Design of Transformer
Design of Transformer
I hereby certify that I have completed the fifteen weeks training in partial fulfillment of the
requirements for the award of BS ELECTRICAL ENGINEERING TECHNOLOGY. I did my
training in Transfopower industries from 15-02-2018 to 15-06-2018.
The matter presented in this report has not been submitted by me for the award of any other
degree elsewhere.
Student Signature:
Muhammad Ashfaq
2014-GCUF-15947
Examined by:
Engr. Mouzzam Rehman
Incharge HOD:
Electrical Engineering Technology Department
ACKNOWLEDGMENT
First of all, I would like to thanks my Institute, GCUF (Sahiwal Campus), for arranging the
internship program for me. I am also grateful to Transforpower industry Lahore for recruiting
me as an intern. I would like to place on record my deep sense of gratitude to Engr Javeed
Iqbal.
I would like to place on record my deep sense of gratitude to HR Manager and faculty member.
I take this opportunity to express me profound gratitude and deep regards to my Team Leader
for his exemplary guidance, monitoring and constant encouragement throughout the course of
this internship. The blessing, help and guidance given by him time to time shall carry me a
long way in the journey of life on which I am about to embark. I am extremely grateful and
remain indebted to Transfopower industry for being a source of inspiration and for his constant
support in intern.
I am obliged to all my team members, for the valuable information provided by them in their
respective fields. I am grateful for their cooperation during the period of my internship.
I am obliged to all my team members, for the valuable information provided by them in their
respective fields. I am grateful for their cooperation during the period of my internship.
I‘m thankful to them for their continual constructive criticism and invaluable suggestions and
help, which benefited me a lot at my intern.
I would like to specially thanks Engr. Mouzzam Rehman for his proper assistance and
guidance.
I
Table of Contents
Actnowledgement......................................................................................................................I
List of Abbreviations..................................................................................................................V
List of Figures............................................................................................................................VI
List of Tables.............................................................................................................................VII
II
Chapter No.3 Skill Attaining...................................................................................................42
4.1 Conclusion............................................................................................................................57
4.2 Recommendation..................................................................................................................58
4.3 References.............................................................................................................................59
List of Abbreviations
III
BCT Before Connection Test
CT Current Transformer
PT Potential Transformer
DC Direct Current
AC Alternating Current
LB Load Breaker
MS Mild Steel
SS Stainless Steel
List of Figures
2.12 CT 28
2.13 CT Structure 29
2.14 PT 31
3.2 Mugger 43
List of Table
V
2.5 Breaker and fuse rating for PMT 28
VI
Chapter 1
Introduction
Introduction of Transfopower Industry
Transfopower Industries (Pvt) Limited is a leading company in Pakistan’s transformer
manufacturing sector. Established in 1990 by a team of engineers who literally pioneered
transformer manufacturing and design in the country, the company has quickly risen to
consolidate its position as a technology leader and, one of the most esteemed producers of high
performance transformers both in terms of quality and innovation.
With a strong commitment to engineering excellence at the core of company philosophy and a
dedicated research and development focus on transformers the company has the capability to
produce a wide range of products including Distribution transformers , Power transformers,
Furnace transformers, Dry type and Non inflammable transformers. special purpose
transformers designed for specific application offering the best in price, delivery & quality.
Presently, we are manufacturing transformers in 5KVA to 5000KVA range, for WAPDA Area
Electricity Boards, DISCO’s, KESC, AJK (WAPDA House, Mangla and Tarbela Power
Projects) and leading projects in the private sector (Bahria Town, DHA, GHQ, Shell, KSB
Pumps, Chashma Nuclear Power Plant, Sui Northern, CWO and other industries both local and
multinational of all sectors).
Due to a total quality orientation Transfopower Industries (Pvt) Ltd has been achieving
customer satisfaction, catering to both the local and export markets. We aim to further
strengthen our established base and achieve and exceed customer expectation by striving for
continuous improvement in product development, design and services, keeping abreast of the
latest developments in global technology and ensuring human resource development through
training, motivation and provision of suitable work environment.
The manufacturing process is supervised and quality assured by a team of highly focused
technical staff at all stages in compliance with all international quality standards at our state of
the art manufacturing facility. Also tests according to relevant standards are carried out before
dispatch. Transfopower is ISO 9001:2000 Certified Company. We believe in environmentally
friendly manufacturing.
The scope of all our certifications according to international standards is for the design
manufacture and sale of Distribution, Power, Furnace and Special transformers.
Since 2013, Transfopower Industries (Pvt) Ltd has stepped into the Energy Metering market
and has become one of the fastest growing Energy Meter Manufacturers in Pakistan. Our
products range from both conventional Single phase/Three Phase/CTO meters to Smart
Metering solutions offering state of the art features for meter data collection, data storage and
2
billing. Transfopower’s Energy Metering division caters for a range of Clients including
WAPDA and its distribution companies, AJK, K-Electric (formerly KESC) and for the private
sector. Due to total quality orientation Transfopower Industries (Pvt) Ltd has been achieving
customer satisfaction, catering to both the local and export markets. Transfopower Industries
(Pvt) Ltd is an ISO 9001:2008, ISO 14001:2004 and OHSAS 18001:2007 Certified Meter
Manufacturer.
Quality Policy
Presently, we are manufacturing Transformers from 5KVA to 5000KVA for WAPDA Area
Electricity Boards, KESC, AJK and the Private Sector like Housing Societies, Shopping
Plazas, Fuel Stations, Industries (Sugar, Textile, Cement, and Engineering etc.). Also Furnace
Transformers have been manufactured for STEEL MILLS in Pakistan and Africa.
To achieve this aim, the Management at Transfopower is committed to:
• Implement an effective management system for the continual improvement.
• Increasing our business and performance through excellent QHSE awareness.
• Conducting business in a manner that protects public, Environment, occupational health and
safety (prevention of injury & ill health) of employees.
• Striving to eliminate all accidents and incidents.
• Making QHSE consideration a priority in our business.
• Reducing emissions, wastes, energy and natural resources efficiently and intelligently.
• Complying with QHSE laws and regulations & other requirements.
3
4
Chapter 2
Training Work
2.1 Introduction of Transformer
Definition:
Electrical power transformer is a static device which transforms electrical energy from one
circuit to another without any direct electrical connection and with the help of mutual
induction between two windings. It transforms power from one circuit to another without
changing its frequency but may be in different voltage level.
Working of Transformer
6
The transformer is based on two principles: first, that an electric current can produce a
magnetic field (electromagnetism), and, second that a changing magnetic field within a coil of
wire induces a voltage across the ends of the coil . Changing the current in the primary coil
changes the magnetic flux that is developed. The changing magnetic flux induces a voltage in
the secondary coil.
Parts of transformer:
1) Steel tank
2) Core
3) Windings
4) Conservator
5) Breather
6) Thermometer
7) Pressure relief pipe
8) Valves
9) Buchholz relay
10) Bushings
11) Tap changing switch
12) Oil gauge
13) Radiator
14) Cooling fans
15) oil pumps
16) Transformer insulation
(1)Conservator
Conservator is a type of tank , used to help oil filling this is situated upper portion of the
power transformer . mainly these are cylindrically shaped.
2) Tank
Basically this is a container used to keep windings(both) and cooling oil.
3) Buchholz Relay
This is a protecting device used to protect our transformer windings . this is a double ended
device one end is connect to conservator other is connected to tank. there are two windings
inside the relay one for detecting oil level gain to empty and other is connected to a alarm
7
circuit for warning.
4) Breather
Breather is a device used for absorb the moisture content of a oil and sucked air
5) Silica jell
It is a chemical material these are the only one main component inside the breather basically
silica jell is a brown colour one after the absorbtion silica jel become pink.
6) Oil level scale
This is a ordinary part situated on the side of the conservator for proper oil checking oil tank
wants a specific amount of oil
7) Primary winding
In the case of power transmission primary windings are the main element external
connection from the power is connected to winding
8) Secondary winding
This is a another winding for reducing power(in the case of step down purpose)
9) Drain valve
This valve is used for taking damaged oil from the oil tank for the proper oil collection this
valve is situated under the oil tank.
10) Purceline bush
This is a outer unit , this is used to prevent unwanted leakage of electricity
11) Radiator
This device is used to cooling oil.
8
Following sections are included in manufacturing transformers.
1. Designing
2. Quality control
3. Windings
4. Cores
5. Assemble Testing
Objectives
In this section , I have studied how to test different materials used in making transformer.
Materials include enameled copper wire, paper insulated copper strip , round and flat copper
bus bars, copper sheet, mild steel material, hardware materials and rubbers material.
Magnet wire or enameled wire is a copper coated with a very thin layer of insulation. It is used
in the construction of transformers, inductors, motors, speakers, hard disk head actuators,
electromagnets, and other applications that require tight coils of insulated wire.Copper is used
because it has a low electrical resistance. This means that it is easy for the current to flow
through it. Also, copper wire can be easily shaped to make a coil.
9
Work Instruction
1)Take the sample of 1000 mm of all copper reels and label the serial numbers on
each copper wire and reels with stickers.
2)Remove the enamel from each wire (about 3 to 4 inches from ends) with help of
sulfuric acid (H2SO4) or by burning.
3)Measure the insulated enamel wire size and copper bare size.
4)Calculate the standard resistance* at room temperature.
Rs = pl/A*235+Temp/235+20 ( p= 0.0172, A=3.14 d^2/4 )
5)Measure the resistance of enamel copper wire with Ohm Meter.
6)Check the difference between measured and standard resistance.
7)The difference should be with in tolerance (max +1%).
8)Make the sample of twisted enamel wire for high voltage test.
9)The twisted area should be 125 mm and number of turns* & break down voltage*(BDV)
should be according to copper bare size.
Table 2.1: BDV procedure of enamel wire
Sr.No Size Turns BDV
1 0.11 mm – 0.25 mm 32 1.7KV
2 0.25 mm – 0.35 mm 28 2.0KV
3 0.35 mm – 0.51 mm 16 2.8KV
4 0.51 mm – 0.75 mm 12 3.2KV
5 0.75 mm – 1.05 mm 8 4.0KV
6 1.05 mm – 1.50 mm 6 4.3KV
7 1.50 mm – 2.15 mm 4 4.4KV
8 2.15 mm – 2.50 mm 3 5.0KV
Equipments Used
Mili Ohm Meter
Digital Micro meter
High Voltage Transformer (0 – 15 kV)
Thermometer
10
Heat Shock Test
This test is used to check the quality of enamel on enamel copper wire. The sample prepared
for the mandrill test is placed in electric oven at temperature 155 Co to 166 Co for ½ hour and
again mandrill test will be performed for test compliance.
11
Weight = area * copper density (d=8.9 g/cm^3) , Aw = weight/density
8)Check the difference between measured and standard area.
The difference should be with in tolerance (max +4 %).
9)Calculate the standard resistance* at room temperature.
Rs = pl/A*235+temp/235+20
10) Measure the resistance of PI Copper Strip with Ohm Meter.
11)Check the difference between measured and standard resistance.
12)The difference should be with in tolerance (max +1%).
* The edge factor according to thickness
0.00 mm to 1.70 mm => 0.1 mm
1.71 mm to 3.99 mm => 0.3 mm
4.00 mm to above => 0.9 mm
Equipments Used:
Micro Ohm Meter
Digital Micro meter
Digital Vernier Calliper
Digital Weighing Scale
Thermometer
12
Work Instructions:
13
Work Instructions:1)Check the MS material (Sheet, Angle, Channel, Flat& Elliptical
Tubes) physically.
6) Place the sample under diamond cone (hardened steel ball indenter) on Rockwell
Hardness Tester and set it at 60 N with zero setting.
7)Rotate the round lever until the big needle complete three rotations.
8)Make sure that the small needle should not cross the red mark.
9)Pull the loading lever and release it and wait for stability of big needle.
Equipments Used
Digital Micro meter
Digital Vernier Calliper
Rockwell Hardness Tester
Equipments Used:
Di – Electric Tester
14
Electric Cutter
Digital Vernier Caliper
Work Instructions:
1)Check all the rubber material (Gasket, Ring Washers and Round Washer) physically.
2) Check the entire Dimensions according to specific drawings.
3) Burn the rubber material and it should extinguish itself after burning.
4) Wound the enamel copper wire on rubber material and burn it, the Green flame should be
observed.
5) Crush the rubber material into pieces for Chemical Test.
6) Drop the crushed rubber material in Hydrochloric Acid (HCL), the pungent smell should
be observed.
7)Drop the crushed rubber material in Nitric Acid (HNO3) and boil it, brown smoke should
be observed.
8) Check the Hardness of rubber material with shore Durometer (60 – 90).
9)Take a sample of rubber material and check its weight for Change in Mass Test.
10) Dip that sample of rubber material in mineral oil and place it in the furnace for 72 hours at
temperature of 110o C. %E = Fw-Iw/Iw*100
11)Check the difference in mass that should be in accepted tolerance (-5% to +15%)
12)Crush the rubber material and check its mass for Specific Gravity Test.
13)Drop the crushed rubber material in water filled jar and check the water volume difference.
14)Multiply that difference with factor 1.15 and 1.35 to determine the required accepted
weight range.
15)The weight of rubber material should be with in calculated range.
15
2.2.7 Insulating Varnish
Work Instruction:
1) Make the box tray of size 1 ½ x 1 ½ inch with press pan paper (0.1 mm thickness).
2)Take the samples of Insulating Varnish from each can (canister) and put in the trays.
3)Fill the trays with entire varnish samples up to 5mm.
4)Put the varnish filled trays in furnace for 24 hours at temperature of 120 °C.
5)Take the trays out from furnace and wait for cool them down to normal temperature.
6)The varnish should be flexible, it should not be breakable.
7)The varnish should be completely dried.
Equipments Used:
Thermostatic Electric Furnace
Digital Vernier Caliper
16
2.2.8 Hardware Material
Bushing
Fuse clamp
Tap changer
17
Work Instructions:
Check the following hardware material physically:
MS, SS and Brass Nut, Bolt & Washers (Spring & Round)
Check entire dimensions of all hardware material according to specific drawings.
Perform High Voltage Test to check Break Down Voltage of following material:
Press Pan Papers, HT Insulating Tubes, HT Insulator, Arc Stranglers
Equipments Used:
High Voltage Transformer
Digital Varnier Caliper
Digital Micro Meter
18
2.2.9 Method of Testing Panel Box According To
Drawing & Specification
1. Check the length of panel frame.
2. Check the width of panel frame.
3. Check the Height of panel frame.
4. Check the distance of roof to body.
5. Check the door gaps.
6. Check the size of L.T Compartment side.
7. Check the C2C distance b/w base plate angle.
8. Check the length of base plate angle.
9. Check the size of fitting accessories.
10. Check the distance between foundation supports.
11. Check the door alignment.
12. Make report and get it signed By GM Works/S.E.D.
3. Check the Height, length and width of tank body from inner side.
19
13. Check the distance between stiffeners.
In the winding section L.V and H.V windings of the coil are made.
Raw Material
For LV winding:
(2)Copper foil
For HV winding:
(2)Paper insulated flat copper wire (usually for 400KVA and above)
Types of Windings:
(1)Disc winding
(2)Packet winding
(3)Layer winding
(4)Foil winding
Foil and layer windings are usually used in LV. Layer, packet and disc winding is usually used
in HV. HV winding is done over LV winding, both are insulated from each other. Connections
are made from start and end in LV and HV winding. But in HV we give taping connection at
different places according to design. On HV winding we used paper to insulate it from tank.
20
Oil is also used for this purpose. Winding turns are according to design. At the end of this
section testing of winding is done using transformer turns ratio (TTR) meter which gives no. of
turns. we check it according to design
Machines Used:
Slitting machine
LV Foil winding machines are used for foil winding on L.V side for transformers of the rating
100KVA and above.
LV paper insulated copper winders are used for winding of P.I copper wire for transformers of
the rating 10KVA to 50KVA.
HV paper insulated copper winders are used for the winding of P.I copper wire for
transformers of the rating 400KVA and above.
HV enamel copper winders are used for the winding of enamel copper wire for the transformer
of the rating 10KVA to 400KVA.
Sr.No Voltages
1 11275
2 11000 (principle tap)
3 10725
4 10450
5 10175
21
2.4 Transformer Core Section
In the core section upper, center, side and yoke limbs of the core are made.
22
Table 2.4: Core stacking for 25 KVA
Sr.No Side limb size(mm) Center limb size(mm) Yoke size (mm)
W L NOS W L NOS W L NOS
1 30 285 104 30 245 52 30 440 104
2 55 310 104 55 To 52 55 465 104
3 70 325 160 70 255 80 70 480 160
4 85 340 176 85 88 85 495 176
5 95 350 300 95 150 95 505 300
Raw Material
Raw material used for the making of core is M4 grade silicone steel sheet which is an alloy
Machines
Slitting machine is used to cut the big roll of silicon steel sheet in required sizes
Power press machines are used to make limbs. They are operated manually.
After cutting of limbs V punching is done on the yoke limb which is called yoke
notching.
PLC cutting machines are also used to make limbs. There are two PLC machines.
Iron Losses
Iron losses are the flux losses in core. Major factors in iron losses are;
Quality of material.
Bur.
Air gap.
Reduce iron losses
23
Limbs should be rust free.
After cutting of the limbs, they are stacked in a way that there is no air gap between the limbs.
All the limbs are joined except the upper yoke limb which is filled in the assembly section.
Outer side of the core is varnished to avoid rusting. Core is tightened using upper and lower
pressing beams. Then its goes to assembly section.
Frame
Cover plate
Bottom
Side plate
Fin Walls
Conservator
Raw Material:
Raw material for tank and other components are
Shearing Machine
Shearing machine is used to cut the MS sheet in different sizes. This machine is used for the
cutting of frame, side wall, bottom wall and cover plate.
CNC Nibbling and Punching Machine
CNC nibbling and punching machine has 32 tools to make holes of different size. It can make
holes of the shape round, square, rectangle.
Bending Machine
This machine is used to bend cover plate and frame.
Embossing Machine
This machine is used for the embossing of holes on cover plate.
Component Welding
In this area lifting lugs, carrying beams and studs are welded using arc welding.
Frame Punching and Welding Machine
Frame is punched and then welded in this machine.MIG welding is used in this machine.
24
Fin Folding Machine
This machine is used for fin folding. Digital control panel is used to enter height, weight and
pitch. Pitch is the distance between two adjacent fins.
Fin Welding
After fin folding they are welded. MIG welding is used in this machine.
Automatic Fin Welding Machine
MIG welding is used in this machine. Metal strip is welded to support the panel.
Bottom Side Plate Welding
In this section bottom and side plates are welded together.
Tank Assembly
Here all the parts of the tank are joint together.
Tank Welding
Tank is welded to stop leakage.
Shot Blasting
To remove oil particles from tanks body and make its surface smooth shot blasting is done.
After that tank is dipped in degreasing, rinsing and phosphate tank to remove oil particles.
Sand Blasting
It is used for removal of oil particles from tanks make its surface smooth for transformer
rating above 200KVA.
Tank Testing
For tanks up to 200KVA diesel spray testing is used.
Above 200KVA pressure testing is used to check leakage.
Powder Coating
Tank is first passed through a chamber for pre treatment and then powder coating is done.Tank
is painted with machines at end
25
2.6 Transformer Assembly Section
In the assembly section there are 17 processes in which all the components of the
transformer are put together to form a transformer. Important processes in the assembly
section are;
In the core coil assembly coil is fitted in the core and upper yoke limb is inserted to
complete the core, then core is tightened using upper and lower pressing beams. For
coil to coil insulation and core to coil insulation press pan sheet is used. For insulation
In the BCT area turns ratio of the coil is checked using TTR meter.
In this section Y-Delta connections are made. Tap changer is connected with the coil.
26
Connections are made according to work order specifications given by the design
In the ACT area turns ratio of the transformer is checked using TTR meter.
Furnace
After ACT transformer is kept in the furnace for 48 to 72 hours according to its rating. It
is done to evaporate all the moisture from core or coil. Temperature of the furnace is 120 to
130.
In this section H.T, L.T bushings, through bolts, eye bolts connectors, arcing horns and
When transformer is unloaded from the furnace it is inserted in the tank as quickly as
possible to avoid the getting of moisture in the live part. Live part of the transformer
27
can be installed in places that do not have room for a fenced enclosure. Padmount transformers
are used with underground electric power distribution lines at service drops, to step down the
primary voltage on the line to the lower secondary voltage supplied to utility customers. A
single transformer may serve one large building, or many homes.
Pad-mounted transformers are made in power ratings from around 75 to around 5000 kVA and
often include built-in fuses and switches. Primary power cables may be connected with elbow
connectors, which can be operated when energized using a hot stick and allows for flexibility
in repair and maintenance.
28
Pad mounted transformer:
Main components of this unit are medium voltage switchgear arranged to function as a Ring
Main Unit (2- TP disconnect switches and 1-fused T-off), transformer, LV Switchgear and
control gear, corresponding interconnections and auxiliary equipment .Enclosure is made of 2-
3 mm sheet steel. These sub-stations are manufactured for outdoor use, suitable for mounting
on a concrete pad. Door interlocks and other safety features are inherent part of the design.
These compact substations are used in distribution centers and industrial installations having
underground cabling.
29
Chapter 3
Skill Attaining
30
31
3.1:Transformer Testing
Purpose :
This test method is used to measure the rated turn ratio of the transformer.
Testing Equipment:
Operational Steps:
Connect the HV side leads to the HT side of transformer under testing accordingly i.e.
H1 to red phase , H2 to yellow phase and H3 to blue phase.
Connect the LV side leads to the LT side of transformer under testing accordingly i.e.
X1 to red phase, X2 to yellow phase, X3 to blue phase and X0 to Neutral.
32
Select the phase configuration of transformer (star and delta configuration) and start the
test.
Note down the voltage ratio from screen for 3 phase voltage ratio of transformer.
33
3.1.2: Mugger test procedure
Let’s take 100KVA transformer as an example as shown in figure For normal working
transformer, both windings must be electrically isolated from each other and from ground. So
Mugger test is done to check
To check the insulation level between HV and LV winding, put one terminal on HV winding
and one on LV winding. Apply the correct value of voltage (voltage values shown in above
table) and check the reading of the megger. Megger test equipment will show resistance
between the HV and LV winding. The value of resistance will show the insulation strength
between HV and LV winding.
Safety precaution:
Testing yard should be properly cordoned off and warming light should be on during
testing.
Make sure the transformer under testing is on floor / ground.
Use HV safety cloves when handling and connecting the power line and earth wire to the
transformer.
Make sure the distance of at least 15 feet from transformer under testing.
34
Do not touch connection leads, earth wire and transformer connection and body during
testing.
Make sure no body should not be entered in testing area / yard during testing.
Purpose:
This test used to measure the resistance of primary winding and secondary winding of
the transformer.
Testing Equipment:
Ohm meter.
Operational Steps:
Connect the red, yellow, blue phase of HT winding of under testing transformer with
leads of winding ohm meter accordingly i.e. RY, YB, BR.
Note the reading of winding ohm meter when readings become stable for measurement
of HT winding resistance of subjected transformer.
Connect the red, yellow, blue phase of LT winding with neutral phase of under testing
transformer with leads of winding ohm meter accordingly i.e. rn, yn, bn.
Note the reading from winding ohm meter when reading become stable for
measurement of LT winding resistance of subjected transformer.
35
3.1.4:Load losses (Copper losses) test
Purpose:
This test is used to measure the load losses is called short circuit test.
Testing equipment:
Operational steps:
1) Short the LT side of transformer under testing with copper bus bar.
2) Connect the leads of 3 power phase supply to HT side.
3) Apply the 3 phase power supply at rated frequency (50 HZ) and allow the rated current to 4)
flow in HT side of transformer under testing .
5) Get reading of absorbed active power in 3 phase (W1, W2, W3) from the power analyzer
meter .
6) This losses should be nearly same.
7) Tolerance should be +5%.
Safety precaution:
1)Testing yard should be properly cordoned OFF and warming should be ON during test.
2)Make sure the transformer under testing is on floor /ground.
3)Make sure equipment using for testing is properly ground by using earth wire .
4)Make sure the distance of at least 15 feet from transformer under testing.
5)Do not touch the connection leads, earth wires, transformer connector and body during
testing.
36
Apply the 3 phase rated voltage ( 415v for WAPDA & 420v for K-Electric) at rated
frequency (50Hz) on LT side of transformer under testing.
Get reading of absorbed active power in 3 phase (W1, W2, W3) from the reference
equipment(power quality analyzer, AC power analyzer).
Take algebraic sumof 3 reading that give measurement of no load losses for transformer
under testing.
Take the average of three reading that give measurement of no load losses.
Safety Precautions:
Testing yard should be properly cordoned off and warming light should be on during
testing.
Make sure the transformer under testing is on floor or ground.
Make sure the equipment using for testing is properly ground by using earth wire.
Do not touch the connection leads, earth wire and transformer connector and body during
testing.
38
Table 3.3: Pressure Test procedure
KVA rating Pressure rating(PSI) Time(hours)
25 1 8
50 1 8
100 1 8
200 1 8
250 1 8
400 10 8
630 10 8
1000 15 8
Visual Inspection
Specific Gravity
Viscosity
Flash Point
Dielectric Strength
Acidity Value
Pour Point
a)Visual Inspection
It should be free from contamination as per IEC-296 and IEC-60296recommendations.
b)Viscosity
Viscosity meter is used for this test. Reading is taken at two different temperatures. AT -20 Co
reading should be less than 40mm 2
/sec and at 40 Co reading should be less than12mm 2/sec as per IEC-296 and IEC-60296
specifications.
c)Specific Gravity
Specific gravity meter is used for this test. Reading is taken at -30 Co Before
use specific gravity of oil should be less than .895 g/mil. After use reading should be less
than .895g/mil as per IEC-269 and IEC-60296 recommendations.
39
d)Flash Point
The point at which the oil catches fire is known as flash point. Flash point of transformer oil
should be greater than 140 Co
as per new recommendation of IEC in IEC-60296.
e)Dielectric Strength Test
Dielectric strength tester is used for this test. Oil is filled in a box which has electrode switch
are 2.5mm apart. Voltage is applied to the box which increases at the rate of 2kvper sec.
Reading is taken at point where breakdown has occurred. Seven readings are taken and their
arithmetic mean is the breakdown voltage. Oil which is purchased should have dielectric
strength greater than 30kv. When oil is stored and all the moisture and impurities are removed
than its strength should be greater than 70kv. For the oil which is used reading should not be
less than 55kv. All these values are according to the recommendations of IEC mentioned in
IEC-60296.
f)Acidity Value
Acidity value meter is used for this test. For unused oil reading of meter should be less
g)Pour Point
The point at which oil freezes is known as pour point. Oil should not freeze before -30 Co
to pass this test.
40
4. Insulation resistance measure between core to core than L terminal connected one side of
core and other connected with other side of core and applies voltage and note reading.
5. When the measure the insulation resistance than L terminal connected with primary and E
with secondary and apply voltage and measure reading at scale.
41
Chapter 4
Feedback&
Recommendations
42
4.1: Conclusion
In conclusion, I am well satisfied on our training in Transfopower and PEL industries. I have
learned new technical subjects and very new technical skills. It is very strongly related to my
academic through this increase my theoretical skill into practical skill. Inside the university, I
learned details about electrical appliances but not see in physical form but in training period I
saw all appliances in physical form and learned how it is operate and work. I may count our
technical skill learned and improved at training site are following:
2. The main component of Transfopower industries is power Transformer and electric panel.
I learned inside university about transformer at theoretical biases but at training site I learned
actual function of transformer and physical structure of power transformer.
3. Protection devices used for provide protection to system, this system is helpful for me how it
is protect all electrical system or in live form.
4. Through tests increase my testing skill, inside university labs, I performed small test but at
training site performed all types of test conduct at installed equipment.
5. Annul test conduct at control room relays, these relay sense fault occur in circuit and out of
circuit. If any relay fail then system under dangerous condition.
6. Inside University learned function and working of relays but at training site physical
function of relay and how it is operates and how trip the circuits.
7. Trip circuit of relays are operate at DC supply therefore, design DC supply structure it
contains at several units of batteries that connected in series. If DC supply fails than all
protection system faulty condition.
It is so good to acquire such a large number skills in 4 month of training period. So training
in132kv Grid Station is very valuable.
43
4.2: Recommendation
Recommendation which tell how many step takes university in labs that helpful for internship
students. It is contains at following steps;
1. I’m done sixteen week internship in Transfopower industries. We know main equipment
here power transformer and electric panel it has many other accessories to perform good
function. I give here recommendation, the university arranged transformer labs which student
learned and physical see firstly transformer structure and other accessories that attached with
transformer and how worked therefore, save time in training period and learned extra technical
skills.
3. Control system is a complex and important part of any firm. Where control and monitor
whole system it is contains at panels. These are panel has switches, relays and measuring
instruments. So control main part of any firm one lab design related to control circuit where
student learn how control circuit construct and operate.
4. When the students move for internship it is short time to learned about firm. Inside grid
station mostly equipment high voltage. At internship site we are not see internal structure of
equipment therefore it is unauthorized. While the annual shutdown occurs at this time only test
and maintenance performed at installed appliances not it’s open. So learned about internal
circuit of instrument, appliances and equipment design labs where student by self-open
equipment and see internal circuit and reassemble. Through this student skills increase very
much and will not any problem come inside at internship site.
However, valuable benefit I gained from training at Transfopower industries lets my overall
evaluation of training there be very good. So I’m learned and enjoy training period at
Transfopower industries. It is very helpful to increase my all technical and non-technical
skills.
44
4.3: References
https://www.emworks.com/application/3-phase-transformer
https://www.electronics-tutorials.ws/transformer/three-phase-transformer.html
https://www.electricaleasy.com/2014/05/three-phase-transformer-connections.html
electrical-engineering-portal.comt
https://www.electrical4u.com/transformer-cooling-system-and-method
http://electrical-engineering-portal.com/power-transformer-turns-ratio-t
www.ganpatielectricals.com/electric-panels.html
www.voltaicpower.in/products/lt-panels-ht-panels
www.inspection-for-industry.com/power-transformer-testing.html
44
45