Barrage Training Report
Barrage Training Report
1.BARRAGE
A barrage, by definition, is a weir structure fitted with gates to regulate the Water level in the
pool behind in order to divert water through a canal for Irrigation, power generation, and flow
augmentation to another river.
The barrages may be classified as being located in the following four types of river Regimes:
i
Doon Institute of Engineering & Technology
Afflux created is high due to relatively high Due to low crest of the weirs (the ponding
weir being done mostly by gate operation), the
crests. afflux during high floods is low. Since the
gates may be lifted up fully, even above the
high flood level.
ii
Doon Institute of Engineering & Technology
4.2.Rating Curve
In the absence of detailed data, preliminary rating curve may be prepared by computing the
discharge at different water levels using the following formula:
Q=(AR2/3.S1/2) /n
4.3.Afflux
If the flood in the river is less than the design flood, then some of the gates would be fully
opened but the remaining opened to such an extent which would permit the maintaining of the
pond level. However, when a design flood or a higher discharge through the barrage structure, all
the gates have to be opened. Nevertheless, the structure would cause a rise in the water level on
the upstream compared to level in the downstream at the time of passage of a
high flood (equal to or more than the design flood) with all the gates open. This rise in water
level on the upstream is called afflux. The amount of afflux will determine the top levels of the
guide bunds and marginal bunds, piers etc.
4.4.Freeboard
Freeboard is the difference b/w high flood level and normal flow level. Sufficient Free Board
has to be provided so that there is no overtopping of the components like abutments, piers, flank
walls, guide bunds, afflux bunds etc.
4.5.Waterway
The sectional area or the amount of opening provided for flow of water through barrages/weirs,
head regulators, etc. Waterway, or the clear opening of a barrage to allow flood flow to pass has
iii
Doon Institute of Engineering & Technology
a bearing on the afflux. Hence, a maximum limit placed on the afflux also limits the minimum
waterway.
Many a times, the Lacey’s stable perimeter for the highest flood discharge is taken as the basis of
calculating the waterway.
P = 4.75 Q1/2
Where Q is the design flood discharge in m 3/s for the 50 years frequency flood.
4.6.Spillway Bays
This is the main body of the barrage for controlling the discharges and to raise the water level to
the desired value to feed the canals. It is a reinforced concrete structure designed as a raft
foundation supporting the weight of the gates, piers and the bridge above to prevent sinking into
the sandy river bed foundation.
4.7.Undersluice Bays
These low crested bays may be provided on only one flank or on both flanks of the river
depending upon whether canals are taking-off from one or both sides. The width of the
undersluice portion is determined on the basis of the following considerations.
• It should be capable of passing at least double the canal discharge to ensure good scouring
capacity
• It should be capable of passing about 10 to 20 percent of the maximum flood discharge at high
floods
• It should be wide enough to keep the approach velocities sufficiently lower than critical
velocities to ensure maximum settling of suspended silt load.
Undersluices are often integrated with RCC tunnels or barrels, called silt excluders, extending
up to the width of the Canal Head Regulator. These
tunnels are provided in order to carry the heavier silt from a distance upstream and discharge it
on the downstream, allowing relatively clear water to flow above from which the Canal Head
Regulator draw its share of water.
The set of undersluice bays with low crest elevations are separated from the set of spillway bays
with a small weir hump by a long wall, called the divide wall.
4.9.Glacis
The sloping portion of the floor upstream and downstream of the crest.
iv
Doon Institute of Engineering & Technology
4.10.Cut-off
Cut-offs are barriers provided below the floor of the barrage both at the upstream and the
downstream ends. They may be in the form of concrete lungs or steel sheet-piles. The cutoffs
extend from one end of the barrage up to the other end on the other bank.
During low-flow periods in rivers, when most of the gates are closed in order to maintain a pond
level, the differential pressure head between upstream and downstream may cause uplift of river
bed particles. A cutoff increases the flow path and reduces the uplift pressure, ensuring stability
to the structure.
During flood flows or some unnatural flow condition, when there is substantial scour of the
downstream riverbed, the cutoffs or sheet piles protect the undermining of the structure
foundation.
Figure V : Riverbed scour resisted by sheet pile protects the foundation barrage floors
v
Doon Institute of Engineering & Technology
4.11.Sheet piles
Figure VI
Made of mild steel, each portion being 1/2’ to 2’ in width and 1/2' thick and of the required
length, having groove to link with other sheet piles
4.12.Piers
Concrete or masonry structure constructed over the waterway for supporting bridge decking,
gates and hoist operating mechanism.
4.13.Hydraulic Jump
The sudden and usually turbulent passage of water from a lower level (below critical depth) to
higher level (above critical depth), during which head loss occurs and the flow passes from
supercritical to subcritical state.
4.14.Specific Energy
It is the energy of stream flow per unit weight at any section of a channel measured with respect
to the channel bottom as datum, namely vertical depth plus velocity head corresponding to the
mean velocity.
4.15.Abutment
A wall constructed at both ends of the structure mainly for effective keying the main
barrage/weir structure into the ground at either end and also to perform additional functions, such
as retaining the backfill, protecting the bank from erosion, supporting load from superstructure
and confining the flow to the desired waterway at the structure.
vi
Doon Institute of Engineering & Technology
4.16.Apron
A protective layer of stone or other material provided in the bed of the river where it is desired to
prevent erosion
4.17.Exit Gradient
The upward seepage force per unit volume of seepage water through foundation soil at the tail
end of a barrage/weir, tending to lift up the soil particles if it is more than the submerged weight
of a unit volume of the latter. It is also defined as the hydraulic gradient of emerging stream lines
at the end of an impervious apron.
4.18.Retrogression of level
A general decrease in the bed level of the river or channel over a sufficiently long length
downstream of a structure.
5.1.Barrage
A diversion head works structure constructed across a river for the purpose of raising water
level in the river so that it can be diverted into the off-taking canals. A barrage has a low crest
wall with high gates. As the height of the crest above the river bed is low most of the ponding is
done by gates. During the floods the gates are opened so afflux is very small.
5.2.Undersluices
These are gates controlled openings in the weir with crest at low level. They are located on the
same side as off-take canal. If two canal take off on either side of the river, it would be necessary
to provide undersluices on either side.
Functions of undersluices
· To preserve a clear and defined river channel approaching the canal regulator.
· To scour silt deposited in front of canal regulator and control silt entry in the canal
· To facilitate working of weir crest shutters or gates. The flood can easily pass
· To lower the highest flood level.
vii
Doon Institute of Engineering & Technology
5.3.Divide Wall
A divide wall is a wall constructed parallel to the direction of flow of river to separate the weir
section and the undersluices section to avoid cross flows. If there are undersluices at both the
sides, there are two divide walls. It is a concrete or masonry structure, with top width 1.5 to 3
meter, and aligned at right angle to the weir axis.
viii
Doon Institute of Engineering & Technology
5.4.Fish Ladder
A fish ladder is a passage provided adjacent to the divide wall on the weir side for the fish to
travel from the upstream to the downstream and vice versa. Fish migrate upstream or
downstream of the river in search of food or to reach their sprawling places. In a fish ladder the
head is gradually dissipated so as to provide smooth flow at sufficiently low velocity. Suitable
baffles are provided in
the fish passage to reduce the flow velocity.
The head regulator is normally aligned between 90° - 120° in respect to the axis of the weir. The
regulation done by means of gates, steel gates of spans ranging between (8 m-12 m) are used and
operated by electric winches.
5.6.Silt Excluder
A silt excluder is a structure in the undersluices pocket to pass silt laden water to the downstream
so that only clear water enters into the canal through head regulator. The bottom layer of water
which are highly charged with silt pass down the silt excluder an escape through the
undersluices.
5.7.Guide banks
Guide banks are provided on either side of the diversion head works for a smooth
approach and to prevent the river from outflanking. Marginal bunds are provided on either side
of the river upstream of diversion headwork to protect the land an property which is likely to be
submerged during ponding of water in floods.
x
Doon Institute of Engineering & Technology
xi
Doon Institute of Engineering & Technology
6.3.Infrastructure planning
This aspect of planning needs to ensure approach roads, power and water supply, workshop,
stores, aggregate processing plant, concrete batching and mixing plants, camps and work sheds.
It also requires the establishment of other amenities, such as market, schools, medical facilities,
and other social and cultural needs of the field staff and workers. The planning should be carried
out to the extent possible before the work starts, so that the uncertainties and delays in execution
of work, and precise time estimates for the job planning could be evaluated.
6.4.Invstigations
Investigations are generally done in two stages:
1. Preliminary investigations, and
2. Detailed investigations.
6.4.1.Preliminary Investigations
These investigations should include the following:
1) Study of available maps including remote sensing maps;
2) Regional and site geology;
3) Study of existing projects upstream and downstream of barrage;
4) Assessment of water requirement;
5) Effect of proposed barrage or weir contemplated on environment and ecology;
6) Limitations or constraints imposed by custom, water laws and rights or accepted policy;
7) Availability of construction materials;
8) Land for utility services; and
9) Communication to site of work.
6.4.2.Detailed Investigations
After preliminary selection of site, the following investigation should be carried out in detail
with a view to collect data for the design of the main structure and the appurtenant works for the
site chosen;
a) Detailed topographical survey;
b) Collection of hydrological and meterological data;
c) Sediment studies;
d) Design discharge of major hydraulic structure upstream of the proposed site, if any;
xii
Doon Institute of Engineering & Technology
6.5.Programme of works
This should be prepared at the start of the construction activities and consist mainly of Bar Chart
Programme for the project duration showing the quantities and monthly progress required for
various major items of the project. Another master network plan based on PERT/CPM planning
may have to be worked out for monitoring the project work. Based on these programmes, the
planning for finance, manpower, equipment required for various activities in different seasons of
work have to be prepared.
6.7.Sequence of construction
This important activity has to be planned perfectly, since mistakes at this stage would be difficult
to be rectified later. The major items under the sequence of construction are as follows:
● Layout of the barrage axis as per the approved plan by constructing short pillars called axis
pillars at suitable locations along the line of the axis across the river.
● Benchmark location has to be established the entire project area to help site the various
components like floor, crest, piers, etc. at proper elevation.
● Temporary access bridge has to be constructed for transporting men, material and equipment
from one bank of the river to the other.
● Layout of cofferdams have to be decided on the site conditions, nature of river course, and
programme of works for the season. Coffer dams are temporary structures constructed in the
riverbed to provide an enclosed area where the actual construction might be executed. Details of
the design of a cofferdam may be had from Bureau of Indian Standards Code IS:10084-
1982(Part1) “Criteria for design of diversion works: Coffer dams”.
xiii
Doon Institute of Engineering & Technology
● Once the coffer dams are constructed, the water within the enclosure has to be dewatered. The
Bureau of Indian Standards Code IS:9759-1981 “Guidelines for dewatering during construction”
may be referred for details, but the main points are noted below:
1. After completion of the excavation above the water table, dewatering of the foundations have
to be commenced by well points or open pumps and the water table progressively lowered. Well
point systems may be suitable for sandy soils but in silty clay foundations strata open pumps
and/or deep well pump may be preferred. If an impermeable compact shingles-coffle layer is
sand witched between sandy layers in the depth to be excavated, then deep well pumps with
strainer throughout its depth has to be used.
2. The preliminary requirements of dewatering pumps should be bored on the inflow to the work
area, calculated on the basis of permeability of the strata and closeness of the water source.
3. During dewatering operation, care should be taken to ensure that there is no removal of fines
from the sub-strata that may weaken the foundation.
4. Any seepage of water from the foundation at local points or springs have to be taken care of
properly so that there is no piping of the foundation material.
5. Excavation of the foundation to the barrage profile is to be made either manually or by
machines in reasonably dry conditions. During excavation, water table should be maintained at a
lower level at which the excavation is being done. The excavated soil should be disposed- off
either manually or by machines, to suite the site requirements. In case machinery is employed,
the final excavation of the lowest layer should be done manually to the specified depth.
6. Cutoff walls may be steel sheet -piles driven from riverbed in case of non bouldery strata of
riverbed but in bouldery strata, either concrete or steel sheet pile cut-offs have to be constructed,
both by excavating a trench and then back filling with sand. For a discussion of the details of
steel sheet pile driving or construction of cutoff walls in trenches the code IS:11150-1993
“Construction of concrete barrages - code of practice” may be referred.
7. Once the cut-off walls on the upstream and downstream sides of the barrage are installed and
partially covered with pile caps, the foundation surface of the raft floor has to be properly
leveled, dressed and consolidated. The foundation should not contain loose pockets or materials
and they should be watered and compacted to the specified relative density. Clay pockets should
be treated as specified by the designer. It has to be ensured that proper drainage arrangements in
the foundation according to the designs including inverted filter, wherever indicated, are
provided and concreting work is taken up.
8. Instruments like piezometers, pressure cells, soil stress meters, tilt meters as specified should
be installed carefully such that the electric or mechanical connections to a central control panel is
least disturbed during construction.
9. The batching, mixing, placing and protection of concrete has to be done in accordance with
IS:456-1978 “Code of practice for plain and reinforced concrete”.
10. Where mechanical parts like gate guidening rails, gate seals are to be installed, block outs
should be left out so that the parts may be embedded later.
11. Dowel bars, or if necessary, metal sealing strips should be provided for the joints between the
pile caps and barrage floor.
xiv
Doon Institute of Engineering & Technology
12. The sequence of construction of barrage bays, silt excluder and piers have to be done in lifts,
starting from the downstream end of the barrage and with continuous pour in suitable layers, or
as specified by the designer.
13. Abutment and flared out walls may be constructed on pile foundations or on well foundations
14. Divide walls have to be constructed on well foundations and the wells have to be sunk to the
founding levels and the work of barrage bays on either side of the divide wall should be taken up
after construction of well caps.
15. The cement concrete blocks in the flexible apron on the upstream and downstream of the
solid aprons of the barrage floor may be cast in-situ with alternate blocks cast at a time. These
may be constructed with form work that should be so designed that when it is stripped off, the
required gap is formed for filling the filler material to facilitate speedy construction, pre-cast
blocks may be used.
7.MISCELLANEOUS
7.1.Dewatering
It is lowering of water table to facilitate construction of the barrage substructure and connected
works in fairly dry condition either by means of well-point system, deep-well pumping, surface
or open pumping, or any other method and /or suitable combination of methods adopted to suit
site conditions. The method adopted to suit the site conditions. The method adopted should be
such that uninterrupted dewatering is possible to keep the water table at least 300mm below the
levels at which permanent works are constructed and free flow of particles below the foundation
is prevented.
xv
Doon Institute of Engineering & Technology
7.3.Architecture
Wherever possible, the shapes of the pier ends, finish of the abutment, pier, divide walls surfaces
etc. can be modified to increase the architectural beauty of the structure. But hydraulic
performance and safety should not be sacrificed.
7.4.Pier Cap
Properly designed pier caps shall be provided under the bridges. Their broad features shall
satisfy aesthetic requirements also.
thickness- The thickness of the pier cap shall not be less than 300 mm for spans up to 25 mtr
reinforcement - The reinforcement of the pier cap should be distributed both at the top and
bottom in the longitudinal directions. In addition to this, two layers of mesh reinforcement of 6
mm diameter spaced at 75 mm centre to centre shall be placed under the bearings of road/ rail
bridge beams.
7.5.Model Studies
For important barrages, model studies should be carried out to get an idea of hydraulic
conditions, layout of guide bunds, location and axis to barrage and also to determine distributions
of flow
8.PROTECTION WORKS
8.1.Upstream block protection
Just beyond the upstream end of the impervious floor, pervious protection comprising of cement
concrete blocks of adequate size laid over loose stone shall be provided. The cement concrete
blocks shall be of adequate size so as not to get dislodged, and shall generally be of
1500 X 1500 X 900mm size for barrages in alluvium reaches of rivers.
xvi
Doon Institute of Engineering & Technology
specified size, the loose stone apron shall be provided in the form of cement concrete blocks of
suitable size depending on the economies.
xvii
Doon Institute of Engineering & Technology
9.2.Groynes or Spurs:
Groynes or spurs are constructed transverse to the river flow extending from the bank into the
river. This form of river training works perform one or more functions such as training the river
along the desired course to reduce the concentration of flow at the point of attack, creating a
slack flow for silting up the area in the vicinity and protecting the bank by keeping the flow away
from it.
These are
Permeable or impermeable
Submerged or non-submerged
xviii
Doon Institute of Engineering & Technology
9.3.Cut-offs: Cut-offs as river training works are to be carefully planned and executed in
meandering rivers. The cut-off is artificially induced with a pilot channel to divert the river from
a curved flow which may be endangering valuable land or property or to straighten its approach
xix
Doon Institute of Engineering & Technology
to a work or for any other purpose. As the cut-off shortens the length of the river, it is likely to
cause disturbance of regime upstream and downstream till readjustment is made. A pilot cut
spreads out the period of readjustment and makes the process gradual. Model tests come in
handy in finalizing this form of river training works wherever needed.
xx
Doon Institute of Engineering & Technology
10.VIRBHADRA BARRAGE
10.1.INTRODUCTION
A barrage and head regulator on river ganga at Virbhadra, 5kms downstream of Rishikesh, has
been constructed under Garhwal Rishikesh Chilla Hydel Scheme for hydroelectric generation.
This would diver a maximum 680 cumecs (2400 cusecs) of river water in 14.3km. long power
channel. Out of this discharge, 115 cumecs (4000 cusecs) shall pass through silt ejector tunnels
and 565 cumecs (20000 cusecs) shall be used for generation of power by utilizing a head of 32.5
km at chilla power house. The water after generation of power at chilla is again dropped in river
Ganga about 5km u/s of Haridwar.
10.2.DESCRIPTION OF WORKS
The barrage comprise of 4 under sluices and 11 spillway bays of 18mtr clear span. A divide wall
has been provided separating the under sluices and spillway bays. A free flow channel, 1.5 mtr
wide has been provided adjacent to the divided well for which an additional pier 1.5 m wide has
been constructed. The under sluice and spillway bays is one meter higher i.e 326.50 km. Silt
excluder tunnels, six in number haver been provided in first under sluice bay on the basis of
model studies for excluding big boulders.
The head regulator on left bank of the river has its axis at an angle of 108 degree form axis. It
comprises 5 bays of 11 mtr clear span. The width of piers is 2mtr.
Nominal guide bunds have been provided on u/s and d/s on both banks of barrage. An afflux
bund about 1.4 km long has also been provided on u/s right bank. A head of supply channel of
1.4 cumecs (50 cusecs) for water supply to I.D.P.L is located in the afflux bund at about 280mtr
form barrage. It has two 1 mtr dia steel pipes at the mouth, fitted with steel gates which can be
manually operated from the top. Though the required discharge in the channel could be fed by
one pipe line only, one stand bye pipe has been provided. It is proposed to bring back the
conditionally clean water cumecs ( 40 cusecs ) from I.D.P.L to river upstream of barrage by
means of a feedback channel. Its tail fall has been constructed in afflux bund at about 740 meters
from barrage.
The barrage gates are vertical lift fixed wheel type. The under sluice gates are 11.5 mtr high and
spillway bay gate are 10.15 high. The under sluice gates have been provided in two tiers with
bottom tier 8 mtr height and top tier of 3.15 mtr height. This has been done to flush logs/sleepers,
which may find their way upto barrage and choke the head regulator, by raising, only the top tier
of gate provision for stop log gates in all the bays of barrage, except no. 01, in which silt
excluder tunnels have been provided has been made. There is however one set of stop log gate
which will be operated by means of 50 MT gantry crane moving on rail track constructed on the
upstream.
xxi
Doon Institute of Engineering & Technology
The head regulator gates are vertical lift fixed wheel type. The height of head regulator gates in
7.2 mtr. A trash rack of size 75 mm with an inclination of 10 degree form vertical has been
provided at the head regulator to check entry of trash and bed load material plus 75 mm size in
power channel.
The power channel starting from head regulator to 0.208 km can carry a maximum discharge of
680 cumecs (24000 cusecs). The width of unlined section of channel in this reach is 42 mtr with
side slopes of 1:1.75 mtr and bed slope of 1 in 2320 in initial 148 mtr and 1 in 100 in last 60 mtr
At 0.208 km of power channel silt ejector tunnels have been provided to eject bed load material
of plus 1 mm size. There are 12 smaller tunnels (2.5 X 1.6 mtr ) four converging to one main
tunnel, thus making 3 tunnels at the exit. As such there are 3 gates at the outlet of tunnels. The
silt ejector channel is approximately 375 mtr long with 1 mtr fall at chainage 250 mtr. It has a
bed slope of 1:1. This channel is boulder pitches both at bed and sides and is designed for a
discharge of 115 cumecs (4000 cusecs ) with a water depth of 4 mtr. The silt ejector channel
discharges in river ganga at about 400 mtr d/s of the barrage.
10.3.SALIENT FEATURES
10.3.1.River
o Catchment area 21400 sq km
o Snow catchment area at barrage site 8450 sq km
o Maximum flood 18560 cumecs
o River Slope 1 in 435
o Assumed design Afflux 1.2 mtr
o U/S H.F.L for design discharge 336 mtr
o D/S H.F.L for design discharge 334.8 mtr
10.3.2.barrage
o Length between abutments 312 mtr
o Normal Pond level (R.L) 334.5 mtr
o Maximum pond level 336.5 mtr
o Minimum pond level 333.15 mtr
o Clear roadway over bridge 7.5 mtr
o Level of Road (R.L) 338.5 mtr
o Design discharge of barrage 14750 cumecs
o Pond storage capacity 6610 Acre Fit
xxii
Doon Institute of Engineering & Technology
10.3.3.Under Sluice
o Length b/w abutments 84 mtr
o Size of Bays (4 nos) 18 mtr
o Thickness of piers (3 nos ) 3 mtr
o Size of gates (4 nos) 18 X 8 mtr
o bottom tier(clear) (in two tiers) 18 X 3.15 mtr
o Total weight of gate 76.77 MT
o Crest level 326.5 mtr
o Length of impervious floor 179 mtr
o Depth of U/s cut off 2.3 mtr
o Depth of D/s cut off 4.75 mtr
o Cistern level 321.75 mtr
o Discharging capacity at H.F.L / Bay approx. 960 cumec
10.3.4.Silt Excluder
o Width of tunnels at entrance (6 nos) 2 nos. 3.2 mtr wide
2 nos. 3.1 mtr wide
2 nos. 2.5 mtr wide
o Width of tunnels at exit 2.5 mtr wide
o Height of tunnels 1.6 mtr
o Maximum length of tunnels 107.4 mtr
o Thickness of Partition walls 0.6 mtr
10.3.5.Ram Dhara
o Width 1.5 mtr
o Crest level 322 mtr
o Discharge at normal pond Approx. 10 cumecs
o Discharge at minimum pond Approx. 3 cumecs
xxiii
Doon Institute of Engineering & Technology
10.3.8.Power Channel
o Capacity upto 0 km from head 680 cumecs
o Capacity from 0.2 onward 565 cumecs
o Total length 14.3 kms
o Bed width in head reaches 42 mtrs
o Bed width of channel below 0.617 kms 12.5 mtr
o Side slopes 1.75 : 1
o Capacity 4 X 36 = 144 MW
o Maximum head 32.5 mtr
o Type of Turbine Kaplan
o Speed of Turbine 187.5 rpm
o Generation Voltage 11000 V
o Transmission Voltage 132000 V
o Make of Machine BHEL
o Total project cost Rs 98 crore
xxv
Doon Institute of Engineering & Technology
xxvi
Doon Institute of Engineering & Technology
xxvii