The trio of estimates incorporated into the formula are derived from experienced from other
projects. The advice of people skilled in a project area is taken into consideration. In addition,
the concept of “best guess” is also brought into play. The formula in CPM standing alone is:
E = (a + 4m + b) / 6
Time estimation developed when CPM is integrated with PERT results in essentially the
same based three-point analysis, although it uses slightly different terminology:
The formula utilized in CPM when PERT is incorporated into the process is:
In the final analysis, the integration of PERT in CPM lessens the reliance on what commonly
is referenced as “best guess” in the stand-alone CPM analysis. The hope is that by integrating
PERT into CPM, better time calculations are ensured for each individual task that comprise
the overall project to be managed. Project scheduling will necessarily always involve some
level of speculation; this structure is designed to limit it.