100% found this document useful (1 vote)
277 views

ECC Condition/s Status of Compliance Actions Taken YES NO: Complied

The document summarizes the status of compliance with conditions for an environmental compliance certificate (ECC) by a proponent. It lists 6 conditions and whether the proponent is in compliance or not. All conditions are marked as complied with. The conditions include conforming with environmental laws, making budget available for environmental monitoring, undertaking education campaigns, posting the ECC publicly, setting up an environmental unit to monitor requirements, and notifying the environmental agency prior to any abandonment.

Uploaded by

evelyn maddela
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
277 views

ECC Condition/s Status of Compliance Actions Taken YES NO: Complied

The document summarizes the status of compliance with conditions for an environmental compliance certificate (ECC) by a proponent. It lists 6 conditions and whether the proponent is in compliance or not. All conditions are marked as complied with. The conditions include conforming with environmental laws, making budget available for environmental monitoring, undertaking education campaigns, posting the ECC publicly, setting up an environmental unit to monitor requirements, and notifying the environmental agency prior to any abandonment.

Uploaded by

evelyn maddela
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Status of

ECC Condition/s Compliance Actions Taken


YES NO
1. The proponent’s operation shall conform with the provisions COMPLIED
of RA 6969 (Toxic and Hazardous and Nuclear Wastes

Control Act of 1990), RA 9003 (An Act Providing for an
Ecological Solid Waste Management Program), RA 9275
(Philippine Clean Water Act of 2004), and RA 8749
(Philippine Clean Air Act of 1999);

2. The proponent shall make available budget of Php 30,000 ✓ COMPLIED


based on the project scheduled as indicated in the submitted
Environmental Monitoring Plan (EMoP) summary for the
implementation of the project and the mitigating measures in
the operational phase. An accomplishment report on the
implemented monitoring activities and the corresponding
cost of the EMP activities shall be submitted to the Office on
a quarterly basis for monitoring;

3. The proponent shall undertake and effective and wide ✓ COMPLIED


information, Education and Communication (IEC) campaign
to explain publicly its mitigating measures as well as the
conditions of this ECC. It shall open opportunities to educate
the public especially the affected community, interested
academic institutions and other parties on the environment
and human health features of the project;

4. A copy of the ECC shall also be posted by the Proponent ✓ COMPLIED


inside its administration office and at the barangay bulletin
board of the affected barangay within 30 days from receipt
of the certification;

5. The proponent shall set up an Environmental Unit who shall ✓ COMPLIED


handle the environmental aspects of the projects, which shall
have the following responsibilities;
a. Monitoring requirements as defined under EMP;
b. Monitor actual project impact vis-à-vis predicted
impacts and management measures in the EMP;
c. Make recommendations for the revision of the EMP as
necessary;
d. Ensure that post-assessment permits are in order;
e. Ensure that monitoring and reporting are undertaken;
f. Ensure compliance to all ECC conditions and
restrictions of approved ECC;
6. In case of abandonment, the proponent shall notify the EMB ✓ COMPLIED
Regional Office concerned within three months prior to the
abandonment and the proponent shall submit its
abandonment.

You might also like