Job Hazard Analysis PDF
Job Hazard Analysis PDF
Job Description: Chute Pipe Installation Date completed: Mar 24, 2018
Hard Hat Safety Glasses High Vis markings Hearing protection Safety Footwear
PPE Required
Gloves Respirator Life jacket Skin protection Other: __________
Complete FLHA • Unknown hazards Unfamiliar hazards E3 • Crew to complete FLHA prior to starting task. D1
Page 1 of 8
JOB HAZARD ANALYSIS Control number MYR-JHA- 2018-02-06
Subject: Chute Pipe Installation Page 2 of 8
Gravitational Body and Chemical Radiation Electrical Stored Sound Thermal Motion and
Energy Biological Energy Energy Energy Energy Energy Energy Moving Parts
JOB HAZARD ANALYSIS Control number MYR-JHA- 2018-02-06
Subject: Chute Pipe Installation Page 3 of 8
Gravitational Body and Chemical Radiation Electrical Stored Sound Thermal Motion and
Energy Biological Energy Energy Energy Energy Energy Energy Moving Parts
JOB HAZARD ANALYSIS Control number MYR-JHA- 2018-02-06
Subject: Chute Pipe Installation Page 4 of 8
• Ensure all crew members are off the slope during the
• Flying debris drilling operation.
• Noise • Hearing protection required when drilling.
• Heavy lifting • Use the buddy system when placing anchor rods
Drill anchor points with machine and
• Manually handling Flying debris D1 • Dywidags to be secured in case they are dropped while C1
install anchors
dywidags installing.
• Dywidags not set properly • Ensure dywidags are properly grouted in place and the
grout is set to manufactures specs before placing load
on them. QA/QC testing on the grout
• Ensure all rigging is properly inspected prior to use and
rated for to load being lifted. Ensure rigger is trained
• Improper rigging and competent.
• Miscommunication with • Ensure signalman has clean line of sight with the
operator operator.
Dropped loads
Install bend section and anchor • Suspended loads D3 • Use taglines when handling load. Do not stand under C1
Possible crush points
• Pinch points suspended load.
• Load movement • Stay out of the line of fire. Watch hand and foot
• Ground is stable to support placement when setting bend section in place.
• Ensure anchors are installed before rigging is
disconnected
• Excavator operator will build a stable surface to work
from before digging the trench.
• Steep slope
• All crew members will be off the slope during
• Falling rocks
trenching.
• People or equipment
Excavate slope for first section of pipe. Equipment roll over D3 • Access to work area below will be barricaded off. C1
entering work area below
• Follow trenching procedures HSRC
• Survey control to be used following design criteria
Gravitational Body and Chemical Radiation Electrical Stored Sound Thermal Motion and
Energy Biological Energy Energy Energy Energy Energy Energy Moving Parts
JOB HAZARD ANALYSIS Control number MYR-JHA- 2018-02-06
Subject: Chute Pipe Installation Page 5 of 8
• Unsupported load
• Install cable anchor slings to anchors as per design.
Install cable anchors and bolt up • Lowering cables into Body parts caught in
D3 • Good communication between crew members when C1
coupling position. the line of fire
lowering cables into position.
Gravitational Body and Chemical Radiation Electrical Stored Sound Thermal Motion and
Energy Biological Energy Energy Energy Energy Energy Energy Moving Parts
JOB HAZARD ANALYSIS Control number MYR-JHA- 2018-02-06
Subject: Chute Pipe Installation Page 6 of 8
• All workers will keep hands out of the line of fire when
connecting piping to the back of the hopper.
• 100% Tie-off at all times when working at height of 6ft
Repeat steps for installing anchors and lowering pipe for all bottom sections
Unwanted Inherent
Hazards Event Risk Controls Residual Risk
Activity: List hazards associated with each Risk associated Measures that need to be taken to eliminate or minimize the risk Remaining risk associated with
Provide a step-by-step breakdown of the task What harm would result with each hazard each hazard once control
step if something went before any associated with each hazard measures have been put in place
controls are put in
wrong?
place
Low: Proceed with Medium: Proceed with High: Proceed with Very High: Proceed with
supervisor approval Manager approval GM approval corporate approval .
Criteria
Medium Medium High Very High Very High Very High
Could occur within days to weeks F
F1 F2 F3 F4 F5 F6
Low Medium High High Very High Very High
Could occur within weeks to months E
E1 E2 E3 E4 E5 E6
Low Medium Medium High Very High Very High
Likelihood
Gravitational Body and Chemical Radiation Electrical Stored Sound Thermal Motion and
Energy Biological Energy Energy Energy Energy Energy Energy Moving Parts
JOB HAZARD ANALYSIS Control number MYR-JHA- 2018-02-06
Subject: Chute Pipe Installation Page 7 of 8
Gravitational Body and Chemical Radiation Electrical Stored Sound Thermal Motion and
Energy Biological Energy Energy Energy Energy Energy Energy Moving Parts
JOB HAZARD ANALYSIS Control number MYR-JHA- 2018-02-06
Subject: Chute Pipe Installation Page 8 of 8
Sign-Off Sheet
I understand the hazards and mitigations in this document. I will follow the mitigations identified to keep me and my coworkers safe. I will
update this living document as conditions change. I will tell others of changes to this JHA so they are aware of the new hazards/mitigations.
Gravitational Body and Chemical Radiation Electrical Stored Sound Thermal Motion and
Energy Biological Energy Energy Energy Energy Energy Energy Moving Parts