The document outlines the tasks, duration, predecessors and resources required to complete an engineering project. It involves basic design, hardware and software development, procurement, fabrication, installation and testing. Various roles like project managers, designers, engineers, testers, purchasers etc. are required with different skill levels. The number of resources estimated for each task range from 1 to 15 depending on the type of work and skills required to complete the task successfully within the scheduled timelines.
Download as XLSX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
33 views
MS PRoject Exercise
The document outlines the tasks, duration, predecessors and resources required to complete an engineering project. It involves basic design, hardware and software development, procurement, fabrication, installation and testing. Various roles like project managers, designers, engineers, testers, purchasers etc. are required with different skill levels. The number of resources estimated for each task range from 1 to 15 depending on the type of work and skills required to complete the task successfully within the scheduled timelines.
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 6
S.No.
Task Name Duration Predecessors
1 Basic Design 10 wks
2 Hardware A 3 Design of A 8 wks 1 4 Drawings of A 5 wks 3 5 Hardware B 6 Design of B 6 wks 1 7 Drawings of B 4 wks 6 8 Software Specification 2 wks 6 9 Freezed design 0 wks 8 10 Fabrication 11 Part A 12 Assembly of A 1 wk 24,4 13 Test of A 2 wks 12 14 Part B 15 Assembly of B 5 wks 7,27 16 Test of B 3 wks 15 17 Site Operations 18 Installation Drawings 5 wks 3,6 19 Final Installation 8 wks 18,13,16 20 Test 6 wks 19,30 21 Procurement 22 Part A 23 Purchase A 4 wks 3 24 Delivery A 3 wks 23 25 Part B 26 Purchase B 4 wks 6 27 Delivery B 5 wks 28 Software 29 Purchase Software 5 wks 8 30 Delivery software 3 wks 29 Number of Resources Task description Resource required Basic Design Project Manager 2 Assistant Manager 10 Project Engineer 9 Hardware Design A Design head 2 Senior Designer 9 Junior Designer 8 Hardware Design B Design head 3 Senior Designer 15 Junior Designer 14 Drawings B Senior Draftsman 3 Junior Draftsman 3 Software specs Project Manager 5 Assistant Manager 8 Project Engineer 8 Parts Purchase B Purchase head 1 Purchase staf 1 Parts Purchase A Purchase head 1 Purchase staf 1 Drawings A Senior Draftsman 9 Junior Draftsman 9 Installation Drawings Design head 6 Senior Draftsman 8 Junior Draftsman 9 Software Purchase Purchase head 1 Purchase staf 1 Delivery B Project Manager 1 Delivery A Project Manager 1 Delivery Software Project Manager 1 Assembly A Project Manager 1 Senior engineer 7 Junior Engineer 8 Assembly B Project Manager 2 Senior engineer 14 Junior Engineer 14 Test A Testing head 1 Senior Tester 10 Junior Tester 10 Test B Testing head 1 Senior Tester 10 Junior Tester 10 Final Installation Project Manager 3 Senior engineer 10 Junior Engineer 8 Final Test Testing head 3 Senior Tester 11 Junior Tester 7 Resource Name Type Material Label Initials Group Max. Units Std. Rate
Project Work P Managerial 200% $120.00/hr
Managers Assistant Work A Managerial 1000% $96.00/hr Manager Senior Work S Design 1000% $96.00/hr Designers
Design Heads Work D Design 200% $104.00/hr
Junior Work J Design 1200% $80.00/hr
Designers Senior Work S Design 500% $104.00/hr Draftsman Junior Draftsman Work J Design 10000% $72.00/hr
Project Work P Engineering 900% $60.00/hr
Engineers Junior Work J Engineering 1000% $80.00/hr Engineers