Engineering Appreciation
Engineering Appreciation
Rate analysis has been carried out in the working rate/output of various
equipments based on output of various similar equipments are required
c) Repair and Maintenance Charges @ 80% of cost of machine per hour 65.43
d) P.O.L charges
Rated HP of Machine 125
Actual fuel consumption = 0.22 x 125 x C1 x C2 27.50
Type factor C1 = 1.0, Type factor C2 = 1.0
e) Labour Charges
Rated Life in hour/year/shift 1,000.00
Regular
1)Operator -1 No. 11,660.00
2) Electrician-1/2 No. 6,600.00
3) Foreman - 1/8 No. 1,911.25
4)Mechanic - 1/3 No. 4,400.00
Sub - Total 24,571.25
Casual
5)Helper-1 No. 8,910.00
6)Chowkidar 1/4 No. 2,101.00
Sub - Total 11,011.00
Total Direct crew charges / month (in Rs.) 35,582.25
Add for indirect crew cost (in Rs.) 25,713.05
(80% of direct charges for regular worker & 55% of direct crew charges for casual
workers
Total crew charges/ month (in Rs.) 61,295.30
I) Cost of Compressor at site including Freight,insurance and all other taxes 735,000.00
ii)Life of air compressor in hours 30,000.00
d) Labour Charges
Rated Life in hour/year/shift 1,000.00
Regular
1)Operator -1 No. 11,660.00
2) Electrician-1/2 No. 6,600.00
3) Foreman - 1/8 No. 1,911.25
4)Mechanic - 1/4 No. 3,300.00
Sub - Total 23,471.25
Casual
5)Helper-1 No 8,910.00
6)Chowkidar 1/4 No. 2,101.00
Sub - Total 11,011.00
Total Direct crew charges / month (in Rs.) 34,482.25
Add for indirect crew cost (in Rs.) 24,833.05
(80% of direct charges for regular worker & 55% of direct crew charges for casual
workers
c) P.O.L charges
FHP of the engine 148.00
Actual Fuel Consumption per hour = 0.22xC1xC2xFHP 32.56
Type factor C1 = 1.00, Duty factor C2 = 1.00
i) Cost of fuel consumption @ Rs.37.08 1,173.02
ii)Cost of lubricants and oil @ 25% of c(I) above. 293.25
iii) Sundries and miscellaneous suplies @10% of (b) above 7.88
d) P.O.L charges
Rated FHP of Machine 200.00
Actual diesel consumption = 0.22 x C1 x C2 x 200 13.20
Type Factor C1 = 0.30 and Duty Factor C2 = 1.00
i)Cost of 13.20 ltr diesel @ Rs.36.03/liter 475.55
ii)Cost of lubricants and oil @ 25% of c(I) above. 118.89
iii) Sundries and miscellaneous supplies @10% of (b) above 32.08
Total P.O.L Charges 626.52
d) Labour Charges
Rated Life in hour/year/shift 1,000.00
Regular
1) Foreman - 1/4 No. 3,822.50
2) Mechanic - 1/4 No. 3,300.00
3) Driver - 1 No. 11,660.00
Sub - total 18,782.50
Casual
4) Helper-1 No. 8,910.00
5) Chowkidar 1/4 No. 2,101.00
Sub - total 11,011.00
Total Direct crew charges / month (in Rs.) 29,793.50
Add for indirect crew cost (in Rs.) 21082.05
(80% of direct charges for regular worker & 55% of direct crew charges for
casual workers
Total crew charges/ month (in Rs.) 50,875.55
Total crew charges/ year (in Rs.) 610,506.60
i) Cost of Rear End Tipper at site including Freight, insurance and all
other taxes and excluding tyres 893,025.00
Life of Rear End Tipper in years 8.00
Life of Rear End Tipper in hours 10,000.00
Annual scheduled production hours 3,000.00
Life time repair provision 175.00
Depreciation charges per hour 241,116.75
Depreciation with reference to year 100,465.31
d) P.O.L charges
Rated HP of Machine 110.00
e)Labour Charges
Rated Life in hour/year 1,000.00
Regular
1) Driver -1 No. 11,660.00
2) Mechanic - 1/8 No. 1,650.00
Sub - Total 13,310.00
Casual
3) Cleaner - 1 No. 8,910.00
4) Chowikar - 1/6 No. 1,400.67
Sub - Total 10,310.67
Total Direct crew charges / month (in Rs.) 23,620.67
Add for indirect crew cost (in Rs.) 16,318.87
(80% of direct charges for regular worker & 55% of direct crew
charges for casual workers
Say 1,035.00
not in bghep
3.6 Material Truck 10 Tonne
Rs./Km
a) Depreciation Charges
i) Cost of Material Truck 10 Tonne at site 644,962.50
including Freight,insurance and all other taxes
and including Tyres
ii) Life of Material Truck 10 Tonne in years 10.00
Life of Material Truck 10 Tonne in Km 200000
Life time repair provision 175.00
Annual Scheduled Operational KM 25,000.00
Depreciation charges
Depreciation in terms of life in years per km. (in 2.32
Depreciation in terms of life in km per km. (in Rs. 2.90
2.61
d) P.O.L charges
Deisel Engine Powered
FHP of Engine 130.00
Hourly Fuel Consumption = 0.22*C1*C2*FHP 8.58
Assuming 25 km per hour, lt/km 0.34
i) Cost of 0.34 litre of Diesel per km. 12.36
ii) Cost of lubricants and oil @ 25% of c(i) above. 3.09
e) Labour Charges
Regular
1) Driver -1 No. 11,660.00
3) Mechanic - 1/8 No. 1,650.00
Sub - total 13,310.00
Casual
4) Cleaner-1 No. 8,910.00
5) Chowkidar 1/6 No. 1,400.67
Sub - total 10,310.67
Total Direct crew charges / month (in Rs.) 23,620.67
Add for indirect crew cost (in Rs.) (80% of 16,318.87
direct charges for regular worker & 55% of
direct crew charges for casual workers)
d) P.O.L charges
FHP of Machine 180
Actual fuel consumption =0.22 x 180 x C1 x C2 22.57
Type factor C1 = 0.57, Duty Factor = 1.0
e) Labour Charges
Rated Life in hour/year 1000
Regular
1) Dozer Driver -1 No. 11,660.00
2) Foreman - 1/4 No. 3,822.50
3) Mechanic - 1/4 No. 3,300.00
Sub - Total 18,782.50
Casual
4) Helper-1 No. 8,910.00
5) Chowkidar 1/4 No. 2,101.00
Sub - Total 11,011.00
d) P.O.L charges
Rated HP of Machine 99
Actual fuel consumption = 0.22 x 99 x C1 x C2 12.41
Type factor C1 = 0.57, Type factor C2 = 1.0
e) Labour Charges
Rated Life in hour/year 1,000.00
Regular
1) Dozer Driver -1 No. 11,660.00
2) Foreman - 1/4 No. 3,822.50
3) Mechanic - 1/4 No. 3,300.00
Sub - Total 18,782.50
Casual
4) Helper-1 No. 8,910.00
5) Chowkidar 1/4 No. 2,101.00
Sub - Total 11,011.00
d) P.O.L charges
FHP of Machine 112
Hourly Fuel Consumption = 0.22 x FHP x C1 x C2 14.29
216.68
105.93
642.00
707.78
556.20
2,228.58
2,229.00
3.10 Hydraulic Excavator 0.6 cum
Rs./Hr
a) Depreciation Charges
Cost of Hydraulic Excavator at site including freight, insurance
and all other taxes 3,024,320.00
Life of Hydraulic Excavator in years 10
Life of Hydraulic Excavator in hours 12000
Annual scheduled production hours 3000
Life time repair provision 150
Depreciation charges in hours 680,472.00
Depreciation charges with reference to life in years 272,188.80
Average depriciation yearly (in Rs.) 476330.4
Average depriciation hourly (in Rs.) 158.78
b) Interest on capital investment
Average annual cost 3024320 X{(12+1)/(2X12)} 1663376.00
Hourly interest-1663376.00X12/100/3000 66.54
c) P.O.L charges
FHP of Machine 131.00
Actual fuel consumption = 0.22 x C1 x C2 x FHP Type Factor C1 14.41
= 0.50, Duty Factor C2 = 1.0
d) Labour Charges
Rated Life in hour/year 1000
Regular
1) Operator -1 No. 11,660.00
2) Foreman - 1/4 No. 3,822.50
3) Mechanic - 1/4 No. 3,300.00
Sub - Total 18,782.50
Casual
4) Helper-1 No. 8,910.00
5) Chowkidar 1/4 No. 2,101.00
Sub - Total 11,011.00
Total Direct crew charges / month (in Rs.) 29,793.50
Add for indirect crew cost (in Rs.) (80% of direct charges for 21,082.05
regular worker & 55% of direct crew charges for casual workers)
a) Depreciation Charges
i) Cost of Diesel Shovel at site including Freight,insurance and all other 4,630,500.00
taxes
Life of Diesel Shovel in years 12
Life of Diesel Shovel in hours 15000
Life time repair provision 150
Annual scheduled Production hours 3000
Depreciation charges per hour 833,490.00
Depreciation with reference to year 347,287.50
Average Depriciation yearly (in Rs.) 590388.75
Average Depriciation hourly (in Rs.)
d) P.O.L charges
FHP of the engine 180.00
Actual fuel consumption = 0.22 x C1 x C2 x FHP, Type Factor C1 = 0.50, 19.80
Duty Factor C2 = 1.00
i) Cost of 19.80 ltr diesel @ Rs.36.03/liter 713.32
ii) Cost of lubricants and oil @ 25% of c(i) above. 178.33
iii) Sundries and miscellaneous supplies @10% of (b) above 46.31
e) Labour Charges
Rated Life in hour/year 1000
Regular
1) Operator -1 No. 11,660.00
2) Foreman - 1/4 No. 3,822.50
3) Mechanic - 1/2 No. 6,600.00
4) Supervisor - 1 No. 13,200.00
Sub - Total 35,282.50
Casual
4) Helper-1 No. 8,910.00
5) Chowkidar 1/4 No. 2,101.00
Sub - Total 11,011.00
Say
Rs./Hr
196.80
463.05
937.96
966.91
2,665.04
2,665.00
3.13 Pressure grout pump
a) Depreciation Charges
i) Cost of machine at site including grouting mixer and grouting agitator 347,800.00
Life of machine in years 10
Life of machine in hours 12000
Annual Scheduled production hours 3000
Life time repair provision 100
Depreciation charges in hours 78,255.00
Depreciation charges with ref to life in years 31,302.00
Average yearly Depreciation (in Rs.) 54778.50
Average hourly Depreciation (in Rs.)
c) P.O.L charges
HP of motor 15.00
Energy required/hour = 15 x 0.746 x1.0 x1.0 , Type factor C1 = 1.0, 11.19
Duty factor C2 = 1.00
i) Cost of 11.19 kwh electric energy @ Rs.12.00/unit 134.28
ii) Cost of lubricants and oil @ 25% of c(i) above 33.57
iii) Sundries and miscellaneous supplies @10% of (b) above 2.90
e) Labour Charges
Rated Life in hour/year 1000
Regular
1) Operator -1 No. 11,660.00
2) Foreman - 1/8 No. 1,911.25
3) Mechanic - 1/6 No. 2,200.00
Sub - Total 15,771.25
Casual
4) Helper-1 No. 8,910.00
5) Chowkidar 1/6 No. 1,400.67
Sub - Total 10,310.67
18.26
7.65
28.98
167.85
532.44
755.18
755.00
3.14 Wet Shortcrete machine 8-18 cum with Robo Arm
Rs./Hr
a) Depreciation Charges
i) Cost of machine at site 8,486,096.00
Life of machine in years 10
Life of machine in hours 15000
Life time repair provision 100
Annual scheduled production hours 3000
Depreciation charges in hours 1,527,497.28
Depreciation charges with ref to life in years 763,748.64
Average yearly depreciation (in Rs.) 1145622.96
Average hourly depreciation (in Rs.) 381.87
b) Interest on capital investment
Average annual cost 8486096 X{(5+1)/(2X5)} 4,667,352.80
Hourly interest-5091657X12%/3000 186.69
d) Labour Charges
Rated Life in hour/year 1000
Regular
1) Operator -2 No. 23,320.00
2) Foreman - 1/8 No. 1,911.25
3) Mechanic - 1/4 No. 3,300.00
Sub - Total 28,531.25
Casual
4) Helper-2 No. 17,820.00
5) Chowkidar 1/4 No. 2,101.00
Sub - Total 19,921.00
Say 4,542.45
4,542.00
3.2 Concrete pump30cum
a) Depreciation Charges
i) Cost of machine at site 1,897,765.00
Life of machine in years 5
Life of machine in hours 8000
Life time repair provision 100
Annual scheduled production hours 2200
Depreciation charges per hour 469,696.84
Depreciation with reference to years 341,597.70
Average yearly depreciation (in Rs.) 405647.26875
c) P.O.L charges
Power of Electric Motor (HP) 60.00
Hourly Energy consumption (KWH) C1=1, C2=1 44.76
Cost of Electricity (Rs.) 537.12
Lubricants- 25% of fuel and elecricity charges 134.28
Hourly POL and Energy Charges (Rs.) 671.40
(e) Miscellaneous Charges (10% of Repair Charges) 23.72
Total P.O.L Charges 695.12
d) Labour Charges
Rated Life in hour/year 1100
Regular
1) Operator -1 No. 11,660.00
2) Foreman - 1/8 No. 1,911.25
3) Mechanic - 1/6 No. 2,200.00
Sub - Total 15,771.25
Casual
4) Helper-1 No. 8,910.00
5) Chowkidar 1/6 No. 1,400.67
Sub - Total 10,310.67
Total Direct crew charges / month (in Rs.) 26,081.92
Add for indirect crew cost (in Rs.) (80% of direct charges for regular 18,287.87
worker & 55% of direct crew charges for casual workers)
Total crew charges/ month (in Rs.) 44,369.78
e) Labour Charges
Rated Life in hour/year 1100
Regular
1) Operator -1 No. 11,660.00
2) Foreman - 1/8 No. 1,911.25
3) Mechanic - 1/4 No. 3,300.00
Sub - Total 16,871.25
Casual
4) Helper-1 No. 8,910.00
5) Chowkidar 1/4 No. 2,101.00
Sub - Total 11,011.00
Total Direct crew charges / month (in Rs.) 27,882.25
Add for indirect crew cost (in Rs.) 19,553.05
(80% of direct charges for regular worker & 55% of direct crew
charges for casual workers
Total crew charges/ month (in Rs.) 47,435.30
Total crew charges/ year (in Rs.) 569,223.60
Hourly Crew charges / hour (in Rs.) 517.48
Hourly Use Rate of Transit Mixer 2.0 cum (Truck mounted) 1818.84
Say 1,819.00
3 Portable Concrete pump 25 cum/hr. capacity
a) Depreciation Charges
I) Cost of machine at site 3,045,000.00
Life of machine in years 5
Life of machine in hours 8000
Annual scheduled production hours 2200
Life time repair provision 75
Depreciation charges in hours 753637.5
Depreciation charges with reference to life in years 548100
Average yearly depreciation (in Rs.) 650868.75
d) P.O.L charges
FHP of the engine 60.00
Fuel consumption = 0.22 x C1 x C2 x FHP 13.20
Type factor C1 = 1.00, Duty factor C2 = 1.00
i) Cost of diesel @ Rs.36.03/hr 475.55
ii) Cost of lubricants and oil @ 25% of c(i) above. 118.89
iii) Sundries and miscellaneous supplies @10% of (b) above 28.55
Electrical Charges
BHP of the engine 67.00
Hourly energy consumption = 0.746xC1xC2xBHP 49.98
Type factor C1 = 1.00, Duty factor C2 = 1.00
i) Cost of 28.49 KWh electric energy @ Rs.2.00/kwh 99.96
ii) Cost of lubricants and oil @ 25% of c(i) above. 24.99
Total P.O.L Charges 747.94
e) Labour Charges
Rated Life in hour/year 1,100.00
Regular
1) Operator -1 No. 11,660.00
2) Foreman - 1/8 No. 1,911.25
3) Mechanic - 1/6 No. 2,200.00
Sub - Total 15,771.25
Casual
4) Helper- 1 Nos. 8,910.00
5) Chowkidar - 1/6 1,400.67
Sub - Total 10,310.67
Say 1,913.00
as per bghep
3.20 Batching and Mixing Plant 40 cum/hour capacity
a) Depreciation Charges
i) Cost of machine at site 6,930,000.00
Life of machine in years 18
Life of machine in hours 30000
Life time repair provision 75
Annual Schedule Production Hours 2200
Depreciation charges in hours 457,380.00
Depreciation charges with ref to life in years 346,500.00
Average Depreciation yearly (in Rs.) 401,940.00
Average Depreciation hourly (in Rs.) 182.70
d) P.O.L charges
KWH of the engine 80.00
Electrical energy consumed 80.00
e) Labour Charges
Rated Life in hour/year 1,100.00
Regular
1) Operator -2 No. 23,320.00
2) Foreman - 1/2 No. 7,645.00
3) Mechanic - 1/2 No. 6,600.00
Sub - Total 37,565.00
Casual
4) Beldar - 6 No. 50,424.00
5) Chowkidar 1 No. 8,404.00
Sub - Total 58,828.00
Say 2,505.00
Production charges/cum 90.76
(Assuming 69% efficiency)
Say 91
not in bghep
3.21 Batching and Mixing Plant 30 cum/hour capacity
a) Depreciation Charges
i) Cost of machine at site 4,113,075.00
Life of machine in years 18
Life of machine in hours 30000
Annual Scheduled production hours 2200
Life time repair provision 75%
Depreciation charges in hours 271,462.95
Depreciation charges with ref to life in years 205,653.75
Average Depreciation yearly (in Rs.) 238,558.35
Average Depreciation hourly (in Rs.) 108.44
Total Depreciation charges 108.44
d) P.O.L charges
KWH of the engine 20.00
Energy required = C1 x C2 x KWh Type factor 20.00
C1=1.00,Duty factor C2=1.00
c) P.O.L charges
HP of motor in HP 40.00
Energy required/hour = 40 x 0.746 x1.0 x1.0 , Type factor C1 = 29.84
1.0, Duty factor C2 = 1.00
i) Cost of 29.84 kwh electric energy @ Rs.12.00/unit 358.08
ii) Cost of lubricants and oil @ 25% of c(i) above 89.52
iii) Sundries and miscellaneous supplies @10% of (b) above 0.38
d) Labour Charges
Regular
1) Operator -1/8 No. 1,457.50
2) Mechanic - 1/8 No. 1,650.00
Sub-Total 3,107.50
Casual
1) Helper - 1/2 No. 4,455.00
Say 620.00
3.24 Aggregate processing and classification plant 60 T
Capacity of plant in MT/hr 60.00
Density of coarse Aggregate in Kg/cum 1,780.00
Ideal production/hour in cum 33.71
Assuming 69% efficiency of Actual production in cum/hour 23.26
a) Depreciation Charges
i) Cost of plant at site including erection 11,058,694.00
Life of machine in years 15.00
Life of machine in hours 30,000.00
Annual scheduled production hours 3,000.00
Life time repair provision 100.00
Depreciation charges in hours 995,282.46
Depreciation charges with ref to life in years 663,521.64
Average Depreciation yearly (in Rs.) 829402.05
Average Depreciation hourly (in Rs.) 276.47
ii)Depreciation of civil works-cost of civil works@10% of plant cost 1,105,869.40
Taking life of civil works as 20000 hrs. 20,000.00
Depreciation charges /hour 55.29
Total Depreciation charges 331.76
c) P.O.L charges
KWH of the engine 186.00
Energy required = C1 x C2 x KWh Type factor 186.00
C1=1.00,Duty factor C2=1.00
i)Cost of 120 kwh electric energy 2,232.00
ii)Cost of lubricants and oil @ 25% of c(i) above. 558.00
iii) Sundries and miscellaneous supplies @10% of (b) above 36.86
d) Labour Charges
Regular
1) Operator - 1 No. 11,660.00
2) Foreman - 1/4 No. 3,822.50
3) Mechanic - 1/4 No. 3,300.00
Sub - Total 18,782.50
Casual
4) Chowkidar - 1 No. 8,404.00
5) Beldar - 6 No. 50,424.00
Sub - Total 58,828.00
d) P.O.L charges
KWH of the engine 600.00
Energy required = C1 x C2 x KWh Type factor 600.00
C1=1.00,Duty factor C2=1.00
i)Cost of 120 kwh electric energy 1,200.00
ii)Cost of lubricants and oil @ 25% of c(i) above. 300.00
iii) Sundries and miscellaneous supplies @10% of (b) above 83.33
e) Labour Charges
Regular
1) Operator - 2 No. 23,320.00
2) Foreman - 1 No. 15,290.00
3) Mechanic - 1/4 No. 3,300.00
Sub - Total 41,910.00
Casual
4) Chowkidar - 1 No. 8,404.00
5) Beldar - 10 No. 84,040.00
Sub - Total 92,444.00
d) P.O.L charges
HP of motor in HP 10.00
Energy required/hour = 10 x 0.746 x1.0 x1.0 , Type factor C1 = 7.46
1.0, Duty factor C2 = 1.00
i) Cost of 7.46 kwh electric energy @ Rs.2.00/unit 14.92
e) Labour Charges
Regular
1) Operator -1/6 No. 1,943.33
2) Mechanic - 1/8 No. 1,650.00
Sub-Total 3,593.33
Casual
1) Helper - 1/2 No. 4,455.00
Say 188.00
as per bghep
3.27 Raise Climber
a)Depreciation Charges
d) P.O.L charges
FHP of the engine 25.00
Consumption of diesel = 0.22 x C1 x C2 x FHP 2.75
e)Labour Charges
Regular
1) Operator -2 No. 23,320.00
2) Foreman - 1/8 No. 1,911.25
3) Mechanic - 1/4 No. 3,300.00
4) Electrician - 1/4 No. 3,300.00
Sub - Total 31,831.25
Casual
5) Helper-2 No. 17,820.00
6) Chowkidar 1/4 No. 2,101.00
Sub - Total 19,921.00
Say 6369.00
as per bghep
3.28 Wagon drill/Air Track
a)Depreciation Charges
I) Cost of machine at site 729,303.75
Life of machine in years 8.00
Life of machine in hours 8,000.00
Annual scheduled production hours 3,000.00
Life time repair provision 80.00
Depreciation charges in hours ( Cost / life in hr x 90% x 3000 ) 246140.02
Depreciation charges with ref to life in years ( 82046.67
Average yearly depreciation (in Rs.) 164093.34
Average hourly depreciation (in Rs.)
d) P.O.L charges
Compressed air required in cfm 400.00
e)Labour Charges
Regular
1) Operator - 1 No. 11,660.00
2) Foreman - 1/8 No. 1,911.25
3) Mechanic - 1/8 No. 1,650.00
Sub-Total 15,221.25
Casual
4) Chowkidar - 1/4 No. 2,101.00
5) Helper - 1 No. 8,910.00
Sub-Total 11,011.00
54.70
72.93
2,637.29
533.58
3314.91
3315.00
3.29 Hydraulic Drill Jumbo - 2 Boom
Cost of Equipment (Rs.) 32,500,000.00
Scheduled Life in years 10.00
Scheduled Life in hours 15,000.00
Life time repair provision (% of Cost of Equipment) 120.00
Estimated annual operational hours 3,000.00
(a) Depreciation
Hourly dereciation wrt life in years 975.00
Hourly dereciation wrt life in hours 1,950.00
Average hourly dereciation (Rs.) 1,462.50
Helper/ SemiSkilled
For Dumper/Dozer/Pocklain/Drill Jumboo/ Rs. 3200 - 85 - 4900 4050 4860
shotcrete machine/conctret pump/crane etc.
Mechanic, Electrician, Supervisor / Skilled Rs. 4500 - 125 - 7500 6000 7200
For Dumper/Dozer/Pocklain/Drill Jumboo/
shotcrete machine/conctret pump/crane etc.
8910
11660
13200
15290
3.31 Rock Bolter, Fully Mechanised
Cost of Equipment (Rs.) 17,500,000.00
Scheduled Life in years 10.00
Scheduled Life in hours 15,000.00
Life time repair provision (% of Cost of Equipment) 120.00
Estimated annual operational hours 3,000.00
(a) Depreciation
Hourly dereciation wrt life in years 525.00
Hourly dereciation wrt life in hours 1,050.00
Average hourly dereciation (Rs.) 787.50
b) Interest on capital investment
Average annual cost 17,500,000.00 X(10+1)/(2X10) 9,625,000.00
Hourly interest-9,625,000.00X12%/3000.00 385.00
(a) Depreciation
Hourly dereciation wrt life in years 715.91
Hourly dereciation wrt life in hours 1,050.00
Average hourly dereciation (Rs.) 882.955
a)Depreciation Charges
I) Cost of machine at site 3,500,000
Life of machine in years 10
Life of machine in hours 10000
Annual scheduled production hours 2200
Life time repair provision 120
Depreciation charges in hours 693000
Depreciation charges with ref to life in years 315000
Average Depreciation yearly (in Rs.) 504000
d) P.O.L charges
FHP of the engine 160.00
Fuel consumption per hour = 0.22 x C1 x C2 x FHP in liter 10.56
Type factor C1 = 0.30, Duty factor C2 = 1.00
e)Labour Charges
Rated Life in hour/year 1100
Regular
1) Operator -1 No. 11,660.00
2) Foreman - 1/8 No. 1,911.25
3) Mechanic - 1/4 No. 3,300.00
Sub - Total 16,871.25
Casual
4) Helper-1 No. 8,910.00
5) Chowkidar 1/4 No. 2,101.00
Sub - Total 11,011.00
Hourly Use Rate of Transit Mixer 2.5 cum (Truck mounted) 1789.12
Say 1789.00
as per bghep
3.12 Electric Shovel 3 cum
Rs./Hr
a) Depreciation Charges
i) Cost of Electric Shovel at site including Freight,insurance and all 10,997,437.50
other taxes
Life of Electric Shovel in years 15
Life of Electric Shovel in hours 25000
Annual Scheduled production hours 3000
Life time repair provision 150
Depreciation charges in hours 1,187,723.25
Depreciation charges with res. to life in years 659,846.25
Average yearly depreciation (in Rs.) 923784.75
Average yearly depreciation (in Rs.) 307.93
e) Labour Charges
Rated Life in hour/year 1,000.00
Regular
1) Operator -1 No. 6,825.00
2) Foreman - 1/4 No. 3,150.00
3) Mechanic - 1/2 No. 4,200.00
4) Supervisor - 1 No. 2,625.00
5) Electrician - 1/2 No. 3,675.00
Sub - Total 20,475.00
Casual
6) Helper-1 No. 6,300.00
7) Chowkidar 1/4 No. 918.75
8) Cableman - 1 No. 3,675.00
Sub - Total 10,893.75
a)Depreciation Charges
d) P.O.L charges
BHP of the engine 20.00
Energy required = 0.746 x C1 x C2 x BHP 14.92
e)Labour Charges
Rated Life in hour/year 1,000.00
Regular
1) Operator -1 No. 6,825.00
2) Electrician - 1/8 No. 918.75
3) Mechanic - 1/4 No. 2,100.00
Sub - Total 9,843.75
Casual
1) Helper 1 No. 6,300.00
1.58
1.58
37.46
329.81
371.39
371
3.19 Centrifugal Pump 10 HP
a) Depreciation Charges
Cost of machine at site 25,000.00
Life of machine in years 12
Life of machine in hours 20000
Annual scheduled production hours 3000
Life time repair provision 70
Depreciation charges in hours 3,375.00
Depreciation charges with ref to life in years 1,875.00
Average yearly depreciation (in Rs.) 2625
c) P.O.L charges
BHP of the engine 10.00
d) Labour Charges
Rated Life in hour/year 1,000.00
Regular
1) Operator -1 /2 No. 3,412.50
2) Electrician - 1/8 No. 918.75
3) Mechanic - 1/8 No. 1,050.00
Sub - Total 5,381.25
Casual
1) Helper 1 No. 6,300.00
Say 254
D.G Set (500 KVA)
a) Deprecation
1 Cost of equipment at site 2854958
Life in hours 30000
Life in Year 15
Annual Scheduled Production hours 3000
Hourly deprecation (Cost / Life in hours) 256946.22
Depreciation charges with reference to life in years 171297.48
Average yearly depreciation charges 214121.85
Average hourly depriciation (in Rs.) 71.37395
2 Interest on capital investment
Average annual cost 2854958 X{(15+1)/(2X15)} 1522644.267
Hourly interest-1522644.27X12/100/3000 60.91 60.91
Total 214254.13
b) Repair & Maintanence
R&M Charges @120% 120 114.20
Operator 1 10000 40
Electrician 0.5 11000 22
Foreman 0.125 20000 10
Mechanic 0.33 14000 18.67
90.67
Helper 1 7000 28
Chowkidar 0.25 6500 6.5
34.5
Direct Charges 125.167
Add for indirect charges(80% on skilled&55%on
unskilled) 91.51
216.68 216.68
Hourly use rate of equipment (D.G.Set) 3863.19
earlier 15%
3.7 D.G Set (500 KVA)
i) Cost of DG SET at site including Freight,insurance and all other taxes 2854958
Life of Crawler dozer in years 15
Life of Crawler dozer in hours 30000
Annual Scheduled production hours 3000
Life time repair provision 120
Depreciation charges in hours 256,946.22
Depreciation with reference to life in years 171,297.48
d) P.O.L charges
FHP of Machine 600
Actual fuel consumption =0.22 x 600 x C1 x C2 75.24
Type factor C1 = 0.57, Duty Factor = 1.0
e) Labour Charges
Rated Life in hour/year 3000
Regular
1) Dozer Driver -1 No. 11,660.00
2) Foreman - 1/4 No. 3,822.50
3) Mechanic - 1/4 No. 3,300.00
4) Electrician - 1/4 No. 3,300.00
Sub - Total 18,782.50
Casual
4) Helper-1 No. 8,910.00
5) Chowkidar 1/4 No. 2,101.00
Sub - Total 11,011.00