Detailed Estimate For The Concreting Ofaccess Road at Sitio Romeo Barangay San Rafael Centro
Detailed Estimate For The Concreting Ofaccess Road at Sitio Romeo Barangay San Rafael Centro
I. SIGNAGE P
A. Materials
135.7 cu.m Aggregate Base Course @ P 380.00 /cu.m.
P
B. Labor
1 Construction Foreman @ P 600.00 /day x 3 days P
6 Labor @ 330.00 /day x 3 days
P
SUMMARY
Materials P 51,582.72
Labor 7,740.00
Sub-Total P 59,322.72
A. Materials
1,145 bags Portland Cement @ P 250.00 /bag P
64 cu.m. Washed Sand @ 450.00 /cu.m.
127 cu.m. Screened Gravel @ 600.00 /cu.m.
120 cu.m. Filling Materials @ 300.00 /cu.m.
24 pcs. 2" x 6" x 12' Good Lumber @ 974.40 /pc.
8 pcs. 12 mm dia. RSB (Spikes) @ 290.00 /pc.
1 pcs. Concrete Cutting Disc, #14" @ 6,240.00 /pc.
2 pcs. 24" dia. X 1.0m Concrete Pipe @ 3,500.00 /pc.
2 kgs. CW Nails @ 120.00 /kg.
P
B. Labor
1 Construction Foreman @ P 600.00 /day x 15 days P
2 Mason @ 450.00 /day x 15 days
15 Labor @ 330.00 /day x 15 days
P
C. Equipment Expenses
1 Concrete Mixer @ P 1,200.00 /day x 12 days P
1 Concrete Cutter @ 1,200.00 /day x 3 days
P
SUMMARY
Materials P 466,510.10
Labor 96,750.00
Equipment Expenses 18,000.00
Sub-Total P 581,260.10
R E CAPITU LATI O N
I SIGNAGE 5
II AGGREGATE BASE COURSE (Correction) 75
III PORTLAND CEMENT CONCRETE PAVEMENT ( 0.15m X 3.0m x 282.8m ) 738
TOTAL PROJECT COST P 818,5
5,000.00
51,582.72
51,582.72
1,800.00
5,940.00
7,740.00
286,335.00
28,633.50
76,356.00
36,000.00
23,385.60
2,320.00
6,240.00
7,000.00
240.00
466,510.10
9,000.00
13,500.00
74,250.00
96,750.00
14,400.00
3,600.00
18,000.00
5,000.00
75,339.85
738,200.33
818,540.18
Republic of the Philippines
Province of Pangasinan
MUNICIPALITY OF SAN NICOLAS
Source of
Name of Project Issued Release CDC
Fund
Implementation Procedure
BY CONTRACT
P 818,540.18
100.00% P 818,540.18
B. INDIRECT COST
1. OCM 7.83% 64,058.28
2. CP 7.83% 64,058.28
3. VAT 5.48% 44,840.80
SUB-TOTAL - P -
III. CONTINGENCIES/RESERVE
TOTAL ESTIMATED PROJECT COST 100.00% P 818,540.18
Checked by:
ITEM DESCRIPTION UNIT QUANTITY UNIT COST AMOUNT %WEIGHT DURATION 15CD 30CD 45CD 60CD
IV. Portland cement concrete pavement sq. m. 2,400 1,030.58 2,473,387.50 77.29% 45