Journal of Engineering, Design and Technology: Article Information
Journal of Engineering, Design and Technology: Article Information
Access to this document was granted through an Emerald subscription provided by emerald-
srm:332610 []
For Authors
If you would like to write for this, or any other Emerald publication, then please use our Emerald
for Authors service information about how to choose which publication to write for and submission
guidelines are available for all. Please visit www.emeraldinsight.com/authors for more information.
About Emerald www.emeraldinsight.com
Emerald is a global publisher linking research and practice to the benefit of society. The company
manages a portfolio of more than 290 journals and over 2,350 books and book series volumes, as
well as providing an extensive range of online products and additional customer resources and
services.
Emerald is both COUNTER 4 and TRANSFER compliant. The organization is a partner of the
Committee on Publication Ethics (COPE) and also works with Portico and the LOCKSS initiative for
digital archive preservation.
JEDT
13,3
Development of value stream
map for an Indian automotive
components manufacturing
380 organization
Received 4 August 2010 S. Vinodh, T. Selvaraj, Suresh Kumar Chintha and Vimal K.E.K.
Revised 17 February 2012
Accepted 21 February 2012 Department of Production Engineering, National Institute of Technology,
Tiruchirappalli, India
Downloaded by La Trobe University At 11:26 25 May 2016 (PT)
Abstract
Purpose – This paper aims to apply Value Stream Mapping (VSM) for enabling leanness in an Indian
automotive components manufacturing organization.
Design/methodology/approach – The study was initiated with the selection of product line,
construction of current state map, identification of various wastes and the development of future state map.
The improvement proposals were subjected to implementation and performance measures were quantified.
Findings – The expected outcomes of the study include the quantification of wastes, improvement in
manpower productivity, quality improvement and throughput time reduction.
Research limitations/implications – The implementation study has been conducted in only one
manufacturing organization. The experiences gained by the conduct of this implementation study are
feasible and deployable in similar manufacturing organizations.
Practical implications – The results of the study indicated that significant improvement in lean
characteristics is possible as a result of the implementation of VSM.
Originality/value – The paper reports a real-time study conducted in an automotive components
manufacturing organization. Hence, the contributions are original.
Keywords Lean manufacturing, Value stream mapping, Lean production, 5S, Pull production,
Time reduction
Paper type Case study
1. Introduction
The increasing competition has been forcing the manufacturing organizations to
transform their current manufacturing paradigm (Chen et al., 2006). The history of
development of Production Systems is as follows. The evolution of manufacturing
system starts with Craft Production System (1890-1910) in Automobile manufacturing,
and, in the year 1910, Ford Motor Company introduced Mass Production System which
is based on economies of scale. After the World War II, an advanced production system
called Toyota Production System (TPS) (1950 onwards) was introduced in Toyota
Motor Company; then, in 1980, lean manufacturing was evolved by integrating
advanced tools from world-class manufacturing system and TPS which also includes
Journal of Engineering, Design
and Technology Supply Chain Management. The lean manufacturing concept was originated from TPS
Vol. 13 No. 3, 2015
pp. 380-399
and Just-in-Time (JIT) concepts. The contemporary manufacturing organizations have
© Emerald Group Publishing Limited
1726-0531
been witnessing a transition from mass manufacturing to lean manufacturing. Lean
DOI 10.1108/JEDT-08-2010-0054 manufacturing is focused on the reduction of wastes and non-value-added activities of
different types (Lummus et al., 2006). Lean operations eliminate obvious wastes, reduce Development
variability, reduce inventory and thereby reduce cost. The essence of leanness is of value
efficient use of resources through the minimization of wastes.
Lean manufacturing has various definitions. The definition given by National
stream map
Institute of Standards and Technology is a “Systematic approach of identifying and
eliminating wastes (non value added activities) through continuous improvement by
flowing the product at the pull of customer in pursuit of perfection”. Another way of 381
defining it is “integrated manufacturing system intended to maximize capacity,
reutilization and minimize buffer inventories through the minimization of system
variability” (Narasimhan et al., 2006). The majorly occurring wastes in any
manufacturing process are: over production, over processing, waiting time,
transportation, defects, inventory and storage. Some of the leanness parameters include
lead time, total cycle time, work in process inventory, on time delivery, defects in parts
per million (ppm) and uptime.
Downloaded by La Trobe University At 11:26 25 May 2016 (PT)
2. Literature review
The literature has been reviewed from the perspectives of lean manufacturing and VSM.
management.
3. Methodology
The methodology followed during this study is shown in Figure 1.
Literature review on Lean manufacturing and VSM Development
of value
stream map
Selection of VSM for implementation
383
Study of the manufacturing processes followed in the organisation
Development of current state value stream map for the identified product line
Downloaded by La Trobe University At 11:26 25 May 2016 (PT)
Identification of wastes
Figure 1.
Development of future value stream map and implementation in the case organization
Methodology
First, the literature on lean manufacturing and VSM was reviewed. VSM was selected as
the tool to overcome the problem faced by the case organization. Then data collection
was done, and, based on the data collected, further calculations were done. Various
activities were identified with the micro-level analysis in the shop floor. Based on the
data collected, activity categorization was done to exactly identify the useful activity
and wastes. Then Current State Map for the identified product line was developed. Then
brain storming session is being organized to analyze the current state map and some
improvement proposals were arrived in consultation with the executives of the
organization. These improvement proposals were deployed in the future state map.
The inferences were derived from the future state map. Finally, the developed future
state map was implemented in the case organization. The results have been derived
from the trial implementation of the proposed future state map.
4. Case study
The case study was carried out in automotive components manufacturing organization
located in Tamil Nadu, India (hereafter referred to as ABC).
snapshot in time of how the value stream was actually operating at a given point in time.
4.3.1 Takt time. It is the pace of customer demand. Takt time is the rate at which a
company must produce a product to satisfy customer demand and was calculated using
equation (1) (Abdulmalek and Rajgopal, 2007):
4.3.2 Pitch. Pitch is the amount of time based on Takt time required for an upstream
operation to release a predetermined pack out quantity of work in process (WIP) to a
downstream operation and was calculated using equation (2):
4.3.3 Available time. The available time is the difference between total production time
and planned down time and was calculated using equation (3):
4.3.5 Days of WIP on hand. It is the ratio between the Total amount of WIP between
process to the number of parts shipped per day and was calculated using equation (5):
level and observing the past data concerning major losses, some improvement proposals
have been derived.
• As the WIP is more before the first operation, to reduce the lead time, it is proposed
to adopt the single piece flow or one more material movement operator is
introduced from store to the start of the line.
• As the line is characterized with cluttered environment, 5S was recommended
with more emphasis on third 5S improvement, i.e. “Shine”.
• As frequent breakdowns are occurring at machines of P1 and P2 which, in turn,
affects the operation of the entire line, TPM study was recommended to adopt for
the machines used for P1 and P2.
• One of the key observations made was that the operators are doing gauge
inspection after machining, keeping the component loaded in the machine which
reduces the available time of the machine. To overcome this problem, it is
recommended to provide proper training to the operators.
These improvement proposals are incorporated and Future State Map is constructed
and the performance measures are estimated. After arriving at the improvement
proposals, the Future State Map was developed using the same procedure as that
followed for developing current state map in the following way.
A Kaizen burst icon was used to represent the first improvement proposal, i.e.
introducing one more operator to reduce the WIP. The data boxes are drawn for all the
manufacturing operations indicating the number of operators, cycle time, changeover time
(per shift), availability and uptime of the machine. Two Kaizen burst icons were used at P1
and P2 machines to improve their utilization. The Kaizen burst icon indicating 3rd 5S
improvement is drawn at P5, P6 and P7. From the last operation in the line, an arrow was
drawn toward the customer who goes through a trolley icon. A WIP icon was drawn in
between every two operations which represents the items that are waiting for upstream
operation which, in turn, is a non-value-added activity. A time line was drawn to indicate
value-added time and non-value-added time. A box was drawn below the time line, and the
data about lead time and total cycle time were entered. The sum of all days of WIP generates
lead time and sum of all cycle time generate total cycle time. Now, the Future State Map is
developed which is shown in Figure 3.
Downloaded by La Trobe University At 11:26 25 May 2016 (PT)
387
of value
13,3
388
JEDT
Figure 3.
Future State Map
4.5 Total productive maintenance Development
In the part of the TPM study for the machines used for P1 and P2, their past six-month of value
breakdown data were collected, and Fault Tree Analysis was done as shown in
Figure 4 to find the major and minor causes to reduce the attending time for repairs.
stream map
After analyzing the data, the causes are tabulated and presented in Table I. From
these data, the probability failures of the causes were estimated and were used to
calculate the system failure (breakdown) which, in turn, gives the system reliability. 389
4.5.1 Reliability calculation. Reliability of a unit or product is the probability that the
unit performs its intended function adequately for a given period of time under the
stated operating conditions or environment.
4.5.2 Probability failure of sub-causes. P(x1) ⫽ 0.0056, P(x2) ⫽ 0.0056, P(x3) ⫽ 0.0056
(collected from industry shop floor).
P (A) ⫽ P(x1) ⫹ P(x2) ⫹ P(x3) ⫺ P(x1) ⫻ P(x2) ⫺ P(x2) ⫻ P(x3) ⫺ P(x3) ⫻ P(x1) ⫹
P(x1) ⫻ P(x2) ⫻ P(x3) ⫽ 0.0166.
Downloaded by La Trobe University At 11:26 25 May 2016 (PT)
P (B) ⫽ 0.0221, P (C) ⫽ 0.0276, P (D) ⫽ 0.0111, P (E) ⫽ 0.0056, P (F) ⫽ 0.0111.
Probability of system failure P(S) ⫽ 0.0925.
Reliability of system ⫽ 1 ⫺ P(S) ⫽ 1 ⫺ 0.0925 ⫽ 0.9075 ⫽ 90.75 per cent.
Similarly, reliability was calculated and Fault Tree Analysis was done for machine II.
The breakdown data of both the machines were analyzed and compared for identifying
frequently occurred failures and they analyzed up to the basic levels to develop the Fault
Tree Diagrams for each failure.
A Pareto chart was developed using the above data and is shown in Figure 5.
From the above Pareto chart, it is observed that the frequently occurring causes were
identified as a component that comes out from the spindle, servo alarm, and they were
analyzed to develop the Fault Tree Diagrams, respectively. As an excerpt the Fault Tree
Diagram for cause “component comes out from spindle” was shown in Figure 6.
390
Downloaded by La Trobe University At 11:26 25 May 2016 (PT)
Figure 4.
Fault Tree Diagram
for machine 1
4.6.3.1 Solution. Currently, in the 12-slot tool magazine, only 5 slots are being used. The
unused tool slots in 12-slot tool magazine could be used to improve the utilization
reducing the tool changeover time.
4.6.4 Constraint 4. When the operator is attending the gauge inspection of
components, machines are idle and WIP is accumulated.
4.6.4.1 Solution. Instead of inspecting the single component with all the gauges, each
component needs to be inspected for a particular dimension using a single gauge.
Total
Development
Serial no. Problem Sub-cause Frequency occurrence of value
stream map
1 Door not OK (A) Door side open/close connecting link 1 3
screw problem(x1)
Heavy air leakage(x2) 1
Door fixing screw fell down(x3) 1
2 Component comes out Jaw boring not proper(x4) 1 4
391
from the spindle (B) Wrong entry(x5) 1
Low chuck pressure(x6) 2
3 Servo alarm (C) Seal side high drill feed rate(x7) 1 5
Z-axis overload alarm(x8) 1
Over travel(x9) 1
Seal side trip(x10) 1
TRIP(x11) 1
Downloaded by La Trobe University At 11:26 25 May 2016 (PT)
4.6.4.2 Observation. At the work station, P5, before loading the component, extra
cleaning is being done (where it is not necessary) which accounts for the waste “Over
processing”.
Existing cleaning time ⫽ 30 seconds.
Necessary time ⫽ 10 seconds.
Over processing time ⫽ 20 seconds.
4.6.4.3 Solution. Standard Operating Procedure (SOP) needs to be evolved to create
awareness for the operator to reduce the over processing time.
392
Downloaded by La Trobe University At 11:26 25 May 2016 (PT)
Figure 5.
Fault Tree Diagram
for “Component
comes out from the
spindle”
Figure 6.
Pareto chart for the
break down data
Downloaded by La Trobe University At 11:26 25 May 2016 (PT)
1 Lead time 412 minutes 242 minutes 41.26% reduction in lead time
2 Utilization of turning 96.3% 97.8% 1.5% increase in utilization Table V.
machine Comparison of
3 Value addition 5.3% 8.7% 3.4% increase performance
4 Overall equipment 56% 66% 10% increment measures in current
effectiveness state and future state
development of VSM for ABC. The results of the conduct of the case study indicate
that VSM could be practically applied in manufacturing industrial scenario for
quantification of wastes, improvement in manpower productivity, quality
improvement and throughput time reduction to achieve core competency in the
global market scenario. The improvements are subjected to rigorous
implementation. The results of the study were compared with other similar studies
and are shown in Table VII.
References
Abdulmalek, F.A. and Rajgopal, J. (2007), “Analyzing the benefits of lean manufacturing and
value stream mapping via simulation: a process sector case study”, International Journal of
Production Economics, Vol. 107 No. 1, pp. 223-236.
Chen, J.C.H., Parker, L.J. and Lin, B. (2006), “Technopreneurship in native American businesses:
current issues and future trends with a case study”, International Journal of Management
and Enterprise Development, Vol. 3 Nos 1/2, pp. 70-84.
Crute, V., Ward, Y., Brown, S. and Graves, A. (2003), “Implementing lean in aerospace-challenging
the assumptions and understanding the challenges”, Technovation, Vol. 23 No. 12,
pp. 917-928.
Doolen, T.L. and Hacker, M.E. (2005), “A review of lean assessment in organizations: an
exploratory study of lean practices by electronic manufacturers”, Journal of Manufacturing
Systems, Vol. 24 No. 1, pp. 55-67.
Hines, P. and Rich, N. (1997), “The seven value stream mapping tools”, International Journal of
Operations & Production Management, Vol. 17 No. 1, pp. 46-64.
Hines, P., Rich, N. and Esain, A. (1999), “Value stream mapping a distribution industry
application”, Benchmarking: An International Journal, Vol. 6 No. 1, pp. 60-77.
Holweg, M. (2007), “The genealogy of lean production”, Journal of Operations Management,
Vol. 25 No. 2, pp. 420-437.
Hummels, H. and Leede, J.D. (2000), “Teamwork and morality: comparing lean production and
sociotechnology”, Kluwer Academic Publishers, Vol. 26 No. 1, pp. 75-88.
Lasa, I.S., Laburu, C.O. and Vila, R.C. (2008), “An evaluation of the value stream mapping tool”,
Business Process Management Journal, Vol. 14 No. 1, pp. 39-52.
Lummus, R.R., Vokurka, R.J. and Rodeghiero, B. (2006), “Improving quality through value stream Development
mapping: a case study of a physician’s clinic”, Total Quality Management, Vol. 17 No. 8,
pp. 1063-1075.
of value
Narasimhan, R., Swink, M. and Kim, S.W. (2006), “Disentangling leanness and agility:
stream map
an empirical investigation”, Journal of Operations Management, Vol. 24 No. 5,
pp. 440-457.
Rivera, L. and Chen, F.F. (2007), “Measuring the impact of lean tools on the cost–time investment 397
of a product using cost–time profiles”, Robotics and Computer–Integrated Manufacturing,
Vol. 23 No. 6, pp. 684-689.
Rivera, L., Wan, H., Chen, F.F. and Lee, W.M. (2007), “Beyond partnerships: the power of lean
supply chains”, Trends in Supply Chain Design and Management, Springer, London,
pp. 241-268.
Salem, O., Solomon, J., Genaidy, A. and Minkarah, I. (2006), “Lean construction: from
theory to implementation”, Journal of Management in Engineering, Vol. 22 No. 4,
Downloaded by La Trobe University At 11:26 25 May 2016 (PT)
pp. 168-175.
Seth, D., Seth, N. and Goel, D. (2008), “Application of value stream mapping (VSM) for minimization of
wastes in the processing side of supply chain of cottonseed oil industry in Indian context”,
Journal of Manufacturing Technology Management, Vol. 19 No. 4, pp. 529-550.
Shah, R. and Ward, P.T. (2003), “Lean manufacturing: context, practice bundles, and
performance”, Journal of Operations Management, Vol. 21 No. 2, pp. 129-149.
Shah, R. and Ward, P.T. (2007), “Defining and developing measures of lean production”, Journal of
Operations Management, Vol. 25 No. 4, pp. 785-805.
Sullivan, W.G., McDonald, T.N. and Van Aken, E.M. (2002), “Equipment replacement decisions
and lean manufacturing”, Robotics and Computer Integrated Manufacturing, Vol. 18
Nos 3/4, pp. 255-265.
Vinodh, S., Arvind, K.R. and Somanaathan, M. (2010), “Application of value stream mapping in an
Indian camshaft manufacturing organization”, Journal of Manufacturing Technology
Management, Vol. 21 No. 7, pp. 888-900.
Vinodh, S. and Chintha, S.K. (2009), “Leanness assessment using multi grade fuzzy approach”,
International Journal of Production Research, Vol. 49 No. 2, pp. 1-15.
Further reading
Bayou, M.E. and Korvin, A.D. (2008), “Measuring the leanness of manufacturing systems-a case
study of ford motor company and general motors”, Journal of Engineering Technology
Management, Vol. 25 No. 4, pp. 287-304.
Herrona, C. and Hicksb, C. (2007), “The transfer of selected lean manufacturing techniques from
Japanese automotive manufacturing into general manufacturing (UK) through change
agents”, Robotics and Computer–Integrated Manufacturing, Vol. 24 No. 4.
Mabry, B.G. and Morrison, K.R. (1996), “Transformation to lean manufacturing by an
automotive component supplier”, Computers and Industrial Engineering, Vol. 31
Nos 1/2, pp. 95-98.
Naylor, J.B., Naim, M. and Berry, D. (1999), “Leagility: integrating the lean and agile
manufacturing paradigms in the total supply chain”, International Journal of Production
Economics, Vol. 62 Nos 1/2, pp. 107-118.
Parry, G.C. and Turner, C.E. (2006), “Application of lean visual process management tools”,
Production Planning & Control, Vol. 17 No. 1, pp. 77-86.
JEDT Appendix
13,3 Process P10
Cycle time ⫽ 1 minutes 30 seconds ⫽ 90 seconds
Changeover time ⫽ 15 minutes ⫽ 900 seconds
Availability ⫽ 27,900 seconds
398 Uptime ⫽ (27300 ⫺ 900)/(27,300) ⫽ 96.38 per cent
WIP ⫽ number of units between P9 and P10 ⫽ 2
Days of WIP on hand ⫽ 2/360 days ⫽ 8 minutes
Process P9
Cycle time ⫽ 1 minute 42 seconds ⫽ 102 seconds
Changeover time ⫽ 15 minutes ⫽ 900 seconds
Availability ⫽ 24,900 seconds
Uptime ⫽ (27300 ⫺ 900)/(23,900) ⫽ 96.38 per cent
Downloaded by La Trobe University At 11:26 25 May 2016 (PT)
Corresponding author
S. Vinodh can be contacted at: [email protected]
For instructions on how to order reprints of this article, please visit our website:
www.emeraldgrouppublishing.com/licensing/reprints.htm
Or contact us for further details: [email protected]