0% found this document useful (0 votes)
1K views

Bill of Materials: Description Quantity Unit Cost Amount I Layout / Stakeout and Earthworks

The document is a bill of materials for a proposed two-storey residential building project. It includes estimates for: 1) Excavation, earthworks and gravel bedding totaling P32,814. 2) Reinforced concrete works like footings, slabs and beams totaling P259,481.92. 3) Masonry works like installing hollow blocks and plastering totaling P99,955.

Uploaded by

Jm Barangco
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views

Bill of Materials: Description Quantity Unit Cost Amount I Layout / Stakeout and Earthworks

The document is a bill of materials for a proposed two-storey residential building project. It includes estimates for: 1) Excavation, earthworks and gravel bedding totaling P32,814. 2) Reinforced concrete works like footings, slabs and beams totaling P259,481.92. 3) Masonry works like installing hollow blocks and plastering totaling P99,955.

Uploaded by

Jm Barangco
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 35

BILL OF MATERIALS

PROJECT: PROPOSED TWO-STOREY RESIDENTIAL BUILDING


OWNER: TERESITA ILAO
LOCATION: LUMANG BAYAN, CALAPAN CITY

DESCRIPTION QUANTITY UNIT COST AMOUNT

I LAYOUT / STAKEOUT AND EARTHWORKS


Excavated Materials 16.58 cu. m. 300.00 P 4,974.00
Gravel Bedding 34.80 cu. m. 800.00 P 27,840.00

SUB-TOTAL P 32,814.00

II REINFORCED CONCRETE 46.639 cu. m.

1. COLUMN FOOTINGS 2.16 cu. m.


Portland Cement 19.44 bags @ 250.00 P 4,860.00
Gravel ¾” 2.16 cu. m. @ 800.00 1,728.00
Sand 1.08 cu. m. @ 600.00 648.00
16 mm Ø def.bars x 6 m 20 pcs. @ 290.00 5,800.00
# 16 Tie Wire 2 kgs. @ 70.00 154.00
P 13,190.00

2. WALL FOOTINGS 3.312 cu. m.


Portland Cement 29.808 bags @ 250.00 P 7,452.00
Gravel ¾” 1.17 3.312 cu. m. @ 800.00 2,649.60
Sand 0.58 1.656 cu. m. @ 600.00 993.60
10 mm Ø def.bars x 6 m 28 pcs. @ 220.00 6,160.00
# 16 Tie Wire 3 kgs. @ 70.00 210.00
P 17,465.20

3. GROUND FLOOR SLAB 5.800 cu. m.


Portland Cement 43.5 bags @ 250.00 P 10,875.00
Gravel ¾” 5.8 cu. m. @ 800.00 4,640.00
Sand 2.9 cu. m. @ 600.00 1,740.00
P 17,255.00

4. COLUMNS 3.821 cu. m.


Portland Cement 34.3872 bags @ 250.00 P 8,596.80
Gravel ¾” 3.32 3.82 cu. m. @ 800.00 3,056.64
Sand 1.66 1.91 cu. m. @ 600.00 1,146.24
16 mm Ø def.bars x 6 m 36 pcs. @ 290.00 10,440.00
10 mm Ø def.bars x 6 m 75 pcs. @ 140.00 10,500.00
# 16 Tie Wire 16 kgs. @ 70.00 1,120.00
P 34,859.68

5. SECOND FLOOR BEAMS 3.312 cu. m.


Portland Cement bags
32.5008 @ 250.00 P 8,125.20
Gravel ¾” 8.69 3.6112 cu. m. @ 800.00 2,888.96
Sand 4.34 1.8056 cu. m. @ 600.00 1,083.36
16 mm Ø def.bars x 6 m 46 pcs. @ 220.00 10,120.00
10 mm Ø def.bars x 6 m 76 pcs. @ 140.00 10,640.00
# 16 Tie Wire 16 kgs. @ 70.00 1,120.00
P 33,977.52

6. SECOND FLOOR SLAB 5.800 cu. m.


Portland Cement 43.5 bags @ 250.00 P 10,875.00
Gravel ¾” 10.08 5.8 cu. m. @ 800.00 4,640.00
Sand 5.04 2.9 cu. m. @ 600.00 1,740.00
10 mm Ø def.bars x 6 m 207 pcs. @ 140.00 28,980.00
# 16 Tie Wire 27 kgs. @ 70.00 1,890.00
P 48,125.00

7. ROOF BEAMS 3.312 cu. m.


Portland Cement bags
32.5008 @ 250.00 P 8,125.20
Gravel ¾” 7.61 3.6112 cu. m. @ 800.00 2,888.96
Sand 3.80 1.8056 cu. m. @ 600.00 1,083.36
16 mm Ø def.bars x 6 m 46 pcs. @ 220.00 10,120.00
10 mm Ø def.bars x 6 m 76 pcs. @ 140.00 10,640.00
# 16 Tie Wire 16 kgs. @ 70.00 1,120.00
P 33,977.52

8. STAIRS 1.155 cu. m.


Portland Cement 11 bags @ 250.00 P 2,750.00
Gravel ¾” 7.61 1.2 cu. m. @ 800.00 960.00
Sand 3.80 0.6 cu. m. @ 600.00 360.00
16 mm Ø def.bars x 6 m 11 pcs. @ 220.00 2,420.00
10 mm Ø def.bars x 6 m 7 pcs. @ 140.00 980.00
# 16 Tie Wire 1.6 kgs. @ 70.00 112.00
` P 7,582.00

9. FORMWORKS
Assorted sizes of lumber 396 bd.ft. @ 16.00 P 6,336.00
Assorted sizes of nails 25 kgs. @ 70.00 1,750.00
1/4 marine plywood 27 pcs. @ 450.00 12,150.00
P 20,236.00

SUB-TOTAL P 259,481.92

III MASONRY and plastering WORKS sq.m.

1.1 INSTALLATION sq.m.


100 mm CHB 946 pcs. @ 7.00 P 6,622.00
150 mm CHB 1844 pcs. @ 9.00 16,596.00
Portland Cement 92 bags @ 250.00 23,000.00
Sand 16 cu. m. @ 600.00 9,600.00
10 mm Ø def.bars x 6 m 124 pcs. @ 140.00 17,360.00
# 16 Tie Wire 7.1 kgs. @ 70.00 497.00
73,675.00

2.1 FINISHING/PLASTERING 442.161 sq.m.


Portland Cement 67 bags @ 250.00 22,500.00
Sand 5.3593 cu. m. @ 600.00 3,600.00
Screen 1 mtrs @ 60.00 180.00
P 26,280.00

SUB-TOTAL P 99,955.00

V ROOFING WORKS 115.558 sq.m.

1. ROOF FRAMING, TRUSSES / RAPTERS & PURLINS


2" x 2" x 3/16" L-BAR 12 pcs. @ 850.00 P 10,200.00
1 1/2" x 1 1/2" x 3/16" L-BAR 18 pcs. @ 600.00 10,800.00
2" x 3" x 1.2mm C-purlins 18 pcs. @ 450.00 8,100.00
Welding Rod 20 kgs. @ 90.00 1,800.00
Epoxy Primer w/ epoxy reducer ( 6 gal. @ 680.00 4,080.00
Epoxy Enamel 6 gal. @ 1,200.00 7,200.00
Lacquer Thinner 2 gal. @ 356.00 712.00
Paint Brush 4 pcs. @ 50.00 200.00
P 43,092.00

2. PRE-PAINTED ROOFING AND ACCESSORIES


0.40mm Pre-Painted Multi R-SPA 21.000 l.m. @ 360.00 P 7,560.00
28.5 0.40mm Pre-Painted Flashing (4' x 8') 2 pcs. @ 700.00 1,400.00
Tekscrew 1,200 pcs. @ 2.00 2,400.00
Blind Rivet 2 box @ 350.00 700.00
Water Proofing Paint (concrete gutter) 5 gal. @ 850.00 4,250.00
P 16,310.00

SUB-TOTAL P 59,402.00

VI DOORS AND WINDOWS

A. DOORS
1.98 x 2.06m Aluminum Flush Door w/ jamb 1 set @ 4,500.00 4,500.00
1.88 x 2.21m Aluminum Flush Door w/ jamb 4 set @ 4,500.00 18,000.00
1.69 x 2.21m Glass Door w/ jamb 0 set @ 4,000.00 0.00
0.76 x 2.16m Aluminum Flush Door w/ jamb 2 set @ 2,200.00 4,400.00
0.81 x 2.22m Aluminum Flush Door w/ jamb 0 set @ 2,200.00 0.00
26,900.00
B. WINDOWS
4
1.20 x 1.20m Sliding Window @ brown Alu. Frame w/ screen set @ 4,500.00 18,000.00
0.73 x 0.39m Awningg Window @ Alu. Fram 3 set @ 3,200.00 9,600.00
27,600.00

SUB-TOTAL P 54,500.00

VII CARPENTRY WORKS


CEILING, CABINETS AND OTHER MISC. CARPENTRY WORKS
PLYWOOD 11 bd.ft.@ 1050 Php 11550
NAILS 2 kgs @ 90 Php 180
2"x2" COCO LUMBER 23 bd.ft.@ 13 Php 299
P 12029

SUB-TOTAL P 12,029.00

VIII TITLE WORKS AND MISCELINOUS WORKS

GROUND FLOOR and SECOND FLOOR


TILES 131.356 sq.m.@ 200 Php 26271.2
TILE GROUT 3 Kgs @ 250 Php 750
TILE ADHESIVE 30 Kgs @ 235 Php 7050
STEEL WORKS LS mtrs @ LS Php 15000
P 49071.2

SUB-TOTAL P 49,071.20

IX ELECTRICAL WORKS

ELECTRICAL CONDUITS 12 pcs @ 65 Php 780


JUNCTION BOXES 33 pcs @ 25 Php 825
ELECTRICAL FITTINGS 30 pcs @ 150 Php 4500
ELECTRICAL WIRES THWN/THHN 2 sq.m. 3 roll 80 Php 240
ELECTRICAL WIRES THWN/THHN 3.5 sq.m 3 roll 4500 Php 13500
ELECTRICAL WIRES THWN/THHN 8.0 sq.m 5 roll 5000 Php 25000
PVC CONDUIT PIPE 15mm 2 roll 75 Php 150
PVC CONDUIT PIPE 16mm 3 roll 85 Php 255
SINGLE GANG SWITCH 3 pcs @ 60 Php 180
DOUBLE GANG SWITCH 18 pcs @ 150 Php 2700
TRIPLE GANG SWITCH 9 pcs @ 200 Php 1800
POWER OUTLET 13 pcs @ 50 Php 650
LIGHTING OULET 6 pcs @ 50 Php 300
PANEL BOARD 3 pcs @ 1500 Php 4500
AIRCONDITION UNIT 3 pcs @ 5000 Php 15000
Php 70380

SUB-TOTAL P 70,380.00

X PLUMBING WORKS
Septic Tank (3.0 x 2.0m) 0 unit @ 20,000.00 0.00
WATER CLOSET 3 set @ 2512 Php 7536
LAVATORY W/ FITTINGS & ACC. 2 set @ 1500 Php 3000
FAUCET 4 pcs @ 110 Php 440
PVC Orange #4 8 pcs @ 578 Php 4624
PVC Pipe #2 5 pcs @ 78.08 Php 390.4
Blue Pipe 1/2 10 pcs @ 61.76 Php 617.6
SHOWER HEAD W/ VALVE 2 pcs @ 650 Php 1300
KITCHEN SINK 3 pcs @ 1200 Php 3600
FLOOR DRAIN 3 pcs @ 230 Php 690
WATER METER 1 pcs @ 1500 Php 1500
OTHERS LS pcs @ 6000 Php 6000
29,698.00

SUB-TOTAL P 29,698.00

XI PAINTING WORKS 1030.143 sq.m.

ACRYLIC LATEX PAINT 2 gal @ 230 Php 460


MASONRY PUTTY 1 gal @ 300 Php 300
CONCRETE NEUTRALIZER 3 gal @ 575 Php 1725
QUICK DRYING ENAMEL 6 gal @ 300 Php 1800
PAINT METAL EPOXY 1 gal @ 250 Php 250
PAINT ALUMINUN 3 gal @ 400 Php 1200
PAINT TINTING COLOR 2 gal @ 500 Php 1000
THINNER PAINT 4 gal @ 220 Php 880
THINNER LACQUER 3 gal @ 280 Php 840
BRUSH PAINT 6 pcs @ 50 Php 300
BRUSH ROLLER 5 pcs @ 200 Php 1000
9,755.00

SUB-TOTAL P 9,755.00
PROJECT COST SUMMARY
PROJECT: PROPOSED TWO-STOREY RESIDENTIAL BUILDING
OWNER : Ms. Jamaica Rose G. Rolloque, Engr.
LOCATION: Calero, Calapan City

ITEM NO. SCOPE OF WORK AMOUNT

I - LAYOUT / STAKEOUT AND EARTHWORKS P 32,814.00

II - REINFORCED CONCRETE P 259,481.92

III - MASONRY WORKS P 99,955.00

V - ROOFING WORKS P 43,092.00

VI - DOORS AND WINDOWS P 54,500.00

VII - CARPENTRY WORKS P 12,029.00

VIII - TILE WORKS AND OTHER MISC WORKS P 49,071.20

IX - ELECTRICAL WORKS LS P 28,000.00

X - PLUMBING WORKS P 29,698.00

XI - PAINTING WORKS P 9,755.00

1. TOTAL MATERIAL COST P 618,396.12

2. LABOR COST 247,358.45


40% of TMC
3. Overhead,Miscellaneous (OM) & Expenses 216,438.64
25% of (TMC + LC)
4. Contingencies 54,109.66
5% of (TMC + LC+OM)

DIRECT COST 517,906.75


TOTAL PROJECT COST P 1,136,302.87

Prepared by:

ROLAND C. PATULOT
BSCE-V
Total Floor Area= 116.00 sq.m.
Cost per sq.m.= Php 9,795.71 per sq.m.
EARTH WORKS

EXCAVATION

LENGTH OF COLUMN FOOTING 1.2


WIDTH OF COLUMN FOOTING 1.2
DISTANCE FROM BOTTOM OF FOOTING 1.2
TO GROUND SURFACE
NO. OF COLUMN 6
TOTAL LENGTH OF WALL 41.4
WIDTH OF FOOTING 0.3
DISTANCE FROM BOTTOM OF WALL 0.5
FOOTING TO GROUND SURFACE

VOLUME= 16.578

BACKFILL

SLAB
AREA 58
THICKNESS 0.6

VOLUME 34.8

EXCAVATION 16.58 cu. meter

BACKFILL 34.8 cu. meter


CONCRETE

CONCRETE PROPORTIONS
MIXTURE CEMENT IN BAG
PROPORTION SAND(cu. m) GRAVEL(cu. m)
CLASS 40 Kg 50 Kg
AA 1 : 1 1/2 : 3 12 9.5 0.5 1
A 1:02:04 9 7 0.5 1
B 1 : 2 1/2 : 5 7.5 6 0.5 1
C 1:03:06 6 5 0.5 1

FIRST AND SECOND FLOOR SLAB CEMENT SAND GRAVEL


Area Thickness Number
87 5.8 11.6
(sq.m.) (m) (unitless)
58 0.1 2 bags cu.m. cu.m.
VOLUME: 11.6 cu.meter

COLUMN FOOTING CEMENT SAND GRAVEL


Area Thickness Number 19.44 1.08 2.16
(sq.m.) (m) (unitless) bags cu.m. cu.m.
1.44 0.25 6
VOLUME: 2.16 cu.meter

WALL FOOTING CEMENT SAND GRAVEL


Area Length X Quantity 29.808 1.656 3.312
(sq.m.) (m) bags cu.m. cu.m.
0.08 41.4
VOLUME 3.312

COLUMN CEMENT SAND GRAVEL


Area Height Number 34.3872 1.9104 3.8208
(sq.m.) (m) (unitless) bags cu.m. cu.m.
0.08 7.96 6
VOLUME 3.8208

BEAM 1 CEMENT SAND GRAVEL


Area Length X Quantity
32.5008 1.8056 3.6112
32.5008 1.8056 3.6112
(sq.m.) (m)
0.08 45.14 bags cu.m. cu.m.
VOLUME 3.6112

ROOF BEAM CEMENT SAND GRAVEL


Area Length X Quantity
32.5008 1.8056 3.6112
(sq.m.) (m)
0.08 45.14 bags cu.m. cu.m.
VOLUME 3.6112

STAIRS CEMENT SAND GRAVEL


Area LENGTH Number 5.67 0.315 0.63
(sq.m.) (m) (unitless) bags cu.m. cu.m.
0.0525 1 12
VOLUME 0.63

LANDING CEMENT SAND GRAVEL


Area LENGTH Number 0.99 0.055 0.11
(sq.m.) (m) (unitless) bags cu.m. cu.m.
0.11 1 1
VOLUME 0.11
MASONRY

QUANTITY OF CEMENT AND SAND SAND FOR CHB MORTAR PER SQ. METER

SIZE OF CHB in NUMBER BAGS CEMENT MIXTURE


SAND
cm per sq. m A B C D
10x20x40 12.5 0.792 0.522 0.394 0.328 0.0435
15x20x40 12.5 1.526 1.018 0.763 0.633 0.0844
20x20x40 12.5 2.260 1.500 1.125 0.938 0.1250

OUTERWALL 15x20x40
FIRST FLOOR
AREA CHB CEMENT SAND
77.676 971 80 6.5558544
SECOND FLOOR
AREA CHB CEMENT SAND
69.7784 873 72 5.88929696

TOTAL
CHB 1844 pcs.
CEMENT 152 bags
SAND 12.44515 cu. meter

INNERWALL 10x20x40
FIRST FLOOR
AREA CHB CEMENT SAND
32.04 401 17 1.39374
SECOND FLOOR
AREA CHB CEMENT SAND
43.586 545 23 1.895991

TOTAL
CHB 946 pcs.
CEMENT 40 bags
SAND 3.289731 cu.meter
QUANTITY OF CEMENT AND SAND SAND FOR PLASTER PER SQ. METER

CEMENT OF IN BAGS, THICKNESS OF PLASTER


MIXTURE CLASS 8 mm 12 mm 16 mm 20 mm 25 mm
A 0.144 0.216 0.288 0.360 0.450
B 0.096 0.144 0.192 0.240 0.300
C 0.072 0.108 0.144 0.180 0.255
D 0.060 0.090 0.120 0.150 0.188
Sand 0.008 0.012 0.016 0.020 0.025

FIRST FLOOR
EXTERNAL WALL
AREA CEMENT SAND
77.676 23 1.864224
INTERNAL WALL
AREA CEMENT SAND
32.04 10 0.76896
SECOND FLOOR
EXTERNAL WALL
AREA CEMENT SAND
69.7784 21 1.6746816
INTERNAL WALL
AREA CEMENT SAND
43.586 13 1.046064

TOTAL
CEMENT 67 bags
SAND 5.35393 cu.meter
METAL REINFORCEMENT

CONCRETE HOLLOW BLOCK REINFORCEMENT

LENGTH OF REINFORCING BARS FOR CHB IN METERS

SPACING VERTICALof
REINFORCEMENT Length SPACING HORIZONTAL REINFORCEMENT
bars in meter
cm per block per sq. m. layer per block per sq. m.
40 0.235 2.93 2 0.264 3.3
60 0.171 2.13 3 0.172 2.15
80 0.128 1.6 4 0.138 1.72

FIRST FLOOR
AREA VERTICAL (m) HORIZONTAL(m)
109.716 175.5456 188.71152
SECOND FLOOR
AREA VERTICAL HORIZONTAL
113.3644 181.38304 194.986768

TOTAL= 740.626928

NO OF REBARS(10mm bars)= 124 pcs.

NO 16 G.I. WIRE FOR CHB REINFORCEMENT PER SQ. M.

KILOGRAMS PER SQ. M.


VERTICAL SPACING HORIZONTAL SPACING
25 cm tie 30 cm tie 40 cm tie
40 2 0.054 0.065 0.086
40 3 0.039 0.047 0.063
40 4 0.024 0.029 0.039
60 2 0.036 0.044 0.057
60 3 0.026 0.032 0.042
60 4 0.02 0.024 0.032
80 2 0.027 0.033 0.044
80 3 0.02 0.024 0.032
80 4 0.015 0.018 0.024

TIE WIRE: 7.1 Kgs

MAJOR FOOTING REINFORCEMENT

LENGTH 1.2

CONCRETE COVER 0.075

NO. OF BARS PER 8


LENGTH OF FOOTING
NO. OF FOOTINGS 6
COMMERCIAL LENGTH
OF REBARS 6

LENGTH OF TIES 0.3

NET LENGTH: 1.05 m


NO. OF CUT BARS: 16 pcs

TOTAL NO. OF CUT 96 pcs


BARS:
CUTS OBTAINED: 5 pcs
NO OF 20 pcs
BARS(16mm):
TOTAL TIES: 384 ties
TOTAL LENGTH OF 115.2 meters
TIES:
TIE WIRE(#16): 2.2 Kgs

POST AND COLUMN REINFORCEMENT

MAIN BAR
BEND @ BASE FOOTING 0.2
LENGTH FROM FOOTING TO 1.2
GROUNDFLOOR
HEIGHT OF BACKFILL 0.6
THICKNESS OF FLOOR SLAB 0.1
HEIGHT FROM GROUND LINE TO
BEAM 2.9
DEPTH OF BEAM 0.4
NO. OF BARS 6
COMMERCIAL LEGTH OF REBARS 6
NO. OF COLUMN 6

TOTAL LENGTH 5.4 m


NO. OF MAIN BARS 1 pcs
TOTAL NO. OF MAIN BARS 36 pcs
(16mm)

LATERAL TIES
SPACING 0.05
NO OF LATERAL TIES 32
LENGTH 1
USE COMMERCIAL LENGTH 6

SPACING 0.1
NO OF LATERAL TIES 42
LENGTH 1
USE COMMERCIAL LENGTH 6

SPACING 0.15
LENGTH 0.1
USE COMMERCIAL LENGTH 6
NO OF LATERAL TIES 4

TOTAL LENGTH 32 m
PCS OF LATERAL TIES PER
C.L. 6 pcs

NO OF LATERAL TIES 32 pcs

TOTAL LENGTH 42 m
PCS OF LATERAL TIES PER
C.L. 6 pcs

NO OF LATERAL TIES 42 pcs


PCS OF LATERAL TIES PER 60 pcs
C.L.
TOTAL NO OF TIES 24 pcs
TOTAL NO OF TIES 24 pcs
NO OF LATERAL TIES 1 pcs

OVER ALL TOTAL OF TIES(10mm): 75 PCS.

TIE WIRE
LENGTH OF TIES 0.3

TOTAL TIES: 2808 ties

TOTAL LENGTH OF TIES: 842.4 m

TOTAL NO. OF TIE WIRE (#16): 16 KGS.

SLAB REINFORCEMENT

LENGTH 20.4 NO. OF BARS


WIDTH 9.6 HORIZONTAL: 50 pcs
SPACING 0.4 VERTICAL: 23 pcs
TOTAL LENGTH: 1240.8 m

TOTAL NO. OF BARS (10mm): 207 PCS.

TIE WIRE
TOTAL TIES: 2300 ties
LENGTH OF TIES 0.3
TOTAL LENGTH OF TIES: 1380 m

TOTAL tie wire (#16): 27 KGS.

WALL FOOTING

LENGTH OF WALL 41.4 TOTAL LENGTH OF CONTINOUS 124.2 m


BAR SPACE 0.3 BARS:
NO. OF CONTINUOS TOTAL LENGTH OF TEMPERATURE
3 41.7 m
BARS BARS:

TOTAL NO. OF BARS (10mm) 28 PCS.

TIE WIRE
TOTAL TIES: 417 ties
LENGTH OF TIES 0.3
TOTAL LENGTH OF TIES: 125.1 m

TOTAL TIE WIRE (#16) 3 KGS.

2ND FLOOR BEAM

TOTAL LENGTH OF BEAM 45.14 TOTAL LENGTH


STIRRUP'S SPACING 0.1 OF MAIN BARS: 270.84 m
NO. OF MAIN BAR 6 LENGTH OF 1.4 m
EFFECTIVE COVER 0.05 STIRRUPS:

HOOK 0.15 TOTAL NO. OF


STIRRUPS: 453 m
EFFECTIVE DEPTH 0.45
WIDTH 0.3

TOTAL NO. OF MAIN BARS (16mm): 46 pcs.

TOTAL NO. OF STIRRUPS (10mm): 76 pcs.

TIE WIRE

TOTAL TIES: 2718 ties


LENGTH OF TIES 0.3
TOTAL LENGTH OF TIES: 815.4 m

TOTAL TIE WIRE (#16): 16 KGS.

ROOF BEAM REINFORCEMENT


TOTAL LENGTH OF BEAM 45.14 TOTAL LENGTH
STIRRUP'S SPACING 0.1 OF MAIN BARS: 270.84 m
NO. OF MAIN BAR 6 LENGTH OF 1.4 m
EFFECTIVE COVER 0.05 STIRRUPS:

HOOK 0.15 TOTAL NO. OF


STIRRUPS: 453 m
EFFECTIVE DEPTH 0.45
WIDTH 0.3

TOTAL NO. OF MAIN BARS (12mm): 46 pcs.

TOTAL NO. OF STIRRUPS (10mm): 76 pcs.

TIE WIRE

TOTAL TIES: 2718 ties


LENGTH OF TIES 0.3
TOTAL LENGTH OF TIES: 815.4 m

TOTAL TIE WIRE (#16): 16 KGS.


FORMWORKS

Quantity of Lumber for scaffolding or Staging

COLUMN BEAM FLOORING


LUMBER SIZE BOARD FT. PER M. HEIGHT BD. FT.PER M. HEIGHT BOARD FT.
PER SQ.
VER. HOR. BRACE VER. HOR. M.
2"X2" 4.7 21 11.7 4 4 6.1
2"X3" 7 31.68 17.5 6 6 9.1
2"X4" 9.35 42.25 23.35 8 8 12.1

Board Foot of Wood Frame for Column and Bem for Plywood Form

THICKNESS OF PLYWOOD FORM


SIZE OF WOOD FRAME POST BEAM
6mm(1/4") 12mm(1/2") 6mm(1/4") 12mm(1/2")
2"X2" 29.67 20.33 25.06 18.66
2"X3" 44.5 30.5 37.6 28

FORMS

COLUMN 1 BEAM TIE BEAM ROOF BEAM


NO. OF COLUMN/BEAM 6 1 1 1
WIDTH 0.2 0.2 0.2 0.2
DEPTH 0.4 0.4 0.4 0.4
HEIGHT/ LENGTH 5.5 41.4 27.6 82.4
PERIMETER 1.4 1.1 1.1 1.1
AREA 46.2 45.54 30.36 90.64

NO. OF PLYWOOD REQUIED


(PCS) 17 16 11 32
Total Number of #2 1/2
CWNails: (KGS) 2 4 3 8
Total Number of #1 Finishing
Nails: (KGS) 1 2 2 3
2"X2" WOOD FRAME(BD.FT)
504.39 400.96 275.66 801.92
SCAFFOLDING

COLUMN C1 BEAM B1 TB RB
NO. OF COLUMN 6 NO. OF BEAM 1 0 1
HEIGHT 5.5 LENGTH 41.4 0 82.4
TOTAL LENGTH 33 TOTAL LENGTH 41.4 0 82.4

COLUMN BEAM
VERTICAL SUPPORT 2"X2"(BD.FT.) 155.1 171.95
HORIZONTAL SUPPORTS 2"X2"(BD.FT.) 693 171.95
DIAGONAL BRACES 2"X2" (BD.FT.) 386.1

CONCRETE SLAB
SCAFFOLD
2"X3"(BD.FT.)
AREA 116 1055.6

1,055.60 Bd.f
W1 (in) W2 (in) L (ft)
2 2 8
Total Number of Lumber: 396.00 PCS
Total Number of #4 CWNails: 25.00 KGS
CARPENTRY WORKS
CEILING JOIST

AREA= 116 Sq.m.

SPACING IN CENTIMERTERS (CENTER TO CENTER)


LUMBER SIZE IN INCHES
30x30 30x60 40x40 40x60 60x60
1X2 4.103 3.147 3.189 2.686 2.268
2X2 8.198 6.293 6.379 5.373 4.594
2X3 12.284 9.44 9.569 8.06 6.898
2X4 16.414 12.592 12.758 10.746 9.195
NO. OF JOIST USING
740 bd.f.
2"X2" @ 40x40 cm=
Total Number of Lumber in Pieces/Lengths (pcs) 278

CEILING BOARD

BOARD SIZE IN NO. OF PIECES PER SQUARE


EFFECTIVE COVERING PER BOARD
CENTIMETERS METER
30x30 0.09 11.11
40x40 0.16 6.25
40x60 0.24 4.167
60x60 0.36 2.778
60x120 0.72 1.389
90x180 1.62 0.0617
120x240 2.88 0.347

AREA= 58 Sq.m.

NO. OF CEILING 60x120 BOARD= 81 pcs.

USING 1/4" ORDINARY PLYWOOD or 4' x 8' HARDIFLEX BOARD


TOTAL # OF 4'X 8' ORDINARY PLYWOOD USED (ONE SIDE) SHTS 55 Sheets
TOTAL # OF 4'X 8' ORDINARY PLYWOOD USED (TWO SIDES) SHTS 109 Sheets

# OF 1" CWNails Used for Boards (ONE SIDE) KGS 3.1 KGS
# OF 1" CWNails Used for Boards (TWO SIDES) KGS 6 KGS
# OF 2 1/2" CWNails Used for Joining the Studs together KGS 7.9 KGS
PAINTING WORKS

PRIMERS
KIND OF PAINT USES THINING DRYING TIME COVERAGE/GAL

FOR INTERIOR 2HRS/ALLOW


1.INTERIOR PRIMER & WOOD PURPOSES PAINT THINNER OVERNIGHT BEFORE 20 T0 30 sq.m.
SEALER RECOATING

6HRS/ALLOW
2.EXTERIOR WOOD FOR EXTERIOR
WOOD PURPOSES PAINT THINNER OVERNIGHT BEFORE 30 T0 40 sq.m.
PRIMER RECOATING

PRIMER FOR
FERROUS AND
3.RED OXIDE PRIMER PAINT THINNER 3 HOURS 35 TO 40 sq.m.
NON FERROUS
SURFACES

RUST PREVENTIVE
PRIMER FOR
4.RED LEAD PRIMER PAINT THINNER 3 HOURS 30 TO 40 sq.m.
FERROUS
SURFACES

FOR STEEL 6HRS/ALLOW


5.EPOXY PRIMER ALUMINUM, EPOXY REDUCER OVERNIGHT BEFORE 30 TO 40 sq.m.
GALVANIZED IRON RECOATING

WALL
TOTAL AREA: 223.0804 sq.m.
NO. OF GALLONS: 7 gal. ACRYLIC LATEX PRIMER
2ND COVER: 7 gal. ACRYLIC GLOSS LATEX
NEUTRLIZER: 3 qrts.

CEILING

TOTAL AREA: 116.09 sq.m.


NO. OF GALLONS: 4 gal. WOOD PRIMER
2ND COVER: 5 gal. INTERIOR SEMI GLOSS ENAMEL
NEUTRLIZER: 4 qrts. THINNER
TILING WORK
FLOOR AREA 116 sq.m.
FLOOR AREA(CR) 3.356 sq.m.
WALL AREA(CR) 12 sq.m.

TOTAL AREA 131.356 sq.m.

TABLE 7-1 QUANTITY OF TILES PER SQUARE FOOT AND METER


COMMERCIAL SIZE NUMBER OF PIECES PER
inches cm. sq.ft. sq.m.
3x3 7.5x7.5 16 177.8
4x4 10x10 9 100
4¼ x 4¼ 10.6x10.6 8 88.4
4x8 10x20 6 50
6x6 15x15 4 44.44

6x8 15x20 3 33.33


6x12 15x30 2 2.22
8x8 20x20 2.25 2
8x12 20x30 0.5 16.66
8x16 20x40 1.125 12.5

10x10 25x25 1.44 16


12x12 30x30 1 11.11
12x24 30x60 0.5 5.56
16x16 40x40 0.56 6.25
20x20 50x50 0.36 4
24x24 60x60 0.25 2.78

5-point pent. tiles 5 6/ft. 20/Ln. M.


6-point hex. tiles 5 4.9/ft. 16/Ln. M.
External corner bead-- By direct count
Internal corner bead - By direct count

Cement mortar - 0.086 bags per sq. m.


White cement joint filler- 0.50 kg. per sq.m.
Tile ADHESIVE........ 0.11 bag per sq.m.
TILE SIZE
NO. PER sq.m.
Inches cm
8x8 20x20 84
8x12 20x30 200
16x16 40x40 725

CEMENT MORTAR 15 BAGS


WHITE CEMENT 65.7 kgs
ADHESIVE 15 bags

NO. OF BAGS OF WHITE 2


CEMENT (40 kg)
STAIRS

CONCRETE STAIRS

RISER HEIGHT (Rh) = 0.21 m


TREAD RUN (Tr)= 0.25 m
STAIR WIDTH (W)= 1 m
NO. OF STEPS= 15 steps

STRINGER THICKNESS(Ts)= 0.05 m

CEMENT IN BAGS SAND GRAVEL


MIXTURE CLASS
40 Kg 50 Kg cu. m. cu.m.
AA 12 9.5 0.5 1
A 9 7 0.5 1
B 7.5 6 0.5 1
C 6 5 0.5 1

TOTAL VOLUME OF CONCRETE= 1.155 cu.m.


NO. OF CEMENT= 11 bags
VOLUME OF SAND 0.6 cu.m.
VOLUME OF 3/4" GRAVEL= 1.2 cu.m.

REINFORCEMENT

USE LENGTH OF TIES (cm): 30

STEPS LATERAL
BAR DIAMETER
(mm)
78
STEPS LATERAL
STRINGER BAR DIAMETER
HORIZONTAL (mm)
STRINGER LATERAL BAR DIAMETER
BAR DIAMETER (mm) 56
(mm) 24
12

TOTAL NO. OF LATERAL BARS REQUIRED @ STEPS= 6 pcs


TOTAL NO. OF HORIZONTAL BARS REQUIRED @ STEPS= 5 pcs
TOTAL NO. OF LATERAL BARS REQUIRED @ STRINGER= 4 pcs
TOTAL NO. OF HORIZONTAL BARS REQUIRED @STRINGER= 3 pcs
NO. OF #16 TIE WIRE REQUIRED= 1 pcs
DOORS & WINDOWS

DOORS

DOORS PIECES DIMENSION AREA


D1 1 1 x 2.1 2.1
D2 4 0.9 x 2.1 7.56
D3 2 0.75 x 2.06 3.09
TOTAL AREA 13

WINDOWS

DOORS PIECES DIMENSION AREA


W1 3 1.8 x 1.5 8.1
W1 4 0.9 x 1.4 5.04
W3 3 0.57 x 0.5 0.855
TOTAL AREA 13.995

TOTAL AREA OF DOORS AND WINDOWS 26.995


ROOFING MATERIALS

EFFECTIVE COVERING OF G.I. ROOFING SHEETS

EFFECTIVE COVERING SIDE LAPPING PURLINS NO. OF


LENGTH FT-METER SPACING NAILS/RE
1 1/2 2 1/2 IN M. V
5'-1.50 0.7 0.6 0.6 14
6'-1.80 0.7 0.6 0.75 14
7'-2.10 0.7 0.6 0.6 18
8'-2.40 0.7 0.6 0.7 18
9'-2.70 0.7 0.6 0.6 22
10'-3.00 0.7 0.6 0.67 22
12'-3.60 0.7 0.6 0.66 26

CORRUGATED G.I. SHEETS


LENGTH 5.598
NO 4
USE COMMERCIAL LENGTH 6
LENGTH OF RAFLER 6.7
NO OF LAYER 2
ALLOWANCE 1
NO. OF ROOF SHEAR 5

ORDERED G.I SHEET (6')= 20 PCS.

ORDERED G.I SHEET (7')= 20 PCS.

ORDERED G.I SHEET (10')= 20.6 PCS.

UMBRELLA NAILS
6' 280
7' 360 pcs
10' 453.2
TOTAL 1093.2 pcs

ORDERED UMBRELLA NAILS 9.11 KGS.


ROOF FRAMING
NO OF BOARD FOOT OF STUDS AND NAILING JOIST PER SQUARE METER

LUMBER SIZE IN SPACING IN CM (CENTER TO CENTER)


INCHES 30X30 30X60 40X40 40X60 60X60
1X2 4.103 3.147 3.189 2.686 2.268
2X2 8.198 6.293 6.379 5.373 4.594
2X3 12.284 9.44 9.569 8.06 6.898
2X4 16.414 12.592 12.758 10.746 9.195

ROOF TRUSS
TOP CHORD: 2"X6"
KING POST: 2"X6"
COLLAR PLATE: 2"X6"
BOTTOM CHORD: 2"X6"
DIAGONAL STRUT: 2"X4"
VERTICAL STRUT: 2"X4"

TRUSS 1

TYPE LENGTH NO
TOP CHORD 5.6 4
KING POST 800 5
COLLAR PLATE 0 0
BOTTOM CHORD 6.22 5
DIAGONAL STRUT 24.6 5
VERTICAL STRUT 14.7 5

TOTAL BOARD FEET 2"x6"= 4053.5

TOTAL BOARD FEET 2"x6"= 131

PURLINS
TOTAL LENGTH (FT) 2"x4" 56.9

TOTAL BOARD FEET 2"x6"= 4053.5


TOTAL BOARD FEET 2"x4"= 187.9
ROOFING WORKS

EFFECTIVE COVERING OF G.I. ROOFING SHEETS

EFFECTIVE COVERING SIDE PURLINS


SPACING NO. OF NAILS/
LENGTH LAPPING RIVETS PER
ft-m IN SHEET
METERS
1 1/2 2 1/2
5'-1.5 0.7 0.6 0.6 14
6'-1.8 0.7 0.6 0.75 14
7'-2.1 0.7 0.6 0.6 18
8'-2.4 0.7 0.6 0.7 18
9'-2.7 0.7 0.6 0.6 22
10'-3 0.7 0.6 0.67 22
12'-3.6 0.7 0.6 0.66 26

END LAPPING 25-30 cm

DETERMINING THE NO. OR ROOF SHEETS

ROOFING TOTAL WIDTH= 10.99 m


ROOFINGTOTL LENGTH= 8.87 m
EFFECTIVE WIDTH= 0.15 m
FACTOR FOR NO. OF NAILS/RIVETS:
C1= 20
C2= 0
AREA= 56 Sq.m.

QUANTITY OF ROOF ACCESSORIES IN KILOGRAMS

MATERIALS NUMBER PER Kg


GI ROOF NAILS 120
GI RIVETS 180
GI WASHERS 126
LEAD WASHERS 75
UMBRELLA NAILS 120

SIZE & QUANTITY OF STEPS IN ONE PLAIN GI SHEET

SIZE OF GI STRAP IN INCHES NO. PLAIN


OF SRAP IN ONE
SIZE OF PURLINS SHEET
2x3 1x9 384
2x4 1x10 342
2x5 1x11 312
2x6 1x12 288

USING ONLY TWO SHEETS

# OF 1ST ROOF SHEET USED @ 8' LONG AT ONE SODE ONLY= 148 Sheets
# OF THE 2ND ROOF SHEET USED @ 10' LONG AT ONE SIDE ONLY= 148 Sheets
NO. OF UMBRELLA NAILS/ TEKSCREW= 24.7 pcs
NO. OF THE GI WASHER= 47 pcs
NO. OF THE PLAIN GI STRAP ON 2"x3" PURLINS= 8.1 pcs
NO. OF LEAD WASHERS= 39.5 pcs
ELECTRICAL ESTIMATE
QTY UNIT DESCRIPTION U/PRICE
5 pcs SERVICE ENTRANCE CAP (3/4'') -
1 roll 8.0 mm² THW -
1 roll 2.0 mm² THHN -
1 roll 3.5 mm² THHN -
5 pcs 25 mm ø PVC -
5 pcs 30 mm ø PVC -
50 pcs 15 mm ø PVC/FLEXIBLE -
60 pcs PVC CLAMP -
1 pcs 60A CKT.BKR. -
6 pcs 20A CKT. BKR. -
2 pcs 15A CKT. BKR. -
2 set PANEL BOARD W/ 6 SLOTS -
13 set 1-GANG SWITCH(SET) -
6 set 2-GANG SWITCH(SET) -
1 set 2-GANG REF. C.0. -
2 set 2-GANG ACU. C.0. -
3 set 2-GANG WHTR. PROOF C.0. -
12 set CONVINIENCE OUTLET -
14 pcs JUNCTION BOX -
28 pcs UTILITY BOX -
25 pcs CEILING RECEPTICLE -
25 pcs DAYLIGHT BULB -
12 roll ELECTRICAL TAPE -
MISCELLANEOUS AND OTHERS TO COMPLETE -
TEL. CABLE
T.V. CABLE
TOTAL:

PLUMBING ESTIMATE
PLUMBING ESTIMATE
QTY UNIT DESCRIPTION U/PRICE AMOUNT
8 pc PVC Orange #4 - 578 4,624.00
25 pc PVC Pipe #3 - 303.80 7,595.00
5 pc PVC Pipe #2 - 78.08 390.38
10 pc Blue Pipe 1/2 - 61.76 617.65
1 pc P Trap #2 - 80.00 80.00
6 pc Wye 3 x3 - 76.00 456.00
4 pc PVC Elbow 3x45 - 35.00 140.00
4 pc Elbow 1/2 - 20.00 80.00
2 pc Faucet - 360.00 720.00
2 pc Faucet - 110.00 220.00
15 pc Coupling - 25.00 375.00
10 pc Teflon big - 20.00 200.00
2 pc Strainer 4x4 - 100 200.00
3 pc Water Closet - 2,512.00 7,536.00
2 pc Shower valve - 650 1,300.00
2 pc Vulcaseal - 380.00 760.00
4 pc Floor Strainer - 120 480.00
2 pc Clean Out #3 - 40.00 80.00
2 pc Bedit Spray - 500.00 1,000.00
2 ft Hose - 30.00 60.00
2 pc Lavatory - 1,500.00 3,000.00
TOTAL: 29,914.03

Engr. Emmanuelle Bren V. Borras


(CIVIL ENGINEER)/(MASTER PLUMBER)

You might also like