Updated Work Programme With Additional Work
Updated Work Programme With Additional Work
At No. 104, Chitra Lane, Colombo 05. No. 151, Nawala Road, Narahenpita,
Colombo - 5
ID Task Name Duration Start Finish Jul '19 Aug '19 Sep '19 Oct '19 Nov '19 Dec '19 Jan '20 Feb '20 Mar '20 Apr '20
1 Balance Work as at 9th August 2019 216 days Thu 8/1/19 Tue 3/3/20
2 Third Floor 110 days Fri 8/23/19 Tue 12/10/19
3 Plumbing 56 days Fri 10/11/19 Thu 12/5/19
4 Finalizing of details(According to re-revised on 13 days Fri 10/11/19 Wed 10/23/19 10/11 10/23
10/11/2019
5 Finalizing of dummy wall in toilet by consultant (Design 12 days Fri 10/18/19 Tue 10/29/19 10/18 10/29
not given)
6 Finalizing of dummy wall in toilet 7 days Wed 10/30/19 Tue 11/5/19 10/30 11/5
7 Dummy wall in toilet 7 days Wed 11/6/19 Tue 11/12/19 11/6 11/12
8 Core cutting 1 day Wed 11/13/19 Wed 11/13/19 11/13 11/13
9 Completion of balance plumbing work 4 days Thu 11/14/19 Sun 11/17/19 11/14 11/17
10 Waterproofing work 2 days Mon 11/18/19 Tue 11/19/19 11/18 11/19
11 Pond test 5 days Wed 11/20/19 Sun 11/24/19 11/20 11/24
12 Protective bed and internal plastering 11 days Mon 11/25/19 Thu 12/5/19 11/25 12/5
13 Electrical 103 days Fri 8/23/19 Tue 12/3/19
14 Testing and commissioning phase 1 3 days Fri 8/23/19 Sun 8/25/19 8/23 8/25
15 Finalizing DB location & variation by LCMC 30 days Thu 9/19/19 Fri 10/18/19 9/19 10/18
16 Cable tray and related balance works 8 days Sat 10/19/19 Sat 10/26/19 10/19 10/26
17 Finalizing of details in Kitchen by LCMC 8 days Fri 10/11/19 Fri 10/18/19 10/11 10/18
18 Balance electrical works in the kitchen 5 days Sat 10/19/19 Wed 10/23/19 10/19 10/23
19 DB Fabrication & installation 35 days Sat 10/19/19 Fri 11/22/19 10/19 11/22
20 Testing and commissioning phase 11 4 days Sat 11/23/19 Tue 11/26/19 11/23 11/26
21 Approval for as built drawing - wiring for lighting & 7 days Wed 11/27/19 Tue 12/3/19 11/27 12/3
power
22 Windows 72 days Mon 9/30/19 Tue 12/10/19
23 Timber sashes Variation Submission & get approval 8 days Mon 9/30/19 Mon 10/7/19 9/30 10/7
24 Fabrication of window sashes 46 days Tue 10/8/19 Fri 11/22/19 10/8 11/22
25 Fixing of window sashes 18 days Sat 11/23/19 Tue 12/10/19 11/23 12/10
26 Timber Doors 92 days Tue 9/10/19 Tue 12/10/19
27 Timber Frame Variation Submission & get approval 8 days Tue 9/10/19 Tue 9/17/19 9/10 9/17
28 Timber Cutting & treatment 25 days Wed 9/18/19 Sat 10/12/19 9/18 10/12
29 Making of Timber Frame 14 days Sun 10/13/19 Sat 10/26/19 10/13 10/26
30 Fixing Timber frame 6 days Sun 10/27/19 Fri 11/1/19 10/27 11/1
31 Making Of Timber Sashes 30 days Sun 10/27/19 Mon 11/25/19 10/27 11/25
32 Fixing of Timber Sashes 15 days Tue 11/26/19 Tue 12/10/19 11/26 12/10
33 Second Floor 137 days Sat 9/7/19 Tue 1/21/20
34 Plumbing 63 days Fri 10/11/19 Thu 12/12/19
35 Finalizing of details( According to re-revised on 13 days Fri 10/11/19 Wed 10/23/19 10/11 10/23
10/11/2019)
36 Finalizing of dummy wall in toilet by consultant (Design 12 days Fri 10/18/19 Tue 10/29/19 10/18 10/29
not given)
37 Dummy wall in toilet 12 days Wed 11/13/19 Sun 11/24/19 11/13 11/24
38 Core cutting 1 day Mon 11/25/19 Mon 11/25/19 11/25 11/25
39 Completion of balance plumbing work 3 days Tue 11/26/19 Thu 11/28/19 11/26 11/28
40 Waterproofing work 2 days Fri 11/29/19 Sat 11/30/19 11/29 11/30
41 Pond test 5 days Sun 12/1/19 Thu 12/5/19 12/1 12/5
42 Protective bed and internal plastering 7 days Fri 12/6/19 Thu 12/12/19 12/6 12/12
43 Electrical 98 days Sat 9/7/19 Fri 12/13/19
44 Finalizing of details(According to re-revised on 19 days Sat 9/7/19 Wed 9/25/19 9/7 9/25
09.07.2019
45 Marking of design on walls by ID contractor 19 days Thu 9/26/19 Mon 10/14/19 9/26 10/14
46 wiring work for lighting and power 9 days Tue 10/15/19 Wed 10/23/19 10/15 10/23
47 Approval for DB location and variation 19 days Fri 10/18/19 Tue 11/5/19 10/18 11/5
48 DB Fabrication & installation 35 days Wed 11/6/19 Tue 12/10/19 11/6 12/10
49 Testing and commissioning 3 days Wed 12/11/19 Fri 12/13/19 12/11 12/13
50 Windows 60 days Sat 11/23/19 Tue 1/21/20
51 Fabrication of window sashes 45 days Sat 11/23/19 Mon 1/6/20 11/23 1/6
52 Fixing of window sashes 15 days Tue 1/7/20 Tue 1/21/20 1/7 1/21
53 Timber Doors 75 days Sun 10/27/19 Thu 1/9/20
54 Making of Timber Frame 14 days Sun 10/27/19 Sat 11/9/19 10/27 11/9
55 Fixing Timber frame 7 days Sun 11/10/19 Sat 11/16/19 11/10 11/16
56 Making Of Timber Sashes 30 days Tue 11/26/19 Wed 12/25/19 11/26 12/25
57 Fixing of Timber Sashes 15 days Thu 12/26/19 Thu 1/9/20 12/26 1/9
58 Handrails 70 days Tue 10/1/19 Mon 12/9/19
59 Fabrication of sample and get approval 26 days Tue 10/1/19 Sat 10/26/19 10/1 10/26
60 Construction of concrete ledge for fixing of handrail 7 days Sun 10/27/19 Sat 11/2/19 10/27 11/2
61 Fabrication of Staircase / Balcony Handrails 30 days Sun 10/27/19 Mon 11/25/19 10/27 11/25
62 Fixing of handrail in staircase and Guard walls 14 days Tue 11/26/19 Mon 12/9/19 11/26 12/9
63 First Floor 156 days Fri 8/30/19 Sat 2/1/20
64 Plumbing 71 days Fri 10/11/19 Fri 12/20/19
65 Finalizing of details(According to re-revised on 13 days Fri 10/11/19 Wed 10/23/19 10/11 10/23
10/11/2019
66 Finalizing of dummy wall in toilet by consultant (Design 12 days Fri 10/18/19 Tue 10/29/19 10/18 10/29
not given)
67 Dummy wall in toilet 10 days Mon 11/25/19 Wed 12/4/19 11/25 12/4
68 Core cutting 3 days Thu 12/5/19 Sat 12/7/19 12/5 12/7
69 Completion of balance plumbing work 4 days Thu 12/5/19 Sun 12/8/19 12/5 12/8
70 Waterproofing work and testing for water tightness 6 days Mon 12/9/19 Sat 12/14/19 12/9 12/14
71 Protective bed and Plastering in toilets 6 days Sun 12/15/19 Fri 12/20/19 12/15 12/20
72 Electrical 74 days Fri 10/4/19 Mon 12/16/19
73 Finalizing of details 20 days Fri 10/4/19 Wed 10/23/19 10/4 10/23
74 Marking of design on walls by ID contractor 5 days Sat 10/19/19 Wed 10/23/19 10/19 10/23
75 Wiring work for lighting and power 21 days Thu 10/24/19 Wed 11/13/19 10/24 11/13
76 Cable tray and related works 7 days Thu 10/24/19 Wed 10/30/19 10/24 10/30
77 Approval for DB location and variation 14 days Thu 10/24/19 Wed 11/6/19 10/24 11/6
78 DB Fabrication & installation 35 days Thu 11/7/19 Wed 12/11/19 11/7 12/11
Proposed Residential Building L. H. Piyasena & Co. (Pvt.) Ltd.
At No. 104, Chitra Lane, Colombo 05. No. 151, Nawala Road, Narahenpita,
Colombo - 5
ID Task Name Duration Start Finish Jul '19 Aug '19 Sep '19 Oct '19 Nov '19 Dec '19 Jan '20 Feb '20 Mar '20 Apr '20
79 Testing and commissioning 5 days Thu 12/12/19 Mon 12/16/19 12/12 12/16
80 Windows 24 days Tue 1/7/20 Thu 1/30/20
81 Fabrication of window sashes 9 days Tue 1/7/20 Wed 1/15/20 1/7 1/15
82 Fixing of window sashes 15 days Thu 1/16/20 Thu 1/30/20 1/16 1/30
83 Timber Doors 84 days Sun 11/10/19 Sat 2/1/20
84 Making of Timber Frame 12 days Sun 11/10/19 Thu 11/21/19 11/10 11/21
85 Fixing Timber frame 6 days Fri 11/22/19 Wed 11/27/19 11/22 11/27
86 Making Of Timber Sashes 25 days Thu 12/26/19 Sun 1/19/20 12/26 1/19
87 Fixing of Timber Sashes 13 days Mon 1/20/20 Sat 2/1/20 1/20 2/1
88 Handrails 55 days Tue 11/26/19 Sun 1/19/20
89 Fabrication of Staircase/Balcony Handrails 40 days Tue 11/26/19 Sat 1/4/20 11/26 1/4
90 Fixing handrails at staircase and pool area 14 days Sun 1/5/20 Sat 1/18/20 1/5 1/18
91 Balcony Hand rail 15 days Sun 1/5/20 Sun 1/19/20 1/5 1/19
92 Swimming Pool 99 days Fri 8/30/19 Fri 12/6/19
93 Finalizing of works around pool area by LCMC 54 days Fri 8/30/19 Tue 10/22/19 8/30 10/22
94 Balance work around the pool 14 days Wed 10/23/19 Tue 11/5/19 10/23 11/5
95 Waterproofing of Pool 15 days Wed 11/6/19 Wed 11/20/19 11/6 11/20
96 Water tightness test 5 days Thu 11/21/19 Mon 11/25/19 11/21 11/25
97 Protective screed bedding 11 days Tue 11/26/19 Fri 12/6/19 11/26 12/6
98 Ground Floor 145 days Fri 10/11/19 Tue 3/3/20
99 Plumbing 85 days Fri 10/11/19 Fri 1/3/20
100 Finalizing of details(According to re-revised on 13 days Fri 10/11/19 Wed 10/23/19 10/11 10/23
10/11/2019
101 Finalizing of dummy wall in toilet by consultant (Design 12 days Fri 10/18/19 Tue 10/29/19 10/18 10/29
not given)
102 Dummy wall in toilet 11 days Sun 12/8/19 Wed 12/18/19 12/8 12/18
103 Core cutting 1 day Thu 12/19/19 Thu 12/19/19 12/19 12/19
104 Completion of balance plumbing work 4 days Fri 12/20/19 Mon 12/23/19 12/20 12/23
105 Waterproofing work and testing for water tightness 6 days Tue 12/24/19 Sun 12/29/19 12/24 12/29
106 Protective bed and Plastering in toilets 5 days Mon 12/30/19 Fri 1/3/20 12/30 1/3
107 Electrical 31 days Tue 11/19/19 Thu 12/19/19
108 Finalizing of details 11 days Tue 11/19/19 Fri 11/29/19 11/19 11/29
109 Marking of design on walls by ID contractor 5 days Mon 11/25/19 Fri 11/29/19 11/25 11/29
110 Balance Wiring work for lighting and power 7 days Sat 11/30/19 Fri 12/6/19 11/30 12/6
111 Cable tray and related works 10 days Sat 12/7/19 Mon 12/16/19 12/7 12/16
112 Testing and commissioning 3 days Tue 12/17/19 Thu 12/19/19 12/17 12/19
113 Windows 34 days Thu 1/16/20 Tue 2/18/20
114 Fixing of balance window frames 10 days Thu 1/16/20 Sat 1/25/20 1/16 1/25
115 Fabrication of window sashes 14 days Thu 1/16/20 Wed 1/29/20 1/16 1/29
116 Fixing of window sashes 20 days Thu 1/30/20 Tue 2/18/20 1/30 2/18
117 Timber Doors 102 days Fri 11/22/19 Mon 3/2/20
118 Making of Timber Frame 14 days Fri 11/22/19 Thu 12/5/19 11/22 12/5
119 Fixing Timber frame 8 days Fri 12/6/19 Fri 12/13/19 12/6 12/13
120 Making Of Timber Sashes 30 days Mon 1/20/20 Tue 2/18/20 1/20 2/18
121 Fixing of Timber Sashes 13 days Wed 2/19/20 Mon 3/2/20 2/19 3/2
122 Handrails 44 days Mon 1/20/20 Tue 3/3/20
123 Fabrication of Handrails 22 days Mon 1/20/20 Mon 2/10/20 1/20 2/10
124 Fixing of staircase handrails 10 days Tue 2/11/20 Thu 2/20/20 2/11 2/20
125 Fixing of Grills above windows 12 days Fri 2/21/20 Tue 3/3/20 2/21 3/3
126 Basement 139 days Fri 10/11/19 Wed 2/26/20
127 Plumbing 138 days Fri 10/11/19 Tue 2/25/20
128 Finalizing of details(According to re-revised on 13 days Fri 10/11/19 Wed 10/23/19 10/11 10/23
10/11/2019
129 Finalizing of dummy wall in toilet by consultant (Design 12 days Fri 10/18/19 Tue 10/29/19 10/18 10/29
not given)
130 Completion of balance plumbing work 16 days Tue 12/24/19 Wed 1/8/20 12/24 1/8
131 Waterproofing and necessary tests for water tightness 11 days Thu 1/9/20 Sun 1/19/20 1/9 1/19
132 Protective bed and Plastering in toilets 10 days Mon 1/20/20 Wed 1/29/20 1/20 1/29
133 Internal plastering work for brick walls 10 days Thu 1/30/20 Sat 2/8/20 1/30 2/8
134 Concrete filling on floor 17 days Sun 2/9/20 Tue 2/25/20 2/9 2/25
135 Electrical 69 days Fri 12/20/19 Wed 2/26/20
136 Finalizing of details and approval 21 days Fri 12/20/19 Thu 1/9/20 12/20 1/9
137 Wiring work for lighting 30 days Fri 1/10/20 Sat 2/8/20 1/10 2/8
138 Cable tray and related works 15 days Sun 2/9/20 Sun 2/23/20 2/9 2/23
139 Testing and commissioning 3 days Mon 2/24/20 Wed 2/26/20 2/24 2/26
140 General Works 214 days Thu 8/1/19 Sun 3/1/20
141 Plumbing 47 days Wed 1/15/20 Sun 3/1/20
142 Fixing of Toilet fittings 45 days Wed 1/15/20 Fri 2/28/20 1/15 2/28
143 Completion of all plumbing work including testing and 47 days Wed 1/15/20 Sun 3/1/20 1/15 3/1
commissioning (water tanks, GRP tanks, etc.)
144 As build drawing preparation and submitting 27 days Wed 1/15/20 Mon 2/10/20 1/15 2/10
145 Electrical - General 182 days Sun 9/1/19 Sat 2/29/20
146 Finalize Main Panel Board Variation 10 days Fri 11/1/19 Sun 11/10/19 11/1 11/10
147 DB fixing and Cable termination and related works 45 days Mon 11/11/19 Wed 12/25/19 11/11 12/25
148 Fixing of Light fittings and socket outlets 27 days Mon 2/3/20 Sat 2/29/20 2/3 2/29
149 Submission and approval for As-built drawings - floor 100 days Wed 10/30/19 Thu 2/6/20 10/30 2/6
by floor
150 Completion of Lightening Protection system including 60 days Sun 9/1/19 Wed 10/30/19 9/1 10/30
testing and commissioning
151 Laying Touch-on Membrane (Water proofing) 20 days Sun 9/1/19 Fri 9/20/19 9/1 9/20
152 Exterior Molding including balance structures 110 days Thu 8/1/19 Mon 11/18/19 8/1 11/18
153 External water proofing 25 days Thu 10/17/19 Sun 11/10/19 10/17 11/10
154 Completion of Fire detection system including testing and 90 days Sun 9/1/19 Fri 11/29/19 9/1 11/29
commissioning
155 Balance retaining wall construction 20 days Thu 10/10/19 Tue 10/29/19 10/10 10/29
156 Additional Works Issued as Variation 143 days Thu 10/10/19 Sat 2/29/20
Proposed Residential Building L. H. Piyasena & Co. (Pvt.) Ltd.
At No. 104, Chitra Lane, Colombo 05. No. 151, Nawala Road, Narahenpita,
Colombo - 5
ID Task Name Duration Start Finish Jul '19 Aug '19 Sep '19 Oct '19 Nov '19 Dec '19 Jan '20 Feb '20 Mar '20 Apr '20
157 External Painting 139 days Mon 10/14/19 Sat 2/29/20
158 External Wall Skim coat application 70 days Mon 10/14/19 Sun 12/22/19 10/14 12/22
159 External 5 Coat System 43 days Mon 12/23/19 Mon 2/3/20 12/23 2/3
160 External Texture Painting 26 days Tue 2/4/20 Sat 2/29/20 2/4 2/29
161 Cement Bed & Rendering (For Fixing of Timber 68 days Thu 10/31/19 Mon 1/6/20
Flooring)
162 3rd Floor (approx. area 526 m2) 30 days Thu 10/31/19 Fri 11/29/19 10/31 11/29
163 2nd Floor (approx. area 457 m2) 26 days Sat 11/30/19 Wed 12/25/19 11/30 12/25
164 1st Floor (approx. area 160 m2) 12 days Thu 12/26/19 Mon 1/6/20 12/26 1/6
165 Boundary Wall 140 days Thu 10/10/19 Wed 2/26/20
166 Drawing receiving 1 day Thu 10/10/19 Thu 10/10/19 10/10
167 Finalized the Variation 20 days Fri 10/11/19 Wed 10/30/19 10/11 10/30
168 Construct of Boundary Wall 111 days Fri 11/8/19 Wed 2/26/20 11/8 2/26
169 Transformer Room 80 days Thu 10/10/19 Sat 12/28/19
170 Drawing receiving 1 day Thu 10/10/19 Thu 10/10/19 10/10
171 Finalized the Variation 20 days Fri 10/11/19 Wed 10/30/19 10/11 10/30
172 Construct of Transformer Room 48 days Mon 11/11/19 Sat 12/28/19 11/11 12/28
173 Security Room 137 days Fri 10/11/19 Mon 2/24/20
174 Drawing receiving 1 day Fri 10/11/19 Fri 10/11/19 10/11
175 Finalized the Variation 20 days Sat 10/12/19 Thu 10/31/19 10/12 10/31
176 Construct of Security Room 58 days Sun 12/29/19 Mon 2/24/20 12/29 2/24
177 Servant Quarters 132 days Fri 10/11/19 Wed 2/19/20
178 Drawing receiving 1 day Fri 10/11/19 Fri 10/11/19 10/11
179 Finalized the Variation 20 days Sat 10/12/19 Thu 10/31/19 10/12 10/31
180 Construct of Servant Quarters 97 days Fri 11/15/19 Wed 2/19/20 11/15 2/19