Construction Schedule For Construction of Common User Facility For Factory/Warehouse at Kwagyi, Sekyere Central District, Ashanti Region

The construction schedule outlines the tasks and timeline for constructing a common user facility comprising an administration block and canteen block from February 2020 to October 2020. Key tasks include site clearance, foundation works, structural works such as column casting, roof construction, and finishing works like plastering, tiling and painting. The administration block will take 90 days to complete while the canteen block will be finished in 80 days. The overall project duration is 235 days.

Uploaded by

Nana Barima
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
89 views2 pages

Construction Schedule For Construction of Common User Facility For Factory/Warehouse at Kwagyi, Sekyere Central District, Ashanti Region

The construction schedule outlines the tasks and timeline for constructing a common user facility comprising an administration block and canteen block from February 2020 to October 2020. Key tasks include site clearance, foundation works, structural works such as column casting, roof construction, and finishing works like plastering, tiling and painting. The administration block will take 90 days to complete while the canteen block will be finished in 80 days. The overall project duration is 235 days.

Uploaded by

Nana Barima
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

CONSTRUCTION SCHEDULE FOR CONSTRUCTION OF COMMON USER FACILITY FOR FACTORY/WAREHOUSE AT KWAGYI,SEKYERE CENTRAL DISTRICT,ASHANTI REGION

Task Name Duration Start Finish February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 Nove
31 03 06 09 12 15 18 21 24 27 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 30 03 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20 23 26 29 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 30 03 06 09 12 15 18 21 24 27 30 02
CONSTRUCTION & COMPLETION OF COMMON USER FACILITY FOR FACTORY & 235 days Sat 01-02-20 Sat 31-10-20
WAREHOUSE AT KWAGYI,SEKYERE CENTRAL DISTRICT,ASHANTI REGION (LOT 1)
ADMINISTRATION BLOCK( Civil & MEP works) 90 days Sat 01-02-20 Fri 15-05-20
Preliminaries 3 days Sat 01-02-20 Tue 04-02-20
Site clearance and Earthworks 3 days Wed 05-02-20 Fri 07-02-20
Setting out 2 days Sat 08-02-20 Mon 10-02-20
Excavation 2 days Tue 11-02-20 Wed 12-02-20
Concrete blinding works 1 day Thu 13-02-20 Thu 13-02-20
Reinforcement works for Column bases 2 days Fri 14-02-20 Sat 15-02-20
Formworks 2 days Mon 17-02-20 Tue 18-02-20
Casting of Column bases 3 days Wed 19-02-20 Fri 21-02-20
Casting of foundation beds 2 days Sat 22-02-20 Mon 24-02-20
Laying of sleeper walls 3 days Tue 25-02-20 Thu 27-02-20
Hardcore filling & Compaction 2 days Fri 28-02-20 Sat 29-02-20
First fix (Plumbing) 3 days Mon 02-03-20 Wed 04-03-20
Reinforcement for ground beams & mesh 4 days Thu 05-03-20 Mon 09-03-20
Formworks for Oversite concrete 3 days Tue 10-03-20 Thu 12-03-20
Casting of Oversite concrete 5 days Fri 13-03-20 Wed 18-03-20
Reinforcement works for ground floor Columns 2 days Thu 19-03-20 Fri 20-03-20
Formwork for ground floor Columns 3 days Sat 21-03-20 Tue 24-03-20
Casting of ground floor Columns 3 days Wed 25-03-20 Fri 27-03-20
Laying of block walls 8 days Sat 28-03-20 Mon 06-04-20
First fix(Electrical) 2 days Tue 07-04-20 Wed 08-04-20
Formwork for roof beams 3 days Thu 09-04-20 Sat 11-04-20
Reinforcement works for roof beams 3 days Mon 13-04-20 Wed 15-04-20
Casting of roof beams concrete 3 days Thu 16-04-20 Sat 18-04-20
Laying of gable walls 4 days Mon 20-04-20 Thu 23-04-20
Roof carcassing works 4 days Fri 24-04-20 Tue 28-04-20
Fixing of roof covering material 4 days Wed 29-04-20 Sat 02-05-20
Ceiling works 5 days Mon 04-05-20 Fri 08-05-20
Internal & External Plastering works 8 days Tue 07-04-20 Wed 15-04-20
Fixing of internal floor tiles 8 days Thu 16-04-20 Fri 24-04-20
Painting works (Skimming works) 7 days Thu 16-04-20 Thu 23-04-20
Installation of doors, windows & building fabric sundries 6 days Fri 24-04-20 Thu 30-04-20
Painting works (final coating) 7 days Fri 01-05-20 Fri 08-05-20
Second fix works(MEP fixtures) 6 days Sat 09-05-20 Fri 15-05-20
CANTEEN BLOCK( Civil & MEP works) 80 days Wed 05-02-20 Thu 07-05-20
Setting out 2 days Sat 08-02-20 Mon 10-02-20
Excavation 3 days Tue 11-02-20 Thu 13-02-20
Concrete blinding of foundation 1 day Fri 14-02-20 Fri 14-02-20
Reinforcement works for Column bases 2 days Sat 15-02-20 Mon 17-02-20
Formworks 2 days Tue 18-02-20 Wed 19-02-20
Casting of Column bases 3 days Thu 20-02-20 Sat 22-02-20
Casting of foundation beds 3 days Mon 24-02-20 Wed 26-02-20
Laying of sleeper walls 3 days Thu 27-02-20 Sat 29-02-20
Hardcore filling & Compaction 2 days Mon 02-03-20 Tue 03-03-20
First fix (Plumbing) 2 days Wed 04-03-20 Thu 05-03-20
Reinforcement for ground beams & mesh 3 days Fri 06-03-20 Mon 09-03-20
Formworks for Oversite concrete 2 days Tue 10-03-20 Wed 11-03-20
Casting of Oversite concrete 3 days Thu 12-03-20 Sat 14-03-20
Reinforcement works for ground floor Columns 3 days Mon 16-03-20 Wed 18-03-20
Formwork for ground floor Columns 2 days Thu 19-03-20 Fri 20-03-20
Casting of ground floor Columns 3 days Sat 21-03-20 Tue 24-03-20
Laying of block walls 3 days Mon 16-03-20 Wed 18-03-20
First fix(Electrical) 2 days Thu 19-03-20 Fri 20-03-20
Formwork for roof beams 3 days Sat 21-03-20 Tue 24-03-20
Reinforcement works for roof beams 2 days Wed 25-03-20 Thu 26-03-20
Casting of roof beams concrete 3 days Fri 27-03-20 Mon 30-03-20
Laying of gable walls 3 days Tue 31-03-20 Thu 02-04-20
Roof carcassing works 4 days Fri 03-04-20 Tue 07-04-20
Fixing of roof covering material 4 days Wed 08-04-20 Sat 11-04-20
Ceiling works 4 days Mon 13-04-20 Thu 16-04-20
Internal & External Plastering works 4 days Fri 17-04-20 Tue 21-04-20
Fixing of internal floor tiles 4 days Wed 22-04-20 Sat 25-04-20
Painting works (Skimming works) 2 days Mon 27-04-20 Tue 28-04-20
Installation of doors, windows & building fabric sundries 3 days Wed 29-04-20 Fri 01-05-20
Painting works (final coating) 5 days Sat 02-05-20 Thu 07-05-20
STEEL WAREHOUSE & FACTORY WORKS(CIVIL&MEP WORKS) 146 days Tue 31-03-20 Wed 16-09-20
Factory washrooms/offices works 100 days Tue 31-03-20 Fri 24-07-20
Setting out works for factory/warehouse & in-house offices 2 days Tue 31-03-20 Wed 01-04-20
Excavation 3 days Thu 02-04-20 Sat 04-04-20
Concrete blinding of foundation 2 days Mon 06-04-20 Tue 07-04-20
Reinforcement works for Column bases 3 days Wed 08-04-20 Fri 10-04-20
Formworks 2 days Sat 11-04-20 Mon 13-04-20
Casting of Column bases & foundation beds 5 days Tue 14-04-20 Sat 18-04-20
Laying of sleeper walls 2 days Mon 20-04-20 Tue 21-04-20
Hardcore filling & Compaction 3 days Wed 22-04-20 Fri 24-04-20
First fix (Plumbing) 2 days Sat 25-04-20 Mon 27-04-20
Reinforcement for ground beams & mesh 3 days Tue 28-04-20 Thu 30-04-20
Formworks for Oversite concrete 2 days Fri 01-05-20 Sat 02-05-20
Casting of Ground beams & Oversite concrete 6 days Mon 04-05-20 Sat 09-05-20
Reinforcement works for Ground floor columns 2 days Mon 11-05-20 Tue 12-05-20
Formwork for Ground floor columns 2 days Wed 13-05-20 Thu 14-05-20
Casting of Ground floor columns 2 days Fri 15-05-20 Sat 16-05-20
Formworks for first floor slab & beams 3 days Mon 18-05-20 Wed 20-05-20
Reinforcement for first floor slab&beams 3 days Thu 21-05-20 Sat 23-05-20
First fix (Plumbing & Electrical) 2 days Mon 25-05-20 Tue 26-05-20
Casting of first floor slab & beams concrete 5 days Wed 27-05-20 Mon 01-06-20
Formworks for staircase 1 day Tue 02-06-20 Tue 02-06-20
Reinforcement works for staircase 1 day Wed 03-06-20 Wed 03-06-20
Casting of staircase concrete 1 day Thu 04-06-20 Thu 04-06-20

Page 1
CONSTRUCTION SCHEDULE FOR CONSTRUCTION OF COMMON USER FACILITY FOR FACTORY/WAREHOUSE AT KWAGYI,SEKYERE CENTRAL DISTRICT,ASHANTI REGION
Task Name Duration Start Finish February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 Nove
31 03 06 09 12 15 18 21 24 27 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 30 03 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20 23 26 29 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 30 03 06 09 12 15 18 21 24 27 30 02
Reinforcement for first floor columns 2 days Fri 05-06-20 Sat 06-06-20
Formwork for first floor columns 1 day Mon 08-06-20 Mon 08-06-20
Casting of first floor columns 4 days Tue 09-06-20 Fri 12-06-20
Formwork for roof beams & slab 1 day Sat 13-06-20 Sat 13-06-20
Reinforcement works for roof beams & slab 3 days Mon 15-06-20 Wed 17-06-20
Casting of roof beam & slab 5 days Thu 18-06-20 Tue 23-06-20
Laying of block walls at ground, first floor & roof copings 6 days Wed 24-06-20 Tue 30-06-20
First fix(Electrical) 2 days Wed 01-07-20 Thu 02-07-20
Ceiling works 5 days Fri 03-07-20 Wed 08-07-20
Internal & External Plastering works 4 days Wed 01-07-20 Sat 04-07-20
Fixing of internal floor tiles 3 days Mon 06-07-20 Wed 08-07-20
Painting works (Skimming works) 4 days Thu 09-07-20 Mon 13-07-20
Installation of doors, windows & building fabric sundries 3 days Tue 14-07-20 Thu 16-07-20
Painting works (final coating) at both floors 4 days Fri 17-07-20 Tue 21-07-20
Second fix works(MEP fixtures) at both floors 3 days Wed 22-07-20 Fri 24-07-20
Steel warehouse&factory works 80 days Tue 16-06-20 Wed 16-09-20
Excavation 3 days Thu 02-04-20 Sat 04-04-20
Concrete blinding of foundation 3 days Wed 08-04-20 Fri 10-04-20
Reinforcement works for Column bases 4 days Sat 11-04-20 Wed 15-04-20
Formworks 5 days Tue 14-04-20 Sat 18-04-20
Casting of Column bases & foundation beds 6 days Mon 20-04-20 Sat 25-04-20
Laying of sleeper walls 5 days Wed 22-04-20 Mon 27-04-20
Hardcore filling & Compaction 3 days Sat 25-04-20 Tue 28-04-20
First fix (Plumbing,Electrical & Mechanical conduits) 4 days Tue 28-04-20 Fri 01-05-20
Reinforcement for ground beams & mesh 4 days Fri 01-05-20 Tue 05-05-20
Formworks for Oversite concrete 3 days Mon 04-05-20 Wed 06-05-20
Casting of Ground beams & Oversite concrete 6 days Mon 11-05-20 Sat 16-05-20
Assembling,installation of column base plates to starter columns 9 days Mon 18-05-20 Wed 27-05-20
Fabricating,assembling& fixing of I-Section columns to base plates 9 days Thu 28-05-20 Sat 06-06-20
Fabrication,assembling & fixing of I-Section beams to column members 10 days Mon 08-06-20 Thu 18-06-20
Fabricating,assembling & fixing of Universal beam rafters to I-Section supports 10 days Fri 19-06-20 Tue 30-06-20
Fabricating,assembling & fixing of Purlins & Angle iron to rafters respectively 10 days Wed 01-07-20 Sat 11-07-20
Assembling & fixing of Eave beams and cable ties 8 days Mon 13-07-20 Tue 21-07-20
Assembling 7 fixing of Cladding rails & Angle irons respectively 14 days Wed 22-07-20 Thu 06-08-20
Fixing of Roofing coverings 14 days Fri 07-08-20 Sat 22-08-20
Fixing of o.6mm Cladding material 15 days Mon 24-08-20 Wed 09-09-20
Fixing of metal gate 3 days Thu 10-09-20 Sat 12-09-20
Second fix works(MEP fixtures) 3 days Mon 14-09-20 Wed 16-09-20
EXTERNAL WORKS(CIVIL WORKS) 60 days Mon 24-08-20 Sat 31-10-20
External lighting works 12 days Mon 24-08-20 Sat 05-09-20
External Generator Plant works 9 days Mon 07-09-20 Wed 16-09-20
External concrete drainage works 10 days Thu 17-09-20 Mon 28-09-20
Hard & Soft Landscaping works 14 days Tue 29-09-20 Wed 14-10-20
Fencewall & retaining walls works 12 days Thu 15-10-20 Wed 28-10-20
HANDING OVER 6 days Mon 26-10-20 Sat 31-10-20
Site cleaning 3 days Mon 26-10-20 Wed 28-10-20
Preparation for handing over 1 day Thu 29-10-20 Thu 29-10-20
Handing over 1 day Sat 31-10-20 Sat 31-10-20