Finishing Melamik Daun Pintu Kayu / m2

The document provides cost estimates for finishing wood doors and door frames using melamine. For doors, the estimated cost is 184 per square meter, including materials like wood filler, wood stain, sealant, paint, thinner, supplies, tools, labor costs for workers, craftsmen, a head craftsman and foreman. For door frames, the estimated cost is 89.5 per cubic meter, following a similar breakdown of materials, supplies, tools and labor costs.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
197 views

Finishing Melamik Daun Pintu Kayu / m2

The document provides cost estimates for finishing wood doors and door frames using melamine. For doors, the estimated cost is 184 per square meter, including materials like wood filler, wood stain, sealant, paint, thinner, supplies, tools, labor costs for workers, craftsmen, a head craftsman and foreman. For door frames, the estimated cost is 89.5 per cubic meter, following a similar breakdown of materials, supplies, tools and labor costs.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Finishing Melamik Daun Pintu Kayu / m2

Wood Filler 0,150 Kg @ 35 5.25


Woodstain 0,250 Liter @ 52 13
Sending sealer 0,350 Liter @ 45 15.75
Melamic top coat 0,250 Liter @ 45 11.25
Thinner 0,500 Liter @ 30 15
Amplas 0,500 Lbr @ 4 2
Alat bantu (alat semprot, dll) 1,000 ls @ 30 30

Pekerja 0,500 OH @ 70 35
Tukang 0,500 OH @ 100 50
Kepala tukang 0,050 OH @ 120 6
Mandor 0,005 OH @ 150 750
Jumlah 184
Dibulatkan 184

Finishing Melamik Kusen Pintu Kayu / m'


Wood Filler 0,075 Kg @ 35 2.625
Woodstain 0,125 Liter @ 52 6.5
Sending sealer 0,175 Liter @ 45 7.875
Melamic top coat 0,125 Liter @ 45 5.625
Thinner 0,250 Liter @ 30 7.5
Amplas 0,250 Lbr @ 4 1
Alat bantu (alat semprot, dll) 0,500 ls @ 25 12.5

Pekerja 0,250 OH @ 70 17.5


Tukang 0,250 OH @ 100 25
Kepala tukang 0,025 OH @ 120 3
Mandor 0,003 OH @ 150 375
Jumlah 89.5