0% found this document useful (0 votes)
62 views

Method Statement: Earthworks: Personal Protective Equipment

This document provides a method statement for earthworks at a road realignment scheme. Personal protective equipment including safety gloves, hearing protection, eye protection, coveralls, high visibility vests, hard hats, and boots are required. Excavation will be carried out according to design drawings using excavators and dump trucks. When the formation level is reached, the area will be inspected by the contractor and employer's site representative before sign off. Any soft spots found below formation level will be excavated and replaced with acceptable fill material. All works will be contained within permanent fencing and material testing will be done to specifications.

Uploaded by

Burim Zeqiri
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
62 views

Method Statement: Earthworks: Personal Protective Equipment

This document provides a method statement for earthworks at a road realignment scheme. Personal protective equipment including safety gloves, hearing protection, eye protection, coveralls, high visibility vests, hard hats, and boots are required. Excavation will be carried out according to design drawings using excavators and dump trucks. When the formation level is reached, the area will be inspected by the contractor and employer's site representative before sign off. Any soft spots found below formation level will be excavated and replaced with acceptable fill material. All works will be contained within permanent fencing and material testing will be done to specifications.

Uploaded by

Burim Zeqiri
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Issue Date

N60 Balla to Claremorris


Method Statement: 0 08/5/14
Road Realignment at
Heathlawn Scheme Earthworks
Ident No.
MS-N60-04 Rev 0

Personal Protective Equipment

Safety Gloves Hearing Eye Respiratory Coveralls Other


Protection Protection Protection
Hi Vis- Vest
Hard Hats
Boots

Yes Where required Yes NO No Yes

Methodology
 All personnel entering the site shall have received a site safety induction and have
attended a job toolbox talk.
 Before any excavations shall commence a permit to excavate shall be issued by the
site engineer and all persons involved in the task shall be fully briefed
 All setting out works required including level profiles and batter rails shall be set out
by the site engineer prior to works commencing.
 Excavation shall be carried out in accordance to line and levels shown on Design
Drawings. Excavation shall be carried out by excavator with material being hauled to
fill area by dump trucks.
 When formation has been reached the Contractor shall inform Jacob‟s Employer‟s
Site Representative (ESR). The area shall be jointly inspected by Contractor and
ESR. Once the area has been deemed acceptable a sign off sheet shall be
completed.
 Should any soft spots be encountered below formation level the area shall be
excavated, recorded jointly by Contractor and ESR and replaced with acceptable fill
material.
 All fill material (including capping) being used in permanent works shall be classified
in accordance with the NRA Specification for Roadworks.
 All formation levels shall be recorded by site engineer.
 All works will be executed within the permanent fencing boundary.
 Material testing to demonstrate compliance with NRA Specification for Roadworks &
specific contract requirements will be undertaken.

Date : 12/5/2014
Page 3

You might also like