Standard Specifications For Construction of Roads
Standard Specifications For Construction of Roads
PART C EARTHWORKS
101(2)g Removal of Pipes other than Pipe Culverts (PVC/GI/Asbestos, up to 200 mm Ø), L=10 ft 30
101(3)a.2 Removal of Existing PCC Pavement, 0.23 m thk (for Reblocking at intermittent section) 32
103(5)a Shoring 54
103(5)b Cribbing/Cofferdamming 55
311(1)b.1 PCC Pavement (Plain) - Using Concrete Paver, 230 mm thk 119
311(1)b.1.1 PCC Pavement (Plain) - Using Concrete Paver, 230 mm thk 120
311(1)b.2 PCC Pavement (Plain) - Using Concrete Paver, 250 mm thk 121
311(1)b.2.1 PCC Pavement (Plain) - Using Concrete Paver, 250 mm thk 122
311(1)b.3 PCC Pavement (Plain) - Using Concrete Paver, 280 mm thk 123
311(1)b.3.1 PCC Pavement (Plain) - Using Concrete Paver, 280 mm thk 124
311(1)b.4 PCC Pavement (Plain) - Using Concrete Paver, 300 mm thk 125
311(1)b.4.1 PCC Pavement (Plain) - Using Concrete Paver, 300 mm thk 126
503(a) Drainage Steel Grating with Frame (675 mm x 975 mm Sump Grating) 147
503(b) Drainage Steel Grating with Frame (715 mm x 2000 mm Trench Grating) 148
504(1)a Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (24" Ø) - 610 mm Ø 149
504(1)b Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (30" Ø) - 760 mm Ø 150
504(1)c Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (36" Ø) - 910 mm Ø 151
504(1)d Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (42" Ø) - 1070 mm Ø 152
504(1)e Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (48" Ø) - 1220 mm Ø 153
504(2)a Removing, Cleaning and Re-laying Salvaged Culvert Pipe (24" Ø) - 610 mm Ø 154
504(2)b Removing, Cleaning and Re-laying Salvaged Culvert Pipe (30" Ø) - 760 mm Ø 155
504(2)c Removing, Cleaning and Re-laying Salvaged Culvert Pipe (36" Ø) - 910 mm Ø 156
504(2)d Removing, Cleaning and Re-laying Salvaged Culvert Pipe (42" Ø) - 1070 mm Ø 157
504(2)e Removing, Cleaning and Re-laying Salvaged Culvert Pipe (48" Ø) - 1220 mm Ø 158
509(c) Concrete Sheet Pile, furnished and driven - 0.50 m x 0.35 m 180
600(3) Concrete Curb and Gutter, Type A (Cast in place) - National Road 188
613 Concrete Joint Sealant (Hot Poured Elastic and Cold-Applied Types) 232
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
Assumed depth of cut is 150 mm all
throughout. A corresponding adjustment in the
output shall be computed based on the actual field
requirements.
Sub - Total for B
C. Total (A + B)
D. Output per hour = 0.05 ha
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
14 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Note:
Add Boom Truck if necessary for trimming in
urban areas.
15 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description : 100(3)b Individual Removal of Trees (small b, above 300 mm Ø up to 500 mm Ø)
Unit of Measurement : ea
Output : 1.00 ea
Note:
Add Boom Truck if necessary for trimming in
urban areas.
16 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description : 100(4)a Individual Removal of Trees (large a, above 500 mm Ø up to 750 mm Ø)
Unit of Measurement : ea
Output per hour : 1.00 ea
Note:
Add Boom Truck if necessary for trimming in
urban areas.
17 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description : 100(4)b Individual Removal of Trees (large b, above 750 mm Ø up to 900 mm Ø)
Unit of Measurement : ea
Output : 1.00 ea
Note:
Add Boom Truck if necessary for trimming in
urban areas.
18 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
B. Equipment
F. Materials
19 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
F. Materials
20 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
F. Materials
21 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
F. Materials
22 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
F. Materials
23 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Boom Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
F. Materials
24 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Boom Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
F. Materials
25 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Boom Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
F. Materials
26 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Boom Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
F. Materials
27 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Boom Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
F. Materials
28 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Boom Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
29 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description : 101(2)g Removal of Pipes other than Pipe Culverts (PVC/GI/Asbestos, up to 200 mm Ø), L=10 ft
Unit of Measurement : ea
Output per hour : 2.00 ea
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Cargo Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
30 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
Production output for other thickness should
be computed proportionately to the output of 0.23
m thk PCCP.
Sub - Total for B
C. Total (A + B)
D. Output per hour = 40.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
31 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description : 101(3)a.2 Removal of Existing PCC Pavement, 0.23 m thk (for Reblocking at intermittent section)
Unit of Measurement : m²
Output per hour : 30.00 m²
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
Production output for other thickness should
be computed proportionately to the output of 0.23
m thk PCCP.
Sub - Total for B
C. Total (A + B)
D. Output per hour = 30.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
32 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
Production output for other thickness should
be computed proportionately to the output of 100
mm thk Asphalt Pavement.
Sub - Total for B
C. Total (A + B)
D. Output per hour = 60.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
33 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
Production output for other thickness should
be computed proportionately to the output of 100
mm thk sidewalk.
Sub - Total for B
C. Total (A + B)
D. Output per hour = 75.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
34 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
35 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
36 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
37 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
38 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
39 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
40 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
41 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
Sub - Total for B
C. Total (A + B)
D. Output per hour = 4.20 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
a. Dynamite kg 0.40
b. Detonation Cord m 2.00 Prices of materials are variable per Region/District
c. Detonator pc 0.15 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Ammonium Sulfate kg 0.20 project site. Refer to the Construction Materials Price
e. Blasting Cap pc 0.40 Data established quarterly by Central Office Price
f. Safety Fuse m 0.10 Monitoring Committee.
42 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description : 102(3)d Roadway Excavation (Surplus Hard Rock) - Blasting (Tunnel Excavation)
Unit of Measurement : m³
Output per hour : 1.65 m³
a. Dynamite kg 2.00
b. Detonation Cord m 1.40 Prices of materials are variable per Region/District
c. Detonator pc 2.00 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Ammonium Sulfate kg 1.00 project site. Refer to the Construction Materials Price
e. Blasting Cap pc 0.45 Data established quarterly by Central Office Price
f. Safety Fuse m 0.10 Monitoring Committee.
43 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
44 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
B. Equipment
45 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
F. Materials
46 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
F. Materials
47 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
F. Materials
48 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
F. Materials
49 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
F. Materials
50 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
F. Materials
51 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
F. Materials
52 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
53 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
54 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
F. Materials
55 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
56 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
57 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
58 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
59 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
60 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
61 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
62 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
63 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
64 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)
F. Materials
F. Materials
A. Labor
F. Materials
Item No./Description : 204 Portland Cement Stabilized Road Mix Base Course
Unit of Measurement : m³
Output per hour : 15.00 m³
F. Materials
F. Materials
Item No./Description : 206 Portland Cement Treated Plant Mix Base Course
Unit of Measurement : m³
Output per hour : 15.00 m³
F. Materials
F. Materials
F. Materials
F. Materials
F. Materials
Item No./Description : 303(4) Bituminous Seal Coat (Asphalt Cement Penetration Grade 120-150)
Unit of Measurement : mt
Output per hour : 0.30 mt
a. Aggregates mt 1.15
(w/ 15% Shrinkage Factor) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.
Item No./Description : 304(2) Bituminous Surface Treatment (Asphalt Cement Penetration Grade 120-150)
Unit of Measurement : mt
Output per hour : 0.30 mt
a. Aggregates mt 1.15
(w/ 15% Shrinkage Factor) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.
Item No./Description : 305(3) Bituminous Penetration Macadam Pavement (RC Cut-back Asphalt)
Unit of Measurement : mt
Output per hour : 0.30 mt
Item No./Description : 306(1) Aggregates for Bituminous Road Mix Surface Course
Unit of Measurement : mt
Output per hour : 12.00 mt
Item No./Description : 306(2) Bituminous Material for Bituminous Road Mix Surface Course
Unit of Measurement : mt
Output per hour : 1.00 mt
F. Materials
Item No./Description : 307 Bituminous Plant Mix Surface Course-General (50 mm thk)
Unit of Measurement : m²
Output per hour : 171.30 m²
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
B. Equipment
B. Equipment
B. Equipment
Item No./Description : 311(1)a.1 PCC Pavement (Plain) - Conventional Method, 150 mm thk
Unit of Measurement : m²
Output per hour : 107.33 m²
Item No./Description : 311(1)a.1.1 PCC Pavement (Plain) - Conventional Method, 150 mm thk
Unit of Measurement : m²
Output per hour : 107.33 m²
Item No./Description : 311(1)a.2 PCC Pavement (Plain) - Conventional Method, 200 mm thk
Unit of Measurement : m²
Output per hour : 80.50 m²
Item No./Description : 311(1)a.2.1 PCC Pavement (Plain) - Conventional Method, 200 mm thk
Unit of Measurement : m²
Output per hour : 80.50 m²
Item No./Description : 311(1)a.3 PCC Pavement (Plain) - Conventional Method, 230 mm thk
Unit of Measurement : m²
Output per hour : 70.00 m²
Item No./Description : 311(1)a.3.1 PCC Pavement (Plain) - Conventional Method, 230 mm thk
Unit of Measurement : m²
Output per hour : 70.00 m²
Item No./Description : 311(1)a.4 PCC Pavement (Plain) - Conventional Method, 250 mm thk
Unit of Measurement : m²
Output per hour : 64.40 m²
Item No./Description : 311(1)a.4.1 PCC Pavement (Plain) - Conventional Method, 250 mm thk
Unit of Measurement : m²
Output per hour : 64.40 m²
Item No./Description : 311(1)a.5 PCC Pavement (Plain) - Conventional Method, 280 mm thk
Unit of Measurement : m²
Output per hour : 57.50 m²
Item No./Description : 311(1)a.5.1 PCC Pavement (Plain) - Conventional Method, 280 mm thk
Unit of Measurement : m²
Output per hour : 57.50 m²
Item No./Description : 311(1)a.6 PCC Pavement (Plain) - Conventional Method, 300 mm thk
Unit of Measurement : m²
Output per hour : 53.67 m²
Item No./Description : 311(1)a.6.1 PCC Pavement (Plain) - Conventional Method, 300 mm thk
Unit of Measurement : m²
Output per hour : 53.67 m²
Item No./Description : 311(1)b.1 PCC Pavement (Plain) - Using Concrete Paver, 230 mm thk
Unit of Measurement : m²
Output per hour : 90.00 m²
Item No./Description : 311(1)b.1.1 PCC Pavement (Plain) - Using Concrete Paver, 230 mm thk
Unit of Measurement : m²
Output per hour : 100.00 m²
Item No./Description : 311(1)b.2 PCC Pavement (Plain) - Using Concrete Paver, 250 mm thk
Unit of Measurement : m²
Output per hour : 82.80 m²
Item No./Description : 311(1)b.2.1 PCC Pavement (Plain) - Using Concrete Paver, 250 mm thk
Unit of Measurement : m²
Output per hour : 100.00 m²
Item No./Description : 311(1)b.3 PCC Pavement (Plain) - Using Concrete Paver, 280 mm thk
Unit of Measurement : m²
Output per hour : 73.93 m²
Item No./Description : 311(1)b.3.1 PCC Pavement (Plain) - Using Concrete Paver, 280 mm thk
Unit of Measurement : m²
Output per hour : 100.00 m²
Item No./Description : 311(1)b.4 PCC Pavement (Plain) - Using Concrete Paver, 300 mm thk
Unit of Measurement : m²
Output per hour : 69.00 m²
Item No./Description : 311(1)b.4.1 PCC Pavement (Plain) - Using Concrete Paver, 300 mm thk
Unit of Measurement : m²
Output per hour : 100.00 m²
Item No./Description : 311(1)c PCC Pavement (Plain) - Conventional Method, 150 mm thk
Unit of Measurement : m²
Output per hour : 12.00 m²
Item No./Description : 311(1)c.1 PCC Pavement (Plain) - Conventional Method, 150 mm thk
Unit of Measurement : m²
Output per hour : 12.00 m²
F. Materials
F. Materials
Installation/Removal of Formworks
a. Skilled Labor 4 1.00
b. Unskilled Labor 8 1.00
Sub - Total for A
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
Note:
*Quantities for lumber, plywood and CWN are
dependent on the type of minor structure.
The above-computed quantities are based on box
culvert.
F. Materials
F. Materials
F. Materials
F. Materials
F. Materials
F. Materials
F. Materials
F. Materials
These pay items are variable in dimensions based on the actual condition
which combines component items, hence standard estimate should be based on
the standard Detailed Unit Price Analysis (DUPA) of each component items, such
as Items 103(3), 404 & 405. See attached DUPA.
Further, these items with unit of measure as 'each' in the Blue Book is
recommended to be broken down separately by component items such as Items
103(3) - Foundation Fill, 404 - Reinforcing Steel Bar and 405 - Structural Concrete
Class A (Minor Structures) in the summary of quantities in the preparation of
design plans.
Item No./Description : 503(a) Drainage Steel Grating with Frame (675 mm x 975 mm Sump Grating)
Unit of Measurement : set
Output : 1.00 set
Item No./Description : 503(b) Drainage Steel Grating with Frame (715 mm x 2000 mm Trench Grating)
Unit of Measurement : set
Output : 1.00 set
Item No./Description : 504(1)a Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (24" dia) - 610 mm Ø
Unit of Measurement : m
Output : 1.00 m
Item No./Description : 504(1)b Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (30" Ø) - 760 mm Ø
Unit of Measurement : m
Output : 1.00 m
Item No./Description : 504(1)c Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (36" Ø) - 910 mm Ø
Unit of Measurement : m
Output : 1.00 m
Item No./Description : 504(1)d Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (42" Ø) - 1070 mm Ø
Unit of Measurement : m
Output : 1.00 m
Item No./Description : 504(1)e Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (48" Ø) - 1220 mm Ø
Unit of Measurement : m
Output : 1.00 m
Item No./Description : 504(2)a Removing, Cleaning and Re-laying Salvaged Culvert Pipe (24" Ø) - 610 mm Ø
Unit of Measurement : m
Output : 1.00 m
Item No./Description : 504(2)b Removing, Cleaning and Re-laying Salvaged Culvert Pipe (30" Ø) - 760 mm Ø
Unit of Measurement : m
Output : 1.00 m
a. Portland Cement bag 0.918 Prices of materials are variable per Region/District
b. Sand m³ 0.052 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
c. Sand Bedding m³ 0.108 project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.
Item No./Description : 504(2)c Removing, Cleaning and Re-laying Salvaged Culvert Pipe (36" Ø) - 910 mm Ø
Unit of Measurement : m
Output per hour : 1.00 m
a. Portland Cement bag 1.080 Prices of materials are variable per Region/District
b. Sand m³ 0.061 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
c. Sand Bedding m³ 0.128 project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.
Item No./Description : 504(2)d Removing, Cleaning and Re-laying Salvaged Culvert Pipe (42" Ø) - 1070 mm Ø
Unit of Measurement : m
Output per hour : 1.00 m
a. Portland Cement bag 1.242 Prices of materials are variable per Region/District
b. Sand m³ 0.070 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
c. Sand Bedding m³ 0.149 project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.
Item No./Description : 504(2)e Removing, Cleaning and Re-laying Salvaged Culvert Pipe (48" Ø) - 1220 mm Ø
Unit of Measurement : m
Output : 1.00 m
a. Portland Cement bag 1.404 Prices of materials are variable per Region/District
b. Sand m³ 0.080 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
c. Sand Bedding m³ 0.170 project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.
Item No./Description : 504(3)a Cleaning Culvert Pipe in place (610 mm Ø) - Half Silted
Unit of Measurement : m
Output per hour : 8.00 m
Item No./Description : 504(3)b Cleaning Culvert Pipe in place (760 mm Ø) - Half Silted
Unit of Measurement : m
Output per hour : 5.25 m
Item No./Description : 504(3)c Cleaning Culvert Pipe in place (910 mm Ø) - Half Silted
Unit of Measurement : m
Output per hour : 3.75 m
F. Materials
Item No./Description : 504(3)d Cleaning Culvert Pipe in place (1070 mm Ø) - Half Silted
Unit of Measurement : m
Output per hour : 2.75 m
F. Materials
Item No./Description : 504(3)e Cleaning Culvert Pipe in place (1220 mm Ø) - Half Silted
Unit of Measurement : m
Output per hour : 2.00 m
F. Materials
Item No./Description : 504(3)f Cleaning Culvert Pipe in place (1520 mm Ø) - Half Silted
Unit of Measurement : m
Output per hour : 1.50 m
F. Materials
F. Materials
F. Materials
F. Materials
F. Materials
A. Labor
F. Materials
a. Boulders m³ 1.05
Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.
Item No./Description : 509(c) Concrete Sheet Pile, furnished and driven - 0.50 m x 0.35 m
Unit of Measurement : m
Output per hour : 1.38 m
Item No./Description : 600(3) Concrete Curb and Gutter, Type A (Cast in place) - National Road
Unit of Measurement : m
Output per hour : 10.30 m
F. Materials
F. Materials
F. Materials
F. Materials
F. Materials
F. Materials
F. Materials
F. Materials
F. Materials
Item No./Description : 603(3)a Metal Guardrails (Metal Beam) including Concrete Post
Unit of Measurement : m
Output per hour : 4.20 m
F. Materials
F. Materials
F. Materials
F. Materials
F. Materials
F. Materials
F. Materials
a. Topsoil m³ 1.05
Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.
F. Materials
F. Materials
a. Sprigs m² 1.05
b. Fertilizer kg 0.10 Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.
a. Sods m² 1.05
Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.
a. Fertilizers kg 3.00
b. Bamboo Pole pc 3.00 Prices of materials are variable per Region/District
c. Polyethylene Sheets m² 3.00 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Tie Wire kg 0.25 project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.
Item No./Description : 613 Concrete Joint Sealant (Hot Poured Elastic and Cold-Applied Types)
Unit of Measurement : kg
Output per hour : 20.00 kg
.
Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)
A. Labor
Rental of equipment presented in the Detailed Unit Price Analysis (DUPA) are based on the prevailing
“Association of Carriers and Equipment Lessors, (ACEL) Inc.” rental rates approved for use by the DPWH
(Presently it is the 2014 ACEL Rates). Rental rates of equipment not indicated in the ACEL booklet shall be
taken from the rental rates prepared by the Bureau of Equipment. For simplicity in computation, the
operated rental rates are preferred over the bare rental rates as the former includes operator’s wages,
fringe benefits, fuel, oil, lubricants and equipment maintenance.
E.1 List of equipment adopted in the standard DUPA with make, model and capacity
FLYWHEEL
DESCRIPTION MODEL CAPACITY RENTAL RATE
HORSEPOWER
1. Earthmoving Equipment
1.1 Bulldozer D6H SERIES II PSDS/DD 165 PhP 3,379.00
1.2 Bulldozer w/ Ripper D6H SERIES II PSDS/DD 165 PhP 3,885.85
1.3 Payloader LX80-2C 1.50 m3/1.95 yd3 110 PhP 1,733.00
1.4 Motorized Road Grader G710A 140 PhP 2,173.00
1.5 Road Grader w/ Scarifier G710A 140 PhP 2,824.90
2. Compaction Equipment
2.1 Pneumatic Tire Roller 9-WHL, 9.00X20, 4PR 10 mt 107 PhP 561.00
2.2 Vibratory Roller SD100DC 10 mt 125 PhP 1,846.00
2.3 Tandem Steel Roller CC421 10.10 mt 123.40 PhP 1,652.00
2.4 Plate Compactor 400-500 Gasoline Engine 5 PhP 123.00
3. Lifting Equipment
3.1 Crawler Crane All Models 36-40 mt 190 PhP 1,902.00
3.2 Truck Mounted Crane All Models 31-35 mt 238 PhP 1,861.00
3.3 Truck Mounted Crane All Models 41-45 mt 246 PhP 2,606.00
4. Excavating Equipment
4.1 Backhoe SE 130 LC-2 0.80 m3/1.04 yd3 99 PhP 1,537.00
3 3
4.2 Backhoe w/ Breaker SE 130 LC-2 0.80 m /1.04 yd 99 PhP 1,998.10
4.3 Backhoe, Wheel Mounted PW60N-1 0.28 m3/0.37 yd3 50 PhP 922.00
5. Foundation Equipment
5.1 Vibro Hammer DPD600T Hydraulic Pile Driver 60 ton 201 PhP 2,123.00
6. Asphalting Equipment
6.1 Asphalt Distributor ROSCO/5 ton 3000 USG 100 PhP 936.00
6.2 Asphalt Paver NF220BIIVDM 80 PhP 1,833.00
7. Concreting Equipment
7.1 Concrete Screeder Wacker Truss Screed 5.50 PhP 545.00
7.2 Concrete Paver COMMANDER III, FOUR-TRACK PhP 6,765.00
7.3 One Bagger Mixer 4-6 ft3/min PhP 172.00
7.4 Transit Mixer All Models 5-6 yd3 175 PhP 1,318.00
8. Hauling Equipment
8.1 Dump Truck All Models 12 yd3 290 PhP 1,420.00
8.2 Cargo/Service Truck All Models 2-5 mt 160 PhP 783.00
8.3 Boom Truck All Models 2-5 mt 160 PhP 1,017.90
8.4 Cargo/Service Truck All Models 9-10 mt 270 PhP 1,212.00
8.5 Water Truck/Pump All Makes 16000 L 360 PhP 2,450.00
9. Air Equipment
9.1 Air Compressor All Models 356-450 cfm 130 PhP 965.00
9.2 Air Compressor All Models 161-185 cfm 69 PhP 502.00
9.3 Air Compressor All Models 15-35 cfm 20 PhP 205.00
9.4 Diamond Drill CP-8 PhP 201.25
9.5 Jackhammer PhP 150.00
9.6 Pneumatic Drilling Machine PhP 170.00
247
OUTPUT/DISCHARGE SOLID SIZE FLYWHEEL
DESCRIPTION RENTAL RATE
(lpm) CAPACITY (mm) HORSEPOWER
10. Pumping Equipment
10.1 Water Pump, 100 mm suction Ø 2,667 50 16 PhP 266.25
FLYWHEEL
DESCRIPTION MODEL AMPERE RENTAL RATE
HORSEPOWER
12. Shop Equipment
12.1 Welding Machine Gas/Diesel Driven 300 48 PhP 371.00
FLYWHEEL
DESCRIPTION MODEL CAPACITY RENTAL RATE
HORSEPOWER
13. Special Support Equipment
13.1 Chainsaw HUSQVARNA 2100 CD with CR22, 7 ft Reach, 9 in Standard Blade PhP 75.36
14. Miscellaneous Equipment
14.1 Concrete Vibrator Flexible Shaft Type 2" Head Ø with 5 Amperes Gasoline Drive Unit PhP 91.25
14.2 Concrete Saw 14" Blade Ø with 4 3/4" Cutting Depth 7.50 PhP 32.63
14.3 Bar Cutter 25 mm Maximum Rebar Ø (Grade 40), Single Phase PhP 219.75
14.4 Bar Bender 25 mm Maximum Rebar Ø, Three Phase PhP 351.50
15. Plants
15.1 Asphalt Concrete Plant Complete with: Cold Feed System, bins, feeder and collecting PhP 4,286.63
conveyors. Drying and Burner System, feed conveyors drum and
fully modulating burner. Fuel feed system. Screening-Weighing-
Mixing System, hot elevator, vibrating screen, hot bins, weighing
scale and twinshaft pugmill mixer. Dust collection and filler feeding
system, bag filter and exhaust fan. Thermal Hot Oil System, delivery
pump and heater and Computerized Plant Control System.
15.2 Concrete Batch Plant Complete with: cement silo and screw conveyor system. Water and PhP 1,759.50
supply system. Aggregate storage bins with vibrators and conveyors
system. Weigh hopper with electronic loadcell for aggregates,
cement, water and admixture. Central twinshaft mixer. Hydraulic
System and Computerized Plant Control System.
18. Others
18.1 Power Broom, Towed Type With Engine 2 m wide 6-30 km/h Sweeping Capacity PhP 130.54
18.2 Hydroseeding Machine PhP 952.00
18.3 Applicator Machine PhP 93.75
18.4 Kneading Machine PhP 187.50
18.5 Drop Hammer PhP 200.00
18.6 Cutting Outfit PhP 45.45
18.7 Steel Wheel w/ Nylon Rope PhP 300.00
18.8 Improvised Bamboo w/ Bucket PhP 200.00
18.9 Asphalt Kettle/Drum PhP 10.00
248