Control of Pulp Levels in Flotation Cells
Control of Pulp Levels in Flotation Cells
net/publication/245158515
CITATIONS READS
12 174
4 authors, including:
Sirkka-Liisa Jamsa-Jounela
Aalto University
178 PUBLICATIONS 1,210 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Artificial Intelligence applied for industrial lime kiln control View project
All content following this page was uploaded by Sirkka-Liisa Jamsa-Jounela on 09 June 2019.
Abstract
The control of pulp levels in flotation cells is a complex control task. Many different aspects such as cell structure and valve sizing,
and their effects on control, have to be taken into account. Control becomes more and more difficult as the complexity of the cell
configurations and the number of cells used in configuration increase. In this paper the mathematical model of a flotation cell is first
developed and several configurations of cells are constructed. Simulations are then performed in order to determine suitable control
parameters for PI and feed-forward controllers of the cell levels. Finally, the effects of valve sizing and cell structure are presented
and discussed.
r 2003 Elsevier Science Ltd. All rights reserved.
Keywords:
Level control; Control valves; Characteristic curves; Valve sizing; Flotation
y1
y2
y3
q
y4
y5
u1
u2
u3
u4
u5
y1 y2 Hlowe rpa rt
y3
q
F1 F2
F3
R tota l
Fig. 2. Double flotation cell series. Fig. 3. Cross-section of a non-linear flotation cell.
TC50, linear and nonlinear pulp level 0.15
4.6
4.4 0.1
-0.1
3.4
3.2 -0.15
3
The flow difference of normal flow (m3/s)
2.8
Fig. 5. Change in valve position as a function of the flow difference for
a 525 mm valve.
2.6
40 45 50 55 60
volume
In industrial applications each flotation cell has In the simulations the configurations of three and six
separate PI controller for the level control via the TC-50 cells in series were studied (1) with the ideal tank
control valve of the cell outflow. In the simulation study assumption, and (2) with the non-linear cell model. The
the following PI algorithm is used: simulations were performed by using the valves sized
according to the ISA standard and with 100% over-
T sizing. Control strategies with conventional PI control-
Dui ¼ K ðei ei1 Þ þ ei ; ð16Þ
I lers and with feed-forward control were simulated. The
where Du is a calculated change in the control output, K simulated configurations are presented in Fig. 6.
the proportional gain, I the integration time, ei a current
error term (set point—process variable), ei1 a previous 4.2. Performance criteria
error term (T seconds ago), and T is the sampling
interval (seconds). The performance criteria set for the comparison of
In industrial process control applications (Niemi et al., alternative designs are overshoot, rise time (i.e. time
1974) feed-forward compensation of measurable dis- for the response to reach the desired value for the
turbances is commonly and successfully used. Available first time) and settling time (time for the response
feed flow measurement makes the feed-forward level to settle within 75% of the desired value). The closed
control possible. loop responses are used for calculating the dynamic
The main purpose of the feed-forward level control is performance criterion of integral of the square
to observe the disturbance in the inflow of the first cell error (ISE) and integral of the absolute value of
Fig. 6. The simulation configurations of conventional PI controllers and PI controllers with feed-forward control.
The simulation results for systems with the ideal tanks The influence of valve sizing and additional feed-
and non-linear cells show that the cell levels can be forward control were also studied in a pilot plant
controlled more accurately using valves sized according (J.ams.a-Jounela, Laurila, Karesvuori, & Timperi, 2001).
to the ISA standard (Fig. 8 and Table 1). There were The test configuration consisted of a flotation cell, pulp
only minor differences in overshoots and in the settling circulation cell, pulp pump, air feed device and two
times. different control valves. The inflow was measured with a
A somewhat larger improvement in cell level control magnetic flow meter and the pulp level with a float. The
was accomplished when feed-forward control was tests were performed with a flotation cell with similar
implemented. In the case of disturbances in the feed, geometries as described above. The results achieved
the overshoots performed by the last cells are signifi- were analogous to those obtained in the simulations
cantly smaller (Fig. 9 and Table 2). (Fig. 13). The control performance was noticeably
The results in Fig. 10 and Table 3 also demon- improved by adding the feed-forward control. It was
strate that there can be differences in control also found that an adaptive feed-forward control gain
performance between ideal tanks and non-linear could result in even greater improvements in control
cells. The disturbances in feed were easier to performance.
2
Outflow of the
1st tank
Volume
H(2) MATLAB
Step H Function 1 MATLAB
1
h2+H-h3 Sqrt s Function
1 Tank level
dV V Level
Level in the Flow out of
calculation
following tank 2nd tank
Hlip 2
ISE Display1
error Out1
0 Valve 2
IAE Display2
4.25 4.25
4.20 4.20
4.15 4.15
4.10 4.10
4.05 4.05
4.00 4.00
0 100 200 300 400 500 0 100 200 300 400 500
Fig. 8. Response of the levels to a +20% change in pulp feed. On the left for 100% valve oversizing, and on the right for valve sizing according to
the ISA standard.
Table 1
The influence of valve sizing: response of the pulp level in the last cell to a +20% change in the feed
Configuration Overshoot (cm) Overshoot (%) Rise time (s) Settling time (s) Dead time (s) ISE IAE
4.20 4.20
4.15 4.15
4.10 4.10
4.05 4.05
4.00 4.00
0 100 200 300 400 500 0 100 200 300 400 500
Fig. 9. Response of the levels to a +20% change in pulp feed. 100% valve oversizing is used in both figures. On the left PI controller, and on the
right PI controller and feedforward controller.
Table 2
The influence of feed-forward control: response of the pulp level in the last cell to a +20% change in the feed
Configuration Overshoot (cm) Overshoot (%) Rise time (s) Settling time (s) Dead time (s) ISE IAE
4.25 4.25
4.20 4.20
4.15 4.15
4.10 4.10
4.05 4.05
4.00 4.00
0 100 200 300 400 500 0 100 200 300 400 500
Fig. 10. Response of the levels to a +20% change in pulp feed. 100% valve oversizing is used in both figures. On the left are non-linear cells, and on
the right model based on the ideal tank assumption.
Table 3
The influence of cell geometry: response of the pulp level in the last cell to a +20% change in the feed
Configuration Overshoot (cm) Overshoot (%) Rise time (s) Settling time (s) Dead time (s) ISE IAE
7. Conclusions the case of ideal tanks than with cells. Higher propor-
tional gains reduce the settling time of the system in PI
All the simulated configurations were successfully control. The opening speeds (from 0% to 100%) of the
tuned. Different valve sizes and different cell types had valves have been estimated to be 30 s regardless of the
an effect on the proportional gain of the PI control: the valve size, i.e. the bigger the valve, the shorter the rise
proportional gains were larger when using valves sized time.
according to the ISA standard than with oversized The valves were sized according to the ISA standard,
valves. Similarly, the proportional gains were larger in and the retention time in each cell was 1.5 min. The
4.25 4.25
4.20 4.20
4.15 4.15
4.10 4.10
4.05 4.05
4.00 4.00
0 100 200 300 400 500 0 100 200 300 400 500
Fig. 11. Response of the levels to a +3 cm change in the set points. 100% valve oversizing is used in both figures. On the left are non-linear cells, and
on the right is the model based on the ideal tank assumption.
5.00 5.00
4.95 4.95
4.90 4.90
4.85 4.85
4.80 4.80
4.75 4.75
4.70 4.70
0 100 200 300 400 500 0 100 200 300 400 500
Fig. 12. Response of the levels to a +20% change in pulp feed. 100% valve oversizing is used in both figures. On the left is the PI controller, and on
the right, PI controller and feedforward controller.
Table 4
The influence of feed-forward control on the configuration with double cells: response of the pulp level in the last cell to a +20% change in the feed
Configuration Overshoot (cm) Overshoot (%) Rise time (s) Settling time (s) Dead time (s) ISE IAE
oversized valves were considerably larger than those urations with ideal cells and with different geometry
sized using the ISA standard. This leads to the situation cells were compared. In every case the results were
where the valve is almost closed during normal clearly better.
conditions, and the valve is operating in the non-linear Feed-forward control implemented with PI control
area. The effect of valve size on the quality of control improved the compensation of the disturbances in every
was minor. Overshooting due to flow disturbances was case. An adaptive feed-forward control gain could result
compensated slightly better when the valves were sized in even bigger improvements in control performance.
according to the ISA standard. In contrast, changing the
set points of the pulp level with oversized valves often
even resulted in better performance indices. 8. Further studies
The geometry of the cell had the greatest effect on the
performance of the level control. A difference in The simulation platform introduced in this paper has
performance was clearly evident when the same config- been used in further studies to develop and compare
-300 References
-310 Andersen, R., Gronli, B., Olsen, T., Kaggerud, I., Ramslo, K., &
(a) Sandvik, K. (1979). An optimal control system of the Rougher
Flotation at the Folldal Verk Concentrator, Norway. Proceedings
-320 of the 13th international mineral processing congress, Vol. II (pp.
1517–1540). New York, USA.
-330 (b)
Hammoude, A., & Smith, H. (1981). Experiments with self-tuning
control of flotation. Proceedings of the 3rd IFAC symposium on
automation in mining, mineral and metal processing (pp. 213–218).
-340 Oxford, UK.
J.ams.a, S.-L., & Herbst, J. A. (1988). A simulation study of expert
(c) control system for flotation. Software for Computer Control 1988
-350 (pp. 67–75). New York, USA.
J.ams.a-Jounela, S.-L., Laurila, H., Karesvuori, J., & Timperi, J. (2001).
-360
Evaluation of the future automation trends in control and fault
0 50 100 150 200 diagnostics—a case study in flotation plant. Proceedings of the 10th
Fig. 13. Responses of the level to a change in pulp feed (0.35-1.1 m3/
View publication stats IFAC symposium on automation in mining, mineral and metal
processing. Tokyo, Japan.
min). The biggest overshoot (a) is obtained using a PI controller, and K.ampj.arvi, P., & J.ams.a-Jounela, S.-L. (2002). Level control strategies
noticeable improvements in control performance are achieved by for flotation cells. Proceedings of the 15th IFAC world congress on
implementing additional feed-forward controllers (b and c). automatic control. Barcelona, Spain.
Koivo, H., & Cojocariu (1977). An optimal control for a flotation
advanced multivariable control strategies for flotation circuit. Automatica 13, 37–45.
cells. Control performance of feed-forward control, Niemi, A., Maijanen, J., & Nihtil.a, M. (1974). Singular optimal
feed forward control of flotation. IFAC/IFORS symposium on
decoupling and different multivariable control methods
optimization methods—applied aspects (pp. 277–283). Varna,
have been studied, discussed and published by K.amp- Bulgaria.
j.arvi and J.ams.a-Jounela (2002). Schubert, J. H., Henning, R. G. D., Hulbert, D., & Craig, I. K. (1995).
Flotation control—a multivariable stabilizer. XIXth IMPC, Vol. 3
(pp. 237–241). San Francisco, USA.
Stenlund, B., & Medvedev, A. (2000). Level control of cascade
Acknowledgements
coupled flotation tanks. Future trends in automation in mineral and
metal processing, IFAC workshop 2000 (pp. 194–199). Helsinki,
The authors would like to thank Outokumpu Mintec. Finland.
In particular, special thanks to Heikki Laurila who Zargiza, R., & Herbst, J. A. (1987). A model based feed forward
helped with the practical details. Financial support of control scheme for flotation plants. 116th AIME annual meeting
(pp. 23–27). Denver, CO, USA.
TEKES is also gratefully acknowledged.