Technical Learning For MEP Engineer
Technical Learning For MEP Engineer
2. Contract terms
3. Profit margins
4. Sources of price
5. Vendor management
6. Requirements of tender
7. Costing Module
Tender contains
a. This Agreement;
b. Appendix to the Tender;
c. Annexure A : Conditions of Contract;
d. Annexure B : Deviations to Specifications;
e. Annexure C : Specifications;
f. Annexure D : Bill of Quantities;
g. Annexure E : Drawings;
h. Annexure F : Health, Safety and Environment (“HSE”) Manual; and
i. Annexure H : Authority Letter for signing of the documents to be issued by competent
persons of the Contractor such as Directors or Partners or Proprietor
MEP Engineers have already started designing near zero and even zero energy buildings.
These buildings would consume only that much net renewable energy in a year as much at it can
produce. The trend that started in Europe is seen to be strongly used in the UAE and other countries.
Value Engineering
Value Engineers are hired to determine whether a certain product gives the value of the cost
invested in it. If not, the product is immediately replaced by another that functions better for the
requirements. Demand for value engineers is expected to rise in 2018.
Pre-Fabrication
Pre-fabrication has helped the speed of the construction largely as whole parts of the
project are built in an altogether different place and transported later at the final site. The one
drawback of this method is that it can only be achieved in areas with advanced transportation
services.
Advancement in technology has helped BIM Modelling to a great extent. Nowadays, experts
prefer 3D Models over the traditional 2D Models. 3D Models give a far better approach towards how
the Mechanical, Plumbing and Electrical arrangements are going to take place in a design.
5D modelling is another advancement over the 3D Model, wherein, the owner and the
project stakeholders get an estimate of the actual working of the project with respect to information
and cost in a visually communicative way.
2018 expects to see greater use of these technologies than ever before. MEP consultants in
Dubai will be able to utilize the projected thermal maps and emission footprints for a project to
come up with the most optimum building design in compliance with the Al SAFAT regulations.
Construction has reached a whole new level of precision and perfection as unmanned robots
replace the tedious human labour. In cities blessed with advanced technology in the fields of
robotics and artificial intelligence, even supervisory robots have been installed. Simple construction
machines include brick laying machines and stone work machines.
Cell phones have helped the speed and precision of reporting on construction sites greatly.
Supervisors need not keep going here and there all the time as the same work can be achieved
remotely through phones.
A lot of potentially sustainable projects were undertaken in 2017. However, 2018 will see
how they turn out. The New Year would give a complete idea whether the feedback of the users and
owners is positive enough. This feedback would help determine future projects and the process of
maintenance and installation of the projects and other things.
In addition, the current trend is to harmonize the design process, with the contractors,
consultants, and architects working in tandem to provide the best building design. As a result, the
problems arising due to incomplete information transfer are expected to be largely eliminated.
Building Information Modeling (BIM) is a design tool that greatly simplifies the cost
estimation procedure. MEP engineers can create a digital model of all building systems,
and then assign material properties to components. Material take off can require several
days with a manual procedure, but modern software can perform calculations within
seconds.
Consider that project cost estimation requires technical knowledge and experience,
even with modern design tools. There is a common misconception that advanced
software displaces engineering services, but software only provides useful results if the
inputs and design parameters are correct. Most projects also involve decisions between
different types of equipment or system layouts, and only qualified engineers can choose
an optimal configuration.
Estimator software
estimate electrical, cable, and data/telecom projects with speed and accuracy.
Quickly count switches, dimmers, receptacles, and outlets. Measure linear distances for
conduits and cable runs with our On-Screen Takeoff application. Calculate pipe and fittings
for a broad range of commercial projects including retail, schools, hospitals, and office
buildings. Add materials from your plumbing or electrical jobs to set up your bid and takeoff
based on current prices and your trusted suppliers. Quickly change prices to match specs for
high-grade pipe, valves, fittings, hangers, clean-outs, vents, pumps and more.