Quality Assurance Manual: Check List For Projects Activity
Quality Assurance Manual: Check List For Projects Activity
DOC No :
URCC/SIMPL/QMS/CL/01, Construction of Shell Fuel Station (NTI/VA)
Rev-00 Date : 14-06-18
Page 1 of 31 Check List for Projects Activity
Sl. No ACTIVITY
1. Earth work
2. Anti termite treatment
4. Foundation PCC
5. Reinforced steel
6. Shuttering
7. Foundation concrete
8 Block work
9 Flooring PCC
10 Earth filling and ramming
11 Structural steel
12 Roof slab
13 Joineries fixing (steel)
14 Plastering
15 Internal plumbing works
16 External plumbing works
17 RCC flooring
18 Painting
19 Tiles flooring
20 HVAC System
21 Electrical System
22 Pile Foundation
23 Paver Block and Kerb Stone Laying
24 Road Work
25 Granite/Marble Flooring work
26 False Ceiling work
27 Water Proofing work
28 Epoxy Flooring
QUALITY ASSURANCE MANUAL
DOC No :
URCC/SIMPL/QMS/CL/01, Construction of Shell Fuel Station (NTI/VA)
Rev-00 Date : 14-06-18
Page 2 of 31 Check List for Projects Activity
EARTH WORK
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
No
a Studying levels ,coordinates and depth of
excavation
b Proper barricade Provisions & guarding
works and marking tools availability
c Making the pillars for marking and
measurements checking
d Whether pre level record is prepared
e Pit alignment
f Ramp/Berms provision if required
g Dewatering requirements if any
h Dewatering materials availability
i Blasting requirements if any
j Arrangements for blasting works
k Location of dumping area and roads and
leveling equipments
l Check the level of excavation still required
for addl. Depth and arrival
m Check any disturbance in marking pillars
n Before and after Blasting of rock check the
safety aspect
O Whether pour card is prepared
Comments if any:
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
No
1. Check that earthworks for the area to be
treated are completed
2. Check that loose earth is removed and
area is clean.
3. Has Roding/Channeling been completed as
specified, where applicable?
4. Check that chemicals used are as per
specifications.
5. Check that concentration of chemical
emulsion is as per specification.
6. Check that spraying equipment like pumps
etc. are in good working condition.
7. Check that rate of application of chemical is
specified.
8. Check for uniform application of chemical
emulsion.
Comments if any:
FOUNDATION PCC
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
NO
a Whether the checklist of Earth work
available
b Water, Material availability nearby
location
including tools and consumables
c Dewatering requirements if any
Comments if any:
REINFORCEMENT STEEL
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
NO
Comments if any:
SHUTTERING WORKS
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
NO
Taking the required shuttering plan at
a workplace
Check the availability of shuttering
b materials runners planks in yard
Check the required materials
c conveyance from yard to work place
Whether surface of materials done with
d oiling
Check the working condition of
e materials
Whether bends are removed in sheets
f and other materials
Whether adequate nails and binding
g wire are available
Whether the nails are removed from
h runners and planks
Comments if any:
FOUNDATION CONCRETE
STRUCTURE
SL. YE
CHECKPOINTS NO NA REMARKS
No S
a Check the Measurements and level Structure
Comments if any:
BLOCK WORK
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
No
a Proper water facility available
b Cement, bricks, sand , tools and if
necessary scaffolding arrangement also
check the availability nearby location
c Hacking RCC surface in joints of
Brickwork and RCC column
d Mark openings as per requirement
Comments if any:
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
No
a Taking the required pre levels to meet-
out the works
b Check the availability of Machineries
related with filling and ramming works
c Check the required materials conveyance
from site stocking yard
d Whether surface of grid done with proper
compaction
e Check the working condition of
machineries
f Whether core-cutter and compaction
factor tests are done
g Whether the operator of machineries
having good knowledge in operations
h Whether the adequate water sources are
available for the continuation of works
i Whether the surface is well consolidated
for doing ramming & rolling
j Whether the soil filled-up with layer by
layer or by randomly
K Ensure the de-shuttered materials
conveyed to other section or yard
Comments if any:
FLOORING PCC
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
NO
a Whether the checklist of Filling
available
b Water, Material availability nearby
location including tools and
consumables
c Clearing the area
Comments if any:
STRUCTURAL STEEL
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
No
a Check the job number and specification
b Check the approved shop drawing availability
c Check the template availability
d Whether all members are marked with code
e Check the working condition of welding machines,
grinding machine and drillers
f Check quality of welding rods and thickness of
welding
g Check the splicing of flanges are provided as per
IS
h Whether plain grinding is done
i Check the correctness of drilling holes which
made by drillers only
k Check the availability of all machineries/tools
and consumables for erection
Comments if any:
ROOF SLAB
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
No
a Check the measurements and level
b Water, Material availability nearby location
including tools especially Tarpaulin and
consumables and staging materials if any required
c Check the bar bending schedule& whether rods
are tied-up properly
d Whether extra rods/laps/chairs and proper cover
are provided
e Whether electrical conduits are placed
f Check the shuttering level, alignment & oiling the
surface
g Check the supporting props and bracing
h Check the working condition of mixer machine and
vibrators
i Whether inserts/openings/Expansion joint pad are
provided properly
j During the concrete, electrical conduits to be kept
with proper tying or not making arrangement to
provide curing bund
k Whether cement slurry is sprinkled over existing
RCC surface
l Check the Mixing/Pouring and vibrating
m Check the required thickness/slope of concrete
and finishing
n Check the arrangements for taken test cubes
o Whether Pour card is prepared
p Making arrangement to provide curing bund
Comments if any:
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
No
a
Check proper gauge of materials used for
frame and shutters
b Check the Frames are painted with
Primary coat
Comments if any:
PLASTERING WORK
STRUCTURE
Comments if any:
STRUCTURE
SL.
CHECK POINTS YES NO NA REMARKS
No
Comments if any:
STRUCTURE
SL.
CHECK POINTS YES NO NA REMARKS
No
Check the availability of client issue drawing, If not,
a ensure the availability of line - sketch by URC
Comments if any:
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
No
Check surface cleaning
a
Water, Material availability nearby location
b including tools and consumables
Comments if any:
PAINTING WORK
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
No
Study the approved make, mixing
a
procedure and number of coats
Check availability of paints, tools and
b consumables and if any scaffolding
required
c Check the safety aspects are provided
Comments if any:
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
No
a Study the mix ratio and thickness of base mortar
Comments if any:
STRUCTURE
SL.
CHECK POINTS YES NO NA REMARKS
No
Comments if any:
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
No
a Equipment mounting & setting
e Lubrication of equipment
f Direction of rotation
l Operation of equipment
Comments if any:
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
No
a All wiring and lights installed As per
Specification
b All electrical equipment and lighting supplied
from a protected circuit
c Source of supply identified.
d Switchboard readily accessible.
Comments if any:
PILE FOUNDATIONS
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
No
a Check the grid line marking and pile point
marking as per the drawing
b Check the soil investigation report
c Check the structural drawing for pile size
,details of reinforcement (if applicable) and
depth of the pile
d Whether adequate machineries are arranged
for the pile driving?
e Whether the sequence of piling is finalized as
per the soil condition?
f Check the erection of temporary casing
g Whether drilling mud (Pentonite suspension)
arranged for stabilizing the bore hole sides?
h Check the hard strata of pile foundations
i Whether cleaning is done satisfactorily for the
bore hole?
j Is the reinforcement cage prepared as per
specification?
k Is the reinforcement cage inserted properly
with suitable cover
L Whether the concrete prepared as per
specification and proper slump maintained?
m Is the method of pouring concrete as
specified?
n Is the pile concreted adequately &
reinforcement projecting sufficiently above the
cut off level
o Check for any deviation from the original
location of pile
p Check depth of the pile Driven
Comments if any:
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
No
a Has the surface been prepared as per level /
slope specified?
b Has the surface been compacted to the
required degree?
c Has bedding sand been spread to the
required thickness?
d Are the pavers as per specified type and
make?
e Are the pavers tested for specified
compressive and crushing strength ?
f Are the pavers placed with 2-4 mm gap in
between?
g Has the compaction been checked with heavy
duty plate compactor?
h Are the gaps filled with filling sand &
compactor applied over that?
i Has the surface been cleaned?
j Is the finished level /slope as specified?
k KERB STONE
Check the Design pattern, levels etc for kerb
stone should be with approved drawings
l Has Surveyor to check and clearly mark all
the required levels, alignment, set outline
where the Kerb stone is to be installed
according to the drawing
M Kerb stone is to be laid on a cement-sand
(1:4) mortar bed with a concrete substrate /
foundation.
n Kerb stone’s joints are to be fixed side-by-side
and touching one another. Joints to be
pointed/flushed with cement-sand mortar bed.
o Has Curing is to be achieved for joints and
mortar bed with minimum of 4 days of
spraying water. Page Conti…
QUALITY ASSURANCE MANUAL
DOC No :
URCC/SIMPL/QMS/CL/01, Construction of Shell Fuel Station (NTI/VA)
Rev-00 Date : 14-06-18
Page 25 of 31 Check List for Projects Activity
Comments if any:
ROAD WORK
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
No
a Are the layouts, gradient and camber of the
road as per the latest drawings?
b Is the sub grade prepared as per the layout &
gradient and compacted to requires degree
compaction?
c Is the course aggregate as per specification,
free from flat elongated and soft stones?
d Is the binding material (murram /quarry dust)
as per specification?
e Has the spreading of the aggregate and the
binding material been checked?
f Has compaction been done with 8-10 T power
/ vibratory roller up to the required no of runs?
g Is the sequence of rolling followed as per
specification?
h Has the application of screening materials
been checked?
i Has the application of roller after spreading of
screening materials been checked?
j Has the surface been applied with sufficient
amount of water and rolled to fill the voids?
k Has binding material been applied to prevent
reveling of WBM?
l Has the compacted thickness been checked?
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
No
a Are the slabs of uniform color & are they free
from cracks, stains, decay etc?
b Are the stones cut to proper size and are the
edges smooth and in right angle?
c Has proper mirror polish been done to the
surfaces?
d Has the floor been cleaned properly and
wetted prior to lying of marble/Granite?
e Has preparation of the bedding mortar been
checked and are the proportion & thickness as
specified?
f Are the slabs laid properly and seated over the
mortar by gently tamping with wooden mallet?
g Are the joints between slabs proper with less
than 1mm thickness?
h Is the top level of the slab as per
specifications?
i Are the joints cleaned of cement and grouted
with suitable grouting materials?
j Has the grinding process of marble slab (for
un finished slab) been done as specified?
k Has the polishing of the surface been done as
specified and is the surface smooth & even
l Is the nosing/chamfering of the edges and
polishing of counter slabs done properly?
m Is the wall cladding/skirting level as specified?
Comments if any:
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
No
a Whether detailed drawings for type of ceiling
anf details of fixtures are available?
b Is the ceiling level marked as per the drawing?
Comments if any:
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
No
a Have the structural cracks (if any) been
repaired properly?
b Has all loose concrete, loose particles, set
mortar, etc been removed and cleaning done
properly?
c Are there any bars from concrete surface to be
treated?
d Has primer coat been applied on the entire
surface without leaving gaps? Coverage area
of primer is 0.24 ltr/m2
e Is the grade of bitumen as per specification?
f Has the bitumen been used at the rate of
1.5Kg/m2 for every course treatment?
g Has the procedure for laying bitumen felt been
followed as per work instructions?
h Is correct method of laying of bitumen felt
followed that is from the lowest level to highest
level?
i Is pressing of the felt using wooden or similar
flat against hot bitumen for proper adherence,
carried out?
j Are the joints of the bitumen felts staggered
while laying succeeding layers?
k Is the over lapping of the bitumen felt 75 mm
at the ends and 100 mm on the sides?
l Is grit or gravel provided at the rate of 0.6 Cum
/ 100m2 for non accessible floors?
Comments if any:
STRUCTURE
SL.
CHECKPOINTS YES NO NA REMARKS
No
a Layout of Flooring as per latest revised
drawings
b Slope and Levels of Flooring Have Checked
with drawings
c Concrete substrates to be cleaned to remove
loose materials and dirt.
d Floor must be cleaned of all dusts and
residues before starting to work
e Priming the surface with epoxy primer
f Filling thin cracks with epoxy grout.
g Is First Coat is applied?
h Check cracks, holes with first layer before
going to apply second coat?
i Before placing the final coat make sure all
holes and cracks have been filled, and that all
dust has been collected.
j Check with Manufacturer specification for
Materials Mixing and Applying.
Comments if any: