0% found this document useful (0 votes)
644 views

Manpower Schedule

The document is a manpower schedule for a plumbing and sanitary project for the Makati Office Project. It outlines the tasks to be completed each month over a 20 month period to install plumbing systems like water, soil, waste and vent lines as well as fixtures in the basement, podium and tower levels. It includes tasks like installing risers, horizontal pipes, toilets and other fixtures. It also notes testing, punchlisting and handover will occur at the end. The schedule is subject to change based on site conditions and the general contractor's schedule.

Uploaded by

Ayhie Garcia
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
644 views

Manpower Schedule

The document is a manpower schedule for a plumbing and sanitary project for the Makati Office Project. It outlines the tasks to be completed each month over a 20 month period to install plumbing systems like water, soil, waste and vent lines as well as fixtures in the basement, podium and tower levels. It includes tasks like installing risers, horizontal pipes, toilets and other fixtures. It also notes testing, punchlisting and handover will occur at the end. The schedule is subject to change based on site conditions and the general contractor's schedule.

Uploaded by

Ayhie Garcia
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 30

L U M B I N G C O R P O R AT I O N

PROJECT: MAKATI OFFICE PROJECT (GRADE 'A')


LOCATION: COR. OF SEN. GIL PUYAT AVE (Buendia Ave)
SUBJECT: MANPOWER SCHEDULE (PLUMBING AND SANITARY)
DATE: July 19,2019

MONTH 1
ITEM DESCRIPTION
WEEKS
1
GENERAL REQUIREMENTS / PRELIMINARIES
Mobilization
Temporary Fascilities
1
Supervisions
Bonds/Insurances
Contingencies
BASEMENT LEVEL
SLEEVING/BLOCKOUTS & PERFORATED PIPE

WATERLINE SYSTEM
1. Installation of Cold Water Line Riser
2.Installation of Water line Horzintal Line
3.Installation of Toilets Water Line
4.Installation of Cold Water Line Discharge, Gravity
EQUIPMENTS
5. Installation of Transfer Pump Discharge Line Supplying Water Tank
6. Installation of Booster Pump Discharge Line
7. Installation of Sump Pump
2 8. Installation of Water Tanks
SOIL DRAIN SYSTEM
9. Installation of Soil Stack/Riser
10. Installation of Soil Toilet and Collector Pipes
WASTE DRAIN SYSTEM
11. Installation of Waste Stack/Riser
12.Installation of Waste Toilet and Collector Pipes
FIXTURES AND ANCILLIARIES
13. Installation of Lavatory Set including Faucet
14. Installation of Water Closet w/ accessories
15. Installation of Urinal including accessories
16. Installation of Shower Head including accessories
PODIUM (GF-11F) WATERLINE SYSTEM
1. Installation of Cold Water Line Riser
2.Installation of Water line Horzintal Line
3.Installation of Toilets Water Line
4.Installation of Cold Water Line Discharge, Gravity
SOIL DRAIN SYSTEM
5. Installation of Soil Stack/Riser
6. Installation of Soil Toilet and Collector Pipes
WASTE DRAIN SYSTEM
7. Installation of Waste Stack/Riser
8.Installation of Waste Toilet and Collector Pipes
VENT SYSTEM
9.Installation of Vent Stack
3
10.Installation of Vent Toilet Pipes
11. Installation of Vent Collector Pipes
STORM DRAIN
12. Installation of Down Spouts Risers
13. Balcony Drain Piping (Collector)
14. Drain Stack
FIXTURES AND ANCILLIARIES
15. Floor Drain
16. Balcony and Deck Drain
17. Installation of Water Closet Set
18. Installation of Lavatory including faucet and Accessories
19. Installation of Urinal including accessories
TOWER (12F-RD) WATERLINE SYSTEM
1. Installation of Cold Water Line Riser
2.Installation of Water line Horzintal Line
3.Installation of Toilets Water Line
4.Installation of Cold Water Line Discharge, Gravity
SOIL DRAIN SYSTEM
5. Installation of Soil Stack/Riser
6. Installation of Soil Toilet and Collector Pipes
WASTE DRAIN SYSTEM
7. Installation of Waste Stack/Riser
8.Installation of Waste Toilet and Collector Pipes
VENT SYSTEM
9.Installation of Vent Stack
10.Installation of Vent Toilet Pipes
4
4
11. Installation of Vent Collector Pipes
STORM DRAIN
12. Installation of Down Spouts Risers
13. Balcony Drain Piping (Collector)
14. Drain Stack
FIXTURES AND ANCILLIARIES
15. Floor Drain
16. Balcony and Deck Drain
17. Roof Drain
17. Installation of Water Closet Set
18. Installation of Lavatory including faucet and Accessories
19. Installation of Urinal including accessories
20. Installation of Kitchen sink

5 TESTING AND COMMISIONING

6 PUNCHLISTING

7 HANDOVER

WEEKLY & MONTHLY


GENERAL NOTE: 0.00%
ACCOMPLISHMENT

1. Subject for revision based on actual site condition


and reflected schedule of Gen. Contractor

PREPARED BY:

ENGR. ARIEL P. GARCIA


PROJECT-IN-CHARGE (PLUMBING)

NOTED & CHECKED BY :

ENGR. DALE BRIAN T. GO


OPERATIONS MANAGER
MONTH 1 MONTH 2 MONTH 3

WEEKS WEEKS WEEKS


2 3 4 1 2 3 4 1 2 3
0.00% 0.00% 0.00%

_______________________________________
CONSTRUCTION MANAGEMENT

______________________________________
OWNER
NTH 3 MONTH 4 MONTH 5 MONTH 6

EEKS WEEKS WEEKS WEEKS


4 1 2 3 4 1 2 3 4 1
00% 0.00% 0.00% 0.00%
MONTH 6 MONTH 7 MONTH 8

WEEKS WEEKS WEEKS


2 3 4 1 2 3 4 1 2 3
0.00% 0.00% 0.00%
NTH 8 MONTH 9 MONTH 10 MONTH 11

EEKS WEEKS WEEKS WEEKS


4 1 2 3 4 1 2 3 4 1
00% 0.00% 0.00% 0.00%
MONTH 11 MONTH 12 MONTH 13

WEEKS WEEKS WEEKS


2 3 4 1 2 3 4 1 2 3
0.00% 0.00% 0.00%
NTH 13 MONTH 14 MONTH 15 MONTH 16

EEKS WEEKS WEEKS WEEKS


4 1 2 3 4 1 2 3 4 1
00% 0.00% 0.00% 0.00%
MONTH 16 MONTH 17 MONTH 18

WEEKS WEEKS WEEKS


2 3 4 1 2 3 4 1 2 3
0.00% 0.00% 0.00%
NTH 18 MONTH 19 MONTH 20 ……..TARGET HANDOV

EEKS WEEKS WEEKS WEEKS


4 1 2 3 4 1 2 3 4 1
00% 0.00% 0.00% 0.00%
……..TARGET HANDOVER

WEEKS
2 3 4
0.00%

You might also like