Action Plan

This document contains a Gantt chart summarizing tasks for the project to uprate the Bay Trafo. The project includes tasks such as constructing guard houses in Padang Panjang and Salak over 45-48 days, expanding cubicles and building transformer houses in Dumai over 39-25 days, and laying cable conduits and access roads over 5-7 days. Key milestones include completing the Salak guard house by August 28th and the overall project by September 8th.

Uploaded by

Ivan Rismanto
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views

Action Plan

This document contains a Gantt chart summarizing tasks for the project to uprate the Bay Trafo. The project includes tasks such as constructing guard houses in Padang Panjang and Salak over 45-48 days, expanding cubicles and building transformer houses in Dumai over 39-25 days, and laying cable conduits and access roads over 5-7 days. Key milestones include completing the Salak guard house by August 28th and the overall project by September 8th.

Uploaded by

Ivan Rismanto
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Name Duration Start Finish Jul 14, '19 Jul 21, '19 Jul 28, '19 Aug

Finish Jul 14, '19 Jul 21, '19 Jul 28, '19 Aug 4, '19 Aug 11, '19 Aug 18, '19 Aug 25, '19 Sep 1, '19 Sep 8, '19
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
1 PROJECT PLN UPRATING BAY TRAFO 56 days Mon 7/15/19 Sun 9/8/19

2 GARDU INDUK PADANG PANJANG 48 days Thu 7/18/19 Tue 9/3/19

22 GARDU INDUK SALAK 45 days Mon 7/15/19 Wed 8/28/19

49 GARDU INDUK DUMAI 39 days Thu 8/1/19 Sun 9/8/19

50 AREA SWICTHYARD 25 days Thu 8/1/19 Sun 8/25/19

51 PERSIAPAN 2 days Thu 8/1/19 Fri 8/2/19

52 PODASI TRAFO 21 days Sat 8/3/19 Fri 8/23/19

53 PODASI TRAFO SEMENTARA 1 day Sat 8/3/19 Sat 8/3/19

54 PONDASI CABLE SUPPORT 2 days Sat 8/24/19 Sun 8/25/19

55 SALURAN KABEL 2 days Sat 8/3/19 Sun 8/4/19

56 JALAN ASPAL 2 days Sat 8/3/19 Sun 8/4/19

57 PENGGANTIAN TUTUP SALURAN KABEL 5 days Sat 8/3/19 Wed 8/7/19

58 PENGGANTIAN TUTUP BORDES 5 days Sat 8/3/19 Wed 8/7/19

59 PERLUASAN KUBIKEL 39 days Thu 8/1/19 Sun 9/8/19

60 PERSIAPAN 1 day Thu 8/1/19 Thu 8/1/19

61 PEKERJAAN TANAH 3 days Fri 8/2/19 Sun 8/4/19

62 PEKERJAAAN BETON 21 days Mon 8/5/19 Sun 8/25/19

63 PEKERJAAN DINDING 14 days Mon 8/26/19 Sun 9/8/19

64 PEKERJAAN LANTAI 2 days Wed 8/28/19 Thu 8/29/19

65 PEKERJAAN ATAP 2 days Mon 8/26/19 Tue 8/27/19

66 PEKERJAAN PINTU DAN JENDELA ALMUNIUM 1 day Mon 8/26/19 Mon 8/26/19

67 PEKERJAAN PENGECATAN 2 days Fri 8/30/19 Sat 8/31/19

68 PEKERJAAN LISTRIK 1 day Mon 8/26/19 Mon 8/26/19

69 PEKERJAAN SALURAN KABEL 7 days Fri 8/2/19 Thu 8/8/19

70 PEKERJAAN SALURAN AIR 2 days Fri 8/30/19 Sat 8/31/19

71 RUMAH TRAFO 25 days Thu 8/1/19 Sun 8/25/19

72 PERSIAPAN 1 day Thu 8/1/19 Thu 8/1/19

73 PEKERJAAN TANAH 3 days Fri 8/2/19 Sun 8/4/19

74 PEKERJAAAN BETON 14 days Mon 8/5/19 Sun 8/18/19

75 PEKERJAAN DINDING 7 days Mon 8/19/19 Sun 8/25/19

76 PEKERJAAN LANTAI 3 days Wed 8/21/19 Fri 8/23/19

77 PEKERJAAN ATAP 2 days Mon 8/19/19 Tue 8/20/19

78 PEKERJAAN PINTU DAN JENDELA ALMUNIUM 1 day Mon 8/19/19 Mon 8/19/19

79 PEKERJAAN PENGECATAN 2 days Sat 8/24/19 Sun 8/25/19

80 PEKERJAAN LISTRIK 1 day Mon 8/19/19 Mon 8/19/19

81 PEKERJAAN SALURAN KABEL 1 day Fri 8/2/19 Fri 8/2/19

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: UPRATING BAY TRAFO
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: 17/7/2019
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress