Operational Manual BP 4.12 - Involuntary Resettlement: Staff Connections - World Bank Intranet
Operational Manual BP 4.12 - Involuntary Resettlement: Staff Connections - World Bank Intranet
12 - Involuntary Resettlement
Operational Manual
1. The planning of resettlement activities is an integral part of preparation for Bank-assisted1 projects that cause
involuntary resettlement.2 During project identification, the task team (TT) identifies any potential involuntary
resettlement under the project. Throughout project processing, the TT consults and seeks the advice of the
regional social development unit,3 Legal Vice Presidency (LEG) and, as necessary, the Resettlement Committee
(see para. 7 of this BP).
2. When a proposed project is likely to involve involuntary resettlement, the TT informs the borrower of the
provisions of OP/BP 4.12. The TT and borrower staff
b. explore all viable alternative project designs to avoid, where feasible, or minimize displacement;4
c. assess the legal framework covering resettlement and the policies of the government and implementing
agencies (identifying any inconsistencies between such policies and the Bank's policy);
d. review past borrower and likely implementing agencies' experience with similar operations;
e. discuss with the agencies responsible for resettlement the policies and institutional, legal, and
consultative arrangements for resettlement, including measures to address any inconsistencies between
government or implementing agency policies and Bank policy; and
f. discuss any technical assistance to be provided to the borrower (see OP 4.12, para. 32).
3. Based on the review of relevant resettlement issues, the TT agrees with the Regional social development unit
and LEG on the type of resettlement instrument (resettlement plan, abbreviated resettlement plan, resettlement
policy framework, or process framework) and the scope and the level of detail required. The TT conveys these
decisions to the borrower and also discusses with the borrower the actions necessary to prepare the resettlement
instrument,5 agrees on the timing for preparing the resettlement instrument, and monitors progress.
4. The TT summarizes in the Project Concept Note (PCN) and the Project Information Document (PID) available
information on the nature and magnitude of displacement and the resettlement instrument to be used, and the TT
periodically updates the PID as project planning proceeds.
5. For projects with impacts under para. 3 (a) of OP 4.12 the TT assesses the following during project preparation:
a. the extent to which project design alternatives and options to minimize and mitigate involuntary
resettlement have been considered;
b. progress in preparing the resettlement plan or resettlement policy framework and its adequacy with
respect to OP 4.12, including the involvement of affected groups and the extent to which the views of such
groups are being considered;
c. proposed criteria for eligibility of displaced persons for compensation and other resettlement assistance;
d. the feasibility of the proposed resettlement measures, including provisions for sites if needed; funding for
all resettlement activities, including provision of counterpart funding on an annual basis; the legal
framework; and implementation and monitoring arrangements; and
e. if sufficient land is not available in projects involving displaced persons whose livelihoods are land-based
and for whom a land-based resettlement strategy is the preferred option, the evidence of lack of adequate
land (OP 4.12, para. 11).
6. For projects with impacts under para. 3 (b) of OP 4.12, the TT assesses the following during project preparation:
a. the extent to which project design alternatives and options to minimize and mitigate involuntary
resettlement have been considered; and
b. progress in preparing the process framework and its adequacy in respect to OP 4.12, including the
adequacy of the proposed participatory approach; criteria for eligibility of displaced persons; funding for
resettlement; the legal framework; and implementation and monitoring arrangements.
7. The TT may request a meeting with the Resettlement Committee to obtain endorsement of, or guidance on, (a)
the manner in which it proposes to address resettlement issues in a project, or (b) clarifications on the application
and scope of this policy. The Committee, chaired by the vice president responsible for resettlement, includes the
Director, Social Development Department, a representative from LEG, and two representatives from Operations,
one of whom is from the sector of the project being discussed. The Committee is guided by the policy and, among
other sources, the Involuntary Resettlement Sourcebook, which reflects good practice.
Appraisal
8. The borrower submits to the Bank a resettlement plan, a resettlement policy framework, or a process framework
that conform with the requirements of OP 4.12, as a condition of appraisal for projects involving involuntary
resettlement (see OP 4.12, paras. 17-31). Appraisal may be authorized before the plan is completed in highly
unusual circumstances (such as emergency operations) with the approval of the Managing Director in consultation
with the Resettlement Committee. In such cases, the TT agrees with the borrower on a timetable for preparing and
furnishing to the Bank the relevant resettlement instrument that conforms with the requirements of OP 4.12.
9. Once the borrower officially transmits the draft resettlement instrument to the Bank, Bank staff--including the
Regional resettlement specialists--review it, determine whether it provides an adequate basis for project appraisal,
and advise the Regional sector management accordingly. The lawyer reviews the legal aspects of the draft
resettlement instrument and other specific items brought to the lawyer’s attention by the TT, and provides
advice to help the TT and Regional resettlement specialists determine whether those aspects provide an
adequate basis for appraisal. Once approval for appraisal has been granted by the Country Director, the TT
sends the draft resettlement instrument to the Bank's InfoShop.6 The TT also prepares and sends the English
language executive summary of the draft resettlement instrument to the Corporate Secretariat, under cover of a
transmittal memorandum confirming that the executive summary and the draft resettlement instrument are subject
to change during appraisal.
10. During project appraisal, the TT assesses (a) the borrower's commitment to and capacity for implementing the
resettlement instrument; (b) the feasibility of the proposed measures for improvement or restoration of livelihoods
and standards of living; (c) availability of adequate counterpart funds for resettlement activities; (d) significant risks,
including risk of impoverishment, from inadequate implementation of the resettlement instrument; (e) consistency of
the proposed resettlement instrument with the Project Implementation Plan; and (f) the adequacy of arrangements
for internal, and if considered appropriate by the TT, independent monitoring and evaluation of the implementation
of the resettlement instrument.7 The TT obtains the concurrence of the Regional social development unit to any
changes to the draft resettlement instrument during project appraisal. For changes made to the legal aspects of
the draft resettlement instrument and specific items brought to LEG's attention, the lawyer will review and
provide advice to the TT and Regional resettlement specialists. Appraisal is complete only when the borrower
officially transmits to the Bank the final draft resettlement instrument conforming to Bank policy (OP 4.12).
11. In the Project Appraisal Document (PAD), the TT describes the resettlement issues, proposed resettlement
instrument and measures, and the borrower's commitment to and institutional and financial capacity for
implementing the resettlement instrument. The TT also discusses in the PAD the feasibility of the proposed
resettlement measures and the risks associated with resettlement implementation. In the annex to the PAD, the TT
summarizes the resettlement provisions, covering, inter alia, basic information on affected populations,
resettlement measures, institutional arrangements, timetable, budget, including adequate and timely provision of
counterpart funds, and performance monitoring indicators. The PAD annex shows the overall cost of resettlement
as a distinct part of project costs.
12. The project description in the Loan Agreement describes the resettlement component or subcomponent. The
legal agreements provide for the borrower's obligation to carry out the relevant resettlement instrument and keep
the Bank informed of project implementation progress.8 At negotiations, the borrower and the Bank agree on the
resettlement plan or resettlement policy framework or process framework. Before presenting the project to the
Board, the TT confirms that the responsible authority of the borrower and any implementation agency have
provided final approval of the relevant resettlement instrument.
Compensation
13. Where the borrower has offered to pay compensation to an affected person in accordance with an approved
resettlement plan, but the offer has been rejected, the taking of land and related assets may only proceed if the
borrower has deposited funds equal to the amount offered as compensation plus 10 percent in a secure form of
escrow or other interest-bearing deposit satisfying the Bank’s fiduciary requirements. The borrower must also
provide a means satisfactory to the Bank for resolving the dispute concerning the offer of compensation in a timely
and equitable manner.
Supervision
14. Recognizing the importance of close and frequent supervision9 to good resettlement outcomes, the Regional
vice president, in coordination with the relevant country director, ensures that appropriate measures are
established for the effective supervision of projects with involuntary resettlement. For this purpose, the country
director allocates dedicated funds to adequately supervise resettlement, taking into account the magnitude and
complexity of the resettlement component or subcomponent and the need to involve the requisite social, financial,
legal, and technical experts. Supervision should be carried out with due regard to the Regional Action Plan for
Resettlement Supervision.10
15. Throughout project implementation the TL supervises the implementation of the resettlement instrument
ensuring that the requisite social, financial, legal, and technical experts are included in supervision missions.
Supervision focuses on compliance with the legal instruments, including the Project Implementation Plan and the
resettlement instrument, and the TT discusses any deviation from the agreed instruments with the borrower and
reports it to Regional Management for prompt corrective action. The TT regularly reviews the internal, and where
applicable, independent monitoring reports to ensure that the findings and recommendations of the monitoring
exercise are being incorporated in project implementation. To facilitate a timely response to problems or
opportunities that may arise with respect to resettlement, the TT reviews project resettlement planning and
implementation during the early stages of project implementation. On the basis of the findings of this review, the TT
engages the borrower in discussing and, if necessary, amending the relevant resettlement instrument to achieve
the objectives of this policy.
16. For projects with impacts covered under para. 3(b) of OP 4.12, the TT assesses the plan of action to determine
the feasibility of the measures to assist the displaced persons to improve (or at least restore in real terms to pre-
project or pre-displacement levels, whichever is higher) their livelihoods with due regard to the sustainability of the
natural resource, and accordingly informs the Regional Management, the Regional social development unit, and
LEG. The TL makes the plan of action available to the public through the InfoShop.
17. A project is not considered complete--and Bank supervision continues--until the resettlement measures set out
in the relevant resettlement instrument have been implemented. Upon completion of the project, the
Implementation Completion and Results Report (ICR)11 valuates the achievement of the objectives of the
resettlement instrument and lessons for future operations and summarizes the findings of the borrower's
assessment referred to in OP 4.12, para. 24.12 If the evaluation suggests that the objectives of the resettlement
instrument may not be realized, the ICR assesses the appropriateness of the resettlement measures and may
propose a future course of action, including, as appropriate, continued supervision by the Bank.
In countries with a series of operations requiring resettlement, the ongoing country and sector
dialogue with the government should include any issues pertaining to the country's policy,
institutional, and legal framework for resettlement. Bank staff should reflect these issues in country
economic and sector work and in the Country Assistance Strategy
1. "Bank" includes IBRD and IDA ; "loans" includes IDA credits and IDA grants, guarantee made by the Bank , including Project
Preparation Facility (PPF) advances and grants under the Institutional Development Fund (IDF) if they include investment
activities; and "project" includes any project supported by under (a) Investment Project Financing under OP 10.00, Investment
Project Financing; (b) grants under the Global Environment Facility and Montreal Protocol for which the Bank is the
implementing/executing agency; and (c) grants or loans provided by other donors that are administered by the Bank. The term
"project" does not include a program supported by Development Policy Lending (for which social aspects are governed by OP
8.60, Development Policy Lending), or a program supported by Program-for-Results Financing (for which social aspects are
governed by OP 9.00, Program-for-Results Financing). Borrower" also includes, wherever the context requires, the guarantor or
the project implementing agency.
2. See OP 4.12, Involuntary Resettlement.
3. Unit or department in the Region responsible for resettlement issues.
4. The Bank satisfies itself that the borrower has explored all viable alternative project designs to avoid involuntary resettlement and,
when it is not feasible to avoid such resettlement, to minimize the scale and impacts of resettlement (for example, realignment of
roads or reduction in dam height may reduce resettlement needs). Such alternative designs should be consistent with other Bank
policies.
5. Such actions may include, for example, developing procedures for establishing eligibility for resettlement assistance; conducting
socioeconomic surveys and legal analyses; carrying out public consultation; identifying resettlement sites; evaluating options for
improvement or restoration of livelihoods and standards of living; or, in the case of highly risky or contentious projects, engaging
a panel of independent, internationally recognized resettlement specialists.
6. See The World Bank Policy on Access to Information, para. 34 (Washington, D.C.: World Bank, 2002).
7. For projects with impacts covered under para. 3 (b) of OP 4.12, the analysis referred to in (b) and (d) above is carried out when
the plan of action is furnished to the Bank (see para. 15 of this BP).
8. In case of resettlement policy framework, the borrower's obligation also includes preparing a resettlement plan in accordance with
the framework, for each sub-project giving rise to displacement, and furnishing it to be the Bank for approval prior to
implementation of the sub-project.
9. See OP/BP 10.00, Investment Project Financing.
10. The Plan is prepared by the regional social development unit in consultation with the TTs and Legal.
11. See OP/BP 10.00, Investment Project Financing.
12. The ICR's assessment of the extent to which resettlement objectives were realized is normally based on a socioeconomic survey
of affected people conducted at the time of project completion, and takes into account the extent of displacement, and the impact
of the project on the livelihoods of displaced persons and any host communities.
Help • Feedback • Site Map • Publishing Guidelines • IFC • MIGA • IDA • ICSID • WB External Site