0% found this document useful (0 votes)
202 views

Standard Specifications For Construction of Roads

The document is a summary table listing items of work and their descriptions for a construction project. It includes over 100 items grouped under parts for earthworks, subbase/base course, and surface course. Each item is given a unique number and code identifying the type of work and material specifications. Page numbers are provided to reference the full descriptions.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
202 views

Standard Specifications For Construction of Roads

The document is a summary table listing items of work and their descriptions for a construction project. It includes over 100 items grouped under parts for earthworks, subbase/base course, and surface course. Each item is given a unique number and code identifying the type of work and material specifications. Page numbers are provided to reference the full descriptions.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 238

B.

1 SUMMARY TABLE OF ITEMS OF WORK AND DESCRIPTION

ITEM NO. DESCRIPTION PAGE NO.

PART C EARTHWORKS

100(1) Clearing & Grubbing (with Stripping) 14

100(3)a Individual Removal of Trees (small a, 150 mm Ø up to 300 mm Ø) 15

100(3)b Individual Removal of Trees (small b, above 300 mm Ø up to 500 mm Ø) 16

100(4)a Individual Removal of Trees (large a, above 500 mm Ø up to 750 mm Ø) 17

100(4)b Individual Removal of Trees (large b, above 750 mm Ø up to 900 mm Ø) 18

101(1) Removal of Structures and Obstruction 19

101(1)a Removal of Concrete Bridge Structures 20

101(1)b Removal of Steel Bridge Structures 21

101(1)c Removal of Stone Masonry Lined Drainage Structures 22

101(1)d Removal of Concrete Drainage Structures 23

101(2)a Removal of RCPC (24" Ø) - 610 mm Ø 24

101(2)b Removal of RCPC (30" Ø) - 760 mm Ø 25

101(2)c Removal of RCPC (36" Ø) - 910 mm Ø 26

101(2)d Removal of RCPC (42" Ø) - 1070 mm Ø 27

101(2)e Removal of RCPC (48" Ø) - 1220 mm Ø 28

101(2)f Removal of RCPC (60" Ø) - 1520 mm Ø 29

101(2)g Removal of Pipes other than Pipe Culverts (PVC/GI/Asbestos, up to 200 mm Ø), L=10 ft 30

101(3)a.1 Removal of Existing Concrete Pavement (0.23 m thk) 31

101(3)a.2 Removal of Existing PCC Pavement, 0.23 m thk (for Reblocking at intermittent section) 32

101(3)b Removal of Existing Asphalt Pavement (100 mm thk) 33

101(3)c Removal of Sidewalk (100 mm thk) 34

101(4)a Removal of Curb 35

101(4)b Removal of Curb & Gutter 36

102(1) Roadway Excavation (Unsuitable) 37

5 Summary Table of Items of Work and Description


ITEM NO. DESCRIPTION PAGE NO.

102(2)a Roadway Excavation (Surplus Common) 38

102(2)b Roadway Excavation (Surplus Common) 39

102(3)a Roadway Excavation (Surplus Soft Rock) 40

102(3)b Roadway Excavation (Surplus Soft Rock) 41

102(3)c Roadway Excavation (Surplus Hard Rock) - Blasting 42

102(3)d Roadway Excavation (Surplus Hard Rock) - Blasting (Tunnel Excavation) 43

102(4) Roadway Excavation (Surplus Unclassified) 44

103(1)a Structure Excavation (Common Soil) 45

103(1)b Structure Excavation (Soft Rock) 46

103(1)c Structure Excavation (Solid Rock) 47

103(2)a Bridge Excavation (Common Soil) 48

103(2)b Bridge Excavation (Soft Rock) 49

103(2)c Bridge Excavation (Solid Rock) 50

103(2)d Bridge Excavation (Solid Rock) 51

103(3) Foundation Fill 52

103(4) Excavation ordered below Plan Elevation 53

103(5)a Shoring 54

103(5)b Cribbing/Cofferdamming 55

103(6) Pipe Culvert and Drain Excavation 56

104(1)a Embankment (from Borrow) 57

104(1)b Embankment from Roadway Excavation 58

104(2) Selected Borrow for topping , case 1 59

104(3) Selected Borrow for topping , case 2 60

104(4) Earth Berm 61

105(1) Subgrade Preparation (Common Material) 62

105(2) Subgrade Preparation (Existing Pavement) 63

105(3) Subgrade Preparation (Unsuitable Material) 64

6 Summary Table of Items of Work and Description


ITEM NO. DESCRIPTION PAGE NO.

PART D SUBBASE AND BASE COURSE

200 Aggregate Subbase Course 65

200(1) Aggregate Subbase Course (for Intermittent Reblocking) 66

201 Aggregate Base Course 67

201(1) Aggregate Base Course (for Reblocking) 68

202 Crushed Aggregate Base Course 69

203 Lime Stabilized Road Mix Base Course 70

204 Portland Cement Stabilized Road Mix Base Course 71

205 Asphalt Stabilized Road Mix Base Course 72

206 Portland Cement Treated Plant Mix Base Course 73

PART E SURFACE COURSE

300(1) Gravel Surface Course (Uncrushed) 74

300(2) Crushed Aggregate Surface Course 75

301(1) Bituminous Prime Coat (MC Cut-back Asphalt) 76

301(2) Bituminous Prime Coat (RC Cut-back Asphalt) 77

302(1) Bituminous Tack Coat (RC Cut-back Asphalt) 78

302(2) Bituminous Tack Coat (Emulsified Asphalt) 79

303(1) Bituminous Seal Coat (Cover Aggregate) 80

303(2) Bituminous Seal Coat (MC Cut-back Asphalt) 81

303(3) Bituminous Seal Coat (RC Cut-back Asphalt) 82

303(4) Bituminous Seal Coat (Asphalt Cement Penetration Grade 120-150) 83

304(1) Bituminous Surface Treatment (Aggregate Grading) 84

304(2) Bituminous Surface Treatment (Asphalt Cement Penetration Grade 120-150) 85

304(3) Bituminous Surface Treatment (MC Cut-back Asphalt) 86

304(4) Bituminous Surface Treatment (RC Cut-back Asphalt) 87

304(5) Bituminous Surface Treatment (Emulsified Asphalt) 88

305(1) Bituminous Penetration Macadam Pavement (Aggregates) 89

7 Summary Table of Items of Work and Description


ITEM NO. DESCRIPTION PAGE NO.

305(2) Bituminous Penetration Macadam Pavement (Asphalt Cement) 90

305(3) Bituminous Penetration Macadam Pavement (RC Cut-back Asphalt) 91

305(4) Bituminous Penetration Macadam Pavement (Emulsified Asphalt) 92

306(a) Bituminous Road Mix Surface Course 93

306(b) Bituminous Road Mix Surface Course 94

306(1) Aggregates for Bituminous Road Mix Surface Course 95

306(2) Bituminous Material for Bituminous Road Mix Surface Course 96

307 Bituminous Plant Mix Surface Course-General (50 mm thk) 97

308(a) Cold Asphalt Plant Mix (50 mm thk) 98

308(b) Cold Asphalt Plant Mix (50 mm thk) 99

309 Bituminous Plant Mix (Stockpile Maintenance Mixture) 100

310(a.1) Bituminous Concrete Surface Course (30 mm thk) 101

310(a.2) Bituminous Concrete Surface Course (40 mm thk) 102

310(a.3) Bituminous Concrete Surface Course (50 mm thk) 103

310(b.1) Bituminous Concrete Surface Course (30 mm thk) 104

310(b.2) Bituminous Concrete Surface Course (40 mm thk) 105

310(b.3) Bituminous Concrete Surface Course (50 mm thk) 106

311(1)a.1 PCC Pavement (Plain) - Conventional Method, 150 mm thk 107

311(1)a.1.1 PCC Pavement (Plain) - Conventional Method, 150 mm thk 108

311(1)a.2 PCC Pavement (Plain) - Conventional Method, 200 mm thk 109

311(1)a.2.1 PCC Pavement (Plain) - Conventional Method, 200 mm thk 110

311(1)a.3 PCC Pavement (Plain) - Conventional Method, 230 mm thk 111

311(1)a.3.1 PCC Pavement (Plain) - Conventional Method, 230 mm thk 112

311(1)a.4 PCC Pavement (Plain) - Conventional Method, 250 mm thk 113

311(1)a.4.1 PCC Pavement (Plain) - Conventional Method, 250 mm thk 114

311(1)a.5 PCC Pavement (Plain) - Conventional Method, 280 mm thk 115

311(1)a.5.1 PCC Pavement (Plain) - Conventional Method, 280 mm thk 116

8 Summary Table of Items of Work and Description


ITEM NO. DESCRIPTION PAGE NO.

311(1)a.6 PCC Pavement (Plain) - Conventional Method, 300 mm thk 117

311(1)a.6.1 PCC Pavement (Plain) - Conventional Method, 300 mm thk 118

311(1)b.1 PCC Pavement (Plain) - Using Concrete Paver, 230 mm thk 119

311(1)b.1.1 PCC Pavement (Plain) - Using Concrete Paver, 230 mm thk 120

311(1)b.2 PCC Pavement (Plain) - Using Concrete Paver, 250 mm thk 121

311(1)b.2.1 PCC Pavement (Plain) - Using Concrete Paver, 250 mm thk 122

311(1)b.3 PCC Pavement (Plain) - Using Concrete Paver, 280 mm thk 123

311(1)b.3.1 PCC Pavement (Plain) - Using Concrete Paver, 280 mm thk 124

311(1)b.4 PCC Pavement (Plain) - Using Concrete Paver, 300 mm thk 125

311(1)b.4.1 PCC Pavement (Plain) - Using Concrete Paver, 300 mm thk 126

311(1)c PCC Pavement (Plain) - Conventional Method, 150 mm thk 127

311(1)c.1 PCC Pavement (Plain) - Conventional Method, 150 mm thk 128

311(2) PCC Pavement (Reinforced), 300 mm thk 129

311(2)1 PCC Pavement (Reinforced), 300 mm thk 130

PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES

404 Reinforcing Steel Bar, Grade 40 (Minor Structures) 131

405 Structural Concrete Class A (Minor Structures) 132

500(1)a Pipe Culverts, 610 mm Ø (24" Ø) 133

500(1)b Pipe Culverts, 760 mm Ø (30" Ø) 134

500(1)c Pipe Culverts, 910 mm Ø (36" Ø) 135

500(1)d Pipe Culverts, 1070 mm Ø (42" Ø) 136

500(1)e Pipe Culverts, 1220 mm Ø (48" Ø) 137

500(1)f Pipe Culverts, 1520 mm Ø (60" Ø) 138

501(1) Underdrain 139

501(2) Blind Drain 140

501(3) Granular Backfill filter material for Underdrains 141

502 Manhole/Catch Basin/Inlet - Pay Items 142

9 Summary Table of Items of Work and Description


ITEM NO. DESCRIPTION PAGE NO.

502 Manhole/Catch Basin/Inlet 143

502(4) Concrete Covers 144

502(5) Metal Frames and Gratings 145

502(6) Metal Frames and Covers (Circular) 146

503(a) Drainage Steel Grating with Frame (675 mm x 975 mm Sump Grating) 147

503(b) Drainage Steel Grating with Frame (715 mm x 2000 mm Trench Grating) 148

504(1)a Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (24" Ø) - 610 mm Ø 149

504(1)b Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (30" Ø) - 760 mm Ø 150

504(1)c Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (36" Ø) - 910 mm Ø 151

504(1)d Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (42" Ø) - 1070 mm Ø 152

504(1)e Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (48" Ø) - 1220 mm Ø 153

504(2)a Removing, Cleaning and Re-laying Salvaged Culvert Pipe (24" Ø) - 610 mm Ø 154

504(2)b Removing, Cleaning and Re-laying Salvaged Culvert Pipe (30" Ø) - 760 mm Ø 155

504(2)c Removing, Cleaning and Re-laying Salvaged Culvert Pipe (36" Ø) - 910 mm Ø 156

504(2)d Removing, Cleaning and Re-laying Salvaged Culvert Pipe (42" Ø) - 1070 mm Ø 157

504(2)e Removing, Cleaning and Re-laying Salvaged Culvert Pipe (48" Ø) - 1220 mm Ø 158

504(3)a Cleaning Culvert Pipe in place (610 mm Ø) - Half Silted 159

504(3)b Cleaning Culvert Pipe in place (760 mm Ø) - Half Silted 160

504(3)c Cleaning Culvert Pipe in place (910 mm Ø) - Half Silted 161

504(3)d Cleaning Culvert Pipe in place (1070 mm Ø) - Half Silted 162

504(3)e Cleaning Culvert Pipe in place (1220 mm Ø) - Half Silted 163

504(3)f Cleaning Culvert Pipe in place (1520 mm Ø) - Half Silted 164

504(4) Reconditioning Drainage Structures 165

505(1) Riprap (Class A) 166

505(2) Riprap (Class B) 167

505(3) Riprap (Class C) 168

505(4) Riprap (Class D) 169

10 Summary Table of Items of Work and Description


ITEM NO. DESCRIPTION PAGE NO.

505(5) Grouted Riprap (Class A) 170

505(6) Grouted Riprap (Class B) 171

505(7) Grouted Riprap (Class C) 172

505(8) Grouted Riprap (Class D) 173

505(9) Filter Layer of Granular Material 174

506 Stone Masonry 175

507 Rubble Concrete 176

508 Hand Laid Rock Embankment 177

509(a) Timber Sheet Pile 178

509(b) Steel Sheet Pile (Slope Protection) 179

509(c) Concrete Sheet Pile, furnished and driven - 0.50 m x 0.35 m 180

510(1) Bed Course Granular Material 181

510(2) Concrete Slope Protection 182

511(1) Gabions 183

511(2) Mattresses 184

511(3) Filter Cloth 185

PART H MISCELLANEOUS STRUCTURES

600(1) Concrete Curb (Cast in place) - 0.45 m x 0.15/0.20 m 186

600(2) Concrete Gutter (Cast in place) - 0.50 m x 0.15 m 187

600(3) Concrete Curb and Gutter, Type A (Cast in place) - National Road 188

600(4) Concrete Curb (Precast) 189

600(5) Concrete Gutter (Precast) 190

600(6) Concrete Curb and Gutter (Precast) 191

601(a) Sidewalk (100 mm thk) 192

601(b) Sidewalk (100 mm thk) 193

602(1)a Right-of-Way Monument 194

602(1)b Right-of-Way Monument (Precast) 195

11 Summary Table of Items of Work and Description


ITEM NO. DESCRIPTION PAGE NO.

602(2)a Maintenance Marker Post 196

602(2)b Maintenance Marker Post (Precast) 197

602(3)a Kilometer Post 198

602(3)b Kilometer Post (Precast) 199

602(4) Guide Post 200

603(1) Cable Wire Guardrail 201

603(3)a Metal Guardrails (Metal Beam) including Concrete Post 202

603(3)b Metal Beam End Piece 203

603(4) Guardrail (Timber) 204

604(1) Fencing (Barbed Wire) - Type I 205

604(2) Fencing (Chain Link Fence Fabric) - Type I 206

604(3) Fencing (Post) - Type I 207

604(4) Fencing (Gates) - (Height 3 m & Length 4.24 m) 208

605(1)a Danger/Warning Signs (60 cm Triangle) 209

605(1)b Danger/Warning Signs (90 cm Triangle) 210

605(2)a Regulatory Signs (60 cm Triangle) 211

605(2)b Regulatory Signs (90 cm Triangle) 212

605(2)c Regulatory Signs (60 cm Octagon) 213

605(2)d Regulatory Signs (90 cm Octagon) 214

605(3)a Informative Signs (12" x 24") 215

605(3)b Informative Signs (12" x 48") 216

605(3)c Informative Signs (18" x 24") 217

605(3)d Informative Signs (18" x 48") 218

606(1) Pavement Marking (Premix Reflectorized) 219

606(2)a Pavement Markings (Reflectorized Traffic Paint - White) 220

606(2)b Pavement Markings (Reflectorized Traffic Paint - Yellow) 221

607(1) Reflective Pavement Studs 222

12 Summary Table of Items of Work and Description


ITEM NO. DESCRIPTION PAGE NO.

607(2) Reflective Pavement Studs (4" RPM) 223

608(1) Furnishing and Placing Topsoil 224

608(2) Placing Topsoil 225

609 Sprigging 226

610 Sodding 227

611(1) Trees (Furnishing and Transplanting), 150 mm Ø or less 228

611(2) Trees (Transplanting), 150 mm Ø or less 229

612(1) Reflectorized Thermoplastic Pavement Markings (White) 230

612(2) Reflectorized Thermoplastic Pavement Markings (Yellow) 231

613 Concrete Joint Sealant (Hot Poured Elastic and Cold-Applied Types) 232

620(a) Chevron Signs (450 mm x 600 mm) 233

620(b) Chevron Signs (600 mm x 800 mm) 234

622(1)a Bio-Engineering Solutions (Coco-net) 235

622(1)b Bio-Engineering Solutions (Coco-net) 236

622(2)a Bio-Engineering Solutions (Coco-logs/Fascine) 237

622(2)b Bio-Engineering Solutions (Coco-logs/Fascine) 238

622(3)a Bio-Engineering Solutions (Vegetation) 239

622(3)b Bio-Engineering Solutions (Vegetation) 240

13 Summary Table of Items of Work and Description


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(1) Clearing & Grubbing (with Stripping)


Unit of Measurement : ha
Output per hour : 0.05 ha

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Dump Truck (12 yd³) 2 1.00


b. Payloader (1.50 m³) 1 1.00
c. Bulldozer, D6H SERIES II PSDS/DD 1 1.00

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
Assumed depth of cut is 150 mm all
throughout. A corresponding adjustment in the
output shall be computed based on the actual field
requirements.
Sub - Total for B
C. Total (A + B)
D. Output per hour = 0.05 ha
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 0.05 ha/h.
To increase the output, additional equipment and labor may be added.

14 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(3)a Individual Removal of Trees (small a, 150 mm Ø up to 300 mm Ø)


Unit of Measurement : ea
Output per hour : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 0.33


b. Skilled Labor 1 0.33 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 0.33
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.25


b. Dump Truck (12 yd³) 1 0.17
c. Chain Saw 1 0.17
Minor Tools (5% of Labor Cost)

Note:
Add Boom Truck if necessary for trimming in
urban areas.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Rope, 1" Ø - 5 uses m 20.00


Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea for 0.33 h.
To increase the output, additional equipment and labor may be added.

15 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(3)b Individual Removal of Trees (small b, above 300 mm Ø up to 500 mm Ø)
Unit of Measurement : ea
Output : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 0.67


b. Skilled Labor 1 0.67 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 0.67
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.50


b. Dump Truck (12 yd³) 1 0.33
c. Chain Saw 1 0.33
Minor Tools (5% of Labor Cost)

Note:
Add Boom Truck if necessary for trimming in
urban areas.

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Rope, 1" Ø - 5 uses m 20.00


Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea for 0.67 h.
To increase the output, additional equipment and labor may be added.

16 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(4)a Individual Removal of Trees (large a, above 500 mm Ø up to 750 mm Ø)
Unit of Measurement : ea
Output per hour : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 3.33


b. Skilled Labor 1 3.33 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 3.33
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 2.50


b. Dump Truck (12 yd³) 1 1.67
c. Chain Saw 1 1.67
Minor Tools (5% of Labor Cost)

Note:
Add Boom Truck if necessary for trimming in
urban areas.

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Rope, 1" Ø - 5 uses m 20.00


Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea for 3.33 h.
To increase the output, additional equipment and labor may be added.

17 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(4)b Individual Removal of Trees (large b, above 750 mm Ø up to 900 mm Ø)
Unit of Measurement : ea
Output : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 6.67


b. Skilled Labor 1 6.67 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 6.67
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 5.00


b. Dump Truck (12 yd³) 1 3.33
c. Chain Saw 1 3.33
Minor Tools (5% of Labor Cost)

Note:
Add Boom Truck if necessary for trimming in
urban areas.

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Rope, 1" Ø - 5 uses m 20.00


Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea for 6.67 h.
To increase the output, additional equipment and labor may be added.

18 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(1) Removal of Structures and Obstruction


Unit of Measurement : ls
Output : 1.00 ls
The unit of measure 'lumpsum' as per Blue Book shall be based on the derived outputs of the following item numbers: Item No. 101(1)a-
Removal of Concrete Bridge Structures, Item No. 101(1)b-Removal of Steel Bridge Structures, Item No. 101(1)c-Removal of Stone Masonry
Lined Drainage Structures and Item No. 101(1)d-Removal of Concrete Drainage Structures

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

See derivations for Item Nos. 101(1)a to 101(1)d

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

See derivations for Item Nos. 101(1)a to 101(1)d

Sub - Total for B


C. Total (A + B)
D. Output =
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

See derivations for Item Nos. 101(1)a to 101(1)d

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses of G
I. Contractor's Profit (CP) of G
J. Value Added Tax (VAT) of (G + H + I)
K. Total Unit Cost (G + H + I + J)

19 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(1)a Removal of Concrete Bridge Structures


Unit of Measurement : m³
Output per hour : 1.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe w/ Breaker (0.80 m³) 1 0.50


b. Jackhammer 2 1.00
c. Air Compressor (356 - 450 cfm) 1 1.00
d. Dump Truck (12 yd³) 1 0.125
e. Payloader (1.50 m³) 1 0.125
f. Truck Mounted Crane (31 - 35 mt) 1 0.25
g. Cutting Outfit 1 1.00
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
Sub - Total for B
C. Total (A + B)
D. Output per hour = 1.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Oxy/Acetylene set 0.10


Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m³/h.
To increase the output, additional equipment and labor may be added.

20 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(1)b Removal of Steel Bridge Structures


Unit of Measurement : kg
Output per hour : 1,000.00 kg

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Truck Mounted Crane (31 - 35 mt) 1 1.00


b. Service Truck/Cargo Truck (2 - 5 mt) 1 1.00
c. Welding Machine (300 A), Gas/Diesel Driven 1 1.00
d. Cutting Outfit 1 1.00
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1,000.00 kg
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Oxy/Acetylene set 0.00025


b. Welding Rod kg 0.002 Prices of materials are variable per Region/District
c. Rope 1" Ø m 0.05 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Note: Data established quarterly by Central Office Price
Include shoring materials if needed based on Monitoring Committee.
actual field condition

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1,000.00 kg/h.
To increase the output, additional equipment and labor may be added.

21 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(1)c Removal of Stone Masonry Lined Drainage Structures


Unit of Measurement : m³
Output per hour : 10.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe w/ Breaker (0.80 m³) 1 0.50


b. Backhoe (0.80 m³) - for loading 1 0.50
c. Dump Truck (12 yd³) 1 1.00

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 10.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 10.00 m³/h.
To increase the output, additional equipment and labor may be added.

22 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(1)d Removal of Concrete Drainage Structures


Unit of Measurement : m³
Output per hour : 2.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe w/ Breaker (0.80 m³) 1 0.50


b. Backhoe (0.80 m³) - for loading 1 0.25
d. Dump Truck (12 yd³) 1 0.50
e. Cutting Outfit 1 1.00

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Oxy/Acetylene set 0.10


Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 2.00 m³/h.
To increase the output, additional equipment and labor may be added.

23 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)a Removal of RCPC (24" Ø) - 610 mm Ø


Unit of Measurement : ea
Output per hour : 6.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 1.00


b. Boom Truck (2 - 5 mt) 1 0.50
Minor Tools (10 % of Labor Cost)

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Boom Truck will be adjusted
accordingly based on the hauling cycle time
analysis.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 6.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 6.00 ea/h.
To increase the output, additional equipment and labor may be added.

24 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)b Removal of RCPC (30" Ø) - 760 mm Ø


Unit of Measurement : ea
Output per hour : 5.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 1.00


b. Boom Truck (2 - 5 mt) 1 0.50
Minor Tools (10 % of Labor Cost)

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Boom Truck will be adjusted
accordingly based on the hauling cycle time
analysis.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 5.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 5.00 ea/h.
To increase the output, additional equipment and labor may be added.

25 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)c Removal of RCPC (36" Ø) - 910 mm Ø


Unit of Measurement : ea
Output per hour : 4.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 1.00


b. Boom Truck (2 - 5 mt) 1 0.50
Minor Tools (10 % of Labor Cost)

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Boom Truck will be adjusted
accordingly based on the hauling cycle time
analysis.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 4.00 ea/h.
To increase the output, additional equipment and labor may be added.

26 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)d Removal of RCPC (42" Ø) - 1070 mm Ø


Unit of Measurement : ea
Output per hour : 4.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Backhoe (0.80 m³) 1 1.00


b. Boom Truck (2 - 5 mt) 1 0.50
Minor Tools (10 % of Labor Cost)

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Boom Truck will be adjusted
accordingly based on the hauling cycle time
analysis.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 4.00 ea/h.
To increase the output, additional equipment and labor may be added.

27 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)e Removal of RCPC (48" Ø) - 1220 mm Ø


Unit of Measurement : ea
Output per hour : 3.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Backhoe (0.80 m³) 1 1.00


b. Boom Truck (2 - 5 mt) 1 0.50
Minor Tools (10 % of Labor Cost)

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Boom Truck will be adjusted
accordingly based on the hauling cycle time
analysis.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 3.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 3.00 ea/h.
To increase the output, additional equipment and labor may be added.

28 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)f Removal of RCPC (60" Ø) - 1520 mm Ø


Unit of Measurement : ea
Output per hour : 2.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 1.00


b. Boom Truck (2 - 5 mt) 1 0.50
Minor Tools (10 % of Labor Cost)

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Boom Truck will be adjusted
accordingly based on the hauling cycle time
analysis.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 2.00 ea/h.
To increase the output, additional equipment and labor may be added.

29 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)g Removal of Pipes other than Pipe Culverts (PVC/GI/Asbestos, up to 200 mm Ø), L=10 ft
Unit of Measurement : ea
Output per hour : 2.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (Wheel Type 0.28 m³) 1 1.00


b. Cargo Truck (2 - 5 mt) 1 0.50
Minor Tools (10% of Labor Cost)

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Cargo Truck will be adjusted
accordingly based on the hauling cycle time
analysis.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 2.00 ea/h.
To increase the output, additional equipment and labor may be added.

30 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(3)a.1 Removal of Existing Concrete Pavement (0.23 m thk)


Unit of Measurement : m²
Output per hour : 40.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe w/ Pavement Breaker (0.80 m³) 1 1.00


b. Payloader (1.50 m³), LX80-2C 1 1.00
c. Dump Truck (12 yd³) 1 0.50
Minor Tools (10% of Labor Cost)

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
Production output for other thickness should
be computed proportionately to the output of 0.23
m thk PCCP.
Sub - Total for B
C. Total (A + B)
D. Output per hour = 40.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 40.00 m²/h.
To increase the output, additional equipment and labor may be added.

31 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(3)a.2 Removal of Existing PCC Pavement, 0.23 m thk (for Reblocking at intermittent section)
Unit of Measurement : m²
Output per hour : 30.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe w/ Pavement Breaker (0.80 m³) 1 1.00


b. Payloader (1.50 m³), LX80-2C 1 1.00
c. Dump Truck (12 yd³) 1 0.50
d. Concrete Saw (7.5 hp), 14" Blade Ø 1 0.50
Minor Tools (10% of Labor Cost)

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
Production output for other thickness should
be computed proportionately to the output of 0.23
m thk PCCP.
Sub - Total for B
C. Total (A + B)
D. Output per hour = 30.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015


Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 30.00 m²/h.
To increase the output, additional equipment and labor may be added.

32 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(3)b Removal of Existing Asphalt Pavement (100 mm thk)


Unit of Measurement : m²
Output per hour : 60.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Motorized Road Grader w/ Scarifier, G710A 1 1.00


b. Payloader (1.50 m³), LX80-2C 1 1.00
c. Dump Truck (12 yd³) 1 0.50
Minor Tools (10% of Labor Cost)

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
Production output for other thickness should
be computed proportionately to the output of 100
mm thk Asphalt Pavement.
Sub - Total for B
C. Total (A + B)
D. Output per hour = 60.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 60.00 m²/h.
To increase the output, additional equipment and labor may be added.

33 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(3)c Removal of Sidewalk (100 mm thk)


Unit of Measurement : m²
Output per hour : 75.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe w/ Pavement Breaker (0.80 m³) 1 1.00


b. Payloader (1.50 m³), LX80-2C 1 1.00
c. Dump Truck (12 yd³) 1 0.50
Minor Tools (10% of Labor Cost)

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
Production output for other thickness should
be computed proportionately to the output of 100
mm thk sidewalk.
Sub - Total for B
C. Total (A + B)
D. Output per hour = 75.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 75.00 m²/h.
To increase the output, additional equipment and labor may be added.

34 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(4)a Removal of Curb


Unit of Measurement : m
Output per hour : 50.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe w/ Breaker (0.80 m³) 1 0.50


b. Backhoe (0.80 m³) 1 0.50
c. Dump Truck (12 yd³) 1 0.50

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 50.00 m/h.
To increase the output, additional equipment and labor may be added.

35 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(4)b Removal of Curb & Gutter


Unit of Measurement : m
Output per hour : 30.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe w/ Breaker (0.80 m³) 1 0.50


b. Backhoe (0.80 m³) 1 0.50
c. Dump Truck (12 yd³) 1 0.50

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 30.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 30.00 m/h.
To increase the output, additional equipment and labor may be added.

36 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(1) Roadway Excavation (Unsuitable)


Unit of Measurement : m³
Output per hour : 20.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Dump Truck (12 yd³) 2 1.00


b. Backhoe (0.80 m³) 1 1.00
c. Payloader (1.50 m³) at disposal site 1 0.10
Minor Tools (10% of Labor Cost)

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 20.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 20.00 m³/h.
To increase the output, additional equipment and labor may be added.

37 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(2)a Roadway Excavation (Surplus Common)


Unit of Measurement : m³
Output per hour : 60.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Bulldozer, D6H SERIES II PSDS/DD 1 1.00


b. Payloader (1.50 m³) 1 1.00
c. Payloader (1.50 m³) - at disposal area 1 0.25
d. Dump Truck (12 yd³) 2 1.00

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 60.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 60.00 m³/h.
To increase the output, additional equipment and labor may be added.

38 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(2)b Roadway Excavation (Surplus Common)


Unit of Measurement : m³
Output per hour : 80.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Bulldozer, D6H SERIES II PSDS/DD 1 1.00


b. Payloader (1.50 m³) 1 1.00
c. Payloader (1.50 m³) - at disposal area 1 0.30
d. Dump Truck (12 yd³) 3 1.00
e. Backhoe (0.80 m³) 1 1.00

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 80.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 80.00 m³/h.
To increase the output, additional equipment and labor may be added.

39 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(3)a Roadway Excavation (Surplus Soft Rock)


Unit of Measurement : m³
Output per hour : 56.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Bulldozer w/ Ripper, D6H SERIES II PSDS/DD 1 1.00


b. Payloader (1.50 m³) 1 1.00
c. Payloader (1.50 m³) - at disposal area 1 0.25
d. Dump Truck (12 yd³) 2 1.00
e. Backhoe (0.80 m³) w/ attachment 1 1.00

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 56.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 56.00 m³/h.
To increase the output, additional equipment and labor may be added.

40 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(3)b Roadway Excavation (Surplus Soft Rock)


Unit of Measurement : m³
Output per hour : 42.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Bulldozer w/ Ripper, D6H SERIES II PSDS/DD 1 1.00


b. Payloader (1.50 m³) 1 1.00
c. Payloader (1.50 m³) - at disposal area 1 0.20
d. Dump Truck (12 yd³) 2 1.00

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 42.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 42.00 m³/h.
To increase the output, additional equipment and labor may be added.

41 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(3)c Roadway Excavation (Surplus Hard Rock) - Blasting


Unit of Measurement : m³
Output per hour : 4.20 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor
a. Construction Foreman (Drilling) 1 0.40
b. Skilled Labor 2 0.40
c. Unskilled Labor 4 0.40 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
a. Construction Foreman (Blasting) 1 0.20
Schedule of Labor Rates.
b. Skilled Labor 1 0.20
c. Unskilled Labor 2 0.20
a. Construction Foreman (Disposal) 1 0.40
b Unskilled Labor 2 0.40
Sub - Total for A
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.20


b. Payloader (1.50 m³) 1 0.15
c. Payloader (1.50 m³) - at disposal area 1 0.05
d. Dump Truck (12 yd³) 1 0.40
e. Pneumatic Drilling Machine 2 0.40
f. Air Compressor (161 - 185 cfm) 1 0.40

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
Sub - Total for B
C. Total (A + B)
D. Output per hour = 4.20 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Dynamite kg 0.40
b. Detonation Cord m 2.00 Prices of materials are variable per Region/District
c. Detonator pc 0.15 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Ammonium Sulfate kg 0.20 project site. Refer to the Construction Materials Price
e. Blasting Cap pc 0.40 Data established quarterly by Central Office Price
f. Safety Fuse m 0.10 Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 4.20 m³/h.
To increase the output, additional equipment and labor may be added.

42 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(3)d Roadway Excavation (Surplus Hard Rock) - Blasting (Tunnel Excavation)
Unit of Measurement : m³
Output per hour : 1.65 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor
a. Construction Foreman (Drilling) 1 1.00
b. Skilled Labor 2 1.00
c. Unskilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
a. Construction Foreman (Blasting) 1 1.00
Schedule of Labor Rates.
b. Skilled Labor 1 1.00
c. Unskilled Labor 2 1.00
a. Construction Foreman (Disposal) 1 0.50
b Unskilled Labor 2 0.50
Sub - Total for A
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
a. Backhoe (0.80 m³) 1 0.50
b. Backhoe w/ Chipping Hammer (0.80 m³) 1 0.10
c. Dump Truck (12 yd³) 1 0.50
d. Pneumatic Drilling Machine 2 1.00
e. Air Compressor (161 - 185 cfm) 1 1.00
f. Payloader (1.50 m³) 1 0.20
g. Payloader (1.50 m³) - at disposal area 1 0.03
h. Water Truck/Pump (16000 L) 1 0.05
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.
Sub - Total for B
C. Total (A + B)
D. Output per hour = 1.65 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Dynamite kg 2.00
b. Detonation Cord m 1.40 Prices of materials are variable per Region/District
c. Detonator pc 2.00 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Ammonium Sulfate kg 1.00 project site. Refer to the Construction Materials Price
e. Blasting Cap pc 0.45 Data established quarterly by Central Office Price
f. Safety Fuse m 0.10 Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.65 m³/h.
To increase the output, additional equipment and labor may be added.

43 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(4) Roadway Excavation (Surplus Unclassified)


Unit of Measurement : m³
Output per hour : 50.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Bulldozer, D6H SERIES II PSDS/DD 1 1.00


b. Payloader (1.50 m³) 1 1.00
c. Payloader (1.50 m³) - at disposal area 1 0.20
d. Dump Truck (12 yd³) 2 1.00

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km,
the travel time of Dump Truck will be adjusted
accordingly based on the hauling cycle time
analysis.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50. m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 50.00 m³/h.
To increase the output, additional equipment and labor may be added.

44 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(1)a Structure Excavation (Common Soil)


Unit of Measurement : m³
Output per hour : 20.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Dump Truck (12 yd³) 2 1.00


b. Backhoe (0.80 m³) 1 1.00
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 20. m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 20.00 m³/h.
To increase the output, additional equipment and labor may be added.

45 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(1)b Structure Excavation (Soft Rock)


Unit of Measurement : m³
Output per hour : 14.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Dump Truck (12 yd³) 2 1.00


b. Backhoe (0.80 m³) 1 0.50
c. Backhoe w/ Breaker (0.80 m³) 1 0.50
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 14.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 14.00 m³/h.
To increase the output, additional equipment and labor may be added.

46 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(1)c Structure Excavation (Solid Rock)


Unit of Measurement : m³
Output per hour : 4.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Dump Truck (12 yd³) 1 1.00


b. Backhoe (0.80 m³) 1 0.25
c. Backhoe w/ Breaker (0.80 m³) 1 0.75
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 4.00 m³/h.
To increase the output, additional equipment and labor may be added.

47 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)a Bridge Excavation (Common Soil)


Unit of Measurement : m³
Output per hour : 20.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

b. Backhoe (0.80 m³) 1 1.00


b. Dump Truck (12 yd³) 2 1.00
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 20.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 20.00 m³/h.
To increase the output, additional equipment and labor may be added.

48 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)b Bridge Excavation (Soft Rock)


Unit of Measurement : m³
Output per hour : 14.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.50


b. Backhoe w/ Breaker (0.80 m³) 1 0.50
c. Dump Truck (12 yd³) 2 1.00
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 14.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 14.00 m³/h.
To increase the output, additional equipment and labor may be added.

49 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)c Bridge Excavation (Solid Rock)


Unit of Measurement : m³
Output per hour : 4.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.50


b. Backhoe w/ Breaker (0.80 m³) 1 1.00
c. Dump Truck (12 yd³) 1 0.50
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 4.00 m³/h.
To increase the output, additional equipment and labor may be added.

50 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)d Bridge Excavation (Solid Rock)


Unit of Measurement : m³
Output per hour : 1.50 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Jack Hammer 2 1.00


b. Air Compressor (356 - 450 cfm) 1 1.00
c. Backhoe (0.80 m³) 1 0.15
d. Dump Truck (12 yd³) 1 0.15
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.50 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.50 m³/h.
To increase the output, additional equipment and labor may be added.

51 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(3) Foundation Fill


Unit of Measurement : m³
Output per hour : 1.25 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Plate Compactor (5 hp) 1 1.00


b. Water Truck/Pump (16000 L) 1 0.01
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Filling Materials m³ 1.15


Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.25 m³/h.
To increase the output, additional equipment and labor may be added.

52 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(4) Excavation ordered below Plan Elevation


Unit of Measurement : m³
Output per hour : 20.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Dump Truck (12 yd³) 2 1.00


b. Backhoe (0.80 m³) 1 1.00
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 20.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 20.00 m³/h.
To increase the output, additional equipment and labor may be added.

53 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(5)a Shoring


Unit of Measurement : ls
Output : 1.00 ls

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

Sub - Total for A

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 ls
E. Direct Unit Cost (C ÷ D)
Direct
Name and Specification Unit Quantity Direct Cost
Unit Cost
F. Materials/Processed Component Pay Item

a. 404 - Reinforcing Steel Bar kg *


b. 405 - Structural Concrete m³ *
c. 509 - Steel Sheet Pile m *

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note:
*) The component quantity of items of work involved such as Items 404/405/509 shall be based on the
actual design of the shoring.
**) Costing of this item shall be based on the standard Detailed Unit Price Analysis (DUPA) of Items 404/405/509
as processed component pay item

54 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(5)b Cribbing/Cofferdamming


Unit of Measurement : ls
Output : 1.00 ls

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 160.00


b. Skilled Labor 2 160.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 160.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Crawler Crane (36 - 40 mt) 1 160.00


b. Vibro Hammer (Hydraulic Operated) 1 160.00
c. Welding Machine (300 A), Gas/Diesel Driven 1 40.00
d. Cutting Outfit 1 40.00
e. Water Pump, 100 mm suction Ø 1 160.00

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 ls
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Steel Sheet Pile kg 69,120.00


b. Walling, Bracing, Diagonal, etc. kg 7,323.77 Prices of materials are variable per Region/District
Miscellaneous (1% of Materials Cost) based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note:
a.) The assumed area to be provided with cofferdam is 12 m x 12 m square with Steel Sheet Piles
depth of 12 m at 48 kg/m.
b.) The quantity of component materials requirement may vary depending on the actual design of
Cribbing/Cofferdamming.

55 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(6) Pipe Culvert and Drain Excavation


Unit of Measurement : m³
Output per hour : 20.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Dump Truck (12 yd³) 2 1.00


b. Backhoe (0.80 m³) 1 1.00
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 20.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 20.00 m³/h.
To increase the output, additional equipment and labor may be added.

56 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(1)a Embankment (from Borrow)


Unit of Measurement : m³
Output per hour : 50.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00


b. Vibratory Roller (10 mt), SD100DC 1 1.00
c. Water Truck/Pump (16000 L) 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Common Borrow (w/ 25% Shrinkage Factor) m³ 1.25


Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 50.00 m³/h.
To increase the output, additional equipment and labor may be added.

57 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(1)b Embankment from Roadway Excavation


Unit of Measurement : m³
Output per hour : 50.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor
For Excavation Work:
a. Construction Foreman 1 0.83
b. Unskilled Labor 2 0.83 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.
Spreading and Compaction:
a. Construction Foreman 1 1.00
b. Unskilled Labor 2 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
For Excavation Work:
a. Bulldozer, D6H SERIES II PSDS/DD 1 0.83
b. Payloader (1.50 m³) 1 0.83
c. Dump Truck (12 yd³) 2 0.83

Spreading and Compaction:


a. Motorized Road Grader (140 hp), G710A 1 1.00
b. Vibratory Roller (10 mt), SD100DC 1 1.00
c. Water Truck/Pump (16000 L) 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 50.00 m³/h.
To increase the output, additional equipment and labor may be added.

58 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(2) Selected Borrow for topping , case 1


Unit of Measurement : m³
Output per hour : 50.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00


b. Vibratory Roller (10 mt), SD100DC 1 1.00
c. Water Truck/Pump (16000 L) 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Selected Borrow (w/ 25% Shrinkage Factor) m³ 1.25


Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 50.00 m³/h.
To increase the output, additional equipment and labor may be added.

59 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(3) Selected Borrow for topping , case 2


Unit of Measurement : m³
Output per hour : 50.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00


b. Vibratory Roller (10 mt), SD100DC 1 1.00
c. Water Truck/Pump (16000 L) 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Selected Borrow (w/ 25% Shrinkage Factor) m³ 1.25


Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 50.00 m³/h.
To increase the output, additional equipment and labor may be added.

60 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(4) Earth Berm


Unit of Measurement : m³
Output per hour : 1.25 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Plate Compactor (5 hp) 1 1.00


b. Water Truck/Pump (16000 L) 1 0.01
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Filling Materials m³ 1.25


Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.25 m³/h.
To increase the output, additional equipment and labor may be added.

61 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 105(1) Subgrade Preparation (Common Material)


Unit of Measurement : m²
Output per hour : 300.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00


b. Vibratory Roller (10 mt), SD100DC 1 1.00
c. Water Truck/Pump (16000 L) 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 300.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 300.00 m²/h.
To increase the output, additional equipment and labor may be added.

62 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 105(2) Subgrade Preparation (Existing Pavement)


Unit of Measurement : m²
Output per hour : 300.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00


b. Vibratory Roller (10 mt), SD100DC 1 1.00
c. Water Truck/Pump (16000 L) 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 300.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 300.00 m²/h.
To increase the output, additional equipment and labor may be added.

63 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 105(3) Subgrade Preparation (Unsuitable Material)


Unit of Measurement : m²
Output per hour : 300.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00


b. Vibratory Roller (10 mt), SD100DC 1 1.00
c. Water Truck/Pump (16000 L) 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 300.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 300.00 m²/h.
To increase the output, additional equipment and labor may be added.

64 Part C - Earthworks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 200 Aggregate Subbase Course


Unit of Measurement : m³
Output per hour : 50.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00


b. Vibratory Roller (10 mt), SD100DC 1 1.00
c. Water Truck/Pump (16000 L) 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Aggregate Subbase Course m³ 1.15


(w/ 15% Shrinkage Factor) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 50.00 m³/h.
To increase the output, additional equipment and labor may be added.

65 Part D - Subbase and Base Course


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 200(1) Aggregate Subbase Course (for Intermittent Reblocking)


Unit of Measurement : m³
Output per hour : 40.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00


b. Vibratory Roller (10 mt), SD100DC 1 1.00
c. Plate Compactor (5 hp) 1 0.25
d. Water Truck/Pump (16000 L) 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 40.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Aggregate Subbase Course m³ 1.15


(w/ 15% Shrinkage Factor) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 40.00 m³/h.
To increase the output, additional equipment and labor may be added.

66 Part D - Subbase and Base Course


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 201 Aggregate Base Course


Unit of Measurement : m³
Output per hour : 50.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00


b. Vibratory Roller (10 mt), SD100DC 1 1.00
c. Water Truck/Pump (16000 L) 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Aggregate Base Course m³ 1.15


(w/ 15% Shrinkage Factor) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 50.00 m³/h.
To increase the output, additional equipment and labor may be added.

67 Part D - Subbase and Base Course


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 201(1) Aggregate Base Course (for Reblocking)


Unit of Measurement : m³
Output per hour : 40.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00


b. Vibratory Roller (10 mt), SD100DC 1 1.00
c. Plate Compactor (5 hp) 1 0.25
d. Water Truck/Pump (16000 L) 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 40.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Aggregate Base Course m³ 1.15


(w/ 15% Shrinkage Factor) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 40.00 m³/h.
To increase the output, additional equipment and labor may be added.

68 Part D - Subbase and Base Course


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 202 Crushed Aggregate Base Course


Unit of Measurement : m³
Output per hour : 50.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00


b. Vibratory Roller (10 mt), SD100DC 1 1.00
c. Water Truck/Pump (16000 L) 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Crushed Aggregate Base Course m³ 1.15


(w/ 15% Shrinkage Factor) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 50.00 m³/h.
To increase the output, additional equipment and labor may be added.

69 Part D - Subbase and Base Course


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 203 Lime Stabilized Road Mix Base Course


Unit of Measurement : m³
Output per hour : 15.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 10 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00


b. Vibratory Roller (10 mt), SD100DC 1 1.00
c. Water Truck/Pump (16000 L) 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 15.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Hydrated Lime, Type N (Normal) bag 2.80


b. Aggregate Base Course m³ 1.15 Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 15.00 m³/h.
To increase the output, additional equipment and labor may be added.

70 Part D - Subbase and Base Course


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 204 Portland Cement Stabilized Road Mix Base Course
Unit of Measurement : m³
Output per hour : 15.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 10 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00


b. Vibratory Roller (10 mt), SD100DC 1 1.00
c. Water Truck/Pump (16000 L) 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 15.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Cement bag 3.00


b. Aggregate Base Course m³ 1.15 Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 15.00 m³/h.
To increase the output, additional equipment and labor may be added.

71 Part D - Subbase and Base Course


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 205 Asphalt Stabilized Road Mix Base Course


Unit of Measurement : m³
Output per hour : 15.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 10 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00


b. Vibratory Roller (10 mt), SD100DC 1 1.00
c. Water Truck/Pump (16000 L) 1 0.25
d. Asphalt Distributor, 10 ft wide (5 ton) 1 1.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 15.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Emulsified Asphalt SS-1 mt 0.07


b. Aggregate Base Course m³ 1.15 Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 15.00 m³/h.
To increase the output, additional equipment and labor may be added.

72 Part D - Subbase and Base Course


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 206 Portland Cement Treated Plant Mix Base Course
Unit of Measurement : m³
Output per hour : 15.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Batch Plant (30 m³) 1 0.50


b. Dump Truck (12 yd³) 3 0.50
c. Motorized Road Grader (140 hp), G710A 1 0.50
d. Vibratory Roller (10 mt), SD100DC 1 0.50
e. Payloader (1.50 m³), LX80-2C 1 0.50
f. Water Truck/Pump (16000 L) 1 0.25
g. Asphalt Distributor, 10 ft wide (5 ton) 1 0.10

Sub - Total for B


C. Total (A + B)
D. Output per hour = 15.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Cement bag 3.00


b. Aggregate Base Course m³ 1.15 Prices of materials are variable per Region/District
c. MC 70 Cut-back Asphalt mt 0.0075 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 15.00 m³/h.
To increase the output, additional equipment and labor may be added.

73 Part D - Subbase and Base Course


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 300(1) Gravel Surface Course (Uncrushed)


Unit of Measurement : m³
Output per hour : 50.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00


b. Vibratory Roller (10 mt), SD100DC 1 1.00
c. Water Truck/Pump (16000 L) 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Uncrushed Aggregate Surface Course m³ 1.15


(w/ 15% Shrinkage Factor) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 50.00 m³/h.
To increase the output, additional equipment and labor may be added.

74 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 300(2) Crushed Aggregate Surface Course


Unit of Measurement : m³
Output per hour : 50.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00


b. Vibratory Roller (10 mt), SD100DC 1 1.00
c. Water Truck/Pump (16000 L) 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Crushed Aggregate Surface Course m³ 1.15


(w/ 15% Shrinkage Factor) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 50.00 m³/h.
To increase the output, additional equipment and labor may be added.

75 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 301(1) Bituminous Prime Coat (MC Cut-back Asphalt)


Unit of Measurement : mt
Output per hour : 0.30 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Asphalt Distributor, 10 ft wide (5 ton) 1 1.00


b. Power Broom (2 m wide) 1 1.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. MC 70 Cut-back Asphalt mt 1.05


(w/ 5% wastage) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 0.30 mt/h.
To increase the output, additional equipment and labor may be added.

76 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 301(2) Bituminous Prime Coat (RC Cut-back Asphalt)


Unit of Measurement : mt
Output per hour : 0.30 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Asphalt Distributor, 10 ft wide (5 ton) 1 1.00


b. Power Broom (2 m wide) 1 1.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. RC 70 Cut-back Asphalt mt 1.05


(w/ 5% wastage) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 0.30 mt/h.
To increase the output, additional equipment and labor may be added.

77 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 302(1) Bituminous Tack Coat (RC Cut-back Asphalt)


Unit of Measurement : mt
Output per hour : 0.30 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Asphalt Distributor, 10 ft wide (5 ton) 1 1.00


b. Power Broom (2 m wide) 1 1.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. RC 70 Cut-back Asphalt mt 1.05


(w/ 5% wastage) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 0.30 mt/h.
To increase the output, additional equipment and labor may be added.

78 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 302(2) Bituminous Tack Coat (Emulsified Asphalt)


Unit of Measurement : mt
Output per hour : 0.30 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Asphalt Distributor, 10 ft wide (5 ton) 1 1.00


b. Power Broom (2 m wide) 1 1.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Emulsified Asphalt SS-1 mt 1.05


(w/ 5% wastage) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 0.30 mt/h.
To increase the output, additional equipment and labor may be added.

79 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(1) Bituminous Seal Coat (Cover Aggregate)


Unit of Measurement : mt
Output per hour : 16.00 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 20 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Tandem Steel Roller (10.1 mt), CC421 1 1.00


b. Water Truck/Pump (16000 L) 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 16.00 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Cover Aggregate mt 1.15


(w/ 15% Shrinkage Factor) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 16.00 mt/h.
To increase the output, additional equipment and labor may be added.

80 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(2) Bituminous Seal Coat (MC Cut-back Asphalt)


Unit of Measurement : mt
Output per hour : 0.30 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Asphalt Distributor, 10 ft wide (5 ton) 1 1.00


b. Power Broom (2 m wide) 1 1.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. MC Cut-back Asphalt mt 1.05


(w/ 5% Wastage) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 0.30 mt/h.
To increase the output, additional equipment and labor may be added.

81 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(3) Bituminous Seal Coat (RC Cut-back Asphalt)


Unit of Measurement : mt
Output per hour : 0.30 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Unskilled Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Asphalt Distributor, 10 ft wide (5 ton) 1 1.00


b. Power Broom (2 m wide) 1 1.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. RC 70 Cut-back Asphalt mt 1.05


(w/ 5% Wastage) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 0.30 mt/h.
To increase the output, additional equipment and labor may be added.

82 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(4) Bituminous Seal Coat (Asphalt Cement Penetration Grade 120-150)
Unit of Measurement : mt
Output per hour : 0.30 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Asphalt Distributor, 10 ft wide (5 ton) 1 1.00


b. Power Broom (2 m wide) 1 1.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Asphalt Cement Penetration Grade 120-150 mt 1.05


(w/ 5% Wastage) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 0.30 mt/h.
To increase the output, additional equipment and labor may be added.

83 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(1) Bituminous Surface Treatment (Aggregate Grading)


Unit of Measurement : mt
Output per hour : 16.00 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 20 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Vibratory Roller (10 mt), SD100DC 1 1.00


b. Water Truck/Pump (16000 L) 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 16.00 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Aggregates mt 1.15
(w/ 15% Shrinkage Factor) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 16.00 mt/h.
To increase the output, additional equipment and labor may be added.

84 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(2) Bituminous Surface Treatment (Asphalt Cement Penetration Grade 120-150)
Unit of Measurement : mt
Output per hour : 0.30 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Asphalt Distributor, 10 ft wide (5 ton) 1 1.00


b. Power Broom (2 m wide) 1 1.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Asphalt Cement Penetration Grade 120-150 mt 1.05


(w/ 5% Wastage) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 0.30 mt/h.
To increase the output, additional equipment and labor may be added.

85 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(3) Bituminous Surface Treatment (MC Cut-back Asphalt)


Unit of Measurement : mt
Output per hour : 0.30 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Asphalt Distributor, 10 ft wide (5 ton) 1 1.00


b. Power Broom (2 m wide) 1 1.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. MC Cut-back Asphalt mt 1.05


(w/ 5% Wastage) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 0.30 mt/h.
To increase the output, additional equipment and labor may be added.

86 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(4) Bituminous Surface Treatment (RC Cut-back Asphalt)


Unit of Measurement : mt
Output per hour : 0.30 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Asphalt Distributor, 10 ft wide (5 ton) 1 1.00


b. Power Broom (2 m wide) 1 1.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. RC 70 Cut-back Asphalt mt 1.05


(w/ 5% Wastage) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 0.30 mt/h.
To increase the output, additional equipment and labor may be added.

87 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(5) Bituminous Surface Treatment (Emulsified Asphalt)


Unit of Measurement : mt
Output per hour : 0.30 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Asphalt Distributor, 10 ft wide (5 ton) 1 1.00


b. Power Broom (2 m wide) 1 1.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Emulsified Asphalt SS-1 mt 1.05


(w/ 5% Wastage) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 0.30 mt/h.
To increase the output, additional equipment and labor may be added.

88 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(1) Bituminous Penetration Macadam Pavement (Aggregates)


Unit of Measurement : mt
Output per hour : 16.00 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 20 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Vibratory Roller (10 mt), SD100DC 1 1.00


b. Water Truck/Pump (16000 L) 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 16.00 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Aggregates mt 1.15
(w/ 15% Shrinkage Factor) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 16.00 mt/h.
To increase the output, additional equipment and labor may be added.

89 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(2) Bituminous Penetration Macadam Pavement (Asphalt Cement)


Unit of Measurement : mt
Output per hour : 0.30 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Asphalt Distributor, 10 ft wide (5 ton) 1 1.00


b. Power Broom (2 m wide) 1 1.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Asphalt Cement mt 1.05


(w/ 5% Wastage) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 0.30 mt/h.
To increase the output, additional equipment and labor may be added.

90 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(3) Bituminous Penetration Macadam Pavement (RC Cut-back Asphalt)
Unit of Measurement : mt
Output per hour : 0.30 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Asphalt Distributor, 10 ft wide (5 ton) 1 1.00


b. Power Broom (2 m wide) 1 1.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. RC 70 Cut-back Asphalt mt 1.05


(w/ 5% Wastage) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 0.30 mt/h.
To increase the output, additional equipment and labor may be added.

91 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(4) Bituminous Penetration Macadam Pavement (Emulsified Asphalt)


Unit of Measurement : mt
Output per hour : 0.30 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Asphalt Distributor, 10 ft wide (5 ton) 1 1.00


b. Power Broom (2 m wide) 1 1.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Emulsified Asphalt SS-1 mt 1.05


(w/ 5% wastage) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 0.30 mt/h.
To increase the output, additional equipment and labor may be added.

92 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(a) Bituminous Road Mix Surface Course


Unit of Measurement : mt
Output per hour : 12.00 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 3 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Motorized Road Grader w/ Scarifier, G710A 1 1.00


b. Tandem Steel Roller (10.1 mt), CC421 1 1.00
c. Pneumatic Tire Roller (10 mt) 1 1.00
d. Asphalt Distributor, 10 ft wide (5 ton) 1 1.00
e. Water Truck/Pump (16000 L) 1 0.25
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 12.00 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Crushed Gravel mt 1.15


b. MC Cut-back Asphalt (7%) mt 0.07 Prices of materials are variable per Region/District
c. Hydrated Lime (0.75%) bag 0.30 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 12.00 mt/h.
To increase the output, additional equipment and labor may be added.

93 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(b) Bituminous Road Mix Surface Course


Unit of Measurement : mt
Output per hour : 12.00 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 3 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Motorized Road Grader w/ Scarifier, G710A 1 1.00


b. Tandem Steel Roller (10.1 mt), CC421 1 1.00
c. Pneumatic Tire Roller (10 mt) 1 1.00
d. Asphalt Distributor, 10 ft wide (5 ton) 1 1.00
e. Water Truck/Pump (16000 L) 1 0.25
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 12.00 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Crushed Gravel mt 1.15


b. Emulsified Asphalt (10%) mt 0.10 Prices of materials are variable per Region/District
c. Hydrated Lime (0.75%) bag 0.30 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 12.00 mt/h.
To increase the output, additional equipment and labor may be added.

94 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(1) Aggregates for Bituminous Road Mix Surface Course
Unit of Measurement : mt
Output per hour : 12.00 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 3 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Motorized Road Grader w/ Scarifier, G710A 1 1.00


b. Tandem Steel Roller (10.1 mt), CC421 1 1.00
c. Pneumatic Tire Roller (10 mt) 1 1.00
d. Water Truck/Pump (16000 L) 1 0.25
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 12.00 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Crushed Gravel mt 1.15


Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 12.00 mt/h.
To increase the output, additional equipment and labor may be added.

95 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(2) Bituminous Material for Bituminous Road Mix Surface Course
Unit of Measurement : mt
Output per hour : 1.00 mt

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 3 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Asphalt Distributor, 10 ft wide (5 ton) 1 1.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 mt
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. MC Cut-back Asphalt mt 1.05


Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 mt/h.
To increase the output, additional equipment and labor may be added.

96 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 307 Bituminous Plant Mix Surface Course-General (50 mm thk)
Unit of Measurement : m²
Output per hour : 171.30 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor
Laying & Compaction
a. Construction Foreman 1 1.00
b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.
Batching/Mixing operation
a. Batching Plant Engineer 1 1.00
b. Mechanical Engineer 1 1.00
c. Electrical Engineer 1 1.00
d. Unskilled Laboratory Technician 1 1.00
e. Unskilled Labor 4 1.00

Sub - Total for A

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Asphalt Paver (80 hp), NF220BIIVDM 1 1.00


b. Pneumatic Tire Roller (10 mt) 1 1.00
c. Tandem Steel Roller (10.1 mt), CC421 1 1.00
d. Dump Truck (12 yd³) 2 1.00
e. Asphalt Batch Plant ( 60-80 tph) 1 1.00
f. Water Truck/Pump (16000 L) 1 1.00
g. Payloader (1.50 m³), LX80-2C 1 1.00
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 171.30 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Bituminous Material (8%) mt 0.00981


b. Aggregates, Sand (79%) m³ 0.041 Prices of materials are variable per Region/District
c. Aggregates, 3/8 (19%) m³ 0.010 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Mineral Filler (7%) bag 0.130 project site. Refer to the Construction Materials Price
e. Diesel L 1.165 Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 171.30 m²/h.
To increase the output, additional equipment and labor may be added.

97 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 308(a) Cold Asphalt Plant Mix (50 mm thk)


Unit of Measurement : m²
Output per hour : 171.30 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor
Laying & Compaction
a. Construction Foreman 1 1.00
b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.
Batching/Mixing operation
a. Batching Plant Engineer 1 1.00
b. Mechanical Engineer 1 1.00
c. Electrical Engineer 1 1.00
d. Unskilled Laboratory Technician 1 1.00
e. Unskilled Labor 4 1.00

Sub - Total for A

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Asphalt Paver (80 hp), NF220BIIVDM 1 1.00


b. Pneumatic Tire Roller (10 mt) 1 1.00
c. Tandem Steel Roller (10.1 mt), CC421 1 1.00
d. Dump Truck (12 yd³) 2 1.00
e. Asphalt Batch Plant ( 60-80 tph) 1 1.00
f. Water Truck/Pump (16000 L) 1 1.00
g. Payloader (1.50 m³), LX80-2C 1 1.00
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 171.30 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Emulsified Asphalt (10%) mt 0.01226


b. Aggregates, Sand (79%) m³ 0.041 Prices of materials are variable per Region/District
c. Aggregates, 3/8 (19%) m³ 0.010 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Mineral Filler (7%) bag 0.130 project site. Refer to the Construction Materials Price
e. Diesel L 1.165 Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 171.30 m²/h.
To increase the output, additional equipment and labor may be added.

98 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 308(b) Cold Asphalt Plant Mix (50 mm thk)


Unit of Measurement : m²
Output per hour : 171.30 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor
Laying & Compaction
a. Construction Foreman 1 1.00
b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.
Batching/Mixing operation
a. Batching Plant Engineer 1 1.00
b. Mechanical Engineer 1 1.00
c. Electrical Engineer 1 1.00
d. Unskilled Laboratory Technician 1 1.00
e. Unskilled Labor 4 1.00

Sub - Total for A

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Asphalt Paver (80 hp), NF220BIIVDM 1 1.00


b. Pneumatic Tire Roller (10 mt) 1 1.00
c. Tandem Steel Roller (10.1 mt), CC421 1 1.00
d. Dump Truck (12 yd³) 2 1.00
e. Asphalt Batch Plant ( 60-80 tph) 1 1.00
f. Water Truck/Pump (16000 L) 1 1.00
g. Payloader (1.50 m³), LX80-2C 1 1.00
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 171.30 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. MC - 70 Cut-back Asphalt (7%) mt 0.00858


b. Aggregates, Sand (79%) m³ 0.041 Prices of materials are variable per Region/District
c. Aggregates, 3/8 (19%) m³ 0.010 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Mineral Filler (7%) bag 0.130 project site. Refer to the Construction Materials Price
e. Diesel L 1.165 Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 171.30 m²/h.
To increase the output, additional equipment and labor may be added.

99 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 309 Bituminous Plant Mix (Stockpile Maintenance Mixture)


Unit of Measurement : m²
Output per hour : 171.30 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor
Laying & Compaction
a. Construction Foreman 1 1.00
b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.
Batching/Mixing operation
a. Batching Plant Engineer 1 1.00
b. Mechanical Engineer 1 1.00
c. Electrical Engineer 1 1.00
d. Unskilled Laboratory Technician 1 1.00
e. Unskilled Labor 4 1.00

Sub - Total for A

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Dump Truck (12 yd³) 2 1.00


b. Asphalt Batch Plant ( 60-80 tph) 1 1.00
c. Water Truck/Pump (16000 L) 1 1.00
d. Payloader (1.50 m³), LX80-2C 1 1.00
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 171.30 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. MC - 70 Cut-back Asphalt (10%) mt 0.01226


b. Aggregates, Sand (79%) m³ 0.041 Prices of materials are variable per Region/District
c. Aggregates, 3/8 (19%) m³ 0.010 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Mineral Filler (7%) bag 0.130 project site. Refer to the Construction Materials Price
e. Diesel L 1.165 Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 171.30 m²/h.
To increase the output, additional equipment and labor may be added.

100 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(a.1) Bituminous Concrete Surface Course (30 mm thk)


Unit of Measurement : m²
Output per hour : 285.51 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Asphalt Paver (80 hp), NF220BIIVDM 1 1.00


b. Pneumatic Tire Roller (10 mt) 1 1.00
c. Tandem Steel Roller (10.1 mt), CC421 1 1.00
d. Water Truck/Pump (16000 L) 1 1.00
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 285.51 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Bituminous Concrete Surface Course mt 0.074


thickness = 30 mm (w/ 5% wastage) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 285.51 m²/h.
To increase the output, additional equipment and labor may be added.

101 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(a.2) Bituminous Concrete Surface Course (40 mm thk)


Unit of Measurement : m²
Output per hour : 214.13 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Asphalt Paver (80 hp), NF220BIIVDM 1 1.00


b. Pneumatic Tire Roller (10 mt) 1 1.00
c. Tandem Steel Roller (10.1 mt), CC421 1 1.00
d. Water Truck/Pump (16000 L) 1 1.00
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 214.13 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Bituminous Concrete Surface Course mt 0.098


thickness = 40 mm (w/ 5% wastage) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 214.13 m²/h.
To increase the output, additional equipment and labor may be added.

102 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(a.3) Bituminous Concrete Surface Course (50 mm thk)


Unit of Measurement : m²
Output per hour : 171.30 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Asphalt Paver (80 hp), NF220BIIVDM 1 1.00


b. Pneumatic Tire Roller (10 mt) 1 1.00
c. Tandem Steel Roller (10.1 mt), CC421 1 1.00
d. Water Truck/Pump (16000 L) 1 1.00
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 171.30 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Bituminous Concrete Surface Course mt 0.123


thickness = 50 mm (w/ 5% wastage) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 171.30 m²/h.
To increase the output, additional equipment and labor may be added.

103 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(b.1) Bituminous Concrete Surface Course (30 mm thk)


Unit of Measurement : m²
Output per hour : 285.51 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Unskilled Labor
Laying & Compaction
a. Construction Foreman 1 1.00
b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.
Batching/Mixing operation
a. Batching Plant Engineer 1 1.00
b. Mechanical Engineer 1 1.00
c. Electrical Engineer 1 1.00
d. Unskilled Laboratory Technician 1 1.00
e. Unskilled Labor 4 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Asphalt Paver (80 hp), NF220BIIVDM 1 1.00


b. Pneumatic Tire Roller (10 mt) 1 1.00
c. Tandem Steel Roller (10.1 mt), CC421 1 1.00
d. Dump Truck (12 yd³) 2 1.00
e. Asphalt Batch Plant ( 60-80 tph) 1 1.00
f. Water Truck/Pump (16000 L) 1 1.00
g. Payloader (1.50 m³), LX80-2C 1 1.00
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 285.51 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Asphalt Cement (8%) mt 0.00588


b. Aggregates, Sand (79%) m³ 0.025 Prices of materials are variable per Region/District
c. Aggregates, 3/8 (19%) m³ 0.006 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Mineral Filler (7%) bag 0.078 project site. Refer to the Construction Materials Price
e. Diesel L 0.699 Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 285.51 m²/h.
To increase the output, additional equipment and labor may be added.

104 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(b.2) Bituminous Concrete Surface Course (40 mm thk)


Unit of Measurement : m²
Output per hour : 214.13 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor
Laying & Compaction
a. Construction Foreman 1 1.00
b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.
Batching/Mixing operation
a. Batching Plant Engineer 1 1.00
b. Mechanical Engineer 1 1.00
c. Electrical Engineer 1 1.00
d. Unskilled Laboratory Technician 1 1.00
e. UnSkilled Labor 4 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Asphalt Paver (80 hp), NF220BIIVDM 1 1.00


b. Pneumatic Tire Roller (10 mt) 1 1.00
c. Tandem Steel Roller (10.1 mt), CC421 1 1.00
d. Dump Truck (12 yd³) 2 1.00
e. Asphalt Batch Plant ( 60-80 tph) 1 1.00
f. Water Truck/Pump (16000 L) 1 1.00
g. Payloader (1.50 m³), LX80-2C 1 1.00
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 214.13 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Asphalt Cement (8%) mt 0.00785


b. Aggregates, Sand (79%) m³ 0.033 Prices of materials are variable per Region/District
c. Aggregates, 3/8 (19%) m³ 0.008 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Mineral Filler (7%) bag 0.104 project site. Refer to the Construction Materials Price
e. Diesel L 0.932 Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 214.13 m²/h.
To increase the output, additional equipment and labor may be added.

105 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(b.3) Bituminous Concrete Surface Course (50 mm thk)


Unit of Measurement : m²
Output per hour : 171.30 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor
Laying & Compaction
a. Construction Foreman 1 1.00
b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.
Batching/Mixing operation
a. Batching Plant Engineer 1 1.00
b. Mechanical Engineer 1 1.00
c. Electrical Engineer 1 1.00
d. Unskilled Laboratory Technician 1 1.00
e. UnSkilled Labor 4 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Asphalt Paver (80 hp), NF220BIIVDM 1 1.00


b. Pneumatic Tire Roller (10 mt) 1 1.00
c. Tandem Steel Roller (10.1 mt), CC421 1 1.00
d. Dump Truck (12 yd³) 2 1.00
e. Asphalt Batch Plant ( 60-80 tph) 1 1.00
f. Water Truck/Pump (16000 L) 1 1.00
g. Payloader (1.50 m³), LX80-2C 1 1.00
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 171.30 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Asphalt Cement (8%) mt 0.00981


b. Aggregates, Sand (79%) m³ 0.041 Prices of materials are variable per Region/District
c. Aggregates, 3/8 (19%) m³ 0.010 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Mineral Filler (7%) bag 0.130 project site. Refer to the Construction Materials Price
e. Diesel L 1.165 Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 171.30 m²/h.
To increase the output, additional equipment and labor may be added.

106 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.1 PCC Pavement (Plain) - Conventional Method, 150 mm thk
Unit of Measurement : m²
Output per hour : 107.33 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 12 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Transit Mixer (5 m³) 4 1.00


b. Concrete Vibrator 2 1.00
c. Concrete Batch Plant (30 m³) 1 1.00
d. Payloader (1.50 m³), LX80-2C 1 1.00
e. Concrete Screeder (5.5 hp) 1 1.00
f. Water Truck/Pump (16000 L) 1 1.00
g. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
h. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 107.33 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.33


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.12 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Steel Forms (Rental) m 0.46 project site. Refer to the Construction Materials Price
e. Sand m³ 0.0825 Data established quarterly by Central Office Price
f. Gravel m³ 0.15 Monitoring Committee.
g. Cement bag 1.43
h. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015
i. Pipe Sleeve, 1" Ø m 0.0078
j. Grease/Tar L 0.0015

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 107.33 m²/h.
To increase the output, additional equipment and labor may be added.

107 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.1.1 PCC Pavement (Plain) - Conventional Method, 150 mm thk
Unit of Measurement : m²
Output per hour : 107.33 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 12 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Vibrator 2 1.00


b. Concrete Screeder (5.5 hp) 1 1.00
c. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
d. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 107.33 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.33


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.12 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Steel Forms (Rental) m 0.46 project site. Refer to the Construction Materials Price
e. Ready Mix Concrete, 3500 psi m³ 0.15 Data established quarterly by Central Office Price
f. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015 Monitoring Committee.
g. Pipe Sleeve, 1" Ø m 0.0078
h. Grease/Tar L 0.0015

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 107.33 m²/h.
To increase the output, additional equipment and labor may be added.

108 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.2 PCC Pavement (Plain) - Conventional Method, 200 mm thk
Unit of Measurement : m²
Output per hour : 80.50 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 12 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Transit Mixer (5 m³) 4 1.00


b. Concrete Vibrator 2 1.00
c. Concrete Batch Plant (30 m³) 1 1.00
d. Payloader (1.50 m³), LX80-2C 1 1.00
e. Concrete Screeder (5.5 hp) 1 1.00
f. Water Truck/Pump (16000 L) 1 1.00
g. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
h. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 80.50 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.39


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.12 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Steel Forms (Rental) m 0.46 project site. Refer to the Construction Materials Price
e. Sand m³ 0.11 Data established quarterly by Central Office Price
f. Gravel m³ 0.20 Monitoring Committee.
g. Cement bag 1.90
h. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015
i. Pipe Sleeve, 1 1/2" Ø m 0.0086
j. Grease/Tar L 0.0056

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 80.50 m²/h.
To increase the output, additional equipment and labor may be added.

109 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.2.1 PCC Pavement (Plain) - Conventional Method, 200 mm thk
Unit of Measurement : m²
Output per hour : 80.50 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 12 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Vibrator 2 1.00


b. Concrete Screeder (5.5 hp) 1 1.00
c. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
d. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 80.50 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.39


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.12 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Steel Forms (Rental) m 0.46 project site. Refer to the Construction Materials Price
e. Ready Mix Concrete, 3500 psi m³ 0.20 Data established quarterly by Central Office Price
f. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015 Monitoring Committee.
g. Pipe Sleeve, 1 1/2" Ø m 0.0086
h. Grease/Tar L 0.0056

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 80.50 m²/h.
To increase the output, additional equipment and labor may be added.

110 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.3 PCC Pavement (Plain) - Conventional Method, 230 mm thk
Unit of Measurement : m²
Output per hour : 70.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 12 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Transit Mixer (5 m³) 4 1.00


b. Concrete Vibrator 2 1.00
c. Concrete Batch Plant (30 m³) 1 1.00
d. Payloader (1.50 m³), LX80-2C 1 1.00
e. Concrete Screeder (5.5 hp) 1 1.00
f. Water Truck/Pump (16000 L) 1 1.00
g. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
h. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 70.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.43


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.12 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Steel Forms (Rental) m 0.46 project site. Refer to the Construction Materials Price
e. Sand m³ 0.1265 Data established quarterly by Central Office Price
f. Gravel m³ 0.23 Monitoring Committee.
g. Cement bag 2.19
h. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015
i. Pipe Sleeve, 2" Ø m 0.0071
j. Grease/Tar L 0.0087

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 70.00 m²/h.
To increase the output, additional equipment and labor may be added.

111 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.3.1 PCC Pavement (Plain) - Conventional Method, 230 mm thk
Unit of Measurement : m²
Output per hour : 70.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 12 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Vibrator 2 1.00


b. Concrete Screeder (5.5 hp) 1 1.00
c. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
d. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 70.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.43


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.12 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Steel Forms (Rental) m 0.46 project site. Refer to the Construction Materials Price
e. Ready Mix Concrete, 3500 psi m³ 0.23 Data established quarterly by Central Office Price
f. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015 Monitoring Committee.
g. Pipe Sleeve, 2" Ø m 0.0071
h. Grease/Tar L 0.0087

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 70.00 m²/h.
To increase the output, additional equipment and labor may be added.

112 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.4 PCC Pavement (Plain) - Conventional Method, 250 mm thk
Unit of Measurement : m²
Output per hour : 64.40 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 12 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Transit Mixer (5 m³) 4 1.00


b. Concrete Vibrator 2 1.00
c. Concrete Batch Plant (30 m³) 1 1.00
d. Payloader (1.50 m³), LX80-2C 1 1.00
e. Concrete Screeder (5.5 hp) 1 1.00
f. Water Truck/Pump (16000 L) 1 1.00
g. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
h. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 64.40 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.45


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.15 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Steel Forms (Rental) m 0.46 project site. Refer to the Construction Materials Price
e. Sand m³ 0.1375 Data established quarterly by Central Office Price
f. Gravel m³ 0.25 Monitoring Committee.
g. Cement bag 2.38
h. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015
i. Pipe Sleeve, 2" Ø m 0.0078
j. Grease/Tar L 0.0095

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 64.40 m²/h.
To increase the output, additional equipment and labor may be added.

113 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.4.1 PCC Pavement (Plain) - Conventional Method, 250 mm thk
Unit of Measurement : m²
Output per hour : 64.40 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 12 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Vibrator 2 1.00


b. Concrete Screeder (5.5 hp) 1 1.00
c. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
d. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 64.40 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.45


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.15 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Steel Forms (Rental) m 0.46 project site. Refer to the Construction Materials Price
e. Ready Mix Concrete, 3500 psi m³ 0.25 Data established quarterly by Central Office Price
f. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015 Monitoring Committee.
g. Pipe Sleeve, 2" Ø m 0.0078
h. Grease/Tar L 0.0095

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 64.40 m²/h.
To increase the output, additional equipment and labor may be added.

114 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.5 PCC Pavement (Plain) - Conventional Method, 280 mm thk
Unit of Measurement : m²
Output per hour : 57.50 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 12 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Transit Mixer (5 m³) 4 1.00


b. Concrete Vibrator 2 1.00
c. Concrete Batch Plant (30 m³) 1 1.00
d. Payloader (1.50 m³), LX80-2C 1 1.00
e. Concrete Screeder (5.5 hp) 1 1.00
f. Water Truck/Pump (16000 L) 1 1.00
g. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
h. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 57.50 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.50


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.17 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Steel Forms (Rental) m 0.46 project site. Refer to the Construction Materials Price
e. Sand m³ 0.154 Data established quarterly by Central Office Price
f. Gravel m³ 0.28 Monitoring Committee.
g. Cement bag 2.66
h. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015
i. Pipe Sleeve, 2" Ø m 0.0078
j. Grease/Tar L 0.0078

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 57.50 m²/h.
To increase the output, additional equipment and labor may be added.

115 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.5.1 PCC Pavement (Plain) - Conventional Method, 280 mm thk
Unit of Measurement : m²
Output per hour : 57.50 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 12 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Vibrator 2 1.00


b. Concrete Screeder (5.5 hp) 1 1.00
c. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
d. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 57.50 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.50


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.17 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Steel Forms (Rental) m 0.46 project site. Refer to the Construction Materials Price
e. Ready Mix Concrete, 3500 psi m³ 0.28 Data established quarterly by Central Office Price
f. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015 Monitoring Committee.
g. Pipe Sleeve, 2" Ø m 0.0078
h. Grease/Tar L 0.0078

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 57.50 m²/h.
To increase the output, additional equipment and labor may be added.

116 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.6 PCC Pavement (Plain) - Conventional Method, 300 mm thk
Unit of Measurement : m²
Output per hour : 53.67 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 12 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Transit Mixer (5 m³) 4 1.00


b. Concrete Vibrator 2 1.00
c. Concrete Batch Plant (30 m³) 1 1.00
d. Payloader (1.50 m³), LX80-2C 1 1.00
e. Concrete Screeder (5.5 hp) 1 1.00
f. Water Truck/Pump (16000 L) 1 1.00
g. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
h. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 53.67 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.55


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.18 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Steel Forms (Rental) m 0.46 project site. Refer to the Construction Materials Price
e. Sand m³ 0.165 Data established quarterly by Central Office Price
f. Gravel m³ 0.30 Monitoring Committee.
g. Cement bag 2.85
h. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015
i. Pipe Sleeve, 2" Ø m 0.0094
j. Grease/Tar L 0.0094

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 53.67 m²/h.
To increase the output, additional equipment and labor may be added.

117 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.6.1 PCC Pavement (Plain) - Conventional Method, 300 mm thk
Unit of Measurement : m²
Output per hour : 53.67 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 12 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Vibrator 2 1.00


b. Concrete Screeder (5.5 hp) 1 1.00
c. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
d. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 53.67 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.55


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.18 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Steel Forms (Rental) m 0.46 project site. Refer to the Construction Materials Price
e. Ready Mix Concrete, 3500 psi m³ 0.30 Data established quarterly by Central Office Price
f. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015 Monitoring Committee.
g. Pipe Sleeve, 2" Ø m 0.0094
h. Grease/Tar L 0.0094

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 53.67 m²/h.
To increase the output, additional equipment and labor may be added.

118 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.1 PCC Pavement (Plain) - Using Concrete Paver, 230 mm thk
Unit of Measurement : m²
Output per hour : 90.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 10 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Batch Plant (30 m³) 1 1.00


b. Concrete Paver, COM. III, FOUR-TRACK 1 1.00
c. Transit Mixer (5 m³) 4 1.00
d. Payloader (1.50 m³), LX80-2C 1 1.00
e. Water Truck/Pump (16000 L) 1 1.00
f. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
g. Concrete Vibrator 1 0.10
h. Bar Cutter, Single Phase 1 0.10

Sub - Total for B


C. Total (A + B)
D. Output per hour = 90.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.43


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.12 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Sand m³ 0.1265 project site. Refer to the Construction Materials Price
e. Gravel m³ 0.23 Data established quarterly by Central Office Price
f. Cement bag 2.19 Monitoring Committee.
g. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015
h. Pipe Sleeve, 2" Ø m 0.0071
i. Grease/Tar L 0.0087

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 90.00 m²/h.
To increase the output, additional equipment and labor may be added.

119 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.1.1 PCC Pavement (Plain) - Using Concrete Paver, 230 mm thk
Unit of Measurement : m²
Output per hour : 100.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 10 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Paver, COM. III, FOUR-TRACK 1 1.00


b. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
c. Concrete Vibrator 1 0.10
d. Bar Cutter, Single Phase 1 0.10

Sub - Total for B


C. Total (A + B)
D. Output per hour = 100.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.43


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.12 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Ready Mix Concrete, 3500 psi m³ 0.23 project site. Refer to the Construction Materials Price
e. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015 Data established quarterly by Central Office Price
f. Pipe Sleeve, 2" Ø m 0.0071 Monitoring Committee.
g. Grease/Tar L 0.0087

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 100.00 m²/h.
To increase the output, additional equipment and labor may be added.

120 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.2 PCC Pavement (Plain) - Using Concrete Paver, 250 mm thk
Unit of Measurement : m²
Output per hour : 82.80 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 10 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Batch Plant (30 m³) 1 1.00


b. Concrete Paver, COM. III, FOUR-TRACK 1 1.00
c. Transit Mixer (5 m³) 4 1.00
d. Payloader (1.50 m³), LX80-2C 1 1.00
e. Water Truck/Pump (16000 L) 1 1.00
f. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
g. Concrete Vibrator 1 0.10
h. Bar Cutter, Single Phase 1 0.10

Sub - Total for B


C. Total (A + B)
D. Output per hour = 82.80 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.45


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.15 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Sand m³ 0.1375 project site. Refer to the Construction Materials Price
e. Gravel m³ 0.25 Data established quarterly by Central Office Price
f. Cement bag 2.38 Monitoring Committee.
g. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015
h. Pipe Sleeve, 2" Ø m 0.0078
i. Grease/Tar L 0.0095

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 82.80 m²/h.
To increase the output, additional equipment and labor may be added.

121 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.2.1 PCC Pavement (Plain) - Using Concrete Paver, 250 mm thk
Unit of Measurement : m²
Output per hour : 100.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 10 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Paver, COM. III, FOUR-TRACK 1 1.00


b. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
c. Concrete Vibrator 1 0.10
d. Bar Cutter, Single Phase 1 0.10

Sub - Total for B


C. Total (A + B)
D. Output per hour = 100.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.45


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.15 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Ready Mix Concrete, 3500 psi m³ 0.25 project site. Refer to the Construction Materials Price
e. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015 Data established quarterly by Central Office Price
f. Pipe Sleeve, 2" Ø m 0.0078 Monitoring Committee.
g. Grease/Tar L 0.0095

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 100.00 m²/h.
To increase the output, additional equipment and labor may be added.

122 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.3 PCC Pavement (Plain) - Using Concrete Paver, 280 mm thk
Unit of Measurement : m²
Output per hour : 73.93 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 10 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Batch Plant (30 m³) 1 1.00


b. Concrete Paver, COM. III, FOUR-TRACK 1 1.00
c. Transit Mixer (5 m³) 4 1.00
d. Payloader (1.50 m³), LX80-2C 1 1.00
e. Water Truck/Pump (16000 L) 1 1.00
f. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
g. Concrete Vibrator 1 0.10
h. Bar Cutter, Single Phase 1 0.10

Sub - Total for B


C. Total (A + B)
D. Output per hour = 73.93 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.50


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.17 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Sand m³ 0.154 project site. Refer to the Construction Materials Price
e. Gravel m³ 0.28 Data established quarterly by Central Office Price
f. Cement bag 2.66 Monitoring Committee.
g. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015
h. Pipe Sleeve, 2" Ø m 0.0078
i. Grease/Tar L 0.0078

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 73.93 m²/h.
To increase the output, additional equipment and labor may be added.

123 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.3.1 PCC Pavement (Plain) - Using Concrete Paver, 280 mm thk
Unit of Measurement : m²
Output per hour : 100.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 10 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Paver, COM. III, FOUR-TRACK 1 1.00


b. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
c. Concrete Vibrator 1 0.10
d. Bar Cutter, Single Phase 1 0.10

Sub - Total for B


C. Total (A + B)
D. Output per hour = 100.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.50


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.17 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Ready Mix Concrete, 3500 psi m³ 0.28 project site. Refer to the Construction Materials Price
e. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015 Data established quarterly by Central Office Price
f. Pipe Sleeve, 2" Ø m 0.0078 Monitoring Committee.
g. Grease/Tar L 0.0078

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 100.00 m²/h.
To increase the output, additional equipment and labor may be added.

124 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.4 PCC Pavement (Plain) - Using Concrete Paver, 300 mm thk
Unit of Measurement : m²
Output per hour : 69.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 10 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Batch Plant (30 m³) 1 1.00


b. Concrete Paver, COM. III, FOUR-TRACK 1 1.00
c. Transit Mixer (5 m³) 4 1.00
d. Payloader (1.50 m³), LX80-2C 1 1.00
e. Water Truck/Pump (16000 L) 1 1.00
f. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
g. Concrete Vibrator 1 0.10
h. Bar Cutter, Single Phase 1 0.10

Sub - Total for B


C. Total (A + B)
D. Output per hour = 69.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.55


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.18 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Sand m³ 0.165 project site. Refer to the Construction Materials Price
e. Gravel m³ 0.30 Data established quarterly by Central Office Price
f. Cement bag 2.85 Monitoring Committee.
g. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015
h. Pipe Sleeve, 2" Ø m 0.0094
i. Grease/Tar L 0.0094

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 69.00 m²/h.
To increase the output, additional equipment and labor may be added.

125 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.4.1 PCC Pavement (Plain) - Using Concrete Paver, 300 mm thk
Unit of Measurement : m²
Output per hour : 100.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 10 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Paver, COM. III, FOUR-TRACK 1 1.00


b. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
c. Concrete Vibrator 1 0.10
d. Bar Cutter, Single Phase 1 0.10

Sub - Total for B


C. Total (A + B)
D. Output per hour = 100.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.55


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.18 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Ready Mix Concrete, 3500 psi m³ 0.30 project site. Refer to the Construction Materials Price
e. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015 Data established quarterly by Central Office Price
f. Pipe Sleeve, 2" Ø m 0.0094 Monitoring Committee.
g. Grease/Tar L 0.0094

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 100.00 m²/h.
To increase the output, additional equipment and labor may be added.

126 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)c PCC Pavement (Plain) - Conventional Method, 150 mm thk
Unit of Measurement : m²
Output per hour : 12.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 8 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 16 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. One Bagger Mixer 1 1.00


b. Water Truck/Pump (16000 L) 1 0.05
c. Concrete Vibrator 2 1.00
d. Bar Cutter, Single Phase 1 0.05
e. Concrete Saw (7.5 hp), 14" Blade Ø 1 0.10
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 12.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.33


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.12 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Steel Forms (Rental) m 0.46 project site. Refer to the Construction Materials Price
e. Sand m³ 0.0825 Data established quarterly by Central Office Price
f. Gravel m³ 0.15 Monitoring Committee.
g. Cement bag 1.43
h. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015
i. Pipe Sleeve, 1" Ø m 0.0078
j. Grease/Tar L 0.0015

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 12.00 m²/h.
To increase the output, additional equipment and labor may be added.

127 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)c.1 PCC Pavement (Plain) - Conventional Method, 150 mm thk
Unit of Measurement : m²
Output per hour : 12.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 8 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 16 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Vibrator 2 1.00


b. Bar Cutter, Single Phase 1 0.05
c. Concrete Saw (7.5 hp), 14" Blade Ø 1 0.10
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 12.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Reinforcing Steel Bar kg 0.33


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.12 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Steel Forms (Rental) m 0.46 project site. Refer to the Construction Materials Price
e. Ready Mix Concrete, 3500 psi m³ 0.15 Data established quarterly by Central Office Price
f. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015 Monitoring Committee.
g. Pipe Sleeve, 1" Ø m 0.0078
h. Grease/Tar L 0.0015

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 12.00 m²/h.
To increase the output, additional equipment and labor may be added.

128 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(2) PCC Pavement (Reinforced), 300 mm thk


Unit of Measurement : m²
Output per hour : 6.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 12 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Batch Plant (30 m³) 1 0.10


b. Concrete Screeder (5.5 hp) 1 0.10
c. Transit Mixer (5 m³) 2 0.10
d. Payloader (1.50 m³), LX80-2C 1 0.10
e. Water Truck/Pump (16000 L) 1 0.10
f. Concrete Vibrator 1 0.10
g. Bar Cutter, Single Phase 1 0.25
h. Bar Bender 1 0.25
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 6.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reinforcing Steel Bar kg 54.21


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.18 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Steel Forms (Rental) m 0.46 project site. Refer to the Construction Materials Price
e. Sand m³ 0.165 Data established quarterly by Central Office Price
f. Gravel m³ 0.30 Monitoring Committee.
g. Cement bag 2.85
h. # 16 GI Tie Wire (2% of RSB) kg 1.084

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 6.00 m²/h.
To increase the output, additional equipment and labor may be added.

129 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(2)1 PCC Pavement (Reinforced), 300 mm thk


Unit of Measurement : m²
Output per hour : 6.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 12 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Screeder (5.5 hp) 1 0.10


b. Concrete Vibrator 1 0.10
c. Bar Cutter, Single Phase 1 0.25
d. Bar Bender 1 0.25
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 6.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reinforcing Steel Bar kg 54.21


b. Curing Compound L 0.29 Prices of materials are variable per Region/District
c. Asphalt Sealant L 0.18 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Steel Forms (Rental) m 0.46 project site. Refer to the Construction Materials Price
e. Ready Mix Concrete, 3500 psi m³ 0.30 Data established quarterly by Central Office Price
f. # 16 GI Tie Wire (2% of RSB) kg 1.084 Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 6.00 m²/h.
To increase the output, additional equipment and labor may be added.

130 Part E - Surface Courses


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 404 Reinforcing Steel Bar, Grade 40 (Minor Structures)


Unit of Measurement : kg
Output per hour : 180.00 kg

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Bar Cutter 1 0.50


b. Bar Bender 1 0.50
c. Cargo Truck (9 - 10 mt) 1 0.15

Sub - Total for B


C. Total (A + B)
D. Output per hour = 180.00 kg
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Tie Wire (2% of RSB) kg 0.021


b. Reinforcing Steel Bar, Grade 40 kg 1.05 Prices of materials are variable per Region/District
(w/ 5% Wastage) based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 180.00 kg/h.
To increase the output, additional equipment and labor may be added.

131 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 405 Structural Concrete Class A (Minor Structures)


Unit of Measurement : m³
Output per hour : 1.40 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.

Installation/Removal of Formworks
a. Skilled Labor 4 1.00
b. Unskilled Labor 8 1.00
Sub - Total for A
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. One Bagger Mixer 1 1.00


b. Concrete Vibrator 1 1.00
c. Water Truck/Pump (16000 L) 1 0.10
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.40 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Lumber, Good - 4 uses bd-ft * 70.00


b. Marine Plywood (1/2" x 4' x 8') - 4 uses pc * 1.60 Prices of materials are variable per Region/District
c. Assorted CWN (1kg/100 bd-ft of Lumber) kg * 0.70 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Cement bag 9.50 project site. Refer to the Construction Materials Price
e. Sand m³ 0.50 Data established quarterly by Central Office Price
f. Gravel m³ 1.00 Monitoring Committee.

Note:
*Quantities for lumber, plywood and CWN are
dependent on the type of minor structure.
The above-computed quantities are based on box
culvert.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.40 m³/h.
To increase the output, additional equipment and labor may be added.

132 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)a Pipe Culverts, 610 mm Ø (24" Ø)


Unit of Measurement : m
Output : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 0.44


b. Skilled Labor 2 0.44 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 0.44
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.22


b. Plate Compactor (5 hp) 1 0.22
Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Portland Cement bag 0.774


b. Sand m³ 0.044 Prices of materials are variable per Region/District
c. RC Pipes (610 mm Ø) pc 1.00 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Sand Bedding/Selected Sandy Soil m³ 0.088 project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m for 0.44 h.
To increase the output, additional equipment and labor may be added.

133 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)b Pipe Culverts, 760 mm Ø (30" Ø)


Unit of Measurement : m
Output : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 0.50


b. Skilled Labor 2 0.50 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 0.50
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.25


b. Plate Compactor (5 hp) 1 0.25
Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Portland Cement bag 0.918


b. Sand m³ 0.052 Prices of materials are variable per Region/District
c. RC Pipes (760 mm Ø) pc 1.00 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Sand Bedding/Selected Sandy Soil m³ 0.108 project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m for 0.50 h.
To increase the output, additional equipment and labor may be added.

134 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)c Pipe Culverts, 910 mm Ø (36" Ø)


Unit of Measurement : m
Output : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 0.57


b. Skilled Labor 2 0.57 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 0.57
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.29


b. Plate Compactor (5 hp) 1 0.29
Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Portland Cement bag 1.080


b. Sand m³ 0.061 Prices of materials are variable per Region/District
c. RC Pipes (910 mm Ø) pc 1.00 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Sand Bedding/Selected Sandy Soil m³ 0.128 project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m for 0.57 h.
To increase the output, additional equipment and labor may be added.

135 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)d Pipe Culverts, 1070 mm Ø (42" Ø)


Unit of Measurement : m
Output : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 0.67


b. Skilled Labor 2 0.67 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 0.67
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.33


b. Plate Compactor (5 hp) 1 0.33
Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Portland Cement bag 1.242


b. Sand m³ 0.070 Prices of materials are variable per Region/District
c. RC Pipes (1070 mm Ø) pc 1.00 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Sand Bedding/Selected Sandy Soil m³ 0.149 project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m for 0.67 h.
To increase the output, additional equipment and labor may be added.

136 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)e Pipe Culverts, 1220 mm Ø (48" Ø)


Unit of Measurement : m
Output : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 0.80


b. Skilled Labor 2 0.80 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 0.80
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.40


b. Plate Compactor (5 hp) 1 0.40
Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Portland Cement bag 1.404


b. Sand m³ 0.080 Prices of materials are variable per Region/District
c. RC Pipes (1220 mm Ø) pc 1.00 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Sand Bedding/Selected Sandy Soil m³ 0.170 project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m for 0.80 h.
To increase the output, additional equipment and labor may be added.

137 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)f Pipe Culverts, 1520 mm Ø (60" Ø)


Unit of Measurement : m
Output per hour : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.50


b. Plate Compactor (5 hp) 1 0.50
Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Portland Cement bag 1.710


b. Sand m³ 0.097 Prices of materials are variable per Region/District
c. RC Pipes (1520 mm Ø) pc 1.00 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Sand Bedding/Selected Sandy Soil m³ 0.210 project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m/h.
To increase the output, additional equipment and labor may be added.

138 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 501(1) Underdrain


Unit of Measurement : m
Output : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 0.80


b. Unskilled Labor 4 0.80 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Plate Compactor (5 hp) 1 0.40


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Coarse Aggregates m³ 0.20


b. Fine Aggregates m³ 0.39 Prices of materials are variable per Region/District
c. Filter Cloth m² 2.00 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. 150 mm Ø Concrete Perforated Pipe pc 1.05 project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m for 0.80 h.
To increase the output, additional equipment and labor may be added.

139 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 501(2) Blind Drain


Unit of Measurement : m
Output per hour : 1.25 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Coarse Aggregates m³ 0.22


b. Fine Aggregates m³ 0.39 Prices of materials are variable per Region/District
c. Filter Cloth m² 2.00 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.25 m/h.
To increase the output, additional equipment and labor may be added.

140 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 501(3) Granular Backfill filter material for Underdrains


Unit of Measurement : m³
Output per hour : 1.25 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Plate Compactor (5 hp) 1 1.00


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Coarse Aggregates (Granular Backfill Materials) m³ 1.15


(w/ 15% Shrinkage Factor) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.25 m³/h.
To increase the output, additional equipment and labor may be added.

141 Part G - Drainage and Slope Protection Structures


ITEM NO. DESCRIPTION

502(1)a Manhole (610 mm Ø RCPC)

502(1)b Manhole (760 mm Ø RCPC)

502(1)c Manhole (910 mm Ø RCPC)

502(1)d Manhole (1070 mm Ø RCPC)

502(1)e Manhole (1220 mm Ø RCPC)

502(2)a Inlet, Type I

502(2)b Inlet, Type I-A

502(3)a.1 Catch Basin (Single Barrel 610 mm Ø RCPC)

502(3)a.2 Catch Basin (Single Barrel 760 mm Ø RCPC)

502(3)a.3 Catch Basin (Single Barrel 910 mm Ø RCPC)

502(3)a.4 Catch Basin (Single Barrel 1070 mm Ø RCPC)

502(3)a.5 Catch Basin (Single Barrel 1220 mm Ø RCPC)

502(3)b.1 Catch Basin (Double Barrel 610 mm Ø RCPC)

502(3)b.2 Catch Basin (Double Barrel 910 mm Ø RCPC)

502(3)b.3 Catch Basin (Double Barrel 1220 mm Ø RCPC)

502(7) Adjusting Manhole, Type I-A

502(8) Adjusting Inlets, Type I and I-A

502(9)a Adjusting Catch Basin (Single Barrel, 610 mm Ø)

502(9)b Adjusting Catch Basin (Double Barrel, 610 mm Ø)

These pay items are variable in dimensions based on the actual condition
which combines component items, hence standard estimate should be based on
the standard Detailed Unit Price Analysis (DUPA) of each component items, such
as Items 103(3), 404 & 405. See attached DUPA.

Further, these items with unit of measure as 'each' in the Blue Book is
recommended to be broken down separately by component items such as Items
103(3) - Foundation Fill, 404 - Reinforcing Steel Bar and 405 - Structural Concrete
Class A (Minor Structures) in the summary of quantities in the preparation of
design plans.

142 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502 Manhole/Catch Basin/Inlet


Unit of Measurement : ea
Output : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Direct
Name and Specification Unit Quantity Direct Cost
Unit Cost
F. Materials/Processed Component Pay Item

a. 103(3) - Foundation Fill m³


b. 404 - Reinforcing Steel Bar kg
c. 405 - Structural Concrete m³

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

143 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(4) Concrete Covers


Unit of Measurement : ea
Output per hour : 5.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. One Bagger Mixer 1 0.50


b. Bar Cutter, Single Phase 1 0.50
c. Concrete Vibrator 1 0.50
d. Welding Machine (300 A), Gas/Diesel Driven 1 0.25
e. Water Truck 1 0.05
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 5.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Dimension: 1.29 m x 0.57 m x 0.20 m w/ Flat Bar Frame


a. Portland Cement bag 1.43 Prices of materials are variable per Region/District
b. Sand m³ 0.075 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
c. Gravel m³ 0.15 project site. Refer to the Construction Materials Price
d. Reinforcing Steel Bar kg 46.46 Data established quarterly by Central Office Price
e. #16 GI Tie Wire (2% of RSB) kg 0.93 Monitoring Committee.
f. 6 mm thk Flat Bar kg 73.58
g. 16 mm thk Steel Plate kg 2.97
h. 1/2" Ordinary Plywood - 2 uses pc 0.33
i. 16 mm Ø U-bolt & Nut set 2.00
j. Welding Rod (1 kg/2000 kg of Steel) kg 0.04

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 5.00 ea/h.
To increase the output, additional equipment and labor may be added.

144 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(5) Metal Frames and Gratings


Unit of Measurement : pair
Output : 1.00 pair

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 0.50


b. Skilled Labor 1 0.50 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 1 0.50
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 pair
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. 410 mm x 660 mm x 60 mm, CI Cover with Frame set 1.00


Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 pair for 0.50 h.
To increase the output, additional equipment and labor may be added.

145 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(6) Metal Frames and Covers (Circular)


Unit of Measurement : pair
Output : 1.00 pair

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 0.50


b. Skilled Labor 1 0.50 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 1 0.50
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 pair
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. 580 mm Ø CI Manhole Cover with Frame set 1.00


Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 pair for 0.50 h.
To increase the output, additional equipment and labor may be added.

146 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 503(a) Drainage Steel Grating with Frame (675 mm x 975 mm Sump Grating)
Unit of Measurement : set
Output : 1.00 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 4.00


b. Skilled Labor 1 4.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 1 4.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Bar Cutter, Single Phase 1 2.00


b. Welding Machine (300 A), Gas/Diesel Driven 1 4.00

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. 65 mm x 5 mm Flat Bar kg 62.657


b. 6 mm Ø x 975 mm Twisted Cross Rod kg 1.244 Prices of materials are variable per Region/District
c. 75 mm x 75 mm x 9 mm Angle Bar kg 38.36 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Welding Rod (1 kg/2000 kg of Steel) kg 0.051 project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 set for 4.00 h.
To increase the output, additional equipment and labor may be added.

147 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 503(b) Drainage Steel Grating with Frame (715 mm x 2000 mm Trench Grating)
Unit of Measurement : set
Output : 1.00 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 8.00


b. Skilled Labor 1 8.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 1 8.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Bar Cutter, Single Phase 1 4.00


b. Welding Machine (300 A), Gas/Diesel Driven 1 8.00

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. 65 mm x 5 mm Flat Bar kg 127.066


b. 6 mm Ø x 975 mm Twisted Cross Rod kg 3.174 Prices of materials are variable per Region/District
c. 75 mm x 75 mm x 9 mm Angle Bar kg 41.64 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Welding Rod (1 kg/2000 kg of Steel) kg 0.086 project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 set for 8.00 h.
To increase the output, additional equipment and labor may be added.

148 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(1)a Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (24" dia) - 610 mm Ø
Unit of Measurement : m
Output : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 0.33


b. Skilled Labor 2 0.33 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 0.33
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.17


b. Boom Truck (2 - 5 mt) 1 0.17
c. Water Truck/Pump (16000 L) 1 0.08
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m for 0.33 h.
To increase the output, additional equipment and labor may be added.

149 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(1)b Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (30" Ø) - 760 mm Ø
Unit of Measurement : m
Output : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 0.40


b. Skilled Labor 2 0.40 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 0.40
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.20


b. Boom Truck (2 - 5 mt) 1 0.20
c. Water Truck/Pump (16000 L) 1 0.10
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m for 0.40 h.
To increase the output, additional equipment and labor may be added.

150 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(1)c Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (36" Ø) - 910 mm Ø
Unit of Measurement : m
Output : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 0.50


b. Skilled Labor 2 0.50 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 0.50
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.25


b. Boom Truck (2 - 5 mt) 1 0.25
c. Water Truck/Pump (16000 L) 1 0.13
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m for 0.50 h.
To increase the output, additional equipment and labor may be added.

151 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(1)d Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (42" Ø) - 1070 mm Ø
Unit of Measurement : m
Output : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 0.50


b. Skilled Labor 2 0.50 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 0.50
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.25


b. Boom Truck (2 - 5 mt) 1 0.25
c. Water Truck/Pump (16000 L) 1 0.13
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m for 0.50 h.
To increase the output, additional equipment and labor may be added.

152 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(1)e Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (48" Ø) - 1220 mm Ø
Unit of Measurement : m
Output : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 0.67


b. Skilled Labor 2 0.67 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 0.67
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.33


b. Boom Truck (2 - 5 mt) 1 0.33
c. Water Truck/Pump (16000 L) 1 0.17
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m for 0.67 h.
To increase the output, additional equipment and labor may be added.

153 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)a Removing, Cleaning and Re-laying Salvaged Culvert Pipe (24" Ø) - 610 mm Ø
Unit of Measurement : m
Output : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 0.67


b. Skilled Labor 2 0.67 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 0.67
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.40


b. Plate Compactor (5 hp) 1 0.33
c. Water Truck/Pump (16000 L) 1 0.10
Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Portland Cement bag 0.774


b. Sand m³ 0.044 Prices of materials are variable per Region/District
c. Sand Bedding m³ 0.088 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m for 0.67 h.
To increase the output, additional equipment and labor may be added.

154 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)b Removing, Cleaning and Re-laying Salvaged Culvert Pipe (30" Ø) - 760 mm Ø
Unit of Measurement : m
Output : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 0.80


b. Skilled Labor 2 0.80 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 0.80
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.48


b. Plate Compactor (5 hp) 1 0.40
c. Water Truck/Pump (16000 L) 1 0.12
Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Portland Cement bag 0.918 Prices of materials are variable per Region/District
b. Sand m³ 0.052 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
c. Sand Bedding m³ 0.108 project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m for 0.80 h.
To increase the output, additional equipment and labor may be added.

155 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)c Removing, Cleaning and Re-laying Salvaged Culvert Pipe (36" Ø) - 910 mm Ø
Unit of Measurement : m
Output per hour : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.60


b. Plate Compactor (5 hp) 1 0.50
c. Water Truck/Pump (16000 L) 1 0.15
Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Portland Cement bag 1.080 Prices of materials are variable per Region/District
b. Sand m³ 0.061 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
c. Sand Bedding m³ 0.128 project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m/h.
To increase the output, additional equipment and labor may be added.

156 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)d Removing, Cleaning and Re-laying Salvaged Culvert Pipe (42" Ø) - 1070 mm Ø
Unit of Measurement : m
Output per hour : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.60


b. Plate Compactor (5 hp) 1 0.50
c. Water Truck/Pump (16000 L) 1 0.15
Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Portland Cement bag 1.242 Prices of materials are variable per Region/District
b. Sand m³ 0.070 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
c. Sand Bedding m³ 0.149 project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m/h.
To increase the output, additional equipment and labor may be added.

157 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)e Removing, Cleaning and Re-laying Salvaged Culvert Pipe (48" Ø) - 1220 mm Ø
Unit of Measurement : m
Output : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.33


b. Skilled Labor 2 1.33 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.33
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (0.80 m³) 1 0.80


b. Plate Compactor (5 hp) 1 0.67
c. Water Truck/Pump (16000 L) 1 0.20
Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Portland Cement bag 1.404 Prices of materials are variable per Region/District
b. Sand m³ 0.080 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
c. Sand Bedding m³ 0.170 project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m for 1.33 h.
To increase the output, additional equipment and labor may be added.

158 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)a Cleaning Culvert Pipe in place (610 mm Ø) - Half Silted
Unit of Measurement : m
Output per hour : 8.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (9 - 10 mt) 1 1.00


b. Steel Wheel with Nylon Rope 1 1.00
c. Improvised Bamboo with Bucket 1 1.00
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 8.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 8.00 m/h.
To increase the output, additional equipment and labor may be added.

159 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)b Cleaning Culvert Pipe in place (760 mm Ø) - Half Silted
Unit of Measurement : m
Output per hour : 5.25 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (9 - 10 mt) 1 1.00


b. Steel Wheel with Nylon Rope 1 1.00
c. Improvised Bamboo with Bucket 1 1.00
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 5.25 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 5.25 m/h.
To increase the output, additional equipment and labor may be added.

160 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)c Cleaning Culvert Pipe in place (910 mm Ø) - Half Silted
Unit of Measurement : m
Output per hour : 3.75 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (9 - 10 mt) 1 1.00


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 3.75 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 3.75 m/h.
To increase the output, additional equipment and labor may be added.

161 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)d Cleaning Culvert Pipe in place (1070 mm Ø) - Half Silted
Unit of Measurement : m
Output per hour : 2.75 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (9 - 10 mt) 1 1.00


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.75 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 2.75 m/h.
To increase the output, additional equipment and labor may be added.

162 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)e Cleaning Culvert Pipe in place (1220 mm Ø) - Half Silted
Unit of Measurement : m
Output per hour : 2.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (9 - 10 mt) 1 1.00


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 2.00 m/h.
To increase the output, additional equipment and labor may be added.

163 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)f Cleaning Culvert Pipe in place (1520 mm Ø) - Half Silted
Unit of Measurement : m
Output per hour : 1.50 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (9 - 10 mt) 1 1.00


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.50 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.50 m/h.
To increase the output, additional equipment and labor may be added.

164 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(4) Reconditioning Drainage Structures


Unit of Measurement : ea
Output : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 0.50


b. Skilled Labor 1 0.50 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 0.50
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (9 - 10 mt) 1 0.25


b. Bamboo with Bucket - 4 uses 1 0.50
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

* If some repair is needed, component materials


required and corresponding man-hour will be
added to DUPA

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea for 0.50 h.
To increase the output, additional equipment and labor may be added.

165 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(1) Riprap (Class A)


Unit of Measurement : m³
Output per hour : 1.50 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.50 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Boulders (15 - 25 kg) m³ 1.05


Miscellaneous (1% of Materials Cost) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.50 m³/h.
To increase the output, additional equipment and labor may be added.

166 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(2) Riprap (Class B)


Unit of Measurement : m³
Output per hour : 1.25 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (Wheel Type 0.28 m³) 1 0.50


Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Boulders (30 - 70 kg) m³ 1.05


Miscellaneous (1% of Materials Cost) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.25 m³/h.
To increase the output, additional equipment and labor may be added.

167 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(3) Riprap (Class C)


Unit of Measurement : m³
Output per hour : 1.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

c. Backhoe (Wheel Type 0.28 m³) 1 0.75


Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Boulders (50 - 100 kg) m³ 1.05


Miscellaneous (1% of Materials Cost) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m³/h.
To increase the output, additional equipment and labor may be added.

168 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(4) Riprap (Class D)


Unit of Measurement : m³
Output per hour : 0.75 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labors 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labors 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Backhoe (Wheel Type 0.28 m³) 1 1.00


Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.75 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Boulders (100 - 200 kg) m³ 1.05


Miscellaneous (1% of Materials Cost) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 0.75 m³/h.
To increase the output, additional equipment and labor may be added.

169 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(5) Grouted Riprap (Class A)


Unit of Measurement : m³
Output per hour : 1.25 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. One Bagger Mixer 1 1.00


b. Water Truck/Pump (16000 L) 1 0.05
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Cement bag 3.00


b. Sand m³ 0.25 Prices of materials are variable per Region/District
c. Gravel Fill m³ 0.015 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Weep Holes (PVC) m 0.30 project site. Refer to the Construction Materials Price
e. Filter Cloth m² 0.015 Data established quarterly by Central Office Price
f. Boulders (15 - 25 kg) m³ 1.05 Monitoring Committee.
Miscellaneous (1% of Materials Cost)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.25 m³/h.
To increase the output, additional equipment and labor may be added.

170 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(6) Grouted Riprap (Class B)


Unit of Measurement : m³
Output per hour : 1.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. One Bagger Mixer 1 1.00


b. Water Truck/Pump (16000 L) 1 0.05
c. Backhoe (Wheel Type 0.28 m³) 1 0.50
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Cement bag 2.50


b. Sand m³ 0.21 Prices of materials are variable per Region/District
c. Gravel Fill m³ 0.015 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Weep Holes (PVC) m 0.30 project site. Refer to the Construction Materials Price
e. Filter Cloth m² 0.015 Data established quarterly by Central Office Price
f. Boulders (30 - 70 kg) m³ 1.05 Monitoring Committee.
Miscellaneous (1% of Materials Cost)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m³/h.
To increase the output, additional equipment and labor may be added.

171 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(7) Grouted Riprap (Class C)


Unit of Measurement : m³
Output per hour : 0.75 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. One Bagger Mixer 1 1.00


b. Water Truck/Pump (16000 L) 1 0.05
c. Backhoe (Wheel Type 0.28 m³) 1 0.75
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.75 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Cement bag 2.20


b. Sand m³ 0.18 Prices of materials are variable per Region/District
c. Gravel Fill m³ 0.015 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Weep Holes (PVC) m 0.30 project site. Refer to the Construction Materials Price
e. Filter Cloth m² 0.015 Data established quarterly by Central Office Price
f. Boulders (60 - 100 kg) m³ 1.05 Monitoring Committee.
Miscellaneous (1% of Materials Cost)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 0.75 m³/h.
To increase the output, additional equipment and labor may be added.

172 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(8) Grouted Riprap (Class D)


Unit of Measurement : m³
Output per hour : 0.50 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. One Bagger Mixer 1 1.00


b. Water Truck/Pump (16000 L) 1 0.05
c. Backhoe (Wheel Type 0.28 m³) 1 1.00
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.50 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Cement bag 1.80


b. Sand m³ 0.15 Prices of materials are variable per Region/District
c. Gravel Fill m³ 0.015 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Weep Holes (PVC) m 0.30 project site. Refer to the Construction Materials Price
e. Filter Cloth m² 0.015 Data established quarterly by Central Office Price
f. Boulders (100 - 200 kg) m³ 1.05 Monitoring Committee.
Miscellaneous (1% of Materials Cost)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 0.50 m³/h.
To increase the output, additional equipment and labor may be added.

173 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(9) Filter Layer of Granular Material


Unit of Measurement : m³
Output per hour : 1.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Granular Materials m³ 1.05


Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m³/h.
To increase the output, additional equipment and labor may be added.

174 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 506 Stone Masonry


Unit of Measurement : m³
Output per hour : 1.60 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. One Bagger Mixer 1 1.00


b. Water Truck/Pump (16000 L) 1 0.05
c. Backhoe (Wheel Type 0.28 m³) 1 0.10
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.60 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Cement bag 5.50


b. Sand m³ 0.30 Prices of materials are variable per Region/District
c. Gravel Fill m³ 0.02 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Weep Holes (PVC) m 0.30 project site. Refer to the Construction Materials Price
e. Filter Cloth m² 0.015 Data established quarterly by Central Office Price
f. Boulders m³ 1.05 Monitoring Committee.
Miscellaneous (1% of Materials Cost)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.60 m³/h.
To increase the output, additional equipment and labor may be added.

175 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 507 Rubble Concrete


Unit of Measurement : m³
Output per hour : 1.40 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. One Bagger Mixer 1 1.00


b. Water Truck/Pump (16000 L) 1 0.05
c. Backhoe (Wheel Type 0.28 m³) 1 0.10
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.40 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Cement bag 4.20


b. Sand m³ 0.2625 Prices of materials are variable per Region/District
c. Gravel Fill m³ 0.02 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Weep Holes (PVC) m 0.30 project site. Refer to the Construction Materials Price
e. Filter Cloth m² 0.015 Data established quarterly by Central Office Price
f. Boulders m³ 0.63 Monitoring Committee.
g. Gravel m³ 0.525
Miscellaneous (2% of Materials Cost)
Note:
60% Boulder
50% Class "B" Concrete (w/ side forms only)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.40 m³/h.
To increase the output, additional equipment and labor may be added.

176 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 508 Hand Laid Rock Embankment


Unit of Measurement : m³
Output per hour : 3.125 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 3.125 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Boulders m³ 1.05
Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 3.125 m³/h.
To increase the output, additional equipment and labor may be added.

177 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 509(a) Timber Sheet Pile


Unit of Measurement : m
Output per hour : 4.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1 1.00


b. Drop Hammer (15 mt) 1 1.00
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Timber Sheet Piles, ave. Ø 395 mm bd-ft 52.25


b. Coco Log - 2 uses m 1.00 Prices of materials are variable per Region/District
c. Lumber (Falsework) - 4 uses bd-ft 16.00 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Nail/Spike (1 kg/100 bd-ft of Lumber) kg 0.16 project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 4.00 m/h.
To increase the output, additional equipment and labor may be added.

178 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 509(b) Steel Sheet Pile (Slope Protection)


Unit of Measurement : m
Output per hour : 10.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Crawler Crane (36 - 40 mt) 1 1.00


b. Vibro Hammer (Hydraulic Operated) 1 1.00
c. Welding Machine (300 A), Gas/Diesel Driven 1 0.25
d. Cutting Outfit 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 10.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Steel Sheet Piles (48 kg/m) kg 48.00


Miscellaneous (3% of Materials Cost) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 10.00 m/h.
To increase the output, additional equipment and labor may be added.

179 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 509(c) Concrete Sheet Pile, furnished and driven - 0.50 m x 0.35 m
Unit of Measurement : m
Output per hour : 1.38 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 6 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 6 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1 0.23


b. Diesel Hammer (K25 or equivalent) 1 0.13
c. One Bagger Mixer 1 0.15
d. Concrete Vibrator 1 0.15
e. Water Truck/Pump (16000 L) 1 0.01
f. Bar Cutter, Single Phase 1 0.20
g. Bar Bender 1 0.20
h. Drop Hammer 1 0.13
i. Jack Hammer 2 0.01
j. Air Compressor (356 - 450 cfm) 1 0.01
k. Plate Compactor (5 hp) 1 0.01
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.38 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
a. Coco Log m 0.71
b. Reinforcing Steel Bar kg 41.64
c. Cement bag 1.66 Prices of materials are variable per Region/District
d. Sand m³ 0.09 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
e. Gravel m³ 0.18 project site. Refer to the Construction Materials Price
f. Marine Plywood, 1/2" x 4' x 8' - 4 uses pc 0.24 Data established quarterly by Central Office Price
g. Good Lumber - 4 uses bd-ft 18.59 Monitoring Committee.
h. # 16 GI Tie Wire (2% of RSB) kg 0.83
i. Spike (1 kg/100 bd-ft of Lumber) kg 0.06
j. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.19
Casting Bed
a. Ready Mix Concrete m³ 0.03
b. Coco Lumber - 4 uses bd-ft 1.50
c. Base Course m³ 0.03
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.38 m/h.
To increase the output, additional equipment and labor may be added.

180 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 510(1) Bed Course Granular Material


Unit of Measurement : m³
Output per hour : 1.25 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Plate Compactor (5 hp) 1 1.00


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Aggregate Subbase Course m³ 1.15


(w/ 15% Shrinkage Factor) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.25 m³/h.
To increase the output, additional equipment and labor may be added.

181 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 510(2) Concrete Slope Protection


Unit of Measurement : m³
Output per hour : 1.00 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.
Installation of Formworks & Rebars
a. Skilled Labor 2 1.00
b. Unskilled Labor 4 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. One Bagger Mixer 1 1.00


b. Water Truck/Pump (16000 L) 1 0.05
c. Backhoe (Wheel Type 0.28 m³) 1 0.10
d. Concrete Vibrator 1 0.50
e. Bar Cutter, Single Phase 1 0.05
f. Bar Bender 1 0.05
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Cement bag 8.40


b. Sand m³ 0.50 Prices of materials are variable per Region/District
c. Weep Holes (PVC) m 0.21 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Filter Cloth m² 0.015 project site. Refer to the Construction Materials Price
e. Gravel m³ 1.00 Data established quarterly by Central Office Price
f. Granular Filter m³ 0.016 Monitoring Committee.
f. Reinforcing Steel Bar kg * 26.03
g. Marine Plywood 1/2" x 4' x 8' - 4 uses pc 0.48
h. Lumber - 4 uses bd-ft 18.76
i. #16 GI Tie Wire (2% of RSB) kg 0.521
j. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.188

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
* Note: RSB quantity is variable based on approved plan.
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 m³/h.
To increase the output, additional equipment and labor may be added.

182 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 511(1) Gabions


Unit of Measurement : m³
Output per hour : 2.50 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

Note: Exclude Excavation Works


Backhoe excluded, excavation should be separate as the
quantity is variable.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.50 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Gabion Wire Mesh (1 m x 1 m x 2 m) pc 0.50


(w/ complete accessories) Prices of materials are variable per Region/District
b. Boulders m³ 1.05 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 2.50 m³/h.
To increase the output, additional equipment and labor may be added.

183 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 511(2) Mattresses


Unit of Measurement : m³
Output per hour : 3.125 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

Note: Exclude Excavation Works


Backhoe excluded, excavation should be separate as the
quantity is variable.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 3.125 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Mattresses (6 m x 2 m x 0.3 m) pc 0.28


(w/ complete accessories) Prices of materials are variable per Region/District
b. Boulders m³ 1.05 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 3.125 m³/h.
To increase the output, additional equipment and labor may be added.

184 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 511(3) Filter Cloth


Unit of Measurement : m²
Output per hour : 100.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (9 - 10 mt) 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 100.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Filter Cloth m² 1.05


Miscellaneous (5% of Materials Cost) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 100.00 m²/h.
To increase the output, additional equipment and labor may be added.

185 Part G - Drainage and Slope Protection Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(1) Concrete Curb (Cast in place) - 0.45 m x 0.15/0.20 m


Unit of Measurement : m
Output per hour : 17.50 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Vibrator 1 1.00


b. One Bagger Mixer 1 1.00
c. Water Truck/Pump (16000 L) 1 0.05
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 17.50 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Cement bag 0.72


b. Sand m³ 0.04 Prices of materials are variable per Region/District
c. Gravel m³ 0.08 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Plywood Marine, 1/2" thk x 4' x 8' - 4 uses pc 0.28 project site. Refer to the Construction Materials Price
e. Form Lumber - 4 uses bd-ft 12.16 Data established quarterly by Central Office Price
f. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.12 Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 17.50 m/h.
To increase the output, additional equipment and labor may be added.

186 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(2) Concrete Gutter (Cast in place) - 0.50 m x 0.15 m


Unit of Measurement : m
Output per hour : 17.50 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Vibrator 1 1.00


b. One Bagger Mixer 1 1.00
c. Water Truck/Pump (16000 L) 1 0.05
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 17.50 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Cement bag 0.72


b. Sand m³ 0.04 Prices of materials are variable per Region/District
c. Gravel m³ 0.08 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Good Lumber - 4 uses bd-ft 3.28 project site. Refer to the Construction Materials Price
e. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.03 Data established quarterly by Central Office Price
f. Reinforcing Steel Bar kg 0.84 Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 17.50 m/h.
To increase the output, additional equipment and labor may be added.

187 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(3) Concrete Curb and Gutter, Type A (Cast in place) - National Road
Unit of Measurement : m
Output per hour : 10.30 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Vibrator 1 1.00


b. One Bagger Mixer 1 1.00
c. Water Truck/Pump (16000 L) 1 0.05
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 10.30 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Cement bag 1.29


b. Sand m³ 0.07 Prices of materials are variable per Region/District
c. Gravel m³ 0.14 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Plywood Marine, 1/2" thk x 4' x 8' - 4 uses pc 0.24 project site. Refer to the Construction Materials Price
e. Form Lumber - 4 uses bd-ft 11.47 Data established quarterly by Central Office Price
f. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.11 Monitoring Committee.
Miscellaneous (2% of Materials Cost)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 10.30 m/h.
To increase the output, additional equipment and labor may be added.

188 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(4) Concrete Curb (Precast)


Unit of Measurement : pc
Output per hour : 4.00 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 1 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Boom Truck (2 - 5 mt) 1 0.50


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.00 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Fabricated Concrete Curb m 1.00


Miscellaneous (5% of Materials Cost) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 4.00 pc/h.
To increase the output, additional equipment and labor may be added.

189 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(5) Concrete Gutter (Precast)


Unit of Measurement : pc
Output per hour : 4.00 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 1 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Boom Truck (2 - 5 mt) 1 0.50


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.00 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Fabricated Concrete Gutter m 1.00


Miscellaneous (5% of Materials Cost) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 4.00 pc/h.
To increase the output, additional equipment and labor may be added.

190 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(6) Concrete Curb and Gutter (Precast)


Unit of Measurement : pc
Output per hour : 3.00 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 1 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Boom Truck (2 - 5 mt) 1 0.50


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 3.00 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Fabricated Concrete Curb and Gutter m 1.00


Miscellaneous (5% of Materials Cost) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 3.00 pc/h.
To increase the output, additional equipment and labor may be added.

191 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 601(a) Sidewalk (100 mm thk)


Unit of Measurement : m²
Output per hour : 161.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 12 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Transit Mixer (5 m³) 4 1.00


b. Concrete Vibrator 2 1.00
c. Concrete Batch Plant (30 m³) 1 1.00
d. Payloader (1.50 m³), LX80-2C 1 1.00
e. Concrete Screeder (5.5 hp) 1 1.00
f. Water Truck/Pump (16000 L) 1 1.00
g. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 161.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Curing Compound L 0.29


b. Asphalt Sealant L 0.12 Prices of materials are variable per Region/District
c. Forms m 0.46 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Sand m³ 0.055 project site. Refer to the Construction Materials Price
e. Gravel m³ 0.10 Data established quarterly by Central Office Price
f. Cement bag 0.95 Monitoring Committee.

Note : Bed Course excluded

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 161.00 m²/h.
To increase the output, additional equipment and labor may be added.

192 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 601(b) Sidewalk (100 mm thk)


Unit of Measurement : m²
Output per hour : 20.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 4 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 12 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. One Bagger Mixer 1 1.00


b. Concrete Vibrator 2 1.00
c. Water Truck/Pump (16000 L) 1 0.125
d. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 20.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Curing Compound L 0.29


b. Asphalt Sealant L 0.12 Prices of materials are variable per Region/District
c. Forms m 0.46 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Sand m³ 0.055 project site. Refer to the Construction Materials Price
e. Gravel m³ 0.10 Data established quarterly by Central Office Price
f. Cement bag 0.95 Monitoring Committee.

Note : Bed Course excluded

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 20.00 m²/h.
To increase the output, additional equipment and labor may be added.

193 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(1)a Right-of-Way Monument


Unit of Measurement : ea
Output per hour : 2.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Vibrator 1 0.20


b. Cargo Truck (9 - 10 mt) 1 0.05
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Concrete Class "A" m³ 0.03


b. Reinforcing Steel Bar, Grade 40 kg 7.15 Prices of materials are variable per Region/District
c. Plywood, 1/2" x 4' x 8' - 4 uses pc 0.22 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Form Lumber, Good - 4 uses bd-ft 13.53 project site. Refer to the Construction Materials Price
e. Reflectorized Paint, Marker L 0.10 Data established quarterly by Central Office Price
f. # 16 Tie Wire (2% of RSB) kg 0.14 Monitoring Committee.
g. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.14

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 2.00 ea/h.
To increase the output, additional equipment and labor may be added.

194 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(1)b Right-of-Way Monument (Precast)


Unit of Measurement : ea
Output per hour : 4.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (9 - 10 mt) 1 0.05


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Fabricated Right-of-Way Monument ea 1.00


(delivered at site) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 4.00 ea/h.
To increase the output, additional equipment and labor may be added.

195 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(2)a Maintenance Marker Post


Unit of Measurement : ea
Output per hour : 2.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Concrete Vibrator 1 0.20


b. Cargo Truck (9 - 10 mt) 1 0.05
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Concrete Class "A" m³ 0.03


b. Reinforcing Steel Bar, Grade 40 kg 7.00 Prices of materials are variable per Region/District
c. Plywood, 1/2" x 4' x 8' - 4 uses pc 0.22 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Form Lumber, Good - 4 uses bd-ft 13.53 project site. Refer to the Construction Materials Price
e. Reflectorized Paint, Marker L 0.10 Data established quarterly by Central Office Price
f. # 16 Tie Wire (2% of RSB) kg 0.14 Monitoring Committee.
g. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.14

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 2.00 ea/h.
To increase the output, additional equipment and labor may be added.

196 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(2)b Maintenance Marker Post (Precast)


Unit of Measurement : ea
Output per hour : 4.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (9 - 10 mt) 1 0.05


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Fabricated Maintenance Marker Post ea 1.00


(delivered at site) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 4.00 ea/h.
To increase the output, additional equipment and labor may be added.

197 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(3)a Kilometer Post


Unit of Measurement : ea
Output : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.50


b. Skilled Labor 1 1.50 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.50
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (9 - 10 mt) 1 0.50


b. Concrete Vibrator 1 0.10
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Concrete Class "A" m³ 0.184


b. Reinforcing Steel Bar kg 7.59 Prices of materials are variable per Region/District
c. Plywood 1/2" x 4' x 8' - 2 uses pc 0.604 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Lumber - 2 uses bd-ft 7.15 project site. Refer to the Construction Materials Price
e. Portland Cement bag 0.775 Data established quarterly by Central Office Price
f. Pebble m³ 0.044 Monitoring Committee.
g. Reflectorized Paint, Marker L 0.20
h. # 16 Tie Wire (2% of RSB) kg 0.14
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.07

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea for 1.50 h.
To increase the output, additional equipment and labor may be added.

198 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(3)b Kilometer Post (Precast)


Unit of Measurement : ea
Output : 2.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.50


b. Skilled Labor 1 1.50 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.50
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (9 - 10 mt) 1 0.50


b. Concrete Vibrator 1 0.05
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Fabricated Kilometer Post ea 1.00


b. Concrete Class "A" m³ 0.095 Prices of materials are variable per Region/District
c. Reflectorized Paint, Marker L 0.20 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 2.00 ea for 1.50 h.
To increase the output, additional equipment and labor may be added.

199 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(4) Guide Post


Unit of Measurement : ea
Output per hour : 50.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Guide Post (Portable) ea 1.00


b. Post Reflector ea 1.00 Prices of materials are variable per Region/District
Miscellaneous (5% of Materials Cost) based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 50.00 ea/h.
To increase the output, additional equipment and labor may be added.

200 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 603(1) Cable Wire Guardrail


Unit of Measurement : m
Output per hour : 1.15 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 8 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. One Bagger Mixer 1 1.00


b. Concrete Vibrator 1 0.25
c. Water Truck/Pump (16000 L) 1 0.10
d. Cargo Truck (2 - 5 mt) 1 0.25
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.15 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Cement bag 4.18


b. Sand m³ 0.22 Prices of materials are variable per Region/District
c. Gravel m³ 0.43 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Guardrail Post set 0.27 project site. Refer to the Construction Materials Price
e. Galvanized Wire Rope (1.21 kg/m) kg 4.92 Data established quarterly by Central Office Price
f. Check Rope set 0.22 Monitoring Committee.
g. Hook Bolt ea 0.33
h. Anchor Bracket unit 0.11
i. Wire Mesh m² 0.11
j. Tension Fittings set 0.65

Miscellaneous (5% of Materials Cost)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.15 m/h.
To increase the output, additional equipment and labor may be added.

201 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 603(3)a Metal Guardrails (Metal Beam) including Concrete Post
Unit of Measurement : m
Output per hour : 4.20 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. One Bagger Mixer 1 0.50


b. Concrete Vibrator 1 0.50
c. Water Truck/Pump (16000 L) 1 0.05
d. Cargo Truck (9 - 10 mt) 1 0.25
Minor Tools (5 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.20 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Cement bag 0.33


b. Sand m³ 0.018 Prices of materials are variable per Region/District
c. Gravel m³ 0.036 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Metal Beam Guardrail m 1.00 project site. Refer to the Construction Materials Price
e. Plywood Marine, 1/2" thk x 4' x 8' - 4 uses pc 0.25 Data established quarterly by Central Office Price
f. Lumber - 4 uses bd-ft 8.00 Monitoring Committee.
g. Reinforcing Steel Bars, Grade 40 kg 4.00
h. Tie Wire (2% of RSB) kg 0.08
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08
j. Bolt, Nut & Washer 5/8" Ø x 9" pc 0.50
k. Bolt, Nut & Washer 5/8" Ø x 1" pc 2.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 4.20 m/h.
To increase the output, additional equipment and labor may be added.

202 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 603(3)b Metal Beam End Piece


Unit of Measurement : ea
Output per hour : 6.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (9 - 10 mt) 1 1.00


Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 6.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Metal Guardrail End Piece ea 1.00


Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 6.00 ea/h.
To increase the output, additional equipment and labor may be added.

203 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 603(4) Guardrail (Timber)


Unit of Measurement : m
Output per hour : 5.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 4 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (9 - 10 mt) 1 0.50


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 5.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Lumber, 8" x 8" x 5.5' Treated Post (Tanguile) bd-ft 14.67


b. Lumber, 3" x 8" Plank (Tanguile) - Untreated bd-ft 6.67 Prices of materials are variable per Region/District
c. Carriage Bolt, 1/2"Ø x 12" pc 1.60 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
Miscellaneous (5% of Materials Cost) project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.
Note: Exclude Excavation Works

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 5.00 m/h.
To increase the output, additional equipment and labor may be added.

204 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 604(1) Fencing (Barbed Wire) - Type I


Unit of Measurement : m
Output per hour : 18.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Welding Machine (300 A), Gas/Diesel Driven 1 0.10


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 18.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. 3-Strand Galvanized Barbed Wire, Ga 12.5 m 1.00


b. 50 mm x 50 mm x 6 mm Angle Bar kg 0.58 Prices of materials are variable per Region/District
c. Ga 9 Twisted Wire Fastener pc 0.39 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
Miscellaneous (2% of Materials Cost, Welding Rod & etc.) project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 18.00 m/h.
To increase the output, additional equipment and labor may be added.

205 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 604(2) Fencing (Chain Link Fence Fabric) - Type I


Unit of Measurement : m
Output per hour : 6.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Welding Machine (300 A), Gas/Diesel Driven 1 0.50


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 6.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Cyclone Wire 8' Ga 10 m 1.00


b. 38 mm x 38 mm x 4 mm Angle Bar kg 9.25 Prices of materials are variable per Region/District
c. Welding Rod (1 kg/2000 kg of Steel) kg 0.005 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 6.00 m/h.
To increase the output, additional equipment and labor may be added.

206 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 604(3) Fencing (Post) - Type I


Unit of Measurement : ea
Output : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.50


b. Skilled Labor 2 1.50 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.50
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. One Bagger Mixer 1 0.75


b. Bar Cutter, Single Phase 1 0.50
c. Bar Bender 1 0.50
d. Water Truck/Pump (16000 L) 1 0.05
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Cement bag 5.68


b. Sand m³ 0.30 Prices of materials are variable per Region/District
c. Gravel m³ 0.60 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Reinforcing Steel Bar kg 22.07 project site. Refer to the Construction Materials Price
e. # 16 Tie Wire (2% of RSB) kg 0.44 Data established quarterly by Central Office Price
f. Plywood 1/4" x 4' x 8' - 2 uses pc 1.94 Monitoring Committee.
g. Lumber - 2 uses bd-ft 28.67
h. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.29

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea for 1.50 h.
To increase the output, additional equipment and labor may be added.

207 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 604(4) Fencing (Gates) - (Height 3 m & Length 4.24 m)


Unit of Measurement : ea
Output : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 3.00


b. Skilled Labor 1 3.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 3.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Welding Machine (300 A), Gas/Diesel Driven 1 2


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. 50 mm Ø GI Pipe, Schedule 40 pc 5.00


b. Cyclone Wire Galvanized 10' Gauge 10 m 4.24 Prices of materials are variable per Region/District
c. 6 mm Ø Plain Bar kg 3.37 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
Miscellaneous (3% of Materials Cost, Gate Lock, Hinge & etc.) project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea for 3.00 h.
To increase the output, additional equipment and labor may be added.

208 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(1)a Danger/Warning Signs (60 cm Triangle)


Unit of Measurement : ea
Output per hour : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25


Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Portland Cement bag 0.48


b. Sand m³ 0.025 Prices of materials are variable per Region/District
c. Gravel m³ 0.050 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Form Lumber, Good - 4 uses bd-ft 8.00 project site. Refer to the Construction Materials Price
e. 3" Ø GI Pipe m 3.10 Data established quarterly by Central Office Price
f. Plate kg 2.00 Monitoring Committee.
g. Bolts, 5 mm Ø pc 12.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea/h.
To increase the output, additional equipment and labor may be added.

209 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(1)b Danger/Warning Signs (90 cm Triangle)


Unit of Measurement : ea
Output per hour : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25


Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Portland Cement bag 0.48


b. Sand m³ 0.025 Prices of materials are variable per Region/District
c. Gravel m³ 0.050 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Form Lumber, Good - 4 uses bd-ft 8.00 project site. Refer to the Construction Materials Price
e. 3" Ø GI Pipe m 3.10 Data established quarterly by Central Office Price
f. Plate kg 2.00 Monitoring Committee.
g. Bolts, 5 mm Ø pc 12.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea/h.
To increase the output, additional equipment and labor may be added.

210 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(2)a Regulatory Signs (60 cm Triangle)


Unit of Measurement : ea
Output per hour : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25


Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Portland Cement bag 0.48


b. Sand m³ 0.025 Prices of materials are variable per Region/District
c. Gravel m³ 0.050 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Form Lumber, Good - 4 uses bd-ft 8.00 project site. Refer to the Construction Materials Price
e. 3" Ø GI Pipe m 3.10 Data established quarterly by Central Office Price
f. Plate kg 2.00 Monitoring Committee.
g. Bolts, 5 mm Ø pc 12.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea/h.
To increase the output, additional equipment and labor may be added.

211 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(2)b Regulatory Signs (90 cm Triangle)


Unit of Measurement : ea
Output per hour : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25


Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Portland Cement bag 0.48


b. Sand m³ 0.025 Prices of materials are variable per Region/District
c. Gravel m³ 0.050 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Form Lumber, Good - 4 uses bd-ft 8.00 project site. Refer to the Construction Materials Price
e. 3" Ø GI Pipe m 3.10 Data established quarterly by Central Office Price
f. Plate kg 2.00 Monitoring Committee.
g. Bolts, 5 mm Ø pc 12.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea/h.
To increase the output, additional equipment and labor may be added.

212 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(2)c Regulatory Signs (60 cm Octagon)


Unit of Measurement : ea
Output per hour : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25


Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Portland Cement bag 0.48


b. Sand m³ 0.025 Prices of materials are variable per Region/District
c. Gravel m³ 0.050 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Form Lumber, Good - 4 uses bd-ft 8.00 project site. Refer to the Construction Materials Price
e. 3" Ø GI Pipe m 3.10 Data established quarterly by Central Office Price
f. Plate kg 2.00 Monitoring Committee.
g. Bolts, 5 mm Ø pc 12.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea/h.
To increase the output, additional equipment and labor may be added.

213 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(2)d Regulatory Signs (90 cm Octagon)


Unit of Measurement : ea
Output per hour : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25


Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Portland Cement bag 0.48


b. Sand m³ 0.025 Prices of materials are variable per Region/District
c. Gravel m³ 0.050 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Form Lumber, Good - 4 uses bd-ft 8.00 project site. Refer to the Construction Materials Price
e. 3" Ø GI Pipe m 3.10 Data established quarterly by Central Office Price
f. Plate kg 2.00 Monitoring Committee.
g. Bolts, 5 mm Ø pc 12.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea/h.
To increase the output, additional equipment and labor may be added.

214 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(3)a Informative Signs (12" x 24")


Unit of Measurement : ea
Output per hour : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25


Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Portland Cement bag 1.320


b. Sand m³ 0.073 Prices of materials are variable per Region/District
c. Gravel m³ 0.145 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Form Lumber, Good - 4 uses bd-ft 8.00 project site. Refer to the Construction Materials Price
e. 3" Ø GI Pipe m 3.10 Data established quarterly by Central Office Price
f. Plate kg 2.00 Monitoring Committee.
g. Bolts, 5 mm Ø pc 12.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea/h.
To increase the output, additional equipment and labor may be added.

215 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(3)b Informative Signs (12" x 48")


Unit of Measurement : ea
Output per hour : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25


Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Portland Cement bag 1.320


b. Sand m³ 0.073 Prices of materials are variable per Region/District
c. Gravel m³ 0.145 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Form Lumber, Good - 4 uses bd-ft 8.00 project site. Refer to the Construction Materials Price
e. 3" Ø GI Pipe m 3.10 Data established quarterly by Central Office Price
f. Plate kg 2.00 Monitoring Committee.
g. Bolts, 5 mm Ø pc 12.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea/h.
To increase the output, additional equipment and labor may be added.

216 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(3)c Informative Signs (18" x 24")


Unit of Measurement : ea
Output per hour : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25


Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Portland Cement bag 1.320


b. Sand m³ 0.073 Prices of materials are variable per Region/District
c. Gravel m³ 0.145 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Form Lumber, Good - 4 uses bd-ft 8.00 project site. Refer to the Construction Materials Price
e. 3" Ø GI Pipe m 3.10 Data established quarterly by Central Office Price
f. Plate kg 2.00 Monitoring Committee.
g. Bolts, 5 mm Ø pc 12.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea/h.
To increase the output, additional equipment and labor may be added.

217 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(3)d Informative Signs (18" x 48")


Unit of Measurement : ea
Output per hour : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25


Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Portland Cement bag 1.320


b. Sand m³ 0.073 Prices of materials are variable per Region/District
c. Gravel m³ 0.145 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Form Lumber, Good - 4 uses bd-ft 8.00 project site. Refer to the Construction Materials Price
e. 3" Ø GI Pipe m 3.10 Data established quarterly by Central Office Price
f. Plate kg 2.00 Monitoring Committee.
g. Bolts, 5 mm Ø pc 12.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea/h.
To increase the output, additional equipment and labor may be added.

218 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 606(1) Pavement Marking (Premix Reflectorized)


Unit of Measurement : m²
Output per hour : 10.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (2 - 5 mt) 1 0.05


Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 10.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Pavement Markings (White) L 1.00


Miscellaneous (5% of Materials Cost) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 10.00 m²/h.
To increase the output, additional equipment and labor may be added.

219 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 606(2)a Pavement Markings (Reflectorized Traffic Paint - White)


Unit of Measurement : m²
Output per hour : 10.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (2 - 5 mt) 1 0.05


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 10.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reflectorized Traffic Paint (White) L 1.00


Miscellaneous (5% of Materials Cost) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 10.00 m²/h.
To increase the output, additional equipment and labor may be added.

220 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 606(2)b Pavement Markings (Reflectorized Traffic Paint - Yellow)


Unit of Measurement : m²
Output per hour : 10.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (2 - 5 mt) 1 0.05


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 10.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reflectorized Traffic Paint (Yellow) L 1.00


Miscellaneous (5% of Materials Cost) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 10.00 m²/h.
To increase the output, additional equipment and labor may be added.

221 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 607(1) Reflective Pavement Studs


Unit of Measurement : ea
Output per hour : 10.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Diamond Drill, CP-8 with attachment 1 1.00


b. Cargo Truck (2 - 5 mt) 1 0.25
c. Air Compressor (15 - 35 cfm) 1 1.00
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 10.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reflective Stud Catcheye Flush Surface pc 1.00


180 mm x 140 mm (type depends on the req.) Prices of materials are variable per Region/District
b. Concrete Epoxy A & B L 0.012 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 10.00 ea/h.
To increase the output, additional equipment and labor may be added.

222 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 607(2) Reflective Pavement Studs (4" RPM)


Unit of Measurement : ea
Output per hour : 10.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 3 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Diamond Drill, CP-8 with attachment 1 1.00


b. Cargo Truck (2 - 5 mt) 1 0.25
c. Air Compressor (15 - 35 cfm) 1 1.00
Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 10.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reflective Stud Catcheye Raised Surface pc 1.00


100 mm x 100 mm (type depends on the req.) Prices of materials are variable per Region/District
b. Concrete Epoxy A & B L 0.012 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 10.00 ea/h.
To increase the output, additional equipment and labor may be added.

223 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 608(1) Furnishing and Placing Topsoil


Unit of Measurement : m³
Output per hour : 1.25 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Plate Compactor (5 hp) 1 1.00


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Topsoil m³ 1.05
Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.25 m³/h.
To increase the output, additional equipment and labor may be added.

224 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 608(2) Placing Topsoil


Unit of Measurement : m³
Output per hour : 1.25 m³

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Plate Compactor (5 hp) 1 1.00


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 m³
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.25 m³/h.
To increase the output, additional equipment and labor may be added.

225 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 609 Sprigging


Unit of Measurement : m²
Output per hour : 35.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Water Truck/Pump (16000 L) 1 0.25


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 35.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Sprigs m² 1.05
b. Fertilizer kg 0.10 Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 35.00 m²/h.
To increase the output, additional equipment and labor may be added.

226 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 610 Sodding


Unit of Measurement : m²
Output per hour : 25.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 8 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Water Truck/Pump (16000 L) 1 0.50


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 25.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Sods m² 1.05
Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 25.00 m²/h.
To increase the output, additional equipment and labor may be added.

227 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 611(1) Trees (Furnishing and Transplanting), 150 mm Ø or less


Unit of Measurement : ea
Output per hour : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (9 - 10 mt) 1 1.00


b. Backhoe (0.80 m³) 1 1.00
c. Water Truck/Pump (16000 L) 1 0.50
Minor Tools (10% of Labor Cost)

Note: Includes watering for three (3) months

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Trees (Delivered at Site) pc 1.00


b. Fertilizers kg 3.00 Prices of materials are variable per Region/District
c. Bamboo Pole pc 3.00 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Polyethylene Sheets m² 3.00 project site. Refer to the Construction Materials Price
e. Tie Wire kg 0.25 Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea/h.
To increase the output, additional equipment and labor may be added.

228 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 611(2) Trees (Transplanting), 150 mm Ø or less


Unit of Measurement : ea
Output per hour : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (9 - 10 mt) 1 1.00


b. Backhoe (0.80 m³) 1 1.00
c. Water Truck/Pump (16000 L) 1 0.50
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Fertilizers kg 3.00
b. Bamboo Pole pc 3.00 Prices of materials are variable per Region/District
c. Polyethylene Sheets m² 3.00 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Tie Wire kg 0.25 project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea/h.
To increase the output, additional equipment and labor may be added.

229 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 612(1) Reflectorized Thermoplastic Pavement Markings (White)


Unit of Measurement : m²
Output per hour : 25.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 6 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck/Delivery Truck (2 - 5 mt) 1 1.00


b. Applicator Machine 1 1.00
c. Kneading Machine 1 1.00
Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 25.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Thermoplastic Paint (White) bag 0.325


b. Glass Beads bag 0.033 Prices of materials are variable per Region/District
c. Primer L 0.120 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. LPG (50 kg) cyl 0.004 project site. Refer to the Construction Materials Price
e. LPG (12 kg) cyl 0.002 Data established quarterly by Central Office Price
f. Calsumine kg 0.125 Monitoring Committee.
Miscellaneous (5% of Materials Cost)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 25.00 m²/h.
To increase the output, additional equipment and labor may be added.

230 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 612(2) Reflectorized Thermoplastic Pavement Markings (Yellow)


Unit of Measurement : m²
Output per hour : 25.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 6 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck/Delivery Truck (2 - 5 mt) 1 1.00


b. Applicator Machine 1 1.00
c. Kneading Machine 1 1.00
Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 25.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Thermoplastic Paint (Yellow)) bag 0.325


b. Glass Beads bag 0.033 Prices of materials are variable per Region/District
c. Primer L 0.120 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. LPG (50 kg) cyl 0.004 project site. Refer to the Construction Materials Price
e. LPG (12 kg) cyl 0.002 Data established quarterly by Central Office Price
f. Calsumine kg 0.125 Monitoring Committee.
Miscellaneous (5% of Materials Cost)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 25.00 m²/h.
To increase the output, additional equipment and labor may be added.

231 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 613 Concrete Joint Sealant (Hot Poured Elastic and Cold-Applied Types)
Unit of Measurement : kg
Output per hour : 20.00 kg
.
Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)
A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 6 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Asphalt Kettle/Drum 1 1.00


Minor Tools (5% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 20.00 kg
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Blown Asphalt kg 1.05


Miscellaneous (5% of Materials Cost) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 20.00 kg/h.
To increase the output, additional equipment and labor may be added.

232 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 620(a) Chevron Signs (450 mm x 600 mm)


Unit of Measurement : ea
Output per hour : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25


Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Portland Cement bag 0.48


b. Sand m³ 0.025 Prices of materials are variable per Region/District
c. Gravel m³ 0.050 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Form Lumber, Good - 4 uses bd-ft 8.00 project site. Refer to the Construction Materials Price
e. 75 mm Ø GI Pipe m 3.25 Data established quarterly by Central Office Price
f. GI Flat Bar, 1 1/2"x1/8" kg 5.00 Monitoring Committee.
g. GI Bolts w/ Nuts & Washer, 5 mm Ø pc 3.00
h. GI Bolts w/ Nuts & Washer, 2 mm Ø pc 12.00
i. Sign Face, 3 mm thk Aluminum Sheet pc 2.00
j. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08
Miscellaneous (0.3% of Materials Cost)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea/h.
To increase the output, additional equipment and labor may be added.

233 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 620(b) Chevron Signs (600 mm x 800 mm)


Unit of Measurement : ea
Output per hour : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Skilled Labor 1 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
c. Unskilled Labor 2 1.00
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25


Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Portland Cement bag 0.48


b. Sand m³ 0.025 Prices of materials are variable per Region/District
c. Gravel m³ 0.050 based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
d. Form Lumber, Good - 4 uses bd-ft 8.00 project site. Refer to the Construction Materials Price
e. 75 mm Ø GI Pipe m 3.45 Data established quarterly by Central Office Price
f. GI Flat Bar, 1 1/2"x1/8" kg 5.00 Monitoring Committee.
g. GI Bolts w/ Nuts & Washer, 5 mm Ø pc 3.00
h. GI Bolts w/ Nuts & Washer, 2 mm Ø pc 12.00
i. Sign Face, 3 mm thk Aluminum Sheet pc 2.00
j. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08
Miscellaneous (0.2% of Materials Cost)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 1.00 ea/h.
To increase the output, additional equipment and labor may be added.

234 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(1)a Bio-Engineering Solutions (Coco-net)


Unit of Measurement : m²
Output per hour : 50.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 8 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Water Truck/Pump (16000 L) 1 0.25


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Erosion Control Net CGN 400 w/ 5 % wastage m² 1.05


(Price includes bamboo pegs) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 50.00 m²/h.
To increase the output, additional equipment and labor may be added.

235 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(1)b Bio-Engineering Solutions (Coco-net)


Unit of Measurement : m²
Output per hour : 50.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 8 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Water Truck/Pump (16000 L) 1 0.25


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Erosion Control Net CGN 700 w/ 5 % wastage m² 1.05


(Price includes bamboo pegs) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 50.00 m²/h.
To increase the output, additional equipment and labor may be added.

236 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(2)a Bio-Engineering Solutions (Coco-logs/Fascine)


Unit of Measurement : m
Output per hour : 15.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 8 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 15.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Coco Fiber Roll (CGR 200) m 1.05


(Price includes nylon ropes and live stakes) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.
`

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 15.00 m/h.
To increase the output, additional equipment and labor may be added.

237 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(2)b Bio-Engineering Solutions (Coco-logs/Fascine)


Unit of Measurement : m
Output per hour : 15.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 8 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 15.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Coco Fiber Roll (CGR 300) m 1.05


(Price includes nylon ropes and live stakes) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 15.00 m/h.
To increase the output, additional equipment and labor may be added.

238 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(3)a Bio-Engineering Solutions (Vegetation)


Unit of Measurement : m²
Output per hour : 62.50 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 2 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Hydroseeding Machine 1 1.00


b. Water Truck/Pump (16000 L) 1 1.00
(including maintenance time)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 62.50 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Grass Cover m² 1.05


(Price includes grass seeds, mulch, cocopeat Prices of materials are variable per Region/District
& binding agent for hydroseeding) based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 62.50 m²/h.
To increase the output, additional equipment and labor may be added.

239 Part H - Miscellaneous Structures


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 622(3)b Bio-Engineering Solutions (Vegetation)


Unit of Measurement : m²
Output per hour : 35.00 m²

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A. Labor

a. Construction Foreman 1 1.00


b. Unskilled Labor 8 1.00 Labor Rates are variable per Region/District based on
minimum wage as approved by DOLE. Refer to the
Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment

a. Water Truck/Pump (16000 L) 1 0.50


Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 35.00 m²
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials

a. Vetiver Grass System m² 1.05


(Price includes cocopeat fertilizer) Prices of materials are variable per Region/District
based on the prevailing unit prices in the locality which
include payment of local taxes and hauling cost to the
project site. Refer to the Construction Materials Price
Data established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%/9%/7%/6% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: The presented DUPA is based on a one (1) gang of labor and equipment with the specified output of 35.00 m²/h.
To increase the output, additional equipment and labor may be added.

240 Part H - Miscellaneous Structures


E. EQUIPMENT RENTAL RATES

Rental of equipment presented in the Detailed Unit Price Analysis (DUPA) are based on the prevailing
“Association of Carriers and Equipment Lessors, (ACEL) Inc.” rental rates approved for use by the DPWH
(Presently it is the 2014 ACEL Rates). Rental rates of equipment not indicated in the ACEL booklet shall be
taken from the rental rates prepared by the Bureau of Equipment. For simplicity in computation, the
operated rental rates are preferred over the bare rental rates as the former includes operator’s wages,
fringe benefits, fuel, oil, lubricants and equipment maintenance.

E.1 List of equipment adopted in the standard DUPA with make, model and capacity

FLYWHEEL
DESCRIPTION MODEL CAPACITY RENTAL RATE
HORSEPOWER
1. Earthmoving Equipment
1.1 Bulldozer D6H SERIES II PSDS/DD 165 PhP 3,379.00
1.2 Bulldozer w/ Ripper D6H SERIES II PSDS/DD 165 PhP 3,885.85
1.3 Payloader LX80-2C 1.50 m3/1.95 yd3 110 PhP 1,733.00
1.4 Motorized Road Grader G710A 140 PhP 2,173.00
1.5 Road Grader w/ Scarifier G710A 140 PhP 2,824.90
2. Compaction Equipment
2.1 Pneumatic Tire Roller 9-WHL, 9.00X20, 4PR 10 mt 107 PhP 561.00
2.2 Vibratory Roller SD100DC 10 mt 125 PhP 1,846.00
2.3 Tandem Steel Roller CC421 10.10 mt 123.40 PhP 1,652.00
2.4 Plate Compactor 400-500 Gasoline Engine 5 PhP 123.00
3. Lifting Equipment
3.1 Crawler Crane All Models 36-40 mt 190 PhP 1,902.00
3.2 Truck Mounted Crane All Models 31-35 mt 238 PhP 1,861.00
3.3 Truck Mounted Crane All Models 41-45 mt 246 PhP 2,606.00
4. Excavating Equipment
4.1 Backhoe SE 130 LC-2 0.80 m3/1.04 yd3 99 PhP 1,537.00
3 3
4.2 Backhoe w/ Breaker SE 130 LC-2 0.80 m /1.04 yd 99 PhP 1,998.10
4.3 Backhoe, Wheel Mounted PW60N-1 0.28 m3/0.37 yd3 50 PhP 922.00
5. Foundation Equipment
5.1 Vibro Hammer DPD600T Hydraulic Pile Driver 60 ton 201 PhP 2,123.00
6. Asphalting Equipment
6.1 Asphalt Distributor ROSCO/5 ton 3000 USG 100 PhP 936.00
6.2 Asphalt Paver NF220BIIVDM 80 PhP 1,833.00
7. Concreting Equipment
7.1 Concrete Screeder Wacker Truss Screed 5.50 PhP 545.00
7.2 Concrete Paver COMMANDER III, FOUR-TRACK PhP 6,765.00
7.3 One Bagger Mixer 4-6 ft3/min PhP 172.00
7.4 Transit Mixer All Models 5-6 yd3 175 PhP 1,318.00
8. Hauling Equipment
8.1 Dump Truck All Models 12 yd3 290 PhP 1,420.00
8.2 Cargo/Service Truck All Models 2-5 mt 160 PhP 783.00
8.3 Boom Truck All Models 2-5 mt 160 PhP 1,017.90
8.4 Cargo/Service Truck All Models 9-10 mt 270 PhP 1,212.00
8.5 Water Truck/Pump All Makes 16000 L 360 PhP 2,450.00
9. Air Equipment
9.1 Air Compressor All Models 356-450 cfm 130 PhP 965.00
9.2 Air Compressor All Models 161-185 cfm 69 PhP 502.00
9.3 Air Compressor All Models 15-35 cfm 20 PhP 205.00
9.4 Diamond Drill CP-8 PhP 201.25
9.5 Jackhammer PhP 150.00
9.6 Pneumatic Drilling Machine PhP 170.00

247
OUTPUT/DISCHARGE SOLID SIZE FLYWHEEL
DESCRIPTION RENTAL RATE
(lpm) CAPACITY (mm) HORSEPOWER
10. Pumping Equipment
10.1 Water Pump, 100 mm suction Ø 2,667 50 16 PhP 266.25
FLYWHEEL
DESCRIPTION MODEL AMPERE RENTAL RATE
HORSEPOWER
12. Shop Equipment
12.1 Welding Machine Gas/Diesel Driven 300 48 PhP 371.00
FLYWHEEL
DESCRIPTION MODEL CAPACITY RENTAL RATE
HORSEPOWER
13. Special Support Equipment
13.1 Chainsaw HUSQVARNA 2100 CD with CR22, 7 ft Reach, 9 in Standard Blade PhP 75.36
14. Miscellaneous Equipment
14.1 Concrete Vibrator Flexible Shaft Type 2" Head Ø with 5 Amperes Gasoline Drive Unit PhP 91.25
14.2 Concrete Saw 14" Blade Ø with 4 3/4" Cutting Depth 7.50 PhP 32.63
14.3 Bar Cutter 25 mm Maximum Rebar Ø (Grade 40), Single Phase PhP 219.75
14.4 Bar Bender 25 mm Maximum Rebar Ø, Three Phase PhP 351.50
15. Plants
15.1 Asphalt Concrete Plant Complete with: Cold Feed System, bins, feeder and collecting PhP 4,286.63
conveyors. Drying and Burner System, feed conveyors drum and
fully modulating burner. Fuel feed system. Screening-Weighing-
Mixing System, hot elevator, vibrating screen, hot bins, weighing
scale and twinshaft pugmill mixer. Dust collection and filler feeding
system, bag filter and exhaust fan. Thermal Hot Oil System, delivery
pump and heater and Computerized Plant Control System.
15.2 Concrete Batch Plant Complete with: cement silo and screw conveyor system. Water and PhP 1,759.50
supply system. Aggregate storage bins with vibrators and conveyors
system. Weigh hopper with electronic loadcell for aggregates,
cement, water and admixture. Central twinshaft mixer. Hydraulic
System and Computerized Plant Control System.
18. Others
18.1 Power Broom, Towed Type With Engine 2 m wide 6-30 km/h Sweeping Capacity PhP 130.54
18.2 Hydroseeding Machine PhP 952.00
18.3 Applicator Machine PhP 93.75
18.4 Kneading Machine PhP 187.50
18.5 Drop Hammer PhP 200.00
18.6 Cutting Outfit PhP 45.45
18.7 Steel Wheel w/ Nylon Rope PhP 300.00
18.8 Improvised Bamboo w/ Bucket PhP 200.00
18.9 Asphalt Kettle/Drum PhP 10.00

248

You might also like