Guideandreqforservice r4
Guideandreqforservice r4
R 0.2
September - 2011
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
Disclaimer
The Load Customer, its employees or agents must recognize that they are, at all times,
solely responsible for their plant design, construction and operation. Neither BC Hydro
nor any of its employees or agents shall be, nor become, the agents of the Load Customer
in any manner whatsoever rising.
BC Hydro’s review of the specifications and detailed plans shall not be construed as
confirming or endorsing the design or as warranting the safety, durability or reliability of
the Load Customer’s facilities. BC Hydro, by reason of such review or lack of review,
shall be responsible for neither the strength, adequacy of design or capacity of equipment
built pursuant to such specifications, nor shall BC Hydro, or any of its employees or
agents, be responsible for any injury to the public or workers resulting from the failure of
the Load Customers facilities.
In general, the advice by BC Hydro, any of its employees or agents, that the Load
Customer’s plant design or equipment meet certain limited requirements of BC Hydro
does not mean, expressly or by implication, that all or any of the requirements of the law
or other good engineering practices have been met by the Load Customer in its plant, and
such judgment shall not be construed by the Load Customer or others as an endorsement
of the design or as a warranty, by BC Hydro, or any of its employees.
The information contained in this document is subject to change and may be revised at
any time. BC Hydro should be consulted in case of doubt on the current application of
any item.
1
NERC/WECC Planning Standards”, Western Electricity Coordinating Council, revised April 10, 2003: Available at:
http://www.wecc.biz/documents/library/procedures/planning/WECC-NERC_Planning%20Standards_4-10-03.pdf.
September 2011 2
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
TABLE OF CONTENTS
September 2011 3
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
September 2011 4
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
APPENDICES
A - Guide & Requirements for Harmonic Control for Customers Supplied at a Voltage
level from 69 kV to 287 kV.
September 2011 5
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
1.1 Intent
September 2011 6
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
September 2011 7
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
For a description of the application process please refer to our website at:
http://transmission.bchydro.com/generator_interconnection/load_interconnections/
Get Connected
To enable BC Hydro to determine what supply facilities are required (for both new
and modified customer installations), the customer shall provide Transmission
Customer Services with the following information in the **Transmission Connection
Information Request Form:
Total connected load and electrical characteristics of the load, including
a list of major motors by size, type and starting characteristics.
Estimated maximum instantaneous and 30-minute average demand and
energy usage (initial and ultimate). Total connected Load and Load
factor.
Data on disturbance-producing equipment such as welders, solid state
switching semiconductors, arc furnaces and electric variable speed drives,
including information on the amount of local generation and intended use.
Service location with a full property description or Latitude and
Longitude.
Anticipated in-service date.
September 2011 8
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
September 2011 9
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
September 2011 10
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
September 2011 11
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
If the Customer wishes to proceed with the interconnection, they shall resubmit to the
Load Interconnections Group, the Transmission Connection Information Request
Form requesting a Preliminary (System Impact) Study Proposal. The Customer will
also submit documents listed in Items 1,2 & 4 of the checklist.
Once received, the Load Interconnections Group shall prepare a System Impact Study
Proposal. This Proposal shall outline the scope of technical studies required, their cost
and estimated time to deliver the System Impact Study.
The System Impact Study will not proceed until an agreement is signed and a
financial commitment is made by the customer. The System Impact Study will provide
the Customer a +100/ -50% estimate for the cost to design and build the Basic
Transmission Extension (BTE) at the Point of Interconnection (POI) and any BC
Hydro System Reinforcements required to support the Customer’s load.
In addition, the customer will receive a service application (form 70340) for
completion and delivery to B.C. Hydro. A copy of the form is contained in Appendix
A.
The customer should submit a formal application for a service at transmission voltage
September 2011 12
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
The customer's application shall include the following in electronic file (pdf format) :
September 2011 13
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
The site plan must show details of the primary electrical installation. The plan shall
show the location and orientation of the substation relative to the customer's plant
and, where feasible, the proposed transmission tap point.
The substation layout (plan and elevation) must show the general arrangement of
equipment including connections to the transmission line terminal structure and to
B.C. Hydro's metering transformer and duct route to the metering cubicle. See also
Section 4 for metering requirements.
September 2011 14
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
September 2011 15
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
September 2011 16
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
BC Hydro
September 2011 17
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
It will be necessary for customers to coordinate their station insulation with the
incoming transmission line insulation. At 230 kV and 287 kV it is BC Hydro's practice
to install overhead ground wires on transmission structures from the station out 500 m.
Customers may wish to use the same practice at their stations. The critical flashover
levels for standard BC Hydro line construction are as follows:
Critical
Nominal Flashover Voltage
Voltage (1.2 x 50µs wave +ve)
69 kV 525 kV
138 kV 860 kV
230 kV 1265 kV
287 kV 1345 kV
Note that in some cases lines may be insulated for higher levels than the level at which
they are energized.
In order to coordinate with the indicated levels, BC Hydro designs its stations as
follows:
69 kV Nominal
Normal Maximum 60 cycle voltage 72.5 kV
BIL All equipment 350 kV
138 kV Nominal
Normal Maximum 60 cycle voltage 145 kV
BIL Transformers 550 kV
Other Equipment 650 kV
230 kV Nominal
Normal Maximum 60 cycle voltage 253 kV
BIL Transformers 850 kV
Other Equipment 950 kV
287 kV Nominal
Normal Maximum 60 cycle voltage 315 kV
BIL Transformers 950 kV
Other Equipment 1050 kV
September 2011 18
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
The entire transmission system is effectively grounded, but the 69 and 138 kV systems
may become ungrounded at some locations, in which case surge arresters rated for
temporary ungrounded operation must be applied. The 230 kV system is almost always
grounded, but some customers connected to radial transmission lines may not be
grounded when separated from the BC Hydro Transmission system.
Surge arresters are recommended for protection of transformers. Where they are
applied, B.C. Hydro metering equipment shall be located close enough to the
surge arrester to be effectively protected.
The preferred location for surge arresters shall be as depicted in Fig. 1, page 22.
If this is not possible the surge arresters must at least be located on the load
side of the manual group operated load break disconnect.
b) Gang operated.
September 2011 19
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
Since the disconnect device is primarily provided for safety and cannot
normally interrupt load current, consideration shall be given as to the
capacity, procedures to open, and the location of the device.
Fuses, circuit breakers or circuit switchers used for fault clearing shall be
capable of interrupting the ultimate fault duty stated by BC Hydro at the
specific location as determined by BC Hydro.
Installations with in-house parallel generation shall have circuit breakers rated
to trip the capacitive load of the incoming supply line.
3.1.3 Transformers
BC Hydro will advise regarding the voltage range at which the customer's
transformers will be supplied. The specifics of each installation should be
discussed with BC Hydro.
September 2011 20
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
Unless the expected life of the installation is shorter, the design regarding
wind and ice storms should be based on a 40 year return period for lines 138
kV and below and a 100 year return period for lines 230 kV and above. Also,
outages due to conductor galloping should be negligible.
The equipment and station shall be grounded in accordance with the latest
Canadian Electrical Code. It is recommended that the ground grid be designed
based on the ultimate fault duty for the site. If not, the customer assumes the
responsibility for upgrading when necessary to accommodate changes to the
system. It is the customer’s responsibility to contact BC Hydro periodically if
they have designed the ground grid to less than the ultimate fault duty
specified by BC Hydro.
September 2011 21
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
(b) The customer's equipment shall be rated to carry and interrupt the
fault levels that are, or will be, available at its location, including
the ultimate fault currents specified by BC Hydro. Customer's
equipment includes those items listed in Subsection 3.1 "Equipment
Requirements" and all protection equipment forming the entrance
protection: current transformers, potential transformers, secondary
cabling, dc system/battery charger, switchboard wiring and
protective relays.
(d) Where protective relays are used as the entrance protection, the HV
interrupting device (i.e., circuit breaker) shall be included in the
entrance protection zone. That is, protective relays shall connect to
source side CT's on the HV interrupting device as shown in Fig. 1.
September 2011 22
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
Note: Where a circuit switcher is applied as the HV interrupting device, the CT's may
be located on the load side of the circuit switcher, provided that the B.C. Hydro
metering equipment is included in the entrance protection zone. Transformer bushing
CT's are therefore not acceptable for this application.
September 2011 23
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
The customer must provide equipment to prevent its generating plant from
energizing a de-energized BC Hydro transmission supply line and to promptly
remove contributions to faults on BC Hydro’s system. The type of equipment
required will depend upon which of three general categories the customer's
installation falls under. In addition to the protection requirements described
herein, requirements listed in Subsections 3.2.1, 3.2.3 and 3.2.4 are also
applicable.
BC Hydro may require the customer to shed load in the event of loss of
customer generation to ensure that the transmission system and/or other
customers are not adversely affected.
September 2011 24
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
For the arrangement shown in Fig. 2 the transfer switch must be a BC Hydro approved
device. For approval process and list of approved transfer switches, contact
Transmission Customer Services.
September 2011 25
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
B.C.H. METERING
CB1
LOAD BUS
CB3
CUSTOMER GENERATION
For the arrangement shown in Fig. 3 Circuit Breaker 1 (CB 1) or Circuit Breaker 2 (CB2)
must be electrically interlocked with CB3 in such a way that CB3 cannot be closed
unless one of CB1 or CB2 is open. Specific details of the proposed interlocking scheme
are to be submitted to BC Hydro for acceptance.
September 2011 26
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
A further alternative for the detection of supply system ground faults is the
application of a power relay (32) which would operate after the BC Hydro
source opened. Should such a device be considered, it is preferred that it be
connected to look into the entrance transformer from the low voltage side
and pick up on the magnetizing watt loss component of the transformer. In
some special circumstances the magnetizing watt loss component will be so
low as to preclude power relay operation. In this case, although it is not the
preferred approach, the power relay will have to be applied to sense loss of
real power flow into the plant. The customer shall provide suitable
manufacturer's transformer/relay test data to confirm whether or not the
preferred connection will work. To check the effectiveness of the power
relay with this connection, BC Hydro will require testing of the device by
actual back energization of the transformer and, where feasible, the supply
line.
September 2011 27
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
The customer shall provide its own synchronizing facilities (25) to allow
synchronization of his generator units to the Transmission system.
September 2011 28
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
September 2011 29
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
The customer shall provide a visible service entrance group-operated isolating switch,
interlocked with the entrance breaker, or a group-operated load break disconnect,
either of which shall be accessible to BC Hydro at all times and capable of being
secured by a standard BC Hydro padlock.
The customer shall provide its own synchronizing facilities to allow synchronization
of its generator units with the BC Hydro.
Fig. 5 is a sample installation which meets the minimum requirements for customers
who provide power to the BC Hydro system.
September 2011 30
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
1
59N
B.C.H. METERING
3 1 3
67 46 27
LOAD BUS
1
25
Optional Device See
Subsection 3.2.1.
September 2011 31
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
The total tripping time of the load shedding scheme (underfrequency relay
operate time + auxiliary relay operate time + circuit breaker operate time) shall
be less than or equal to 14 cycles.
The underfrequency relay usually trips the customer's entrance circuit breaker,
however, at the customer's request and on receipt of detailed proposals, BC
Hydro may permit emergency load retention of approximately 10 percent of
normal load, or 2 MW, whichever is the lesser.
Customers are to ensure that the continuous DC supply voltage rating of any
solid state relay or its associated power supply is not exceeded due to sustained
overvoltages on the DC supply bus. Common examples of conditions resulting
in high sustained overvoltages are:
If there is any chance that the DC rating of a solid state relay will be exceeded,
then a passive voltage regulator of suitable rating shall be applied to each solid
state relay to limit the DC voltage to within the solid state relay's DC rating.
September 2011 32
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
3.3.2 Harmonics
Operation of the customer's plant and equipment shall not introduce adverse
harmonics onto the Transmission system. There are both voltage and current
harmonics each requiring separate analysis and control. Harmonic effects are
dependent on the magnitude and frequency of the harmonic, and the electrical
characteristics of the total electrical system.
September 2011 33
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
The customer shall, upon request, provide BC Hydro with the characteristics of any
harmonic-producing devices in its plant, the magnitude and frequency of harmonics
produced, and harmonic filtering, if any.
On request, BC Hydro will supply customers with ambient harmonic levels at the
customer's supply bus and the harmonic impedance spectrum at the point of
connection.
BC Hydro follows the IEEE Standard 519-1992 titled "Recommended Practices and
Requirements for Harmonic Control in Electric Power Systems". A detailed outline of
the requirements for harmonic control is included as Appendix B.
The harmonic standards outlined in Appendix B are revised standards issued with this
edition of the Guide.
Voltage dips exceeding 6 percent but not exceeding 9 percent may, at times, be
permitted by BC Hydro. Permissible voltage dips more frequent than once per hour or
rapid load fluctuations causing voltage flicker are limited to the percent voltages
indicated by the Border Line of Visibility curve shown in Appendix A. Some
relaxation of these limits may be permitted by BC Hydro provided that the customer
demonstrates that the effects of its operation will not be as severe as sudden load
changes on the average threshold of perceptibility of flicker, such as a slower rate of
change in the voltage.
Of particular concern are the following types of equipment which may cause
excessive voltage disturbances or unbalances to the Transmission system: large motors,
arc furnaces, induction furnaces, resistance welders, static converters, capacitors,
September 2011 34
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
electric shovels, rolling mills and other similar voltage fluctuating equipment.
Unbalanced load in the customer's plant will cause phase voltage unbalance on
BC Hydro's high voltage system with possible harmful effects to other
customers connected to the system. Of particular concern is the negative
sequence voltage created and the resulting effect, particularly on rotating
generators and motors connected to the system. Under normal operating
conditions the negative sequence voltage at the Point of Delivery shall not
exceed 11/2 percent, or such limit as agreed to by BC Hydro.
The minimum power factor (PF) to be maintained by the customer, when the
kV.A demand is greater than 75% of the maximum demand, measured over an
interval of 5 minutes is 95% lagging unless circumstances of electricity supply
require otherwise.
In general, the power factor requirement will be monitored through the use of
information derived from B.C. Hydro's metering equipment. Factors derived
from the several forms of metering equipment would permit the following
power factor calculation:
September 2011 35
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
On a long term basis, power system disturbances at or near the intertie between a
customer's plant and the Transmission network are inevitable.
The following is a list of the most usual types of power system disturbances:
a) sustained overvoltage,
b) sustained undervoltage,
c) sustained underfrequency,
d) impulse, spike, lighting or switching surges,
e) excessive voltage flicker caused by starting of large motors,
f) supply circuit forced outage,
g) voltage sag caused by remote faults.
Items a, b and c are usually emergency upset conditions from which the
Transmission system in the area of the plant is not expected to recover
immediately. For such disturbances, BC Hydro may dictate that either
loads be shed in the plant or the plant be isolated from its system in order
to assist in the recovery to normal voltage and frequency. In some cases,
the customer may have the option of either disconnecting the service
from BC Hydro or riding through the disturbance. In either case, without
in-plant generation to supply the plant load, a plant electrical system
outage and consequent loss of production could be expected.
For Item e, the starting inrush current of large motors, if not controlled,
can cause excessive voltage flicker in the Transmission system and in the
customer's plant.
For Item f, the supply circuit will be interrupted, usually for a short duration. The
September 2011 36
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
For Item g, the supply circuit will remain intact, but the plant supply voltage will dip
to a certain magnitude for a short duration until the remote fault is cleared.
The location and type of fault have an important impact on the severity of
voltage dip on the customer's plant. The majority of faults on the Transmission
system are single-line-to-ground faults which can result in a wide range of
voltage dips. Three-phase faults result in much more severe voltage dips than
single-line-to-ground faults, but are relatively infrequent.
process controllers
control relays
arc furnaces
Any or all of these devices could trip out due to a voltage dip and cause a
shutdown in a specific process area of a customer's plant.
For example, motor starter contactors may drop out at a voltage of about 70%
of rated voltage within 1 or 2 cycles. Modern process electronic power
converters for AC Drives and programmable logic controllers could trip off-
line at about 85% of rate voltage for dips as short as 1/2 cycle.
Some suggestions for minimizing the impact of system disturbances on plant operation
are as follows:
(a) Meet with BC Hydro to gain an understanding of the operation of their system
in the area of the plant and to receive data from them regarding the estimated
frequency and severity of the listed disturbances.
September 2011 37
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
(b) For Items a to c and Item f of section 3.3.6, evaluate the practicality of
operating isolated from BC Hydro, or increasing supply system redundancy
versus accepting the inevitability of plant outages from time to time.
(c) For Item g, consider system and/or equipment design techniques which can
help minimize the effect of system disturbances.
(iii) For loads which are essential to the plant processes, and where
additional expenditure is justified, the following techniques could
be considered:
September 2011 38
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
The main contact for customers in regards to system operating conditions will be the
Area Control Center (ACC) responsible for operating the portion of the system to
which the customer’s plant is interconnected. The appropriate communication
procedures and contact personnel will be provided in the customer’s Local Operating
Order (LOO).
3.4.1 General
Subsections 3.4.2 through 3.4.4 illustrate the protection requirements for
some specific sample installations. These sample installations are not
meant to be an all-encompassing set which covers all customer
installations. The examples do not include any generating facilities. If
these were to be included, additional protection over and above that
detailed in the examples would be required - see Subsection 3.2.2
"Customer's Generation" for more details.
September 2011 39
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
CUSTOMER INSTALLATION
B.C. HYDRO
LINE TERMINAL
LOAD BREAK K
DISCONNECTS
B.C. HYDRO
TRANSMISSION
LINES
N.O.
B.C.H. METERING
B.C. HYDRO
LINE TERMINAL
For a supply connection via .a dual radial system as depicted in Fig. 7, several
considerations apply:
In special cases, permission may be granted to have these switches equipped with
control equipment for automatic transfer of the customer from one source to the
other. Such control equipment would remain under the jurisdiction of BC Hydro and
be subject to periodic testing by BC Hydro personnel.
September 2011 40
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
In the case of a customer tapped into a transmission line as shown in Fig. 8, the
customer shall coordinate on a radial basis with either line terminal. This is
interpreted to mean that the customer's entrance protection shall coordinate with
terminal A relaying when the terminal B breaker is open, and coordinate with
terminal B relaying when the terminal A breaker is open.
There may be particular protection requirements for each of the three BC Hydro
connections shown, but invariably the type and form of protection at the BC Hydro
source station(s) will have a more major impact on the customer's protection than
the supply connection.
In addition to the protection specified in the examples which follow, extra relays may
be installed at the customer's option for improved sensitivity. Optional relays
include: overload (49), phase unbalance (46), gas detector (63).
Typically, fuses for this application must coordinate with the source phase and ground
overcurrent relays over the full range of fault levels specified by BC Hydro. The
coordination curves in Fig. 10 depict this.
September 2011 41
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
In some situations the customer may not be able to apply primary fuses and
assure coordination with BC Hydro's relaying. This may be true for
customers fed from radial/dual-radial sources, but is usually true when a
customer is tapped into a transmission circuit, since these circuits are
generally equipped with high speed protection. Where coordination is not
possible, the customer must consider other alternatives - see Subsections
3.4.3 and 3.4.4 for examples.
As noted in Section 3.1 "Equipment Rating", fuses must have adequate interrupting
capacity for the initial and ultimate fault levels specified by BC Hydro. Maximum
permissible current ratings of the fuses will be specified by BC Hydro for proper
September 2011 42
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
Fuses for this application must coordinate with the source phase and ground
overcurrent relays, with the exception of a range of low ground fault currents
where tripping may be achieved by means of a circuit switcher and a ground
overcurrent relay (51N). In this range the composite curve of the circuit
switcher clearing and the fuse clearing must coordinate with the source
ground overcurrent relay. In addition, the fuses must take over the
interrupting duty for fault currents in excess of the circuit switcher's
interrupting capability, achieved by proper coordination of the customer's
ground relay and fuse time-current curves. These aspects are depicted in the
coordination curves in Fig. 12.
September 2011 43
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
BC
BC
H
H
SO
SO
TIME S
U
U
R
R
C
C
E
E
C
PH
U
G
ST
AS
O
O
E
M
O
ER
VE
O
G
VE
R
R
C
O
U
U
R
N
R
D
EN
R
O
EN
T
VE
R
T
R
EL
C
AY
U
EL
R
S
R
Y
EN
T
R
EL
AY
September 2011 44
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
The relay types, ranges, and time characteristics will be subject to BC Hydro approval
in each individual case.
Example 1
SUPPLY
CONNECTION AS
DETAILED IN
SUBSECTION 3.4.1 3
50/51
B.C.H. METERING
1
50/51N
Minimum relay requirements for this application are three phase overcurrent
relays (51) and one ground overcurrent relay (51 N), all with inverse or very
inverse characteristics. Their pickup and time settings shall be adjusted so that
the composite relay and breaker time curves coordinate with the respective phase
and ground relays at the BC Hydro source(s). The relays must be equipped with
instantaneous trip elements to coordinate with BC Hydro's existing and future
requirements.
September 2011 45
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
Example 2
Minimum relay requirements for this application are three phase overcurrent (50/51)
relays and one ground (50/51N) overcurrent relay of the inverse or very inverse type
September 2011 46
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
with instantaneous trip elements, selected and set so that they will coordinate with the
respective phase and ground relays at the BC Hydro sources.
In fault current ranges where fully selective coordination is not possible, the
customer's relays must trip their associated circuit breaker at the same time as BC
Hydro's line terminal trips, in order to ensure that the customer has definitely been
tripped off prior to automatic or supervisory reclosing of the line terminals.
September 2011 47
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
Example 3
51
K
SUPPLY
CONNECTION AS
DETAILED IN
SUBSECTION 3.4.1
B.C.H. METERING
A
87
September 2011 48
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
3.5.1 General
BC Hydro reserves the right to set and calibration test the under-frequency
relay and test its tripping to the circuit breakers prior to energization of the
installation. BC Hydro also reserves the right to inspect and test the
underfrequency load shedding at any time and will do so at periodic
intervals. The customer will be requested to perform any maintenance that
the testing shows to be necessary.
September 2011 49
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
All revenue metering and billing issues are handled through B.C. Hydro. For B.C.
Hydro’s revenue metering requirements, please visit the BC Hydro website at:
http://www.bchydro.com/youraccount/content/forms.jsp
September 2011 50
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
BRITISH COLUMBIA
APPENDIX A
November 1993
September 2011 51
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
Table of Contents
A1 INTRODUCTION
A1.1 Scope
A1.2 Definitions
A1.3 References
A2 GENERAL PROCEDURE
A3.1 General
A3.2 Harmonic Current Limits
A3.3 Harmonic Voltage Limits
A3.4 Engineering Information Provided by B.C. Hydro
A3.5 Other Considerations
A4.1 General
A4.2 Limits on Current and Voltage Distortions
A4.3 Limits on Telephone Interference
A4.4 Instrumentation Requirements
September 2011 52
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
A.1 INTRODUCTION
A1.2 Scope
A1.2 Definitions
(1) Point of common coupling (PCC): The point of common coupling is defined as
the BC Hydro point electrically nearest to the customer installation. This point is
normally the primary bus of the customer supply transformer.
(2) Individual harmonic distortion (IHD): The individual harmonic distortion value of
a waveform is defined as the RMS value of a harmonic component expressed as a
percentage of the RMS value of the fundamental frequency component. In the case of
harmonic voltage distortion, the nominal operating voltage shall be used as the RMS
value of the fundamental frequency component. In the case of harmonic current
distortion, the maximum fundamental frequency load current under normal operating
conditions shall be used as the RMS value of the fundamental frequency component.
(3) Total harmonic distortion (THD): The total harmonic distortion value of a
waveform is the root-sum-square of individual harmonic distortion values, as defined
in Equations (1.1) and (1.2). BC Hydro requires that up to fortieth (40) harmonics shall
be included in the THD calculation:
(1.1)
(1.2)
Total harmonic current: Total harmonic current of a current waveform is defined as the
root-sum-square of the RMS magnitudes of individual harmonic currents:
'I(
September 2011 53
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
(1.3)
(5) Residual 1*T product: The residual I*T is the root-sum-square value of the zero
sequence RMS harmonic currents multiplied by the TIF weighting factors. The values
of TIF weighting factor can be found in reference [1 ] or [6].
(6) Noise Metallic (Nm): Noise metallic, which is also referred to as telephone circuit
noise, is defined as a metallic voltage impressed between tip and ring of a telephone
set and measured as a power level across a 60052 load. Nm is expressed
mathematically as 10xlog (unit: dBrn) of the square of the difference between the tip-
to-ground and the ring-to-ground voltages divided by the metallic circuit impedance.
The metallic voltage is normally weighted with certain factors at different
frequencies. This guideline uses C-message weighted voltage (dBrnC) [6].
(7) Noise to Ground (Ng): Noise to ground, which is a measurement of the influence
of power system currents on a telephone circuit, is the average of tip-to-ground and
ring-to-ground voltages measured as a power level across a 60052 load. Ng is
expressed mathematically as l0xlog (dBrn) of the square of the average voltage
divided by the reference impedance of 6001 This guideline uses C-message weighted
average voltage (dBrnC) [6].
(9) Background Voltage Harmonics: Background voltage harmonics are the harmonic
voltages that exist at PCC when the customer installation is not connected to the
supply system or is connected but not drawing load current from the supply system.
(10) Total Plant Load: Total plant load is the contract total plant MVA demand,
without subtracting customer's co-generation capacity if any, for normal plant
operation.
(11) Harmonic Loads: Harmonic loads in a plant are those primary industrial loads
that can cause more than 5% of total harmonic distortion in the load currents when
supplied with a sinusoidal 60Hz voltage. In most cases, harmonic loads are DC drives,
variable frequency AC drives, rectifiers, and possibly uninterruptible power supplies.
A1.3 References
September 2011 54
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
[1] IEEE Std.-519: "IEEE Recommended Practices and Requirements for Harmonic
Control in Electric Power Systems", 1992.
September 2011 55
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
Category II (large) installations are required to perform and submit for BC Hydro's
inspection harmonic study at the plant design stage. The study shall demonstrate that
BC Hydro's harmonic design limits are met.
(1) The ratio of total harmonic load MVA in the plant with respect to the total plant
load MVA, in percentage, is below the curves shown Figure B.1. The total
harmonic load MVA shall be estimated according to the following formula:
(2) The customer's capacitors should not cause harmonic resonances, namely the
following condition is satisfied for every harmonic number h:
0.35 h-5,7,11,13,17,...
| h resonance – h| > 0.10 h-2,4, 6, 8,10,... (2.2)
0.15 h-3,9,15,21,27,...
September 2011 56
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
where MVAsys, is the system fault MVA seen at the capacitor bus. This MVA shall
include the contribution of non-harmonic-producing loads such as motors in the plant.
MVA C , is the installed capacitor MVA calculated at normal operating voltage. It shall
be noted that both MVA, y, and MVA C, P may vary with the operating conditions of the
supply system and the plant. The limits of Equation (2.3) shall be satisfied for all
conditions.
Any installations not belonging to category I are considered as category II. These
installations shall satisfy BC Hydro that the harmonic design and/or measurement
limits as specified in Sections 3 and 4 are complied with.
Customers in either category shall provide BC Hydro, via B.C. Hydro customer care,
with the following data:
A2.4 Examples
Example 1
The total plant load is 100MVA
Utility supply is at 287kV
The system fault level at PCC is 5000MVA
= > Therefore ratio of system fault MVA to demand MVA is 50 (=5000/100).
September 2011 57
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
as follows:
* 6.0 MVA 12-pulse DC drives
* 5.0 MVA other harmonic loads
* total harmonic load is then 10.1 MVA (=1.00x5.00+0.85x6.00), as per Eq. (2.1)
==> Therefore percentage total harmonic load is 10.1% (=10.1/100)
Conclusion: As per Figure B.1, point (50, 10.1%) falls above the 287kV curve.
The installation is a category II type.
Example 2
- The total plant load is 30MVA
- Utility supply is at 69kV
- The system fault level at PCC is 1700MVA
Therefore ratio of system fault MVA to demand MVA is 57 (=1700/30).
As per Figure B.1, point (57, 16.3%) falls below the 69kV curve. The
installation passes harmonic chart requirement. Harmonic resonance check is
followed.
Conclusion: Although satisfying the harmonic chart requirement, the plant fails the
harmonic resonance check. The installation is a category II type.
Example 3
- The total plant load is 30MVA
- Utility supply is at 69kV
- The system fault level at PCC is 1700MVA
Therefore ratio of system fault MVA to demand MVA is 57 (=1700/30).
September 2011 58
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
As per Figure B.1, point (57, 16.3%) falls below the 69kV curve. The
installation passes harmonic chart requirement. Harmonic resonance check
is followed.
- The plant capacitor banks, installed in one location, are 2.1 MVar
- The fault level at the capacitor bus is 190MVA
Therefore hresonance is 9.51 (=SQRT(190/2.1))
| hresonance –h | = 0.51 > 0.15 for h=9 => okay
= 0 . 4 9 > 0 . 1 0 for h=10 => okay
September 2011 59
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
A3.1 General
At the plant design stage, category II customers shall satisfy BC Hydro that the
calculated current and voltage distortions at the point of common coupling shall not
exceed the design limits. Worst case normal operating conditions shall be used in the
calculation of harmonic distortions. For customers with transformer arrangements that
result in zero sequence current injections into the Transmission system, the amount of
zero sequence harmonic current injections must be calculated. For those customers
whose loads are unbalanced among three phases and can result in a voltage unbalance2
greater than 1.5% at PCC, three-phase harmonic analysis is required.
Limits for harmonic current distortion are shown in Tables 3.1A, 3.1B and 3.1C. These
limits apply to each phase current individually at the point of common coupling.
Harmonic current distortion shall be calculated using two sets of system impedance
data:
(1) The supply system harmonic impedance as seen from the point of common
coupling is zero at all harmonic frequencies. This assumption is needed since the
system harmonic impedance can be zero at any frequency due to resonances in the
Transmission system. Using zero harmonic impedance also ensures that the
customer plants contain their own harmonic currents and the harmonic currents
escaping into the Transmission system are minimized.
(2) The supply system harmonic impedances are the same as those provided by BC
Hydro. The purpose is to determine if there is any excessive harmonic current
injection into the Transmission system caused by the harmonic resonance between
the system impedance and the customer capacitor banks.
It must be noted that the limits shown in Tables 3.1 apply only to the harmonic currents
introduced by customer installations. A zero background harmonic distortion shall be
assumed in the calculation therefore. The results are the harmonic currents exclusively
due to customer installations. Since problems may be caused by the amount of
harmonic current injections into supply systems irrespective to the magnitude of
fundamental frequency current at the PCC, this guide also imposes ampere limits on
the total harmonic current injection. For most Load customers, satisfying the
percentage harmonic current limits generally results in the satisfaction of the ampere
limits.
-----------------------------------------------------
2
Voltage unbalance is defined as the ratio of negative sequence voltage to the
positive sequence voltage.
September 2011 60
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
September 2011 61
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
Limits for harmonic voltage distortion at the point of common coupling are listed in
Table 3.2. Reducing harmonic voltage distortion is the responsibility shared between
BC Hydro and the customers. A first-come-first-served policy is adopted in this guide.
While BC Hydro is responsible to maintain the voltage distortion within the limits of
Table 3.2, a new customer installation is limited to add certain harmonic voltage
distortion at the PCC such that the combined voltage harmonics of background and
customer contribution is within the limits of Table 3.2:
(3.1)
The harmonic voltage limits apply to each phase voltage individually at the point of
common coupling. The supply system harmonic impedance data provided by BC Hydro
shall be used to determine the harmonic voltage distortions caused by the customer
plants.
Table 3.2: Harmonic Voltage Distortion Limits
September 2011 62
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
BC Hydro will provide, within its own reasonable expense, the necessary engineering
information for customer harmonic analysis. If the information is considered to be
critical to the equipment design, any customer can require BC Hydro to supply more
accurate technical data, at customer's expense, based on dedicated field measurements
or harmonic studies on Transmission system. The engineering information provided
by BC Hydro includes:
(1) System fault level for harmonic studies: It is the fault level calculated for the
normal system operating conditions. The fault level may not be the same as
those used to determine the breaker rating and protection setting of the
customer plant BC Hydro will specify what fault levels shall be used for
harmonic analysis.
September 2011 63
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
with unbalanced three-phase loads (see Section 3.1 for the criteria), three-
phase harmonic analysis is required. A voltage unbalance of 1.5% at the PCC
shall be used in the study.
This guideline imposes no specific design limits on the calculated I*T values. This is
because that the telephone interference is, in the majority of cases, caused by residual
(zero sequence) harmonic currents. For those customers whose supply transformers are
connected with primary in delta or ungrounded-star form, the calculated residual
current flowing into the Transmission system is always zero, and therefore, no direct
telephone interference is expected. It shall be noted, however, that indirect harmonic-
telephone interference is still possible. These interferences may be caused by the
interaction of non-residual harmonic currents with the equipment of the supply system.
Since the indirect interference is impossible to predict in most cases, the philosophy
adopted in this guideline is to limit the total harmonic current in ampere value and the
triple order harmonic current distortion, in addition to the IEEE limitations on IHD and
THD.
(3.2)
While trying to meet BC Hydro's harmonic limits at the point of common coupling,
customers may also keep in mind that their capacitors may become a sink for the
harmonic currents outside their plants. This problem is normally caused by the parallel
resonance between the capacitors and the system impedance (including the supply
transformer impedance). Adherence to Equation (2.2) of Section 2.1 may reduce the
likelihood of resonance and capacitor overload. But detailed harmonic and capacitor
sizing studies are recommended.
September 2011 64
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
September 2011 65
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
A4.1 General
The limits for measured harmonics are based on the design harmonic limits. However,
factors such as time-varying nature of harmonics and customer plant startup conditions
are taken into account. In other words, short time bursts of harmonic distortions higher
than the design limits are generally acceptable. Two indices shall be used to measure
the degree of harmonic bursts:
(1) Maximum Duration of Harmonic Burst (Tmaximum): This is the maximum time
interval in which the harmonic distortion exceeds a particular IHD or THD level
during a 24 hour measurement period.
(2) Total Duration of Harmonic Burst (Ttotal): This is the summation of all the time
intervals in which the harmonic distortion exceeds a particular IHD or THD level
during a 24 hour measurement period.
September 2011 66
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
Instruments, which may include PT's and CT's, used for harmonic distortion and
telephone interference measurements must be certified by BC Hydro. If there is any
dispute over the accuracy of an instrument, CSA standard C22.2 [2,3] shall be used
to resolve the dispute.
September 2011 67
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
September 2011 68
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
Adherence to the recommended limits of this guideline should reduce the risks of
damage to, or malfunctioning of other customer's or the Transmission provider’s
equipment. But there is no guarantee that this can completely prevent a trouble arising.
This section defines the responsibilities of each involved party to mitigate harmonic
problems.
The customer is responsible to ensure that its portion of harmonic current distortion at
the point of common coupling is always within BC Hydro's harmonic current distortion
limits.
The customer is responsible to reduce the harmonic voltage distortion at the point of
common coupling to BC Hydro's voltage distortion limits. However, if the actual
supply system harmonic impedances and background voltage distortions are outside the
ranges determined by BC Hydro at customer's expense, B.C. Hydro is responsible to
reduce the harmonic voltage distortion.
Problems caused by harmonics may arise even if harmonic limits are not violated.
Under these circumstances, all involved parties may be responsible to mitigate the
problems. Exact sharing of responsibilities shall be determined on case by case basis.
September 2011 69
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------
September 2011 70
Guide and Requirements for Service at 69,000 to 287,000 Volts
--------------------------------------------------------------------------------------------------------------------