HINDUSTAN CONSTRUCTION
COMPANY LTD.
2012-2013
SUBMITTED BY: SUBMITTED TO:
BRANCH: CIVIL
R.N. MODI ENGINEERING COLLEGE, KOTA
RAJASTHAN TECHNICAL UNIVERSITY
NAME: KETAN TAK
ROLL NO. :- 09ERNCE024 PAGE NO:- ..
B.TECH IV YEAR (CE) BATCH:-A-1
R.N. MODI ENGINEERING COLLEGE, KOTA
RAJASTHAN TECHNICAL UNIVERSITY
NAME: KETAN TAK
ROLL NO. :- 09ERNCE024 PAGE NO:- ..
B.TECH IV YEAR (CE) BATCH:-A-1
TABLE OF CONTENTS
S.No. PARTICULARS
1. Introduction About the Company.
2. Introduction About the Project.
3. Safety Training.
4. Geology of Site.
5. Blasting Process.
6. Excavation Process.
7. Drilling Process.
8. Grouting Process.
9. Test in Laboratory.
10. Water Proofing.
11. Survey during work.
12. Reinforcement Work.
13. Batching Plant.
14. Crushing Plant.
15. Sand Washing Plant.
16. Conclusion.
R.N. MODI ENGINEERING COLLEGE, KOTA
RAJASTHAN TECHNICAL UNIVERSITY
NAME: KETAN TAK
ROLL NO. :- 09ERNCE024 PAGE NO:- 01
B.TECH IV YEAR (CE) BATCH:-A-1
PREFACE
Project gives an opportunity to implement the principles and
knowledge practically. The experience that one gets
wonderful because what one studies in books is different
from what one fact in the field.
1.
INTRODUCTION ABOUT THECOMPANY
TheHINDUSTAN CONSTRUCTIONCOMPANY INDIALTD. Is the
dignified and indeligible company of India. This company was
established in 27thJan,1926 near MUMBAI with the golden hand
of WALCHAND HIRACHAND, son of cloth merchant in
Sholapur, Maharashtra.
2.
ABOUTTHE PROJECT- &
TECHNICAL SPECIFICATION
1. PROJECT:- Two units of 700 MWe PHWR type nuclear
reactors.
2. LOCATION:- Right bank of Chambal River in Kherli
block
Tehsil- Rawatbhata & 64 KM from Kota (Rajasthan).\
I. Temprat
ure:- Maximum dry bulb temperature 48.7°C; Minimum 3.9°C
.(d). Humidity:- Maximum RH=100% ; Minimum RH=1%
II.Nuclear Building
a. Raft
b. Reactor Building consist of Inner Containment Wall (ICW)
& Outer Containment Wall (OCW).
c. Reactor Auxiliary Building consist Spent Fuel Storage Bay
(SFSB).
11.Dewatering
12.Sewage treatment plant
13.Material & Service by NPCIL
14.Drawing
15.Specifications
16.Layout
17.Quantities
18.Rates:- Labor, materials, tools & plant appliances,Transport,
equipment, taxes, duties, devices & octopi.
19. Testing Requirements for construction materials.
R.N. MODI ENGINEERING COLLEGE, KOTA
RAJASTHAN TECHNICAL UNIVERSITY
NAME: KETAN TAK
ROLL NO. :- 09ERNCE024 PAGE NO:- 11
B.TECH IV YEAR (CE) BATCH:-A-1
3. SafetyTraining
In safety training safety instructor tell us of use of safety
equipment at construction site.
4. Geologyof Site
The rock is predominantly Quartzite sand stone
generally hard and compact with inter bedded
shale seams and clay strain. The site investigation
of the foundation rock carried out by drilling and
coring has sand stone to a depth of over 6m and
drilling core in rock up to of 3m below ground
surface.
NPCIL awarded the construction of nuclear plant
7&8 at RAPP, to HCC. As part of this work, about
15lakh cubic meter of hard rock has to be excavated
by drilling and blasting method for site grading and
foundation excavation. The excavation site is located
close to operating nuclear plant.
R.N. MODI ENGINEERING COLLEGE, KOTA
RAJASTHAN TECHNICAL UNIVERSITY
NAME: KETAN TAK
ROLL NO. :- 09ERNCE024 PAGE NO:- 13
B.TECH IV YEAR (CE) BATCH:-A-1
5. Blasting
Blast Details-
Size of Blast- 115mm diameter.
Drilling Machine- IR Crawler/ Tire mounted.
Burden- About 2.0m to 3.0m. (… Burden<Spacing)
Spacing-About 2.5m to 3.5 m.
No. of Holes- 8 to 61.
Depth-3m to 9m.
Explosive-Raj blast (83mm dia, 2.78Kg Booster and 450mm long)
Charge per hole-11Kg to 61Kg depending on depth of hole.
Explosion Used-
Detonator and Fuse Wire
In under water excavation an electric detonator shall be used.
In dry weather and normal dry excavation, ordinary low explosive
black powder (Gun Powder) in granular form may be used. Granular
black blasting powder in small charges (as in hole 1500mm to
1650mm deep, and 30 to
40mm dia.). As per use the size of hole increased about 150mm.
R.N. MODI ENGINEERING COLLEGE, KOTA
RAJASTHAN TECHNICAL UNIVERSITY
NAME: KETAN TAK
ROLL NO. :- 09ERNCE024 PAGE NO:- 14
B.TECH IV YEAR (CE) BATCH:-A-1
6. EXCAVATION
Excavation- Excavation carried out in two stages-
1- Excavation comprising of area.
2- Excavation are completed and accepted by engineer.
1. SIBY 1000cum/8hr.
2. MCC 550cum/8hr.
3. KCPL 1000cum/8hr.
7. Drilling
Scope of Drilling-
1. Erection of rotary drilling rigs at required location.
2. Collection of soil and rock samples.
R.N. MODI ENGINEERING COLLEGE, KOTA
RAJASTHAN TECHNICAL UNIVERSITY
NAME: KETAN TAK
ROLL NO. :- 09ERNCE024 PAGE NO:- 15
B.TECH IV YEAR (CE) BATCH:-A-1
Purpose of Drilling-
1. To find geological information.
2. Description of extent and nature of sub-surface material.
3. Soil/Rock characteristics.
4. Depth of ground water table.
Equipment Required-
1. Total Station
2. Auto Level
3. Rotary Drilling Rigs (Vol. 90, Long layer, KLR tractor, Mounted
Hydraulic drilling rig).
4. Tripod set with pulley.
5. Drilling rod.
8. Triplex/Water Pump.
9. Measuring Tape (3m and 30m).
10. Pressure gauge.
Procedure-
1. Survey of area. Survey for Borehole drilling.
2. Drilling in overburden soil-
a) Machine set up at borehole location.
b) Borehole drilling by hydraulic rotary drilling rig of 100mm dia.
c) Temporary casing will be provided to support of the borehole,
when drilled through loose, very soft soil to avoid collapse of
borehole.
3. Rotary drilling in rock-
a) Method.
b) Drill rod and core barrels
c) Drilling Fluid-Clean potable water
d) Type of Bit-Diamond tippedcore bit
e) Drilling Run-Not exceed 3m in length.
R.N. MODI ENGINEERING COLLEGE, KOTA
RAJASTHAN TECHNICAL UNIVERSITY
NAME: KETAN TAK
ROLL NO. :- 09ERNCE024 PAGE NO:- 17
B.TECH IV YEAR (CE) BATCH:-A-1
Precautions-
1) To prevent surface water into pit.
2) Warning signboard and safety barricade provided.
3) Powder connection will be protected.
4) Grouting.
8. Grouting
Consolidation Grouting is the process of filling the cracks. Holes
in Grouting- There are two types of holes
i. Primary Hole
ii. Secondary Hole
iii. Tertiary Hole
iv. Agitator
v. Mixing Drum
Plugging-It is the process to fill the hole with sand and cement
in ratio of (1:2).
Grout Mix- Grout Mix is the mix of sand and cement in ratio of
(1:2,1:15,1:10,1:5,1:.05,etc.).
surface there may be different type of cracks and faults. Which causes
out.
Purpose of Grouting-
To fill up the sub surface voids in between rock layers. If it is not done
Procedure of Grouting-
1. Primary Holes-
a) Spacing of holes- 6m c/c.
b) Depth of holes- 9m(from existing ground level)
c) 1st Stage- 1] Perculation from 3 to 9m depth.
d) 2nd Stage- 1] If there cracks or voids or faults is there a cer
R.N. MODI ENGINEERING COLLEGE, KOTA
RAJASTHAN TECHNICAL UNIVERSITY
NAME: KETAN TAK
ROLL NO. :- 09ERNCE024 PAGE NO:- 20
B.TECH IV YEAR (CE) BATCH:-A-1
9 . TESTING LABORATORY
Introduction of Concrete testing lab-
1. Compression Testing Machine(CTM)
2. Flexural Test of Concrete for Beam
3. Soundness Test of Cement
(Expansion of Cement, ”Le Chatelier’s Principal”)
4. Aggregate Abrasion Test
5. Workability or Slump test on Concrete
6. Air Content Test on Concrete
7. Flakie longation Test
8. Sieve analysis of coarse aggregate
9. Sieve analysis of fine aggregate
10. Sand present in aggregate
R.N. MODI ENGINEERING COLLEGE, KOTA
RAJASTHAN TECHNICAL UNIVERSITY
NAME: KETAN TAK
ROLL NO. :- 09ERNCE024 PAGE NO:- 22
B.TECH IV YEAR (CE) BATCH:-A-1
CONCRETE TESTING\LAB
Experiment-1
Compression Testing Machine
USE- Compressive strength test on concrete remove
before 24hrs. Whenever cube is coated.
NOTE:- Load in UTM=140
Kg/cm2. Size of Cube
Mould=15x15x15 cm.
PROCEDURE-
1. Remove the specimen from curing tank.
2. Place the specimen in Compression Testing Machine (CTM),
Capacity-
3000KN.
3. Place the cube so that caste face shall not be at top or bottom.
4. In case so that cast face shall not be capped using Sulphur
Capping. “Sulphur Capping is for the finishing of cube
layer.”
5. Align the axis of specimen with center of thrust of spherically seated
platen
6. Apply the load till specimen break or crack.
R.N. MODI ENGINEERING COLLEGE, KOTA
RAJASTHAN TECHNICAL UNIVERSITY
NAME: KETAN TAK
ROLL NO. :- 09ERNCE024 PAGE NO:- 23
B.TECH IV YEAR (CE) BATCH:-A-1
\ 10. WaterProofing
Water Proofing in Horizontal Surface -
1-AUTO LEVEL
ApparatusUsed-Tripod,Auto-level,Prism,Shaft, Measuring
Tap etc.
Procedure-forTemporaryarrangement
R.N. MODI ENGINEERING COLLEGE, KOTA
RAJASTHAN TECHNICAL UNIVERSITY
NAME: KETAN TAK
ROLL NO. :- 09ERNCE024 PAGE NO:- 31
B.TECH IV YEAR (CE) BATCH:-A-1
1)Setthetripodinlevel(3legsarelevelandequal).
2)Setauto levelontripod.
3)Setbubbleincenter.
4)Read thereading in cross hair level.
ObservationTable forCalculation-
B.S.-Back Sight
I.S.-Intermediate Sight Height of Instrument R.L.-Reduced
Level F.S.-Fore Sight Formulae-
H.I. =R.L.+B.S.
R.L. = I.S.- H.I.
F.S. = H.I. – R.L. of staff in fore direction
2-TOTAL STATION
R.N. MODI ENGINEERING COLLEGE, KOTA
RAJASTHAN TECHNICAL UNIVERSITY
NAME: KETAN TAK
ROLL NO. :- 09ERNCE024 PAGE NO:- 32
B.TECH IV YEAR (CE) BATCH:-A-1
12. ReinforcementWork
Material- HYSD bar and TMT bar Fe 500 to IS 1786.
In Fe 500 steel elongation not more than 14.5% ultimate
tensile strength of bar 15% more than actual 0.2%
proof stress/yield stress.
Storage-Reinforcement steel shall not keep direct contact
with ground; it is kept on timber sleepers or concrete
pedestal. Bending of Reinforcement-The reinforcement
bar shall be
cold bent at appropriate radius of minimum 6D using
“Bar Bending Machine” with proper mandrill. Load
shall be applied gradually on bar.
Lying of Reinforcement- The bars are placed as
according to reinforcement diagram. Chair/ Spacer
made up of reinforcement steel bar shall be provided to
keep the bars in position. The radius of bent is less than 6
times the diameter for HYSD TMT bars. Reinforcement
shall be tied with each other 16 gauge where the spacing
of re-bars is greater than
300mm both ways. If spacing of the bars is less than
300mm, only alternate joint shall be tied both ways.
Spacing- R*Ø
R.N. MODI ENGINEERING COLLEGE, KOTA
RAJASTHAN TECHNICAL UNIVERSITY
NAME: KETAN TAK
ROLL NO. :- 09ERNCE024 PAGE NO:- 33
B.TECH IV YEAR (CE) BATCH:-A-1
TypesofBarsusedinconstructionofReactorBuilding:-
S.No. Name of Bar Diameter of Type of Bar
Aggregate Store-40m3
Admixture Concrete- Cement+Additive+Water+Ice+Aggregate
Storage Bin-
1. 10mm aggregate
2. 20mm aggregate
3. Sand-20mm aggregate(Crush Sand and Natural Sand both)
14. CRUSHING
PLANT
Crushing of stones in machine as per requirement of size of aggregate.
BC-1 Jaw Crusher- To crush 82-100mm size boulders.
BC-2 Chock Pile- Hydrocone Crusher- 10, 20, 40mm
size aggregate.
BC-6 Screen-1 for greater than 40mm size aggregate.
BC-7 VSI Hopper(Vertical Shaft Impector) is used for stock the
aggregate.
BC-8 VSI Crusher(Vertical Shaft Impector) is used for plane the
aggregate.
16. CONCLUSION
On concluding the training report , I would like to say that I got a
good overview of NPCIL & HINDUSTAN CONSTRUCTION CO. LTD.
I learn about the practical knowledge at site. I learnt about many
instrument at the site. I think this training will come good in future use.
Apart from my area of project I also got an idea that “ How to do
work at construction site”, which is important in my future.