Testing & Commissioning Checklist For Fire Pump

The checklist summarizes the key steps for testing and commissioning fire pumps. It includes: 1. Visual checks of the pump installation and components to ensure proper installation and no damage. 2. Electrical tests to confirm correct power supply, voltages, and pump rotation directions. Current and voltage readings are also taken. 3. Functional tests including operating float switches, simulated BMS signals, pump performance tests, and auto-changeover. 4. Recording test results on a pump data sheet for consultant approval.

Uploaded by

Oanh Nguyen
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
80% found this document useful (10 votes)
11K views

Testing & Commissioning Checklist For Fire Pump

The checklist summarizes the key steps for testing and commissioning fire pumps. It includes: 1. Visual checks of the pump installation and components to ensure proper installation and no damage. 2. Electrical tests to confirm correct power supply, voltages, and pump rotation directions. Current and voltage readings are also taken. 3. Functional tests including operating float switches, simulated BMS signals, pump performance tests, and auto-changeover. 4. Recording test results on a pump data sheet for consultant approval.

Uploaded by

Oanh Nguyen
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

PROJECT NAME & LOGO

CHECK LIST FOR:


TESTING & COMMISSIONING OF FIRE PUMPS SET Ref. No:
SUBCONTRACTOR CONTRACTOR Rev. No: 00
X
Page : 1 of 2
SECTION OF WORK: PLUMBING LOCATION:
LEVEL: WIR No.:
STAGE ITEM Checked by Checked Date
by

Consult
S/C CONT
ant
Check that the fire pumps & its components were erected properly
as per approved shop drawings & manufacturer’s instructions or as
per site condition agreed with the Consultant.
Ensure that all components & parts are cleaned & protected with no
visible signs of damage.
Visual Check all supports, fixings & guide rails are tight, plumb & correctly
finished & spaced.
Check the sump pumps capacity was as per the approved material.
Check all valves & gate valves installed in the discharge manifold
as per approved detail.
Ensure lifting hook is properly installed.
1. Ensure power supply is available in the fire pumps & control
panels.
2. Ensure all electrical cables & electrical components
installation has been approved by the consultant.
3. Ensure supply voltage for the fire pumps are as per the
requirement, prior to starting the pumps.
Testing & commissioning

4. Select the selector switch in the controller & ensure pumps


are rotating in correct direction.
5. Take the pumps current & voltage using multi meter.
Ampere : Voltage : (Electric Pump)
Ampere : Voltage : (Diesel Pump)
Ampere : Voltage : (Jockey Pump)
6. Check operation of Float Switches shall be in accordance
to sequence of operation.
7. Check BMS Signals are simulated & change in status of
the output signals. Use continuity tester.
8. Check auto-changeover to equalize the run time.
9. Check the performance of the pumps by measuring the
liquid quantity pumped from the container over a given period
of time.
10. Record all test results on the Pumps Data Sheet (Page 1 of
2). Results shall be approved by the consultant.

For S/C Date: FOR CONTRACTOR Date: For Cons. Rep.: Date:
QA/QC: QA/QC:

Name: Sign: Name: Sign: Name: Sign: