impartial
justice
and
declog
court
dockets.
As
such,
the
State
shall
provide
means
for
the
use
of
ADR
as
an
efficient
tool
and
an
alternative
procedure
for
the
resolution
of
appropriate
cases.
Likewise,
the
State
shall
enlist
active
private
sector
participation
in
the
settlement
of
disputes
through
ADR.
This
Act
shall
be
without
prejudice
to
the
adoption
by
the
Supreme
Court
of
any
ADR
system,
such
as
mediation,
conciliation,
arbitration,
or
any
combination
thereof
as
a
means
of
achieving
speedy
and
efficient
means
of
resolving
cases
pending
before
all
courts
in
the
Philippines
which
shall
be
governed
by
such
rules
as
the
Supreme
Court
may
approve
from
time
to
time.
(Emphasis
supplied)
Our
policy
in
favor
of
party
autonomy
in
resolving
disputes
has
been
reflected
in
our
laws
as
early
as
1949
when
our
Civil
Code
was
approved.[77]
Republic
Act
No.
876[78]
later
explicitly
recognized
the
validity
and
enforceability
of
parties'
decision
to
submit
disputes
and
related
issues
to
arbitration.[79]
Arbitration
agreements
are
liberally
construed
in
favor
of
proceeding
to
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
2
ATTY.
BUSTAMANTE
3
ABSR
arbitration.[80]
We
adopt
the
interpretation
that
would
render
effective
an
arbitration
clause
if
the
terms
of
the
agreement
allow
for
such
interpretation.
Hence,
we
resolve
the
issue
of
whether
DMCI-‐PDI
may
compel
BCDA
and
Northrail
to
submit
to
arbitration
proceedings
in
light
of
the
policy
in
favor
of
arbitration.
9. FRUEHAUF
ELECTRONICS
PHILIPPINES
CORPORATION,
Petitioner,
vs.
TECHNOLOGY
ELECTRONICS
ASSEMBLY
AND
MANAGEMENT
PACIFIC
CORPORATION,
Respondent.
G.R.
No.
204197
BRION,
J.:
The
fundamental
importance
of
this
case
lies
in
its
delineation
of
the
extent
of
permissible
judicial
review
over
arbitral
awards.
We
make
this
determination
from
the
prism
of
our
existing
laws
on
the
subject
and
the
prevailing
state
policy
to
uphold
the
autonomy
of
arbitration
proceedings.
FACTS:
In
1978,
Fruehauf
Electronics
Philippines
Corp.
(Fruehauf)
leased
several
parcels
of
land
in
Pasig
City
to
Signetics
Filipinas
Corporation
(Signetics)
for
a
period
of
25
years
(until
May
28,
2003).
Signetics
constructed
a
semiconductor
assembly
factory
on
the
land
on
its
own
account.
In
1983,
Signetics
ceased
its
operations
after
the
Board
of
Investments
(BOI)
withdrew
the
investment
incentives
granted
to
electronic
industries
based
in
Metro
Manila.
In
1986,
Team
Holdings
Limited
(THL)
bought
Signetics.
THL
later
changed
its
name
to
Technology
Electronics
Assembly
and
Management
Pacific
Corp.
(TEAM).
In
March
1987,
Fruehauf
filed
an
unlawful
detainer
case
against
TEAM.
In
an
effort
to
amicably
settle
the
dispute,
both
parties
executed
a
Memorandum
of
Agreement
(MOA)
on
June
9,
1988.3
Under
the
MOA,
TEAM
undertook
to
pay
Fruehauf
14.7
million
pesos
as
unpaid
rent
(for
the
period
of
December
1986
to
June
1988).
They
also
entered
a
15-‐year
lease
contract4
(expiring
on
June
9,
2003)
that
was
renewable
for
another
25
years
upon
mutual
agreement.
The
contract
included
an
arbitration
agreement.
The
contract
also
authorized
TEAM
to
sublease
the
property.
TEAM
subleased
the
property
to
Capitol
Publishing
House
(Capitol)
on
December
2,
1996
after
notifying
Fruehauf.
On
May
2003,
TEAM
informed
Fruehauf
that
it
would
not
be
renewing
the
lease.
6
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
2
ATTY.
BUSTAMANTE
5
ABSR
the
tribunal
failed
to
properly
appreciate
the
facts
and
the
terms
of
the
lease
contract.
RTC: found
insufficient
legal
grounds
under
Sections
24
and
25
of
the
Arbitration
Law
to
modify
or
vacate
the
award.32
CA:DISMISSED,
BUT
AMENDED
AFTER
MR
The
CA
held
that
Section
29
of
the
Arbitration
Law
does
not
preclude
the
aggrieved
party
from
resorting
to
other
judicial
remedies.50
Citing
Asset
Privatization
Trust
v.
Court
of
Appeals,51the
CA
held
that
the
aggrieved
party
may
resort
to
a
petition
for
certiorari
when
the
R
TC
to
which
the
award
was
submitted
for
confirmation
Has
acted
without
jurisdiction,
or
with
grave
abuse
of
discretion
and
there
is
no
appeal,
nor
any
plain,
speedy
remedy
in
the
course
of
law.
ISSUE:
WHAT
ARE
THE
REMEDIES
OR
THE
MODES
OF
APPEAL
AGAINST
AN
UNFAVORABLE
ARBITRAL
AWARD?
HELD:
If
the
Regional
Trial
Court
is
asked
to
set
aside
an
arbitral
award
in
a
domestic
or
international
arbitration
on
any
ground
other
than
those
provided
in
the
Special
ADR
Rules,
the
court
shall
entertain
such
ground
for
the
setting
aside
or
non-‐
recognition
of
the
arbitral
award
only
if
the
same
amounts
to
a
violation
of
public
policy.
The
court
shall
not
set
aside
or
vacate
the
award
of
the
arbitral
tribunal
merely
on
the
ground
that
the
arbitral
tribunal
committed
errors
of
fact,
or
of
law,
or
of
fact
and
law,
as
the
court
cannot
substitute
its
judgment
for
that
of
the
arbitral
tribunal.116
The
grounds
for
vacating
a
domestic
arbitral
award
under
Section
24
of
the
Arbitration
Law
contemplate
the
following
scenarios:
(a)
when
the
award
is
procured
by
corruption,
fraud,
or
other
undue
means;
or
26
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
ATTY.
BUSTAMANTE
ABSR
(b)
there
was
evident
partiality
or
corruption
in
the
arbitrators
or
any
of
them;
or
(c)
the
arbitrators
were
guilty
of
misconduct
that
materially
prejudiced
the
rights
of
any
party;
or
(d)
the
arbitrators
exceeded
their
powers,
or
so
imperfectly
executed
them,
that
a
mutual,
final
and
definite
award
upon
the
subject
matter
submitted
to
them
was
not
made.
117
The
award
may
also
be
vacated
if
an
arbitrator
who
was
disqualified
to
act
willfully
refrained
from
disclosing
his
disqualification
to
the
parties.
118
Notably,
none
of
these
grounds
pertain
to
the
correctness
of
the
award
but
relate
to
the
misconduct
of
arbitrators.
A
losing
party
is
likewise
precluded
from
resorting
to
certiorari
under
Rule
65
of
the
Rules
of
Court.
124
Certiorari
is
a
prerogative
writ
designed
to
correct
errors
of
jurisdiction
committed
by
a
judicial
or
quasi-‐judicial
body.
125
Because
an
arbitral
tribunal
is
not
a
government
organ
exercising
judicial
or
quasi-‐judicial
powers,
it
is
removed
from
the
ambit
of
Rule
65.
Not
even
the
Court's
expanded
certiorari
jurisdiction
under
the
Constitution
126
can
justify
judicial
intrusion
into
the
merits
of
arbitral
awards.
While
the
Constitution
expanded
the
scope
of
certiorari
proceedings,
this
power
remains
limited
to
a
review'
of
the
acts
of
"any
branch
or
instrumentality
of
the
Government."
As
a
purely
private
creature
of
contract,
an
arbitral
tribunal
remains
outside
the
scope
of
certiorari.
Lastly,
the
Special
ADR
Rules
are
a
self-‐contained
body
of
rules.
The
parties
cannot
invoke
remedies
and
other
provisions
from
the
Rules
of
Court
unless
they
were
incorporated
in
the
Special
ADR
Rules:
Rule
22.1.
Applicability
of
Rules
of
Court.
-‐
The
provisions
of
the
Rules
of
Court
that
are
applicable
to
the
proceedings
enumerated
in
Rule
1.1
of
these
Special
ADR
Rules
have
either
been
included
and
incorporated
in
these
Special
ADR
Rules
or
specifically
referred
to
herein.
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
2
ATTY.
BUSTAMANTE
7
ABSR
Under
the
Arbitration
Law,
the
mode
of
appeal
was
via
petition
for
review
on
certiorari:
Section
29.
Appeals.
-‐
An
appeal
may
be
taken
from
an
order
made
in
a
proceeding
under
this
Act,
or
from
a
judgment
entered
upon
an
award
through
certiorari
proceedings,
but
such
appeals
shall
be
limited
to
questions
of
law.
The
proceedings
upon
such
appeal,
including
the
judgment
thereon
shall
be
governed
by,
the
Rules
of
Court
in
so
far
as
they
are
applicable.130
The
Arbitration
Law
did
not
specify
which
Court
had
jurisdiction
to
entertain
the
appeal
but
left
the
matter
to
be
governed
by
the
Rules
of
Court.
As
the
appeal
was
limited
to
questions
of
law
and
was
described
as
"certiorari
proceedings,"
the
mode
of
appeal
can
be
interpreted
as
an
Appeal
By
Certiorari
to
this
Court
under
Rule
45.
When
the
ADR
Law
was
enacted
in
2004,
it
specified
that
the
appeal
shall
be
made
to
the
CA
in
accordance
with
the
rules
of
procedure
to
be
promulgated
by
this
Court.
131
The
Special
ADR
Rules
provided
that
the
mode
of
appeal
from
the
RTC's
order
confirming,
vacating,
or
correcting/modifying
a
domestic
arbitral
award
was
through
a
petition
for
review
with
the
CA.
132
However,
the
Special
ADR
Rules
only
took
effect
on
October
30,
2009.
In
the
present
case,
the
R
TC
disallowed
TEAM'
s
notice
of
appeal
from
the
former's
decision
confirming
the
arbitral
award
on
July
3,
2009.
TEAM
moved
for
reconsideration
which
was
likewise
denied
on
November
15,
2009.
In
the
interim,
the
Special
ADR
Rules
became
effective.
Notably,
the
Special
ADR
Rules
apply
retroactively
in
light
of
its
procedural
character.
133
TEAM
filed
its
petition
for
certiorari
soon
after.
Nevertheless,
whether
we
apply,
Section
29
of
the
Arbitration
Law,
Section
46
of
the
ADR
Law,
or
Rule
19.12
of
the
Special
ADR
Rules,
there
is
no
legal
basis
that
an
ordinary
appeal
(via
notice
of
appeal)
is
the
correct
remedy
from
an
order
confirming,
vacating,
or
correcting
an
arbitral
award.
Thus,
there
is
no
merit
in
the
CA's
ruling
that
the
RTC
gravely
abused
its
discretion
when
it
refused
to
give
due
course
to
the
notice
of
appeal.
LEONEN, J.:
FACTS:
In
1993,
BF
Corporation
filed
a
collection
complaint
with
the
Regional
Trial
Court
against
Shangri-‐La
and
the
members
of
its
board
of
directors:
Alfredo
C.
Ramos,
Rufo
B.
Colayco,
Antonio
O.
Olbes,
Gerardo
Lanuza,
Jr.,
Maximo
G.
Licauco
III,
and
Benjamin
C.
Ramos.
Alfredo
C.
Ramos,
Rufo
B.
Colayco,
Maximo
G.
Licauco
III,
and
Benjamin
C.
Ramos
filed
a
motion
to
suspend
the
proceedings
in
view
of
BF
Corporation's
failure
to
submit
its
dispute
to
arbitration,
in
accordance
with
the
arbitration
clause
provided...
in
its
contract
In
the
November
18,
1993
order,
the
Regional
Trial
Court
denied
the
motion
to
suspend
proceedings.
They
alleged
that
they
had
resigned
as
members
of
Shangri-‐La's
board
of
directors
as
of
July
15,
1991.
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
2
ATTY.
BUSTAMANTE
9
ABSR
After
the
Regional
Trial
Court
denied...
the
motion
for
reconsideration
Alfredo
C.
Ramos,
Rufo
B.
Colayco,
Maximo
G.
Licauco
III,
and
Benjamin
Ramos
filed
a
petition
for
certiorari
with
the
Court
of
Appeals.
On
April
28,
1995,
the
Court
of
Appeals
granted
the
petition
for
certiorari
and
ordered
the
submission
of
the
dispute
to
arbitration.
Another
issue
arose
after
BF
Corporation
had
initiated
arbitration
proceedings.
BF
Corporation
and
Shangri-‐La
failed
to
agree
as
to
the
law
that
should
govern
the
arbitration
proceedings.
The
Court
of
Appeals
ruled
that
Shangri-‐La's
directors
were
necessary
parties
in
the
arbitration
proceedings.
They
were]
deemed
not
third-‐parties
to
the
contract
as
they
[were]
sued
for
their
acts
in
representation
of
the
party
to
the
contract
pursuant
to
Art.
31
of
the
Corporation
Code,
and
that
as
directors
of
the
defendant
corporation,
[they],
in
accordance
with
Art.
1217
of
the
Civil
Code,
stand
to
be
benefited
or
injured
by
the
result
of
the
arbitration
proceedings,
hence,
being
necessary
parties,
they
must
be
joined
in
order
to
have
complete
adjudication
of
the
controversy.
The
Court
of
Appeals
further
ruled
that
"excluding
petitioners
in
the
arbitration
proceedings
.
.
.
would
be
contrary
to
the
policy
against
multiplicity
of
suits."
HELD:
It
is
also
warranted
in
alter
ego
cases
"where
a
corporation
is
merely
a
farce
since
it
is
a
mere
alter
ego
or
business
conduit
of
a
person,
or
where
the
corporation
is
so
organized
and
controlled
and
its
affairs
are
so
conducted
as
to
make
it...
merely
an
instrumentality,
agency,
conduit
or
adjunct
of
another
corporation."
When
corporate
veil
is
pierced,
the
corporation
and
persons
who
are
normally
treated
as
distinct
from
the
corporation
are
treated
as
one
person,
such
that
when
the
corporation
is
adjudged
liable,
these
persons,
too,
become
liable
as
if
they
were
the
corporation.
Among
the
persons
who
may
be
treated
as
the
corporation
itself
under
certain
circumstances
are
its
directors
and
officers.
13. KOPPEL,
INC.
(formerly
known
as
KPL
AIRCON,
INC.),
Petitioner,
vs.
MAKATI
ROTARY
CLUB
FOUNDATION,
INC.,
Respondent.
PEREZ, J.:
FACTS:
In
1975,
Fedders
Koppel,
Incorporated
(FKI)
bequeathed
a
parcel
of
land
exclusive
of
improvements
thereon
in
favor
of
Respondent
Makati
Rotary
Club
Foundation,
Inc.
by
way
of
aconditional
donation.
Respondent
accepted
the
donation
with
all
of
its
conditions.
On
26
May
1975,
FKI
and
the
Respondent
executed
a
Deed
of
Donation
evidencing
their
consensus.
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
3
ATTY.
BUSTAMANTE
1
ABSR
One
of
the
conditions
of
the
donation
required
the
Respondent
to
lease
the
subject
land
back
to
FKI
under
terms
specified
in
their
Deed
of
Donation.
With
the
Respondent’s
acceptance
of
the
donation,
a
lease
agreement
between
them
was,
therefore,
effectively
incorporated
in
the
Deed
of
Donation.
Pertinent
terms
of
such
lease
agreement,
as
provided
in
the
Deed
of
Donation,
were
as
follows:
1.
The
period
of
the
lease
is
for
twenty-‐five
(25)
years,
or
until
the
25
th
of
May
2.
The
amount
of
rent
to
be
paid
by
FKI
for
the
first
twenty-‐five
(25)
years
is
P40,126.00
perannum.
2000;
The
Deed
of
Donation
also
stipulated
that
the
lease
over
the
subject
property
is
renewable
for
another
period
of
twenty-‐five
(25)
years
“upon
mutual
agreement”
of
FKI
and
the
Respondent.
In
which
case,
the
amount
of
rent
shall
be
determined
in
accordance
with
item
2(g)
of
the
Deed
of
Donation.
In
October
1976,
FKI
and
the
Respondent
executed
an
Amended
Deed
of
Donation
that
reiterated
the
provisions
of
the
Deed
of
Donation,
including
those
relating
to
the
lease
of
the
subject
land.
Verily,
by
virtue
of
the
lease
agreement
contained
in
the
Deed
of
Donation
and
Amended
Deed
of
Donation,
FKI
was
able
to
continue
in
its
possession
and
use
of
the
subject
land.
Two
(2)
days
before
the
lease
incorporated
in
the
Deed
of
Donation
and
Amended
Deed
of
Donation
was
set
to
expire,
or
on
23
May
2000,
FKI
and
Respondent
executed
another
contract
of
lease
(2000
Lease
Contract)
covering
the
subject
land.
In
this
2000
Lease
Contract,
FKI
and
Respondent
agreed
on
a
new
five-‐year
lease
to
take
effect
on
the
26th
of
May
2000,
with
annual
rents
ranging
from
P4M
for
the
first
year
up
to
P4.9M
for
the
fifth
year.
The
2000
Lease
Contract
also
contained
an
arbitration
clause
enforceable
in
the
event
the
parties
come
to
disagreement
about
the
“interpretation,
application
and
execution”
of
the
lease.
After
the
2000
Lease
Contract
expired,
FKI
and
Respondent
agreed
to
renew
their
lease
for
another
five
(5)
years.
This
new
lease
(2005
Lease
Contract)
required
FKI
32
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
ATTY.
BUSTAMANTE
ABSR
to
pay
a
fixed
annual
rent
of
P4.2M.In
addition
to
paying
the
fixed
rent,
however,
the
2005
Lease
Contract
also
obligated
FKI
to
make
a
yearly
“donation”
of
money
to
the
Respondent.
Such
donations
ranged
from
P3M
for
the
first
year
up
to
P3.9M
for
the
fifth
year.
Notably,
the
2005
Lease
Contract
contained
an
arbitration
clause
similar
to
that
in
the
2000
Lease
Contract,
to
wit:
19.
Governing
Law
–
The
provisions
of
this
[2005
Lease
Contract]
shall
be
governed,
interpreted
and
construed
in
all
aspects
in
accordance
with
the
laws
of
the
Republic
of
the
Philippines.
Any
disagreement
as
to
the
interpretation,
application
or
execution
of
this
[2005
Lease
Contract]
shall
be
submitted
to
a
board
of
three
(3)
arbitrators
constituted
in
accordance
with
the
arbitration
law
of
the
Philippines.
The
decision
of
the
majority
of
the
arbitrators
shall
be
binding
upon
[FKI
and
Respondent].
(Emphasis
supplied)
From
2005
to
2008,
FKI
faithfully
paid
the
rentals
and
“donations”
due
it
per
the
2005
Lease
Contract.
But
in
June
of
2008,
FKI
sold
all
its
rights
and
properties
relative
to
its
business
in
favor
of
herein
Petitioner
Koppel,
Incorporated.
On
29
August
2008,
FKI
and
Petitioner
executed
an
Assignment
and
Assumption
of
Lease
and
Donation—
wherein
FKI,
with
the
conformity
of
the
Respondent,
formally
assigned
all
of
its
interests
and
obligations
under
the
Amended
Deed
of
Donation
and
the
2005
Lease
Contract
in
favor
of
Petitioner.
The
following
year,
Petitioner
discontinued
the
payment
of
the
rent
and
“donation”
under
the
2005Lease
Contract.
Petitioner’s
refusal
to
pay
such
rent
and
“donation”
emanated
from
its
belief
that
the
rental
stipulations
of
the
2005
Lease
Contract,
and
even
of
the
2000
Lease
Contract,
cannot
be
given
effect
because
they
violated
one
of
the
“material
conditions”
of
the
donation
of
the
subject
land,
as
stated
in
the
Deed
of
Donation
and
Amended
Deed
of
Donation.
According
to
Petitioner,
the
Deed
of
Donation
and
Amended
Deed
of
Donation
actually
established
not
only
one
but
two
(2)
lease
agreements
between
FKI
and
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
3
ATTY.
BUSTAMANTE
3
ABSR
Respondent,
i.e.,
one
lease
for
the
first
twenty-‐five
(25)
years
or
from
1975
to
2000,
and
another
lease
for
the
next
twenty-‐five
(25)
years
thereafter
or
from
2000
to
2025.
Both
leases
are
material
conditions
of
the
donation
of
the
subject
land.
Petitioner
points
out
that
while
a
definite
amount
of
rent
for
the
second
twenty-‐five
(25)
year
lease
was
not
fixed
in
the
Deed
of
Donation
and
Amended
Deed
of
Donation,
both
deeds
nevertheless
prescribed
rules
and
limitations
by
which
the
same
may
be
determined.
Such
rules
and
limitations
ought
to
be
observed
in
any
succeeding
lease
agreements
between
Petitioner
and
Respondent
for
they
are,
in
themselves,
material
conditions
of
the
donation
of
the
subject
land.
In
this
connection,
Petitioner
cites
item
2(g)
of
the
Deed
of
Donation
and
Amended
Deed
of
Donation
that
supposedly
limits
the
amount
of
rent
for
the
lease
over
the
second
twenty-‐five
(25)
years
to
only
“three
percent
(3%)
of
the
fair
market
value
of
the
[subject]
land
excluding
the
improvements.
For
Petitioner
then,
the
rental
stipulations
of
both
the
2000
Lease
Contract
and
2005
Lease
Contract
cannot
be
enforced
as
they
are
clearly,
in
view
of
their
exorbitant
exactions,
in
violation
of
the
aforementioned
threshold
in
item
2(g)
of
the
Deed
of
Donation
and
Amended
Deed
of
Donation.
Consequently,
Petitioner
insists
that
the
amount
of
rent
it
has
to
pay
thereon
is
and
must
still
be
governed
by
the
limitations
prescribed
in
the
Deed
of
Donation
and
Amended
Deed
of
Donation.
Respondent
then
sent
Demand
Letters
to
Petitioners
notifying
the
latter
of
its
default,
demanding
for
the
settlement
of
the
rent
and
“donations”
due
for
the
year
2009.
Respondent
intimated
of
cancelling
the
2005
Lease
Contract
should
Petitioner
fail
to
settle
the
said
obligations.
In
its
last
sent
Demand
Letter,
Respondent
demand
Petitioner
to
“immediately
vacate
the
leased
premises”
should
it
fail
to
pay
such
obligations
within
seven
(7)
days
from
its
receipt
of
the
letter.
Petitioner
refused
to
comply
with
the
demands
of
the
Respondent.
Instead,
on
30
September
2009,
Petitioner
filed
with
the
RTC
of
Parañaque
City
a
Complaint
for
the
Rescission
or
Cancellation
of
the
Deed
of
Donation
and
Amended
Deed
of
Donation
against
the
Respondent.
Hence,
the
present
Petition
for
Review
on
Certiorari
under
Rule
45.
ISSUE:
WHETHER
OR
NOT
THE
PRESENT
DISPUTE
IS
ARBITRABLE
UNDER
THE
ARBITRATION
CLAUSE
OF
THE
2005
LEASE
AGREEMENT
CONTRACT?
ARGUMENTS:
At
different
points
in
the
proceedings
of
this
case,
the
following
arguments
were
offered
against
the
application
of
the
arbitration
clause
of
the
2005
Lease
Contract:
1.
The
disagreement
between
the
Petitioner
and
Respondent
is
non-‐arbitrable
as
it
will
inevitably
touch
upon
the
issue
of
the
validity
of
the
2005
Lease
Contract.
It
was
submitted
that
one
of
the
reasons
offered
by
the
Petitioner
in
justifying
its
failure
to
pay
under
the
2005
Lease
Contract
was
the
nullity
of
such
contract
for
being
contrary
to
law
and
public
policy.
The
Supreme
Court,
in
Gonzales
v.
Climax
Mining,
Ltd.
[2005],
held
that
“the
validity
of
contract
cannot
be
subject
of
arbitration
proceedings”
as
such
questions
are
“legal
in
nature
and
require
the
application
and
interpretation
of
laws
and
jurisprudence
which
is
necessarily
a
judicial
function.”
2.
The
Petitioner
cannot
validly
invoke
the
arbitration
clause
of
the
2005
Lease
Contract
while,
at
the
same
time,
impugn
such
contract’s
validity.
3.
Even
assuming
that
it
can
invoke
the
arbitration
clause
whilst
denying
the
validity
of
the2005
Lease
Contract,
Petitioner
still
did
not
file
a
formal
application
before
the
MeTC
so
as
to
render
such
arbitration
clause
operational.
Section
24
of
Republic
Act
No.
9285
requires
the
party
seeking
arbitration
to
first
file
a
“request”
or
an
application
therefor
with
the
courtnot
later
than
the
preliminary
conference.
4.
Petitioner
and
Respondent
already
underwent
JDR
proceedings
before
the
RTC.
Hence,
a
further
referral
of
the
dispute
to
arbitration
would
only
be
circuitous.
Moreover,
an
ejectment
case,
in
view
of
its
summary
nature,
already
fulfills
the
prime
purpose
of
arbitration,
i.e.,
to
provide
parties
in
conflict
with
an
expedient
method
for
the
resolution
of
their
dispute.
Arbitration
then
would
no
longer
be
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
3
ATTY.
BUSTAMANTE
5
ABSR
necessary
in
this
case.
HELD:YES
None
of
the
above-‐mentioned
arguments
have
any
merit.
The
MeTC,
RTC
and
CA
all
erred
in
overlooking
the
significance
of
the
arbitration
clause
incorporated
in
the
2005
Lease
Contract.
As
the
SC
sees
it,
that
is
a
fatal
mistake.
Hence,
the
Petition
is
GRANTED
and
thus
referring
the
Petitioner
and
the
Respondent
to
arbitration
pursuant
to
the
arbitration
clause
of
the
2005
Lease
Contract,
repeatedly
included
in
the
2000
Lease
Contract
and
in
the
1976
Amended
Deed
of
Donation.
RATIO
DECIDENDI:
The
arbitration
clause
of
the
2005
Lease
Contract
stipulates
that
“any
disagreement”
as
to
the
“interpretation,
application
or
execution”
of
the
2005
Lease
Contract
ought
to
be
submitted
to
arbitration.
To
the
mind
of
the
Court,
such
stipulation
is
clear
and
is
comprehensive
enough
so
as
to
include
virtually
any
kind
of
conflict
or
dispute
that
may
arise
from
the
2005
Lease
Contractincluding
the
one
that
presently
besets
Petitioner
and
Respondent.
First.
The
disagreement
between
the
Petitioner
and
Respondent
falls
within
the
all-‐
encompassing
terms
of
the
arbitration
clause
of
the
2005
Lease
Contract.
While
it
may
be
conceded
that
in
the
arbitration
of
such
disagreement,
the
validity
of
the
2005
Lease
Contract,
or
at
least,
of
such
contract’s
rental
stipulations
would
have
to
be
determined,
the
same
would
not
render
such
disagreement
non-‐arbitrable.
The
quotation
from
Gonzales
case
that
was
used
to
justify
the
contrary
position
was
taken
out
of
context.
The
pivotal
issue
that
confronted
the
Court
in
the
Gonzales
case
was
whether
the
complaint
for
arbitration
raises
arbitrable
issues
that
the
Panel
of
Arbitrators
of
the
Mines
and
Geosciences
Bureau
(PA-‐MGB)
can
take
cognizance
of.
Gonzales
decided
the
issue
in
the
negative.
In
holding
that
the
PA-‐MGB
was
devoid
of
any
jurisdiction
to
take
cognizance
of
the
complaint
for
arbitration,
this
Court
pointed
out
to
the
provisions
of
R.A.
No.
7942,
or
the
Mining
Act
of
1995,
which
granted
the
PA-‐MGB
with
exclusive
original
jurisdiction
only
over
mining
disputes,
i.e.,
disputes
involving
“rights
to
mining
areas,”
“mineral
agreements
or
permits,”
and
“surface
owners,
occupants,
claimholders
or
concessionaires”
requiring
the
technical
knowledge
and
experience
of
mining
authorities
in
order
to
be
resolved.
SC
in
Gonzales
did
not
simply
base
its
rejection
of
the
complaint
for
arbitration
on
the
ground
that
the
issue
raised
therein,
i.e.,
the
validity
of
contracts,
is
per
se
non-‐
arbitrable.
The
real
consideration
behind
the
ruling
was
the
limitation
that
was
placed
by
R.A.
No.
7942
upon
the
jurisdiction
of
the
PA-‐
MGB
as
an
arbitral
body.
Gonzales
rejected
the
complaint
for
arbitration
because
the
issue
raised
therein
is
not
a
mining
dispute
per
R.A.
No.
7942
and
it
is
for
this
reason,
and
only
for
this
reason,
that
such
issue
is
rendered
nonarbitrable
before
the
PA-‐MGB.
As
stated
beforehand,
R.A.
No.
7942
clearly
limited
the
jurisdiction
of
the
PAMGB
only
to
mining
disputes.
Much
more
instructive
for
our
purposes,
on
the
other
hand,
is
the
recent
case
of
Cargill
Philippines,
Inc.
v.
San
Fernando
Regal
Trading,
Inc
[2011].
In
Cargill,
SC
answered
the
question
of
whether
issues
involving
the
rescission
of
a
contract
are
arbitrable.
The
respondent
in
Cargill
argued
against
arbitrability,
also
citing
therein
Gonzales.
After
dissecting
Gonzales,
SC
ruled
in
favor
of
arbitrability.
Thus,
SC
held:
Respondent
contends
that
assuming
that
the
existence
of
the
contract
and
the
arbitration
clause
is
conceded,
the
CA’s
decision
declining
referral
of
the
parties’
dispute
to
arbitration
is
still
correct.
It
claims
that
its
complaint
in
the
RTC
presents
the
issue
of
whether
under
the
facts
alleged,
it
is
entitled
to
rescind
the
contract
with
damages;
and
that
issue
constitutes
a
judicial
question
or
one
that
requires
the
exercise
of
judicial
function
and
cannot
be
the
subject
of
an
arbitration
proceeding.
Respondent
cites
our
ruling
in
Gonzales,
wherein
we
held
that
a
panel
of
arbitrator
is
bereft
of
jurisdiction
over
the
complaint
for
declaration
of
nullity/or
termination
of
the
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
3
ATTY.
BUSTAMANTE
7
ABSR
subject
contracts
on
the
grounds
of
fraud
and
oppression
attendant
to
the
execution
of
the
addendum
contract
and
the
other
contracts
emanating
from
it,
and
that
the
complaint
should
have
been
filed
with
the
regular
courts
as
it
involved
issues
which
are
judicial
in
nature.
Such
argument
is
misplaced
and
respondent
cannot
rely
on
the
Gonzales
case
to
support
its
argument.
(Emphasis
ours)
Second.
Petitioner
may
still
invoke
the
arbitration
clause
of
the
2005
Lease
Contract
notwithstanding
the
fact
that
it
assails
the
validity
of
such
contract.
This
is
due
to
the
doctrine
of
separability.
Under
the
doctrine
of
separability,
an
arbitration
agreement
is
considered
as
independent
of
the
main
contract.
Being
a
separate
contract
in
itself,
the
arbitration
agreement
may
thus
be
invoked
regardless
of
the
possible
nullity
or
invalidity
of
the
main
contract.
Once
again
instructive
is
Cargill,
wherein
SC
held
that,
as
a
further
consequence
of
the
doctrine
of
separability,
even
the
very
party
who
repudiates
the
main
contract
may
invoke
its
arbitration
clause.
Third.
The
operation
of
the
arbitration
clause
in
this
case
is
not
at
all
defeated
by
the
failure
of
the
Petitioner
to
file
a
formal
“request”
or
application
therefor
with
the
MeTC.
SC
finds
that
the
filing
of
a
“request”
pursuant
to
Section
24
of
R.A.
No.
9285
is
not
the
sole
means
by
which
an
arbitration
clause
may
be
validly
invoked
in
a
pending
suit.
The
“request”
referred
to
in
the
above
provision
is,
in
turn,
implemented
by
Rules
4.1
to
4.3
of
A.M.
No.
07-‐1108-‐SC
or
the
Special
Rules
of
Court
on
Alternative
Dispute
Resolution
(Special
ADR
Rules):
RULE
4:
REFERRAL
TO
ADR
Rule
4.1.
Who
makes
the
request.
–
A
party
to
a
pending
action
filed
in
violation
of
38
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
ATTY.
BUSTAMANTE
ABSR
the
arbitration
agreement,
whether
contained
in
an
arbitration
clause
or
in
a
submission
agreement,
may
request
the
court
to
refer
the
parties
to
arbitration
in
accordance
with
such
agreement.
Rule
4.2.
When
to
make
request.
–
(A)
Where
the
arbitration
agreement
exists
before
the
action
is
filed.
–
The
request
for
referral
shall
be
made
not
later
than
the
pre-‐trial
conference.
After
the
pre-‐trial
conference,
the
court
will
only
act
upon
the
request
for
referral
if
it
is
made
with
the
agreement
of
all
parties
to
the
case.
(B)
Submission
agreement.
–
If
there
is
no
existing
arbitration
agreement
at
the
time
the
case
is
filed
but
the
parties
subsequently
enter
into
an
arbitration
agreement,
they
may
request
the
court
to
refer
their
dispute
to
arbitration
at
any
time
during
the
proceedings.
Rule
4.3.
Contents
of
request.
–
The
request
for
referral
shall
be
in
the
form
of
a
motion,
which
shall
state
that
the
dispute
is
covered
by
an
arbitration
agreement.
Apart
from
other
submissions,
the
movant
shall
attach
to
his
motion
an
authentic
copy
of
the
arbitration
agreement.
The
request
shall
contain
a
notice
of
hearing
addressed
to
all
parties
specifying
the
date
and
time
when
it
would
be
heard.
The
party
making
the
request
shall
serve
it
upon
the
respondent
to
give
him
the
opportunity
to
file
a
comment
or
opposition
as
provided
in
the
immediately
succeeding
Rule
before
the
hearing.
[Emphasis
ours;
italics
original]
Attention
must
be
paid,
however,
to
the
salient
wordings
of
Rule
4.1.
It
reads:
“[a]
party
to
a
pending
action
filed
in
violation
of
the
arbitration
agreement
x
x
x
may
request
the
court
to
refer
the
parties
to
arbitration
in
accordance
with
such
agreement.”
In
using
the
word
“may”
to
qualify
the
act
of
filing
a
“request”
under
Section
24
of
R.A.
No.
9285,
the
Special
ADR
Rules
clearly
did
not
intend
to
limit
the
invocation
of
an
arbitration
agreement
in
a
pending
suit
solely
via
such
“request.”
After
all,
non-‐compliance
with
an
arbitration
agreement
is
a
valid
defense
to
any
offending
suit
and,
as
such,
may
even
be
raised
in
an
answer
as
provided
in
our
ordinary
rules
of
procedure.
In
this
case,
it
is
conceded
that
Petitioner
was
not
able
to
file
a
separate
“request”
of
arbitration
before
the
MeTC.
However,
it
is
equally
conceded
that
the
Petitioner,
as
early
as
in
its
Answer
with
Counterclaim,
had
already
apprised
the
MeTC
of
the
existence
of
the
arbitration
clause
in
the
2005
Lease
Contract
and,
more
significantly,
of
its
desire
to
have
the
same
enforced
in
this
case.
This
act
of
Petitioner
is
enough
valid
invocation
of
his
right
to
arbitrate.
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
3
ATTY.
BUSTAMANTE
9
ABSR
Fourth.
The
fact
that
the
Petitioner
and
Respondent
already
underwent
through
JDR
proceedings
before
the
RTC,
will
not
make
the
subsequent
conduct
of
arbitration
between
the
parties
unnecessary
or
circuitous.
The
JDR
system
is
substantially
different
from
arbitration
proceedings.
The
JDR
framework
is
based
on
the
processes
of
mediation,
conciliation
or
early
neutral
evaluation
which
entails
the
submission
of
a
dispute
before
a
“JDR
judge”
who
shall
merely
“facilitate
settlement”
between
the
parties
in
conflict
or
make
a
“non-‐binding
evaluation
or
assessment
of
the
chances
of
each
party’s
case.”
Thus
in
JDR,
the
JDR
judge
lacks
the
authority
to
render
a
resolution
of
the
dispute
that
is
binding
upon
the
parties
in
conflict.
In
arbitration,
on
the
other
hand,
the
dispute
is
submitted
to
an
arbitrator/s—a
neutral
third
person
or
a
group
of
thereof—who
shall
have
the
authority
to
render
a
resolution
binding
upon
the
parties.
Clearly,
the
mere
submission
of
a
dispute
to
JDR
proceedings
would
not
necessarily
render
the
subsequent
conduct
of
arbitration
a
mere
surplusage.
The
failure
of
the
parties
in
conflict
to
reach
an
amicable
settlement
before
the
JDR
may,
in
fact,
be
supplemented
by
their
resort
to
arbitration
where
a
binding
resolution
to
the
dispute
could
finally
be
achieved.
This
situation
precisely
finds
application
to
the
case
at
bench.
Neither
would
the
summary
nature
of
ejectment
cases
be
a
valid
reason
to
disregard
the
enforcement
of
the
arbitration
clause
of
the
2005
Lease
Contract.
Notwithstanding
the
summary
nature
of
ejectment
cases,
arbitration
still
remains
relevant
as
it
aims
not
only
to
afford
the
parties
an
expeditious
method
of
resolving
their
dispute.
A
pivotal
feature
of
arbitration
as
an
alternative
mode
of
dispute
resolution
is
that
it
is,
first
and
foremost,
a
product
of
party
autonomy
or
the
freedom
of
the
parties
to
“make
their
own
arrangements
to
resolve
their
own
disputes.”
Arbitration
agreements
manifest
not
only
the
desire
of
the
parties
in
conflict
for
an
expeditious
resolution
of
their
dispute.
They
also
represent,
if
not
more
so,
the
parties’
mutual
aspiration
to
achieve
such
resolution
outside
of
judicial
auspices,
in
a
more
informal
and
less
antagonistic
environment
under
the
terms
of
their
choosing.
Needless
to
state,
this
critical
feature
can
never
be
satisfied
in
an
ejectment
case
no
matter
how
summary
it
may
be.
The
Law,
therefore,
should
have
governed
the
fate
of
the
parties
and
this
suit:
R.A.
No.
876
Section
7.
Stay
of
civil
action.
–
If
any
suit
or
proceeding
be
brought
upon
an
issue
arising
out
of
an
agreement
providing
for
the
arbitration
thereof,
the
court
in
which
such
suit
or
proceeding
is
pending,
upon
being
satisfied
that
the
issue
involved
in
such
suit
or
proceeding
is
referable
to
arbitration,
shall
stay
the
action
or
proceeding
until
an
arbitration
has
been
had
in
accordance
with
the
terms
of
the
agreement:
Provided,
That
the
applicant
for
the
stay
is
not
in
default
in
proceeding
with
such
arbitration.
[Emphasis
supplied]
R.A.
No.
9285
Section
24.
Referral
to
Arbitration.
–
A
court
before
which
an
action
is
brought
in
a
matter
which
is
the
subject
matter
of
an
arbitration
agreement
shall,
if
at
least
one
party
so
requests
not
later
that
the
pre-‐trial
conference,
or
upon
the
request
of
both
parties
thereafter,
refer
the
parties
to
arbitration
unless
it
finds
that
the
arbitration
agreement
is
null
and
void,
inoperative
or
incapable
of
being
performed.
[Emphasis
supplied]
It
is
clear
that
under
the
law,
the
instant
unlawful
detainer
action
should
have
been
stayed;
the
Petitioner
and
the
Respondent
should
have
been
referred
to
arbitration
pursuant
to
the
arbitration
clause
of
the
2005
Lease
Contract.
The
MeTC,
however,
did
not
do
so
in
violation
of
the
law—which
violation
was,
in
turn,
affirmed
by
the
RTC
and
Court
of
Appeals
on
appeal.
The
violation
by
the
MeTC
of
the
clear
directives
under
R.A.
Nos.
876
and
9285
renders
invalid
all
proceedings
it
undertook
in
the
ejectment
case
after
the
filing
by
Petitioner
of
its
Answer
with
Counterclaim—the
point
when
the
Petitioner
and
the
Respondent
should
have
been
referred
to
arbitration.
This
case
must,
therefore,
be
remanded
to
the
MeTC
and
be
suspended
at
said
point.
Inevitably,
the
decisions
of
the
MeTC,
RTC
and
the
Court
of
Appeals
must
all
be
vacated
and
set
aside.
The
Petitioner
and
the
Respondent
must
then
be
referred
to
arbitration
pursuant
to
the
arbitration
clause
of
the
2005
Lease
Contract.
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
4
ATTY.
BUSTAMANTE
1
ABSR
G.R.
No.
143581
January
7,
2008
FACTS:
ISSUE:
WHETHER
OR
NOT
THE
ARBITRATION
CLAUSE
IN
THE
CONTRACT
OF
THE
PARTIES
SHOULD
GOVERN.
42
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
ATTY.
BUSTAMANTE
ABSR
Held:
YES.
Established
in
this
jurisdiction
is
the
rule
that
the
law
of
the
place
where
the
contract
is
made
governs.
Lex
loci
contractus.
The
contract
in
this
case
was
perfected
here
in
the
Philippines.
Therefore,
our
laws
ought
to
govern.
Nonetheless,
Art.
2044
of
the
Civil
Code
sanctions
the
validity
of
mutually
agreed
arbitral
clause
or
the
finality
and
binding
effect
of
an
arbitral
award.
Art.
2044
provides,
Any
stipulation
that
the
arbitrators
award
or
decision
shall
be
final,
is
valid,
without
prejudice
to
Articles
2038,
2039
and
2040.
The
arbitration
clause
was
mutually
and
voluntarily
agreed
upon
by
the
parties.
It
has
not
been
shown
to
be
contrary
to
any
law,
or
against
morals,
good
customs,
public
order,
or
public
policy.
There
has
been
no
showing
that
the
parties
have
not
dealt
with
each
other
on
equal
footing.
We
find
no
reason
why
the
arbitration
clause
should
not
be
respected
and
complied
with
by
both
parties.
In
Gonzales
v.
Climax
Mining
Ltd.,
we
held
that
submission
to
arbitration
is
a
contract
and
that
a
clause
in
a
contract
providing
that
all
matters
in
dispute
between
the
parties
shall
be
referred
to
arbitration
is
a
contract.
Again
in
Del
Monte
Corporation-‐USA
v.
Court
of
Appeals,
we
likewise
ruled
that
[t]he
provision
to
submit
to
arbitration
any
dispute
arising
therefrom
and
the
relationship
of
the
parties
is
part
of
that
contract
and
is
itself
a
contract.
Having
said
that
the
instant
arbitration
clause
is
not
against
public
policy,
we
come
to
the
question
on
what
governs
an
arbitration
clause
specifying
that
in
case
of
any
dispute
arising
from
the
contract,
an
arbitral
panel
will
be
constituted
in
a
foreign
country
and
the
arbitration
rules
of
the
foreign
country
would
govern
and
its
award
shall
be
final
and
binding.
Thus,
it
can
be
gleaned
that
the
concept
of
a
final
and
binding
arbitral
award
is
similar
to
judgments
or
awards
given
by
some
of
our
quasi-‐judicial
bodies,
like
the
National
Labor
Relations
Commission
and
Mines
Adjudication
Board,
whose
final
judgments
are
stipulated
to
be
final
and
binding,
but
not
immediately
executory
in
the
sense
that
they
may
still
be
judicially
reviewed,
upon
the
instance
of
any
party.
Therefore,
the
final
foreign
arbitral
awards
are
similarly
situated
in
that
they
need
first
to
be
confirmed
by
the
RTC.
TINGA, J.:
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
4
ATTY.
BUSTAMANTE
3
ABSR
FACTS:
ISSUE:
WHETHER
OR
NOT
IT
WAS
PROPER
FOR
THE
RTC,
IN
THE
PROCEEDING
TO
COMPEL
ARBITRATION
UNDER
R.A.
NO.
876,
TO
ORDER
THE
PARTIES
TO
ARBITRATE
EVEN
THOUGH
THE
DEFENDANT
THEREIN
HAS
RAISED
THE
TWIN
ISSUES
OF
VALIDITY
AND
NULLITY
OF
THE
ADDENDUM
CONTRACT
AND,
CONSEQUENTLY,
OF
THE
ARBITRATION
CLAUSE
THEREIN
AS
WELL
HELD: YES.
The
doctrine
of
separability,
or
severability
as
other
writers
call
it,
enunciates
that
an
arbitration
agreement
is
independent
of
the
main
contract.
The
arbitration
agreement
is
to
be
treated
as
a
separate
agreement
and
the
arbitration
agreement
does
not
automatically
terminate
when
the
contract
of
which
it
is
part
comes
to
an
end.
The
separability
of
the
arbitration
clause
is
confirmed
in
Art.
16(1)
of
the
UNCITRAL
Model
Law
and
Art.
21(2)
of
the
UNCITRAL
Arbitration
Rules.
The
proceeding
in
a
petition
for
arbitration
under
R.A.
No.
876
is
limited
only
to
the
resolution
of
the
question
of
whether
the
arbitration
agreement
exists.
Second,
the
separability
of
the
arbitration
clause
from
the
Addendum
Contract
means
that
validity
or
invalidity
of
the
Addendum
Contract
will
not
affect
the
enforceability
of
the
agreement
to
arbitrate.
Thus,
Gonzales
petition
for
certiorari
should
be
dismissed.
This
brings
us
back
to
G.R.
No.
161957.
The
adjudication
of
the
petition
in
G.R.
No.
167994
effectively
modifies
part
of
the
Decision
dated
28
February
2005
in
G.R.
No.
161957.
Hence,
we
now
hold
that
the
validity
of
the
contract
containing
the
agreement
to
submit
to
arbitration
does
not
affect
the
applicability
of
the
arbitration
clause
itself.
A
contrary
ruling
would
suggest
that
a
parties
mere
repudiation
of
the
main
contract
is
sufficient
to
avoid
arbitration.
That
is
exactly
the
situation
that
the
separability
doctrine,
as
well
as
jurisprudence
applying
it,
seeks
to
avoid.
We
add
that
when
it
was
declared
in
G.R.
No.
161957
that
the
case
should
not
be
brought
for
arbitration,
it
should
be
clarified
that
the
case
referred
to
is
the
case
actually
filed
by
Gonzales
before
the
DENR
Panel
of
Arbitrators,
which
was
for
the
nullification
of
the
main
contract
on
the
ground
of
fraud,
as
it
had
already
been
determined
that
the
case
should
have
been
brought
before
the
regular
courts
involving
as
it
did
judicial
issues.
BELLOSILLO, J.:
FACTS:
This
Agreement
shall
be
governed
by
the
laws
of
the
State
of
California
and/or,
if
applicable,
the
United
States
of
America.
All
disputes
arising
out
of
or
relating
to
this
Agreement
or
the
parties'
relationship,
including
the
termination
thereof,
shall
be
resolved
by...
arbitration
in
the
City
of
San
Francisco,
State
of
California,
under
the
Rules
of
the
American
Arbitration
Association.
The
arbitration
panel
shall
consist
of
three
members,
one
of
whom
shall
be
selected
by
DMC-‐USA,
one
of
whom
shall
be
selected
by
MMI,
and
third
of
whom
shall...
be
selected
by
the
other
two
members
and
shall
46
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
ATTY.
BUSTAMANTE
ABSR
have
relevant
experience
in
the
industry
x
x
x
x...
after
its
appointment,
private
respondent
MMI
appointed
Sabrosa
Foods,
Inc.
(SFI),
with
the
approval
of
petitioner
DMC-‐USA,
as
MMI's
marketing
arm
to
concentrate
on
its
marketing
and
selling
function
as
well
as
to
manage
its
critical
relationship
with
the
trade...
private
respondents
MMI,
SFI
and
MMI's
Managing
Director
Liong
Liong
C.
Sy
(LILY
SY)
filed
a
Complaint[5]
against
petitioners
DMC-‐USA,
Paul
E.
Derby,
Jr.,[6]
Daniel
Collins[7]
and
Luis
Hidalgo,[8]
and
Dewey
Ltd.[9]
before
the
Regional
Trial
Court
of
Malabon,
Metro
Manila.
On
the
alleged
violations
by
petitioners
of
Arts.
20,[10]
21[11]
and
23[12]
of
the
Civil
Code.
According
to
private
respondents,
DMC-‐USA
products
continued
to
be
brought
into
the
country
by
parallel
importers
despite
the
appointment
of
private
respondent
MMI
as
the
sole
and
exclusive
distributor
of
Del
Monte
products
They
alleged
that
the
products
brought
into
the
country
by
these
importers
were
aged,
damaged,
fake
or
counterfeit
Private
respondents
claimed
that
they...
had
exhausted
all
possible
avenues
for
an
amicable
resolution
and
settlement
of
their
grievances...
petitioners
filed
a
Motion
to
Suspend
Proceedings[13]
invoking
the
arbitration
clause
in
their
Agreement
with
private
respondents.
The Motion to Suspend Proceedings was denied by the trial court
On appeal, the Court of Appeals affirmed the decision of the trial court.
Motion
for
Reconsideration
of
the
affirmation
was
denied.
Hence,
this
Petition
for
Review.
Petitioners
contend
that
the
subject
matter
of
private
respondents'
causes
of
action
arises
out
of
or
relates
to
the
Agreement
between
petitioners
and
private
respondents.
Thus,
considering
that
the
arbitration
clause
of
the
Agreement
provides
that
all
disputes
arising
out
of
or...
relating
to
the
Agreement
or
the
parties'
relationship,
including
the
termination
thereof,
shall
be
resolved
by
arbitration,
they
insist
on
the
suspension
of
the
proceedings
in
Civil
Case
No.
2637-‐MN
as
mandated
by
Sec.
7
of
RA
876
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
4
ATTY.
BUSTAMANTE
7
ABSR
Private
respondents
claim,
on
the
other
hand,
that
their
causes
of
action
are
rooted
in
Arts.
20,
21
and
23
of
the
Civil
Code,[19]
the
determination
of
which
demands
a
full
blown
trial
Private
respondents
further
contend
that
the
arbitration
clause
centers
more
on
venue
rather
than
on
arbitration.
They
insist
that
the
filing
of
the
petition
to
compel
arbitration
in
the
United
States
made
the
petition
filed
before...
this
Court
an
alternative
remedy
and,
in
a
way,
an
abandonment
of
the
cause
they
are
fighting
for
here
in
the
Philippines,
thus
warranting
the
dismissal
of
the
present
petition
before
this
Court.
HELD: YES.
A
careful
examination
of
the
instant
case
shows
that
the
arbitration
clause
in
the
Distributorship
Agreement
between
petitioner
DMC-‐USA
and
private
respondent
MMI
is
valid
and
the
dispute
between
the
parties
is
arbitrable.
However,
this
Court
must
deny
the
petition.
Clearly,
only
parties
to
the
Agreement,
i.e.,
petitioners
DMC-‐USA
and
its
Managing
Director
for
Export
Sales
Paul
E.
Derby,
Jr.,
and
private...
respondents
MMI
and
its
Managing
Director
LILY
SY
are
bound
by
the
Agreement
and
its
arbitration
clause
as
they
are
the
only
signatories
thereto.
Petitioners
Daniel
Collins
and
Luis
Hidalgo,
and
private
respondent
SFI,
not
parties
to
the
Agreement
and
cannot
even
be
considered...
assigns
or
heirs
of
the
parties,
are
not
bound
by
the
Agreement
and
the
arbitration
clause
therein.
Consequently,
referral
to
arbitration
in
the
State
of
California
pursuant
to
the
arbitration
clause
and
the
suspension
of
the
proceedings
in
Civil
Case
No.
2637-‐MN
pending
the...
return
of
the
arbitral
award
could
be
called
for[25]
but
only
as
to
petitioners
DMC-‐
USA
and
Paul
E.
Derby,
Jr.,
and
private
respondents
MMI
and
LILY
SY,
and
not
as
to
the
other
parties
in
this
case...
only
parties
to
the
Agreement,
their
assigns
or
heirs
have
the
right
to
arbitrate
or
could
be
compelled
to...
arbitrate.
The
Court
went
further
by
declaring
that
in
recognizing
the
right
of
the
contracting
parties
to
arbitrate
or
to
compel
arbitration,
the
splitting
of
the
proceedings
to
arbitration
as
48
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
ATTY.
BUSTAMANTE
ABSR
to
some
of
the
parties
on
one
hand
and
trial
for
the
others
on
the
other
hand,
or
the...
suspension
of
trial
pending
arbitration
between
some
of
the
parties,
should
not
be
allowed
as
it
would,
in
effect,
result
in
multiplicity
of
suits,
duplicitous
procedure
and
unnecessary
delay
The
object
of
arbitration
is
to
allow
the
expeditious
determination
of
a
dispute.[31]
Clearly,
the
issue
before
us
could
not
be
speedily
and
efficiently
resolved
in
its
entirety
if
we
allow
simultaneous
arbitration
proceedings
and
trial,
or
suspension
of...
trial
pending
arbitration.
Accordingly,
the
interest
of
justice
would
only
be
served
if
the
trial
court
hears
and
adjudicates
the
case
in
a
single
and
complete
proceeding
Principles:
YNARES-‐SANTIAGO, J.:
FACTS:
On
April
29,
1991,
petitioner
Sea-‐Land
Services,
Inc.
and
private
respondent
A.P.
Moller/Maersk
Line
(hereinafter
referred
to
as
"AMML"),
both
carriers
of
cargo
in
containerships
as
well
as
common
carriers,
entered
into
a
contract
entitled,
"Co-‐
operation
in
the
Pacific"2
(hereinafter
referred
to
as
the
"Agreement"),
a
vessel
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
4
ATTY.
BUSTAMANTE
9
ABSR
sharing
agreement
whereby
they
mutually
agreed
to
purchase,
share
and
exchange
needed
space
for
cargo
in
their
respective
containerships.
Under
the
Agreement,
they
could
be,
depending
on
the
occasion,
either
a
principal
carrier
(with
a
negotiable
bill
of
lading
or
other
contract
of
carriage
with
respect
to
cargo)
or
a
containership
operator
(owner,
operator
or
charterer
of
containership
on
which
the
cargo
is
carried).
During
the
lifetime
of
the
said
Agreement,
or
on
18
May
1991,
Florex
International,
Inc.
(hereinafter
referred
to
as
"Florex")
delivered
to
private
respondent
AMML
cargo
of
various
foodstuffs,
with
Oakland,
California
as
port
of
discharge
and
San
Francisco
as
place
of
delivery.
The
corresponding
Bill
of
Lading
No.
MAEU
MNL110263
was
issued
to
Florex
by
respondent
AMML.
Pursuant
to
the
Agreement,
respondent
AMML
loaded
the
subject
cargo
on
MS
Sealand
Pacer,
a
vessel
owned
by
petitioner.
Under
this
arrangement,
therefore,
respondent
AMML
was
the
principal
carrier
while
petitioner
was
the
containership
operator.
The
consignee
refused
to
pay
for
the
cargo,
alleging
that
delivery
thereof
was
delayed.
Thus,
on
June
26,
1992,
Florex
filed
a
complaint
against
respondent
Maersk-‐Tabacalera
Shipping
Agency
(Filipinas),
Inc.
for
reimbursement
of
the
value
of
the
cargo
and
other
charges.3
According
to
Florex,
the
cargo
was
received
by
the
consignee
only
on
June
28,
1991,
since
it
was
discharged
in
Long
Beach,
California,
instead
of
in
Oakland,
California
on
June
5,
1991
as
stipulated.
ISSUE:
WHETHER
OR
NOT
THE
COURT
OF
APPEALS
DISREGARDED
AN
AGREEMENT
TO
ARBITRATE
IN
VIOLATION
OF
STATUTE
AND
SUPREME
COURT
DECISIONS
HOLDING
THAT
ARBITRATION
IS
A
CONDITION
PRECEDENT
TO
SUIT
WHERE
SUCH
AN
AGREEMENT
TO
ARBITRATE
EXISTS.
HELD: YES
To
begin
with,
allowing
respondent
AMML's
Third
Party
Claim
against
petitioner
to
proceed
would
be
in
violation
of
Clause
16.2
of
the
Agreement.
As
summarized,
the
clause
provides
that
whatever
dispute
there
may
be
between
the
Principal
Carrier
and
the
Containership
Operator
arising
from
contracts
of
carriage
shall
be
governed
by
the
provisions
of
the
bills
of
lading
deemed
issued
to
the
Principal
Carrier
by
the
Containership
Operator.
On
the
other
hand,
to
sustain
the
Third
Party
Complaint
would
be
to
allow
private
respondent
to
hold
petitioner
liable
under
the
provisions
of
the
bill
of
lading
issued
by
the
Principal
Carrier
to
Florex,
under
which
the
latter
is
suing
in
its
Complaint,
not
under
the
bill
of
lading
petitioner,
as
containership
operator,
issued
to
respondent
AMML,
as
Principal
Carrier,
contrary
to
what
is
contemplated
in
Clause
16.2.
The
Court
of
Appeals
ruled
that
the
terms
of
the
Agreement
"explicitly
required
that
the
principal
carrier's
claim
against
the
containership
operator
first
be
finally
50
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
ATTY.
BUSTAMANTE
ABSR
determined
by,
among
others,
a
court
judgment,
before
the
right
to
arbitration
accrues."
However,
the
Court
of
Appeals
failed
to
consider
that,
precisely,
arbitration
is
the
mode
by
which
the
liability
of
the
Containership
Operator
may
be
finally
determined.
This
is
clear
from
the
mandate
of
Clause
16.3
that
"(T)he
Principal
Carrier
shall
have
the
right
to
seek
damages
and/or
an
indemnity
from
the
Containership
Operator
by
arbitration"
and
that
it
"shall
be
entitled
to
commence
such
arbitration
at
any
time
until
one
year
after
its
liability
has
been
finally
determined
by
agreement,
arbitration
award
or
judgment".
For
respondent
Court
of
Appeals
to
say
that
the
terms
of
the
contract
do
not
require
arbitration
as
a
condition
precedent
to
judicial
action
is
erroneous.
In
the
light
of
the
Agreement
clauses
aforequoted,
it
is
clear
that
arbitration
is
the
mode
provided
by
which
respondent
AMML
as
Principal
Carrier
can
seek
damages
and/or
indemnity
from
petitioner,
as
Containership
Operator.
Stated
differently,
respondent
AMML
is
barred
from
taking
judicial
action
against
petitioner
by
the
clear
terms
of
their
Agreement.
As
the
Principal
Carrier
with
which
Florex
directly
dealt
with,
respondent
AMML
can
and
should
be
held
accountable
by
Florex
in
the
event
that
it
has
a
valid
claim
against
the
former.
Pursuant
to
Clause
16.3
of
the
Agreement,
respondent
AMML,
when
faced
with
such
a
suit
"shall
use
all
reasonable
endeavours
to
defend"
itself
or
"settle
such
suits
for
as
low
a
figure
as
reasonably
possible".
In
turn,
respondent
AMML
can
seek
damages
and/or
indemnity
from
petitioner
as
Containership
Operator
for
whatever
final
judgment
may
be
adjudged
against
it
under
the
Complaint
of
Florex.
The
crucial
point
is
that
collection
of
said
damages
and/or
indemnity
from
petitioner
should
be
by
arbitration.
All
told,
when
the
text
of
a
contract
is
explicit
and
leaves
no
doubt
as
to
its
intention,
the
court
may
not
read
into
it
any
other
intention
that
would
contradict
its
plain
import.
11
Arbitration
being
the
mode
of
settlement
between
the
parties
expressly
provided
for
by
their
Agreement,
the
Third
Party
Complaint
should
have
been
dismissed.
This
Court
has
previously
held
that
arbitration
is
one
of
the
alternative
methods
of
dispute
resolution
that
is
now
rightfully
vaunted
as
"the
wave
of
the
future"
in
international
relations,
and
is
recognized
worldwide.
To
brush
aside
a
contractual
agreement
calling
for
arbitration
in
case
of
disagreement
between
the
parties
would
therefore
be
a
step
backward.
12
BUENA, J.
FACTS:
Under
a
management
agreement
entered
into,
MCHC
appointed
MCMC
as
manager
for
the
operation
of
its
business
and
affairs.
Pursuant
thereto,
petitioners
and
private
respondent
Rolando
Zosa
entered
into
“Employment
Agreement”
designating
the
latter
as
President
and
CEO
of
MCHC.
Respondent
Zosa
then
was
elected
to
a
new
position
as
MCHC’s
Vice-‐Chairman/Chairman
New
Ventures
Development
to
which
he
communicated
his
resignation
on
the
ground
that
it
had
less
responsibility
and
scope
and
demanded
that
he
be
given
termination
benefits
as
provided
in
the
Employment
Agreement.
MCHC
communicated
its
non-‐acceptance
to
the
resignation
and
advised
respondent
that
the
agreement
is
terminated
on
account
of
the
latter’s
breach
thereof.
Respondent
invoked
the
Arbitration
Clause
of
the
agreement
and
both
parties
designated
their
arbitrators
in
the
panel.
However,
instead
of
submitting
the
dispute
to
arbitration,
respondent
filed
an
action
for
damages
against
petitioners
before
the
RTC.
Petitioners’s
motion
to
dismiss
was
denied.
Petitioners
filed
a
petition
for
certiorari
and
prohibition
in
the
CA
to
which
it
was
given
due
course.
The
RTC
in
compliance
with
the
decision,
declared
the
arbitration
clause
in
the
agreement
partially
void
and
of
no
effect
insofar
as
it
concerns
the
composition
of
arbitrators.
Petitioners
then
filed
this
petition
for
review
on
certiorari.
ISSUE:
WHETHER
OR
NOT
THE
ARBITRATION
CLAUSE
IN
THE
EMPLOYMENT
AGREEMENT
IS
PARTIALLY
VOID
AND
OF
NO
EFFECT.
HELD:
Even
if
procedural
rules
are
disregarded,
and
a
scrutiny
of
the
merits
of
the
case
is
undertaken,
this
Court
finds
the
trial
court’s
observations
on
why
the
composition
of
the
panel
of
arbitrators
should
be
voided,
incisively
correct
so
as
to
merit
our
approval.
Thus,
“From
the
memoranda
of
both
sides,
the
Court
is
of
the
view
that
the
defendants
[petitioner]
MCMC
and
MCHC
represent
the
same
interest.
There
is
no
quarrel
that
both
defendants
are
entirely
two
different
corporations
with
personalities
distinct
52
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
ATTY.
BUSTAMANTE
ABSR
and
separate
from
each
other
and
that
a
corporation
has
a
personality
distinct
and
separate
from
those
persons
composing
the
corporation
as
well
as
from
that
of
any
other
legal
entity
to
which
it
may
be
related.
But
as
the
defendants
[herein
petitioner]
represent
the
same
interest,
it
could
never
be
expected,
in
the
arbitration
proceedings,
that
they
would
not
protect
and
preserve
their
own
interest,
much
less,
would
both
or
either
favor
the
interest
of
the
plaintiff.
The
arbitration
law,
as
all
other
laws,
is
intended
for
the
good
and
welfare
of
everybody.
In
fact,
what
is
being
challenged
by
the
plaintiff
herein
is
not
the
law
itself
but
the
provision
of
the
Employment
Agreement
based
on
the
said
law,
which
is
the
arbitration
clause
but
only
as
regards
the
composition
of
the
panel
of
arbitrators.
“From
the
foregoing
arbitration
clause,
it
appears
that
the
two
(2)
defendants
[petitioners]
(MCMC
and
MCHC)
have
one
(1)
arbitrator
each
to
compose
the
panel
of
three
(3)
arbitrators.
As
the
defendant
MCMC
is
the
Manager
of
defendant
MCHC,
its
decision
or
vote
in
the
arbitration
proceeding
would
naturally
and
certainly
be
in
favor
of
its
employer
and
the
defendant
MCHC
would
have
to
protect
and
preserve
its
own
interest;
hence,
the
two
(2)
votes
of
both
defendants
(MCMC
and
MCHC)
would
certainly
be
against
the
lone
arbitrator
for
the
plaintiff
[herein
defendant].
Hence,
apparently,
plaintiff
[defendant]
would
never
get
or
receive
justice
and
fairness
in
the
arbitration
proceedings
from
the
panel
of
arbitrators
as
provided
in
the
aforequoted
arbitration
clause.
In
fairness
and
justice
to
the
plaintiff
[defendant],
the
two
defendants
(MCMC
and
MCHC)
[herein
petitioners]
which
represent
the
same
interest
should
be
considered
as
one
and
should
be
entitled
to
only
one
arbitrator
to
represent
them
in
the
arbitration
proceedings.
Accordingly,
the
arbitration
clause,
insofar
as
the
composition
of
the
panel
of
arbitrators
is
concerned
should
be
declared
void
and
of
no
effect,
because
the
law
says,
“Any
clause
giving
one
of
the
parties
power
to
choose
more
arbitrators
than
the
other
is
void
and
of
no
effect”
(Article
2045,
Civil
Code).
“The
dispute
or
controversy
between
the
defendants
(MCMC
and
MCHC)
[herein
petitioners]
and
the
plaintiff
[herein
defendant]
should
be
settled
in
the
arbitration
proceeding
in
accordance
with
the
Employment
Agreement,
but
under
the
panel
of
three
(3)
arbitrators,
one
(1)
arbitrator
to
represent
the
plaintiff,
one
(1)
arbitrator
to
represent
both
defendants
(MCMC
and
MCHC)
[herein
petitioners]
and
the
third
arbitrator
to
be
chosen
by
the
plaintiff
[defendant
Zosa]
and
defendants
[petitioners].
We
need
only
to
emphasize
in
closing
that
arbitration
proceedings
are
designed
to
level
the
playing
field
among
the
parties
in
pursuit
of
a
mutually
acceptable
solution
to
their
conflicting
claims.
Any
arrangement
or
scheme
that
would
give
undue
advantage
to
a
party
in
the
negotiating
table
is
anathema
to
the
very
purpose
of
arbitration
and
should,
therefore,
be
resisted.
Wherefore,
premises
considered,
the
petition
is
hereby
dismissed
and
the
decision
of
the
trial
court
is
affirmed.
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
5
ATTY.
BUSTAMANTE
3
ABSR
19.
CARGILL
PHILIPPINES,
INC.,
petitioner,
vs.
SAN
FERNANDO
REGALA
TRADING,
INC.,
respondent.
G.R.
No.
175404,
January
31,
2011
PERALTA,
J.:
FACTS:
Respondent
San
Fernando
Regala
Trading
filed
with
the
RTC
of
Makati
City
a
Complaint
for
Rescission
of
Contract
with
Damages
against
petitioner
Cargill.
It
alleged
that
it
agreed
that
it
would
purchase
from
Cargill
12,000
metric
tons
of
Thailand
origin
cane
blackstrap
molasses
and
that
the
payment
would
be
by
an
Irrevocable
Letter
of
Credit
payable
at
sight.
The
parties
agreed
that
the
delivery
would
be
made
in
April/May.
Cargill
failed
to
comply
with
its
obligations
despite
demands
from
respondent.
The
respondent
then
filed
for
rescission.
The
petitioner
filed
a
Motion
to
Dismiss/Suspend
proceeding,
arguing
that
they
must
first
resort
to
arbitration
as
stated
in
their
agreement
before
going
to
court.
However,
the
RTC
ruled
in
favor
of
the
respondent.
The
CA
affirmed
the
RTC
decision,
adding
that
the
case
cannot
be
brought
under
the
Arbitration
Law
for
the
purpose
of
suspending
the
proceedings
before
the
RTC,
since
in
its
Motion
to
Dismiss/Suspend
proceedings,
petitioner
alleged,
as
one
of
the
grounds
thereof,
that
the
subject
contract
between
the
parties
did
not
exist
or
it
was
invalid;
that
the
said
contract
bearing
the
arbitration
clause
was
never
consummated
by
the
parties,
thus,
it
was
proper
that
such
issue
be
first
resolved
by
the
court
through
an
appropriate
trial;
that
the
issue
involved
a
question
of
fact
that
the
RTC
should
first
resolve.
ISSUE:
WHETHER
THE
CA
ERRED
IN
FINDING
THAT
THIS
CASE
CANNOT
BE
BROUGHT
UNDER
THE
ARBITRATION
LAW
FOR
THE
PURPOSE
OF
SUSPENDING
THE
PROCEEDINGS
IN
THE
RTC.
HELD:
The
petition
is
meritorious.
CIVIL
LAW
-‐
Arbitration;
alternative
dispute
resolution;
contracts
Arbitration,
as
an
alternative
mode
of
settling
disputes,
has
long
been
recognized
and
accepted
in
our
jurisdiction.
R.A.
No.
876
authorizes
arbitration
of
domestic
disputes.
Foreign
arbitration,
as
a
system
of
settling
commercial
disputes
of
an
international
character,
is
likewise
recognized.
The
enactment
of
R.A.
No.
9285
on
April
2,
2004
further
institutionalized
the
use
of
alternative
dispute
resolution
systems,
including
arbitration,
in
the
settlement
of
disputes.
A
contract
is
required
for
arbitration
to
take
place
and
to
be
binding.
Submission
to
arbitration
is
a
contract
and
a
clause
in
a
contract
providing
that
all
matters
in
dispute
between
the
parties
shall
be
referred
to
arbitration
is
a
contract.
The
provision
to
submit
to
arbitration
any
dispute
arising
therefrom
and
the
relationship
of
the
parties
is
part
of
the
contract
and
is
itself
a
contract.
The
validity
of
the
contract
containing
the
agreement
to
submit
to
arbitration
does
not
affect
the
applicability
of
the
arbitration
clause
itself.
A
contrary
ruling
would
suggest
that
a
party's
mere
repudiation
of
the
main
contract
is
sufficient
to
avoid
arbitration.
That
is
exactly
the
situation
that
the
54
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
ATTY.
BUSTAMANTE
ABSR
separability
doctrine,
as
well
as
jurisprudence
applying
it,
seeks
to
avoid.
Petition
is
GRANTED.
FACTS:
On
May
24,
2000,
RCBC
entered
into
a
Share
Purchase
Agreement5
(SPA)
with
Equitable-‐PCI
Bank,
Inc.
(EPCIB),
George
L.
Go
and
the
individual
shareholders6
of
Bankard,
Inc.
(Bankard)
for
the
sale
to
RCBC
of
226,460,000
shares
(Subject
Shares)
of
Bankard,
constituting
67%
of
the
latter’s
capital
stock.
After
completing
payment
of
the
contract
price
(₱1,786,769,400),
the
corresponding
deeds
of
sale
over
the
subject
shares
were
executed
in
January
2001.
The
dispute
between
the
parties
arose
sometime
in
May
2003
when
RCBC
informed
EPCIB
and
the
other
selling
shareholdersof
an
overpayment
of
the
subject
shares,
claiming
there
was
an
overstatement
of
valuation
of
accounts
amounting
to
₱478
million
and
that
the
sellers
violated
their
warrantyunder
Section
5(g)of
the
SPA.7
Subsequently,
the
Arbitration
Tribunal
was
constituted.
Mr.
Neil
Kaplan
was
nominated
by
RCBC;
Justice
Santiago
M.
Kapunan
(a
retired
Member
of
this
Court)
was
nominated
by
the
Respondents;
and
Sir
Ian
Barker
was
appointed
by
the
ICC-‐
ICA
as
Chairman.
On
August
13,
2004,
the
ICC-‐ICA
informed
the
parties
that
they
are
required
to
pay
US$350,000
as
advance
on
costs
pursuant
to
Article
30
(3)
of
the
ICC
Rules
of
Arbitration
(ICC
Rules).
RCBC
paid
its
share
of
US$107,000,
the
balance
remaining
after
deducting
payments
of
US$2,500
and
US$65,000
it
made
earlier.
Respondents’
share
of
the
advance
on
costs
was
thus
fixed
at
US$175,000.
On
October
26,
2007,
RCBC
filed
with
the
Makati
City
RTC,
Branch
148
(SP
Proc.
Case
No.
M-‐6046)amotion
to
confirm
the
First
Partial
Award,
while
Respondents
filed
a
motion
to
vacate
the
same.
ICC-‐ICA
by
letter25
dated
October
12,
2007
increased
the
advance
on
costs
from
US$450,000
to
US$580,000.
Under
this
third
assessment,
RCBC
paid
US$130,000
as
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
5
ATTY.
BUSTAMANTE
5
ABSR
its
share
on
the
increment.
Respondents
declined
to
pay
its
adjudged
total
share
of
US$290,000
on
account
of
its
filing
in
the
RTC
of
a
motion
to
vacate
the
First
Partial
Award.26
The
ICC-‐ICA
then
invited
RCBC
to
substitute
for
Respondents
in
paying
the
balance
of
US$130,000
by
December
21,
2007.27
RCBC
complied
with
the
request,
making
its
total
payments
in
the
amount
of
US$580,000.28
Meanwhile,
on
January
8,
2008,
the
Makati
City
RTC,
Branch
148
issued
an
order
in
SP
Proc.
Case
No.
M-‐6046
confirming
the
First
Partial
Award
and
denying
Respondents’
separate
motions
to
vacate
and
to
suspend
and
inhibit
Barker
and
Kaplan.
Respondents’
motion
for
reconsideration
was
likewise
denied.
Respondents
directly
filed
with
this
Court
a
petition
for
review
on
certiorari
under
Rule
45,
docketed
as
G.R.
No.
182248
and
entitled
Equitable
PCI
Banking
Corporation
v.
RCBC
Capital
Corporation.32
In
our
Decision
dated
December
18,
2008,
we
denied
the
petition
and
affirmed
the
RTC’s
ruling
confirming
the
First
Partial
Award.
On
January
18,
2008,
the
Arbitration
Tribunal
set
a
timetable
for
the
filing
of
submission
by
the
parties
on
whether
it
should
issue
a
Second
Partial
Award
in
respect
of
the
Respondents’
refusal
to
pay
an
advance
on
costs
to
the
ICC-‐ICA.
on June 16, 2010, the Arbitration Tribunal issued the Final Award.
On
July
1,
2010
BDO
filed
in
the
Makati
City
RTC
a
Petition
to
Vacate
Final
Award
Ad
Cautelam,51
docketed
as
SP
Proc.
Case
No.
M-‐6995,
which
was
raffled
to
Branch
65.
On
July
28,
2010,
RCBC
filed
with
the
Makati
City
RTC,
Branch
148
(SP
Proc.
Case
No.
M-‐6046)
a
Motion
to
Confirm
Final
Award.52
BDO
filed
its
Opposition
With
Motion
to
Dismiss53
on
grounds
that
a
Petition
to
Vacate
Final
Award
Ad
Cautelamhad
already
been
filed
in
SP
Proc.
Case
No.
M-‐6995.
BDO
also
pointed
out
that
RCBC
did
not
file
the
required
petition
but
instead
filed
a
mere
motion
which
did
not
go
through
the
process
of
raffling
to
a
proper
branch
of
the
RTC
of
Makati
City
and
the
payment
of
the
required
docket/filing
fees.
Even
assuming
that
Branch
148
has
jurisdiction
over
RCBC’s
motion
to
confirm
final
award,
BDO
asserted
that
RCBC
had
filed
before
the
Arbitration
Tribunal
an
Application
for
Correction
and
Interpretation
of
Award
under
Article
29
of
the
ICC
Rules,
which
is
irreconcilable
with
its
Motion
to
Confirm
Final
Award
before
said
court.
Hence,
the
Motion
to
Confirm
Award
was
filed
precipitately.
Meanwhile,
on
November
10,
2010,
Branch
148
(SP
Proc.
Case
No.
M-‐6046)
issued
an
Order56
confirming
the
Final
Award
"subject
to
the
correction/interpretation
On
December
30,
2010,
George
L.
Go,
in
his
personal
capacity
and
as
attorney-‐in-‐fact
of
the
other
listed
shareholders
of
Bankard,
Inc.
in
the
SPA
(Individual
Shareholders),
filed
a
petition
in
the
CA,
CA-‐G.R.
SP
No.
117451,
seeking
to
set
aside
the
above-‐cited
November
10,
2010
Order
and
to
enjoin
Branch
148
from
further
proceeding
in
SP
Proc.
Case
No.
M-‐6046.
By
Decision57
dated
June
15,
2011,
the
CA
dismissed
the
said
petition.
Their
motion
for
reconsideration
of
the
said
decision
was
likewise
denied
by
the
CA
in
its
Resolution58
dated
December
14,
2011.
ISSUE: WHETHER
THERE
IS
LEGAL
GROUND
TO
VACATE
THE
SECOND
PARTIAL
AWARD
HELD:
As
a
rule,
the
award
of
an
arbitrator
cannot
be
set
aside
for
mere
errors
of
judgment
either
as
to
the
law
or
as
to
the
facts.Courts
are
without
power
to
amend
or
overrule
merely
because
of
disagreement
with
matters
of
law
or
facts
determined
by
the
arbitrators.They
will
not
review
the
findings
of
law
and
fact
contained
in
an
award,
and
will
not
undertake
to
substitute
their
judgment
for
that
of
the
arbitrators,
since
any
other
rule
would
make
an
award
the
commencement,
not
the
end,
of
litigation.Errors
of
law
and
fact,
or
an
erroneous
decision
of
matters
submitted
to
the
judgment
of
the
arbitrators,
are
insufficient
to
invalidate
an
award
fairly
and
honestly
made.
Judicial
review
of
an
arbitration
is,
thus,
more
limited
than
judicial
review
of
a
trial.78
Accordingly,
we
examine
the
merits
of
the
petition
before
us
solely
on
the
statutory
ground
raised
for
vacating
the
Second
Partial
Award:
evident
partiality,
pursuant
to
Section
24
(b)
of
the
Arbitration
Law
(RA
876)
and
Rule
11.4
(b)
of
the
Special
ADR
Rules.
Evident Partiality
Evident
partiality
is
not
defined
in
our
arbitration
laws.
As
one
of
the
grounds
for
vacating
an
arbitral
award
under
the
Federal
Arbitration
Act
(FAA)
in
the
United
States
(US),
the
term
"encompasses
both
an
arbitrator’s
explicit
bias
toward
one
party
and
an
arbitrator’s
inferred
bias
when
an
arbitrator
fails
to
disclose
relevant
information
to
the
parties."
From
a
recent
decision80
of
the
Court
of
Appeals
of
Oregon,
we
quote
a
brief
discussion
of
the
common
meaning
of
evident
partiality:
Evident
partiality
in
its
common
definition
thus
implies
"the
existence
of
signs
and
indications
that
must
lead
to
an
identification
or
inference"
of
partiality.81
Despite
the
increasing
adoption
of
arbitration
in
many
jurisdictions,
there
seems
to
be
no
established
standard
for
determining
the
existence
of
evident
partiality.
In
the
US,
evident
partiality
"continues
to
be
the
subject
of
somewhat
conflicting
and
inconsistent
judicial
interpretation
when
an
arbitrator’s
failure
to
disclose
prior
dealings
is
at
issue."82
EPCIB/BDO,
in
moving
to
vacate
the
Second
Partial
Award
claimed
that
the
Arbitration
Tribunal
exceeded
its
powers
in
deciding
the
issue
of
advance
cost
not
contemplated
in
the
TOR,
and
that
Chairman
Barker
acted
with
evident
partiality
in
making
such
award.
The
RTC
held
that
BDO
failed
to
substantiate
these
allegations.
On
appeal,
the
CA
likewise
found
that
the
Arbitration
Tribunal
did
not
go
beyond
the
submission
of
the
parties
because
the
phrasing
of
the
scope
of
the
agreed
issues
in
the
TOR
("[t]he
issues
to
be
determined
by
the
Tribunal
are
those
issues
arising
from
the
said
Request
for
Arbitration,
Answer
and
Reply
and
such
other
issues
as
may
properly
arise
during
the
arbitration")is
broad
enough
to
accommodate
a
finding
on
the
liability
and
the
repercussions
of
BDO’s
failure
to
share
in
the
advances
on
costs.
Section
10
of
the
SPA
also
gave
the
Arbitration
Tribunal
authority
to
decide
how
the
costs
should
be
apportioned
between
them.
issuance
of
the
Second
Partial
Award
are
not
in
issue
here.
Courts
are
generally
without
power
to
amend
or
overrule
merely
because
of
disagreement
with
matters
of
law
or
facts
determined
by
the
arbitrators.
They
will
not
review
the
findings
of
law
and
fact
contained
in
an
award,
and
will
not
undertake
to
substitute
their
judgment
for
that
of
the
arbitrators.
A
contrary
rule
would
make
an
arbitration
award
the
commencement,
not
the
end,
of
litigation.101
It
is
the
finding
of
evident
partiality
which
constitutes
legal
ground
for
vacating
the
Second
Partial
Award
and
not
the
Arbitration
Tribunal’s
application
of
the
ICC
Rules
adopting
the
"contractual
approach"
tackled
in
Secomb’s
article.
Before
an
injunctive
writ
can
be
issued,
it
is
essential
that
the
following
requisites
are
present:
(1)
there
must
be
a
right
inesse
or
the
existence
of
a
right
to
be
protected;
and
(2)
the
act
against
which
injunction
to
be
directed
is
a
violation
of
such
right.
The
onus
probandi
is
on
movant
to
show
that
there
exists
a
right
to
be
protected,
which
is
directly
threatened
by
the
act
sought
to
be
enjoined.
Further,
there
must
be
a
showing
that
the
invasion
of
the
right
is
material
and
substantial
and
that
there
is
an
urgent
and
paramount
necessity
for
the
writ
to
prevent
a
serious
damage.105
We
find
no
reversible
error
or
grave
abuse
of
discretion
in
the
CA’s
denial
of
the
application
for
stay
order
or
TRO
upon
its
finding
that
BDO
failed
to
establish
the
existence
of
a
clear
legal
right
to
enjoin
execution
of
the
Final
Award
confirmed
by
the
Makati
City
RTC,
Branch
148,
pending
resolution
of
its
appeal.It
would
be
premature
to
address
on
the
merits
the
issues
raised
by
BDO
in
the
present
petition
considering
that
the
CA
still
has
to
decide
on
the
validity
of
said
court's
orders
confirming
the
Final
Award.
But
more
important,
since
BOO
had
already
paid
₱637,941,185.55
m
manager's
check,
albeit
under
protest,
and
which
payment
was
accepted
by
RCBC
as
full
and
complete
satisfaction
of
the
writ
of
execution,
there
is
no
more
act
to
be
enjoined.
Settled
is
the
rule
that
injunctive
reliefs
are
preservative
remedies
for
the
protection
of
substantive
rights
and
interests.
Injunction
is
not
a
cause
of
action
in
itself,
but
merely
a
provisional
remedy,
an
adjunct
to
a
main
suit.
When
the
act
sought
to
be
enjoined
has
become
fait
accompli,
the
prayer
for
provisional
remedy
should
be
denied.
106
ALTERNATIVE
DISPUTE
RESOLUTION
CASE
DIGEST
A.Y.
2019-‐2020
5
ATTY.
BUSTAMANTE
9
ABSR