Project Management Procedure
Project Management Procedure
Revision History
TABLE OF CONTENTS
1.1 OBJECTIVE......................................................................................................................................................4
1.2 SCOPE ............................................................................................................................................................4
1.3 ENTRY CRITERIA..............................................................................................................................................4
1.4 INPUT .............................................................................................................................................................4
1.5 ABBREVIATIONS AND GLOSSARY ........................................................................................................................4
1.5.1 Abbreviations.....................................................................................................................................4
1.5.2 Glossary ..............................................................................................................................................5
1.6 ASSUMPTIONS..................................................................................................................................................6
1.7 PROCESS FLOW ...............................................................................................................................................7
1.8 TASK (RESPONSIBLE, ACCOUNTABLE, CONSULTED AND INFORMED) .....................................................................8
1.9 ROLES AND RESPONSIBILITIES .........................................................................................................................12
1.10 GUIDELINES ..................................................................................................................................................13
1.10.1 Project Planning .............................................................................................................................13
1.10.2 Project Monitoring & Control .......................................................................................................14
1.10.3 Project Closure ...............................................................................................................................15
1.10.4 Project Change Request (CR) Management ................................................................................16
1.11 VERIFICATION AND VALIDATION ......................................................................................................................16
1.12 METRICS AND MEASUREMENT ..........................................................................................................................17
1.13 OUTPUT .......................................................................................................................................................17
1.14 EXIT CRITERIA...............................................................................................................................................17
1.15 APPLICABLE STANDARDS ................................................................................................................................17
1.16 REFERENCES .................................................................................................................................................17
1.2 Scope
The scope of the process is to:
• Develop necessary management plans to execute project on Idea approved as a Project by PAC
and approved Project Charter and CER/OER
• Execute, monitor & control project as per management plans within agreed budget
• Perform project closure activities to ensure completion and delivery of all work-products or
solution and sharing lesson learnt within the team
1.4 Input
• High Level Scope Document for Idea
• Approved Project Charter for New Solution & Major Enhancement / Approved Project Charter
for Enhancement & Change if applicable
• Approved CER/OER for New Solution & Major Enhancement / Approved CER/OER for
Enhancement & Change if applicable
1.5.1 Abbreviations
Terms Description
CM Change Management
CR Change Request
H/w Hardware
Terms Description
KB Knowledge Base
KM Knowledge Management
PM Project Manager
QA Quality Assurance
S/w Software
1.5.2 Glossary
1.6 Assumptions
• Project Management Process will be applicable for “New Solution & Major Enhancement” and
“Enhancement & Change”
• For any change in project (like scope, timeline and effort/budget/cost etc.), the Project
Manager will manage the Project Change as per Project Change Request Management process.
SDLC Vs PMLC
Start
SDLC
Weeks
PAC
Approval
Initiation
Design
Build (Development)
Test
Project
Task Project Project
Tasks SDLC Team Steering
Id Sponsor Manager
Committee
Project Planning
Issue Approved Project Charter as per
1.1 I R/A R I
SDLC initiation phase
Project
Task Project Project
Tasks SDLC Team Steering
Id Sponsor Manager
Committee
1.2 Project Planning meeting R R R/A I
Ensure necessary access on network /
1.3 systems / tools etc. to SDLC team & C I R/A -
Other stakeholders
Prepare Project Management Plan
(PMP) including:
• 1.4a - Establish Project Team
• 1.4b - Identify Project Team and
assign RACI
• 1.4c - Define Resource Plan
including recruitment, staffing,
training etc.
• 1.4d - Define IT Plan including
H/w, S/w, network etc.
1.4 • 1.4e - Select Project Execution C C R/A C
Methodology
• 1.4f - Define Project Status &
Variance Tracking and Controlling
Mechanism
• 1.4g - Define Project Reporting
Mechanism
• 1.4h - Define Project Support
Plans including CM, QA, KM, Risk,
Security & DRBC and
Communication plans etc.
1.5 Review PMP - - R R/A
Project Steering Committee checks if
1.6 the PMP is Ok, if Yes, Go to Step 2.1 I I R R/A
Else Go to Step 1.7
Project Steering Committee along with
PM determines if Project Change is
required.
1.7 R I R R/A
If Yes, Perform Project CR Process
steps 5.1 to 5.9 and then Go back to
Step 1.4 Else Go back to Step 1.4.
Estimate Effort / Size for SDLC
2.1 R/A I R C
Activities
2.2 Prepare / Update Project Schedule R - R/A C
Project Steering Committee reviews
Project Schedule. Project Schedule is
2.3 OK? R I R R/A
If Yes, Go to Step 2.4 Else Go back to
from Step 2.1
2.4 Baseline PMP and Project Schedule I I R/A I
Project Planning Stage-gate and
2.5 R I R/A R
Project Execution Kick-off.
Project
Task Project Project
Tasks SDLC Team Steering
Id Sponsor Manager
Committee
Circulate Minutes of Meeting (MoM)
2.6 and track action items to closure. I I R/A I
Process continues from Step 3.1
Project
Task Project
Project Planning SDLC Team Steering
id Manager
Committee
Project
Task SDLC Project Service Desk/
Project Planning Steering
id Team Manager Support Team
Committee
Project Closure
Project
Task SDLC Project Service Desk/
Project Planning Steering
id Team Manager Support Team
Committee
Ensure all documents completed as per
4.1 C - R/A -
plan
Enable Hypercare to Service Desk / Support
4.2 R - R/A R
team
Arrange Project Closure Meeting with SDLC
4.3 C - R/A -
Team and other stakeholders as per Plan
Participate in Project Closure Meeting and
4.4 R R R/A -
agree on Project Closure
4.5 Share Project Closure Report within team I I R/A I
Update all relevant project related
4.6 R - R/A -
documents / records
Communicate Stakeholders on closure of
4.7 I I R/A I
the Project
4.8a Conduct Project Retrospection Meeting I I R/A -
Participate in Project Retrospection
4.8b R - R/A -
Meeting
4.9 Prepare Project Retrospection Report C - R/A -
Share learning and best practices in KB for
4.10 I I R/A I
team to implement in future projects
Closure Stage-gate to ensure completion of
4.11 the project and release all resources / C C R/A C
teams.
Project
SDLC Project
Task id Project Planning PCCB Steering
Team Manager
Committee
Project
SDLC Project
Task id Project Planning PCCB Steering
Team Manager
Committee
Update Project Schedule/Cost based on
5.6 re-estimated effort / size done by SDLC R R/A - -
Team
Review and approval of the Project
Schedule/Cost. Decision on Project
5.7 Schedule/Cost approved? I R - R/A
If Yes, Go to Step 5.8 Else Go back to Step
5.6
5.8 Re-baseline Project Cost I R/A - I
Update impacted Deliverables as per
5.9 revised approved schedule following SDLC R/A R - I
Process
Roles Responsibilities
Responsible for overall accountability within IT for the project. Key
responsibilities include:
Relationship Manager • Prepare Business Case for Idea with Project Sponsor
(RM) • Communicate the reason for rejection of the Idea to the stakeholders
• Prioritizes Projects for approved Ideas
• Works with PM in preparing Project Charter
• Works with PM in preparing CER / OER
Roles Responsibilities
Responsible for project planning, project monitoring & controlling,
project change control and Project closure. Key responsibilities include:
Project Change • EITS governing body with review & approval responsibility of project
change request.
Control Board (PCCB)
Project governing body with responsibility of approval of:
1.10 Guidelines
During SDLC Initiation Phase, PAC approves Idea as a project for “New Solution & Major Enhancement” OR
“Enhancement & Change”. On approval of Idea as a project during SDLC Initiation Phase:
• In case of Project for New Solution & Major Enhancement, Relationship Manager works on Project Charter
and CER/OER with Project Sponsor and gets the approval from the Project Sponsor.
• Similarly In case of Project for Enhancement & Change, but if applicable, Relationship Manager works on
Project Charter and CER/OER with Project Sponsor and gets the approval from the Project Sponsor.
On completion of SDLC Initiation Phase, the project planning phase starts and the Project Manager (PM) develops
a detailed plan for the project. The PM involves stakeholders from SDLC teams and other stakeholders as
appropriate.
Based on the information collected during the project planning phase, the PM provides necessary access to
identified project resources / teams / stakeholders and starts preparing detailed Project Management Plan
(PMP), which contains all management plans for project execution, monitoring & control. The PM submits the
PMP to Project Steering Committee for review & approval.
While working and review of PMP, the PM evaluates the project requirements and determines if any change
required in Project Scope, Timeline, budget/Cost etc. if any, raises & implement Project CR as per Project CR
Management Process, and updates the PMP accordingly.
The PM ensures effort / size estimates are done by the respective teams for SDLC activities and works with team
to prepare schedule. The PM submits the estimates and schedule to Project Steering Committee for review and
approval.
On approval of the project schedule by Project Steering Committee, the PM conducts Project Planning Stage-
Gate Review:
• Involving Project Steering Committee, SDLC team and other stakeholders as appropriate to review the
completion of all activities / deliverables of project planning phase
• Baselines project scope, effort/budget/cost and schedule
• Tracks action items out of Stage Gate Review till closure
On successful completion of Planning Phase Stage-Gate as per Stage-gate checklist, the PM should communicate
to the teams/stakeholders, the completion of project planning phase to move to the next phase.
The PM, during execution of the project, monitors & controls the project activities as per PMP and Project
Schedule.
• Monitoring & Controlling Variances to the Project Baseline - Tracking of project performance including
effort, schedule and budget/cost etc. against the project baselines and determine the variances if any.
In case any deviations from the project baseline, the PM should determine and implement corrective &
preventive actions with SDLC team & stakeholders.
• Tracking & Mitigating Risks –
o Identifying, tracking and mitigating risks on regular interval as per frequency defined frequency
in PMP and even-driven when required.
o Reporting risks to Stakeholders and Project Steering Committee through Project status reporting
to mitigate the risks.
o Also reporting risks to stakeholders and Project Steering Committee as appropriate on event-
driven basis if required early intervention to mitigate the risks.
o Risks are tracked and reported in Project Status Report through Clarity tool
• Tracking & Resolution Issues –
o Identifying, tracking & resolving the issues by Project / SDLC teams or escalate to Project
Steering Committee as appropriate for resolution or providing resource for resolution or guidance
for resolution.
o Issues are tracked and reported in Project Status Report through Clarity tool
• Tacking & Resolving Non-Conformances – Identifying, tracking & resolving non-conformances to the
defined standards through SDLC Stage-gate review at the end of each phase following Stage-Gate Review
Checklist.
The Project Manager should conduct regular project status meeting with team to identify status of the project
and ensures preparation / generation of the Project Status / progress report in Clarity tool and communicate to
stakeholders and Project Steering Committee as per defined frequency in PMP.
The PM, on regular interval as per defined frequency in PMP, should discuss the Project Status Report with
Stakeholders and Project Steering Committee, circulate MOM including action items, and track the action items
till closure.
The PM should also discuss the change required in scope, timeline, budget/cost etc. if any, raises & implements
Project CR as per Project CR Management Process described in below section, and updates the PMP accordingly.
The PM also ensures project performance review against project baselines, non-conformances to agreed
standards, customer complaints including risks, issues, concerns etc. if any by Project Steering Committee in
order to meet or exceed project baselines.
The PM along with SDLC team tracks progress of all project activities as per project plan and repeats project
monitoring & control till completion of the project work. On completion of all project, the PM performs project
closure.
This phase focusses on ensuring completion of all project activities & artifacts and sign-off from stakeholders.
• Completion of all project deliverables / artifacts by respective teams and delivery of all project
deliverables to stakeholders
• Successful completion of Knowledge Transition, Hypercare Go-live Support & Sign-off between Delivery
and Support team
• Project Closure Meeting with Project Steering Committee and other stakeholders to validate all activities
completed as per scope of the project
• Project retrospection meeting with SDLC team and other stakeholders to identify lesson learned based on
what went wrong and what went right. Retrospection meeting is required for all “New Solution & Major
Enhancement” projects and recommended for “Enhancement & Change” projects that:
o Projects identified as “Strategic Projects in Clarity”
o Projects that finish +/- 10% of Design Phase Baseline Budget
o Projects that finish +/- 10% of Design Phase Baseline Go Live date
o Projects that are abandoned in-flight
o Projects that have over $10000 in capital expense.
• The Project Manager shall share learning within the Project / SDLC teams to implement best practices in
future projects.
• Involving Project Steering Committee, SDLC team and other stakeholders as appropriate to review the
completion of all activities / deliverables of the project
• Tracks action items out of Stage Gate Review till closure
On successful completion of Project Closure Phase Stage-Gate as per Stage-gate checklist, the PM should
communicate to the teams/stakeholders, the closure of the project to all stakeholders and release the team.
The PM during project planning, monitoring & control determines if there is a change required in scope, timeline,
budget/cost etc., raises & implements the Project CR:
The PM should ensure that only approved Project CR are implemented in the project.
1.13 Output
• Project Management Plan
• Project Change Request
• Project Scope, Cost and Schedule Baselines
• Project Schedule
• Project Closure Report
• Lessons Learnt and Best Practices in KB
1.16 References
• Client’s Process 150-5000 Project Baseline Process
• PMBOK
• PRINCE 2.0
• CMMI Project Management Practices