Workflow For Validation of Performance
Workflow For Validation of Performance
FOR VALIDATION
OF PERFORMANCE
Version 2009-02-16
Handled by: Plant Solutions
Checked by: Pontus Luedtke
Approved by: Ferdinand Franz
VALIDATION
OF
PERFORMANCE
Guideline for Validation of Performance
Tetra Pak Processing Systems Page 2 of 10
Plant Solutions 2009-02-16
Introduction
This document describes s, in terms of a workflow, how to validate the performance derived from customer
needs. Separating the selected Performance from the Basic Intended Purpose (commissioning criteria) from
selected performance (performance criteria), provides “Performance Guarantee” possibilities, i.e. contractual
performance criteria.. It is a part of the Deliver phase of the UCCD business approach (figure 1 and 2) and it
addresses the Order Fulfilment Capital Equipment.
Background
Various performance demands on
production need different functionality
and technical solutions to achieve
Figure 1. The UCCD business approach according to Tetra Pak Processing Systems customer needs. This has generated a
working methodology to secure
Deliver Installation to
Performance
performance, with a base platform with
1
Verify Perf.
options for satisfying unique needs.
Preconditions
Commissioning
Using this methodology and the
and Performance 2 4 approved Design Elements will give
Criteria. Trimming of Perfor-
Detailed Solution
Perf. Parameters mance
records repeated and verified performance,
3 which we can support and validate in a
Performance
Test project
The aim of this document is to present
a workflow to validate the
Figure 2. Activities to validate performance in the Deliver phase of the UCCD
business approach. performance (equipment + auto-
mation) of a Production Solution. This
to secure the performance based on
the customer needs and the
corresponding functionality.
The “building block” to secure the
wanted performance is the Process
Path. Each process cell can contain
several Process Paths. A Process Path
can contain several functions.
The Process Path is described as a
functional platform with basic
functionality. On the platform optional
functionality can be added to better
fulfil the customer needs (figure 3). All
selectable solutions are supported by
Tetra PlantMaster.
Figure 3. Examples of different Process Paths shown in a functional diagram. Each process cell
can contain several Process Paths and a Process Path can contain several functions.
Performance Requirements
Supply Capability
- Delivery defects & accuracy
Performance Requirements - Supply flexibility
- Future expansion/
Food Safety adaptation
FACTS 4
Physical Parameters
1 FillToDrainAmount (emptying, source tank)
2 FlushToDrainAmount (emptying, source tank)
3 FillToDestAmount (production)
5 FlushToDestAmount (production)
7 FillToTankAmount (filling, dest tank)
8 FlushToTankAmount(filling, dest tank)
3. Performance Test
Verify and agree on test procedure/-s
Measure in accordance with
FACTS 4
the performance criteria.
Adjust parameters/Modify Test principle
solution
Production Cycle, (minimum scenario)
If the performance parameter From empty pipe to empty pipe
values and tolerances are met, · Filling of pipe
then the test is considered · Production (with a defined time)
completed. If not, adjustments · Empting of pipe
· Cleaning
and modifications are to be
carried out and new tests
performed. Empty
Production (time)
CIP Empty
4. Performance Records
The output is performance test records to be signed in the
performance test certificate.
.
.