Introduction Time Management
Introduction Time Management
logic.
External dependencies: involve relationships between project
1. Find all of the activities that start at node 1. Draw their finish
nodes and draw arrows between node 1 and those finish
nodes. Put the activity letter or name and duration estimate on
the associated arrow.
2. Continuing drawing the network diagram, working from left to
right. Look for bursts and merges. Bursts occur when a single
node is followed by two or more activities. A merge occurs
when two or more nodes precede a single node.
3. Continue drawing the project network diagram until all
activities are included on the diagram that have dependencies.
4. As a rule of thumb, all arrowheads should face toward the
right, and no arrows should cross on an AOA network diagram.
Precedence Diagramming Method (PDM)
In this method activities are represented by boxes, and:
Arrows show relationships between activities
Used by project management software
D=7 5 F=2
a. How many paths are on this network diagram?
b. How long is each path?
c. Which is the critical path?
d. What is the shortest amount of time needed to complete this project?
Determining the Critical Path
More on the Critical Path
If one of more activities on the critical path takes longer than
planned, the whole project schedule will slip unless
corrective action is taken:
Misconceptions - The following ARE TRUE:
There can be more than one critical path if the lengths of
Also:
It is important to update project schedule information
The critical path may change as you enter actual start and
finish dates
If you know the project completion date will slip, negotiate
Example:
PERT weighted average =
(8 workdays + 4 X 10 workdays + 24 workdays) / 6 = 12 days
where 8 = optimistic time, 10 = most likely time, and 24 = pessimistic time
Controlling Changes to Project Schedule
incentives
discipline
negotiation
Using Software in Time Management