Cba 3000
Cba 3000
• Introduction
• Instrument Overview
• Software Overview
• Testing Procedure
• Additional mode
INTRODUCTION
Introduction
Circuit breakers
Circuit breaker is an automatically
operated electrical device, design to
close or open contacts inside the
chambers, thus closing and opening an
electrical circuit under normal or fault
conditions
VT CB CT
Transmission line Relay detect a fault
condition from the VT
Fault and CT secondary values
RELAY
CB
VT CB CT
Transmission line Relay commands the
circuit breaker to open in
order to interrupt the fault
RELAY
CB
Introduction
Circuit breakers – Breaks per phase
High voltage circuit breakers
can have more than one
moving contact (breaker), used
to interrupt the fault.
Vf
Br 1
Vf/2 Vf/2
Available boards:
Opened cb
Closed cb
Timing inputs
Instrument Overview
Timing Inputs – Auxiliary
Opened cb
• Transducer testing:
→ Additional mode: two breaks per phase
Timing inputs
Instrument Overview
Coil commands
Possible settings:
Coil Commands
• Open coil
• Close coil
• Phase selection
(A – B – C – ND)
• Range of measure:
(3A – 10A – 60A)
Instrument Overview
Coil commands
When the C1 coil is closed it energizes
Coil Commands the trip coil (110V), this opens the CB
Instrument Overview
Voltage Inputs
A single Voltage input can be connected
Voltage Inputs using:
• plug connector
• multipole connector
Multipole Plug
Instrument Overview
Voltage Inputs
Possible settings:
Voltage Inputs • Analog IN
generic voltage input
• Current clamp
allows to directly measure/visualize the current
flowing through the primary side of a clamp
• Pressure transducer
allows to directly measure/visualize the pressure
of SF6 gas taken from a transducer
• μohm-meter
Instrument Overview
μohm-meters generators
μΩ-meter generators allow to perform
μohm-meters static and dynamic resistance tests with a
current value up to 200 Adc.
• Test Plan
Test Plan
definition of tests parameters and
operations
HEADER
INSTRUMENT
SETTINGS *
TEST PLAN
RESULTS
TESTING PROCEDURE
Test
Test execution
There are two ways to perform a test:
• to create a list in the test plan. To press START on the result windows will perform all
of the “not executed” tests present in the list.
OTHER FEATURES
TEST CONNECTIONS
• Coil command
used to control the open/close operations of the CB, providing the supply
voltage to the corresponding coils.
• Timing input
used to monitor the CB contact status, and so to detect and measure its
transition time.
Test
Timing test - Connection
Coil connection:
the number of coils involved in the tests depends on the circuit breaker. The most
common situations are:
• 1 Open / 1 Close
generally for medium
voltage CB
• 3 Open / 1 Close
for high voltage CB
• 3 Open / 3 Close
for high voltage CB
3 open coils – 1 close coil
Test
Timing test - Connection
Timing connection:
O to C delay
Record time
Test
Timing test – O/C result
Open time A1
Pretrigger Open Coil duration
Test
Timing test – O/C result
The measure differences between the two methods are extremely low, except in
the tests that involves anti-pump relays.
In this cases the “coil command” settings is no longer valid to obtain correct
results.
Test
Timing test – Type of measurement
Dwell time
OTHER FEATURES
TEST CONNECTIONS
• μΩ-meter generators
used to generate the high current. The use of 3 generators decrease the time
required for the test
• Voltage input
used to measure the voltage during the current generation. They needs to be
connected as close as possible to the main contact of the CB.
Test
Resistance test – Connection
SRM connection:
J
I+
J V2
I-
V1
the position of the voltage inputs seriously affect 2 – correct: voltage inputs nearer
the results. than micrometers
Bad connection or different positioning can easily
cause differences of several μohm:
2
Test
Resistance test – Dynamic resistance
The testing purpose is to obtain the resistance profile of the breaker during its
operation. The tests is repeated during years, and the trend is evaluated through
comparison. It is also used to evaluate the arcing contact condition.
TEST CONNECTIONS
• Coil commands (same as timing test)
• μΩ-meter generators (same as SRM test)
• Voltage input (same as SRM test)
• Jumper cables only in case of 2 Breaks per phase test
(see ch. Additional mode – two breaks per phase)
Note:
timing inputs cannot be connected to the contact during this test, due to μΩ-
meter’s low impedance (they will always reveal closing position).
Test
Resistance test – Connection
DRM connection:
Close contact
Test
Resistance test – Dynamic resistance
DRM test for close operation doesn’t give any additional information.
The noise produced by the transition from infinite to the arcing resistance value
(hundreds of uohm) does not allow to perform any evaluation.
Noise level
Test
Test list – Motion analisys
OTHER FEATURES
TEST CONNECTIONS
• Analog transducer:
can be connected to every available voltage input, plug and multipole
or
• Digital transducer
must be connected one of the first three voltage input - multipole
Test
Motion analysis - Calibration
The final result of the motion analysis is the trend (expressed in mm) of the CB. So
the use of transducer requires a calibration in order to associate the movement of
the transducer to the CB one.
Test
Motion analysis - Calibration
Analog transducers works as a potentiometer (variable resistance):
Vsupply
Vin
Actual Stroke
Example of calibration
Test
Motion analysis - Calibration
After the calibration it is possible to define two Datum points position in order to
calculate the medium speed between them:
• Independent:
123mm - 98mm
Transducer trend:
Speed (mm/s)
Rebound (mm)
Steady close value
(indication)
Overtravel (mm)
OTHER FEATURES
Main contact
opens
Auxiliary
contact opens
Plunger
strikes latch
Test
Timing test – First trip test
Timings are obtained from the current transformer related to the CB. Current
flown drops to zero when an open occurs, so to monitor its trend allow to
determine the opening time. This is achieved using the provided AC current
clamps, connected to the secondary side of the CT.
Close CB Open CB
Test
Timing test – First trip test
To use the CBA coil commands is also dangerous, due to voltage on, also a wrong
connection can cause the CB to trip and to invalidate the test.
It is advisable to monitor the coil current using another DC clamp, and to start the
operation manually, defining a trigger in order to synchronize the instrument to
the start of the test.
Main opens
Test
Test list – Motion analisys
OTHER FEATURES
Batteries continuously discharge, if the black out condition last for too long the
voltage supplied will decrease.
It is possible to reach a situation in which there won’t be enough energy to make
the trip coil to operate, and so to interrupt a fault condition.
Minimum trip coil purpose is to perform an open operation before to reach this
situation.
Test
Timing test – MTC
The purpose of the test is to decrease the
Minimum trip coil voltage supply to the point of
operation, and verify the opening of the CB.
TEST CONNECTIONS
• MTC
create a voltage step to decrease the MTC coil
voltage
OTHER FEATURES
TEST CONNECTIONS
Connections are the same of timing test.
• Connect jumper cables to maintain the current flow, after the first open break
Jumper cables
AN1 → Phase A1
AN2 → Phase B1
AN3 → Phase C1
AN5 → Phase A2
AN6 → Phase B2
AN7 → Phase C2
Phase A
Two breaks per phase mode
Motion analysis
In order to give the possibility to test 3 transducers, it is possible to use PIR card
as transducer input.
Timing 1 – Vsupply
Timing 3 – Tr. A
Timing 5 – Tr. B
Timing 7 – Tr. C
Note: this setup can be used only with Analog trasducers, not digital ones.
Due to higher accuracy it is advisable to use the standard method, whenever available.
ADDITIONAL MODE
Both side grounded
BSG mode
Both side grounded mode
“BSG” is a setup condition required for safety
reasons. It consist on the connection to the
ground of the two ends of the CB.
- Close CB - Open CB
Resistance = Rcb // Rground = μΩ Resistance = Rground = mΩ
- Close CB - Open CB
Note: noise, induction and interaction with phases are digitally filtered/eliminated
in order to obtain correct result.
BSG mode
Both side grounded mode
The expected trends of current and voltage will be the following:
130A 130A
85A
0.92V
0.1V 0.1V
Jumper cables
AN1 → Phase A1
AN2 → Phase B1
AN3 → Phase C1
AN5 → Phase A2
AN6 → Phase B2
AN7 → Phase C2
Phase A
ADDITIONAL MODE
GIS
GIS mode
Gas insulated switchgear
In gas insulated substation (GIS) the high voltage conductors are kept inside
grounded metal enclosures, filled with SF6 gas. This includes circuit breakers, CTs,
VTs, disconnectors, etc.
SF6 gas has a dielectric strength 2,5 times greater than air, and it is 100 times
better for arc interruption.
This allows to reduce the insulation space by 10 times compared to an air
insulated substation (AIS).
GIS mode
Gas insulated switchgear – testing method
For GIS testing we have a situation similar to BSG one. The enclosure is always
strictly grounded through two earth disconnectors, at both sides of the CB.
This results in a parallel resistance to the CBs one. The difference with AIS is that this
resistance has an extremely low value, similar to the CBs contact one (μΩ).
GIS mode
Gas insulated switchgear – testing method
The earth resistance value doesn’t allow to use the same method of AIS for BSG.
The generation and the algorithm used to obtain timings on GIS are completely
different. Due to their complexity they will not be discussed in this training.